B. Jacobs - NRC Response Letter Dated February 12, 2004, Regarding a Meeting to Discuss Entergy Nuclear Northeast'S Plans to Construct an Independent Spent Fuel Storage Installation (ISFSI) at the Indian Point
ML040860015
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 03/26/2004
From: Brian Holian
Division Reactor Projects I
To: Jacobs B
- No Known Affiliation
References
RA 04-18
Download: ML040860015 (3)


Text

March 26, 2004 Ms. Barbara Jacobs 76 Dimond Avenue Cortlandt Manor, New York 10567

Dear Ms. Jacobs:

On behalf of the Nuclear Regulatory Commission (NRC), I am responding to your letter of February 12, 2004, to Hubert Miller, Regional Administrator, Region I, regarding a meeting to discuss Entergy Nuclear Northeasts plans to construct an independent spent fuel storage installation (ISFSI) at the Indian Point Nuclear Generating Station in Buchanan, New York. You requested that a public meeting be held in the community that is host to the plant so that it would be more accessible to local citizens and community leaders.

In a letter dated December 29, 2003, Entergy Nuclear Operations, Inc. notified the NRC of its intent to store spent nuclear fuel in dry casks on the Indian Point site in an Independent Spent Fuel Storage Installation (ISFSI) under the general license provisions of 10 CFR Part 72. The dry cask storage design that Entergy plans to use at Indian Point has been reviewed and approved by the NRC. NRC approves spent fuel cask designs through a rulemaking process.

The rulemaking process includes an opportunity for public review and comment. NRC's approval of a cask design is provided in a Certificate of Compliance. Entergy, as a general licensee, will be required to perform evaluations to ensure that the use of the specific dry cask storage system is bounded by the Part 72 Certificate of Compliance and the existing Part 50 license requirements for Indian Point. Entergys evaluations will be subject to NRC inspection.

Furthermore, NRC will perform inspections during construction, pre-operational testing, and operational activities to ensure that all safety requirements are met.

We understand that residents and local elected officials have questions and concerns regarding the planned ISFSI at Indian Point. During our Annual Assessment meeting with Entergy on April 27, 2004, we plan to discuss, at some level, the NRCs licensing and oversight of dry cask storage systems and ISFSIs. Subsequent to the April 27, 2004 meeting, we plan to hold an additional public meeting in the vicinity of Indian Point to discuss the NRCs role in the Part 72 general licensing process, dry cask storage system technical reviews, and inspection of ISFSI activities. The intent of this meeting is to inform the public about the NRCs oversight, including a discussion of the technical requirements for dry cask storage, and the nature of specific assessments to be completed by Entergy to demonstrate the dry cask storage system meets all requirements. We will also provide general information regarding actions taken and in progress to ensure the security of spent fuel storage and will respond to other questions and concerns that may be raised. In addition, we understand that Entergy plans to conduct an open house in mid-April 2004 to share the specific plans for construction and operation of the ISFSI. These meetings will provide the opportunity for citizens in the vicinity of the Indian Point site to learn more about the NRCs oversight of ISFSIs and Entergys specific ISFSI construction and operating plans.

If you have further questions, please feel free to contact me.

Ms. Barbara Jacobs 2 Sincerely,

/RA/

Brian E. Holian, Deputy Director Division of Reactor Projects

Ms. Barbara Jacobs 3 DOCUMENT NAME: G:\BRANCH2\ISFSI Related Items\RA04-018 Jacobs Citizen letter response.wpd After declaring this document An Official Agency Record it will/will not be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy 2)),&( 5,'53 5,25$ 5,'53 5,'53 

1$0(  :&RRN 7:DONHU %0F'HUPRWW  %+ROLDQ

'$7(    