Request to Postpone 2003 License Examination to Better Support Restart Effort at Davis-Besse Nuclear Power Station
ML023600043
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 12/20/2002
From: Myers L
FirstEnergy Nuclear Operating Co
To:
NRC/RGN-III
References
1-1297
Download: ML023600043 (2)


Text

FENOC FE O North State

&5501 Route 2 RmtEnea* Nuclear OperatingCompany Oak Harbo, Ohio 43449 Lew W. Myers 419-321.7599 Chief OperatbngOfficer Fax- 419-321-7582 Docket Number 50-346 License Number NPF-3 Serial 1-1297 December 20, 2002 Mr. R. Lanksbury Chief Operations Branch United States Nuclear Regulatory Commission Region III 801 Warrenville Road Lisle, Illinois 60532-4351

Subject:

Request to Postpone 2003 License Examination

Dear Mr. Lanksbury:

To better support the restart effort at Davis-Besse Nuclear Power Station (DBNPS),

FirstEnergy Nuclear Operating Company (FENOC) requests that the initial license examination scheduled for the weeks of June 16 and June 23, 2003, be postponed. After restart FENOC will contact the Nuclear Regulatory Commission's Operations Branch to discuss the intentions of rescheduling the exam.

This request constitutes a change in DBNPS's response to the NRC annual examination letter.

Should you have any questions or require additional information, please contact Mr. Patrick J. McCloskey, Manager - Regulatory Affairs, at (419) 321-8450.

Sincerely yours, DJL:AWB/gmo Attachment

Serial 1-1297 Page 1 of 1 COMMITMENT LIST The following list identifies those actions committed to by the Davis-Besse Nuclear Power Station in this document. Any other actions discussed in the submittal represent intended or planned actions by Davis-Besse. They are described only as information and are not regulatory commitments. Please notify the Manager - Regulatory Affairs (419-321-8450) at Davis-Besse of any questions regarding this document or associated regulatory commitments.

COMMITMENTS DUE DATE FENOC will contact the NRC Operations Branch After Restart to discuss the intentions of rescheduling the License Examination.