ML031070397
From kanterella
Jump to navigation
Jump to search
Letter Sequence Other | |
|---|---|
TAC:MB5226, (Approved, Closed) | |
Initiation Questions
| |
MONTHYEARML0301606982002-01-15015 January 2002
[Table View]Docket Information in Support of Staffs Review of H. B. Robinson, Unit 2 License Renewal Application Project stage: Approval ML0222804382002-08-16016 August 2002 Notice of Intent to Prepare an Environmental Impact Statement & Conduct Scoping Process for License Renewal for H. B. Robinson Steam Electric Plant, Unit No. 2 Project stage: Other ML0222801252002-08-29029 August 2002 Notice of Public Meeting at Coker College to Discuss Environmental Scoping Process for Robinson, Unit 2, License Renewal Application Project stage: Meeting ML0227402602002-09-25025 September 2002 Meeting Handouts to Discuss the Environmental Scoping Process for the LRA for Robinson, Unit 2 Project stage: Meeting ML0301706392003-01-16016 January 2003 Summary of Teleconference with National Marine Fishery Service and South Carolina Department of Natural Resources in Support of the Staffs Review of the H.B. Robinson, Unit 2 License Renewal Application Project stage: Meeting ML0303006192003-01-24024 January 2003 Summary of Teleconference with Carolina Power & Light in Support of Staffs Review of H.B. Robinson, Unit 2 License Renewal Application Project stage: Meeting ML0304301542003-02-11011 February 2003 Docket Information in Support of the Staffs Review of the H. B. Robinson, Unit 2, License Renewal Application Project stage: Approval ML0310804172003-02-28028 February 2003 Federal Fish & Wildlife Permit, Dated 02/28/2003 & Migratory Bird Depredation Permit Standard Conditions Project stage: Other ML0310703432003-03-0606 March 2003 /Data Cover Sheet Project stage: Other ML0310703512003-03-0606 March 2003 FW: Robinson Gross Generation 01 02 (Table) Project stage: Other ML0310703572003-03-11011 March 2003 F.W. Robinson Emailing: - Emailing: peedee2K1 Project stage: Other ML0310703682003-03-14014 March 2003 2003 Federal Bird Permit, Dated 2/28/03, E-mail Date: 3/14/03 (Cvr. Sheet) Project stage: Other ML0310703972003-03-19019 March 2003 Cost of Replacement of Yokes Project stage: Other ML0308701572003-03-19019 March 2003 Summary of Teleconference with Carolina Power and Light in Support of the Staffs Review of the H.B. Robinson, Unit 2 License Renewal Application Project stage: Meeting ML0310704102003-03-25025 March 2003 750 and 751 Cost Benefit Rev3.doc Dated 03/25/2003 (Data W/Table) (Robinson Nuclear Plant RHR Valves 750 and 751) Project stage: Other ML0310704212003-03-25025 March 2003 750 and 751 Cost Benefit Rev 3.doc (Cvr. Sheet) March 25, 2003 Project stage: Other ML0310704522003-03-26026 March 2003 Document 2 Dated 03/26/2003 Project stage: Other ML0310704632003-04-0303 April 2003 Radiant Energy Shield SAMA, Dated 4/3/03 Project stage: Other ML0310704722003-04-0808 April 2003 IPEEE Fire Analysis, Dated 04/08/2003 Project stage: Other ML0310702092003-04-15015 April 2003 Docket Information in Support of the Staffs Review of the H.B. Robinson, Unit 2, License Renewal Application Project stage: Approval ML0311304272003-04-22022 April 2003 (S. Bolden) - Biological Assessment for License Renewal at H.B. Robinson Steam Electric Plant, Unit 2 (Tac No. MB5226) Project stage: Other ML0311302502003-04-22022 April 2003 Biological Assessment for License Renewal at H.B. Robinson Steam Electric Plant, Unit 2 Project stage: Other ML0311400302003-04-30030 April 2003 Biological Assessment - H.B. Robinson Steam Electric Plant, Unit 2, (Nuclear) License Renewal Review Hartsville, South Carolina, April 2003 Project stage: Other ML0312600842003-05-0505 May 2003 Notice of Availability of the Draft Plant-Specific Supplement to the Generic Environmental Impact Statement Regarding H.B. Robinson Steam Electric Plant, Unit 2 Project stage: Draft Other ML0312604322003-05-0505 May 2003 Request for Comments on the Draft Plant-Specific Supplement 13 to the Generic Environmental Impact Statement Regarding H.B. Robinson Steam Electric Plant, Unit 2 (Tac No. MB5226) Project stage: Draft Other ML0322706002003-06-25025 June 2003 Corrected Transcript of Proceedings, U.S. Nuclear Regulatory Commission: H.B. Robinson Steam Electric Plant, Draft EIS Public Meeting - Afternoon, Hartsville, Sc ML0321604362003-06-25025 June 2003 E-Mail from L. England to Jan Kozyra Dam Releases Project stage: Other ML0322706012003-06-25025 June 2003 Corrected Transcript of Proceedings: U.S. Nuclear Regulatory Commission: H.B. Robinson Steam Electric Plant Draft EIS Public Meeting - Evening Session, Hartsville, Sc, Enclosure 3 ML0322706042003-08-15015 August 2003 Summary of Visit to Robinson Site in Support of the Staffs Review of the H.B. Robinson, Unit 2, License Renewal Application (Tac No. MB5226) Project stage: Approval ML0322706032003-08-15015 August 2003 Summary of Meeting Held in Support of the Environmental Review for the H.B. Robinson Steam Electric Plant, Unit 2, License Renewal Application (TAC No. Mb 5226) W/Encls. 1 & 4 Project stage: Meeting ML0333200662003-10-17017 October 2003 Comment (8) of Joseph F. Cockrell, U.S. Department of the Interior Regarding License Renewal at H.B. Robinson Steam Electric Plant, Unit 2 Project stage: Other ML0334303752003-12-12012 December 2003 Final Supplement 13 to the Generic Environmental Impact Statement for H.B. Robinson Steam Electric Plant, Unit 2 License Renewal Project stage: Other ML0334505172003-12-31031 December 2003 NUREG-1437 S13, Generic Environmental Impact Statement for License Renewal of Nuclear Plants. Project stage: Acceptance Review 2003-03-14 |
| ML031070397 | |
| Person / Time | |
|---|---|
| Site: | Robinson |
| Issue date: | 03/19/2003 |
| From: | Kozyra J Carolina Power & Light Co |
| To: | Emch R NRC/NRR/DRIP/RLEP |
| Emch R, NRR/DRIP/RLEP, 415-1590 | |
| Shared Package | |
| ML031070230 | List: |
| References | |
| TAC MB5226 | |
| Download: ML031070397 (1) | |
Similar Documents at Robinson | |
|---|---|
Text
From:
"Kozyra, Jan" <jan.kozyra@pgnmail.com>
To:
"RLE@NRC.GOv" <RLE@NRC.GOv>
Date:
3/19/03 4:31PM The cost of replacement of these yokes is:
$20,000 for parts
$40,000 for engineering
$14,100 for installation labor
$155,450 for dose assumes $10,000/Rem
$240,000 to $1,200,000 Critical Path depending on what is going on during the outage. The core must be offloaded to perform this work.
This implies a cost of $469,550 to $1,429,550.