ML033320066

From kanterella
Jump to navigation Jump to search

Comment (8) of Joseph F. Cockrell, U.S. Department of the Interior Regarding License Renewal at H.B. Robinson Steam Electric Plant, Unit 2
ML033320066
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 10/17/2003
From: Cockrell J
US Dept of Interior, Fish & Wildlife Service
To: Kuo P
NRC/ADM/DAS/RDB
References
4-6-03-I-491, 68FR25907 00008, TAC MB5226
Download: ML033320066 (2)


Text

United States Department of the Interior FISH AND WILDLIFE SERVICE 176 Croghan Spur Road, Suite 200 Charleston, South Carolina 29407

§7g/' )3 October 17, 2003 6 s

§&

7 Mr. Pao-Tsin Kuo U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Re:

License Renewal at H.B. Robinson Steam Electric Plant, Unit 2 (RNP)

TAC No. MB5226, Docket No. 50-261 FWS Log No. 4-6-03 -I-491

Dear Mr. Kuo:

The U.S. Fish and Wildlife Service (Service) has reviewed the Biological Assessment and your letter requesting our concurrence regarding the above referenced action in Chesterfield, Darlington, Florence, Lee, and Sumter Counties, South Carolina. We are submitting the following comments under provisions of the Fish and Wildlife Coordination Act (48 Stat. 401, as amended; 16 U.S.C. 661 et seq.) and the Endangered Species Act of 1973 (Act), as amended (16 U.S.C. 1531 etseq.).

According to the information provided, the renewed operating license would allow 20 additional years of plant operation beyond the current RNP licensed operating period of 40 years. No major refurbishment or replacement of important systems, structures, or components are expected during the RNP license renewal period. In addition, no construction activities are expected to be associated with the license renewal.

Based on our review and the information provided, the Service concurs with your determination that the proposed action is not likely to adversely affect the federally-listed red-cockaded woodpecker, Candby's dropwort, American chaffseed, or the rough-leaved loosestrife. We also concur with your determination that the proposed action will have no effect on the additional federally-listed species, under the jurisdiction of the Service, that were identified to have potential to occur within the project area. 'Therefore, the requirements of Section 7 of the Act have been fulfilled relative to the proposed action, and no further consultation is necessary at this time. However, obligations under Section 7 of the Act must be reconsidered if: (1) new information reveals that the proposed project may affect listed species in a manner or to an extent not previously considered, (2) the proposed project is subsequently modified to include activities which were not considered during this consultation; or (3) new species are listed or critical habitat designated that might be affected by the proposed project.

This is your future. Don't leave it blank. - Support the 2000 Census.

a=-,@A,

,§ w) 3 2A -,)/ X Ax,(

tcAf4 Cal 3)

In accordance with provisions of the Fish and Wildlife Coordination Act, the Service has also reviewed the subject project with regard to the effects the proposed action may have on waters of the U.S. and related fish and wildlife resources. Information provided revealed the presence of several streams within the proposed area. Erosion and sedimentation problems are likely to be exacerbated at areas where clearing removes deep-rooted vegetation. Therefore, to maintain the integrity of these aquatic resources during transmission line corridor maintenance, we recommend that at least a 25-foot buffer be lefi on both sides of any stream crossed or paralleled by a transmission line.

The above views and recommendations constitute the report of the Department of the Interior. If you require additional assistance, please contact Phil DeGarmo of my staff at 843-7274707 x21.

Sincerely yours, Joseph F. Cockrell Acting Field Supervisor JFC/PMD/km.