MONTHYEARML21354A7602021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 15 of 18 ML21354A7462021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 1 of 18 ML21354A7632021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 18 of 18 ML21354A7612021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 16 of 18 ML21354A7592021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 14 of 18 ML21354A7572021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 12 of 18 ML21354A7562021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 11 of 18 ML21354A7492021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 4 of 18 ML21021A1142021-01-21021 January 2021 FAQ 20-05 River Bend Uswc - Proposed NRC Response - Final ML20329A1452020-11-20020 November 2020 Terrapower'S QAPD Preliminary Questions ML20288A4042020-10-0909 October 2020 FAQ 20-05: RBS Unplanned Scram May 2019 ML21028A3472020-10-0909 October 2020 FAQ 20-05 River Bend Uswc - Tentatively Approved ML20055C8032020-02-20020 February 2020 Information Request February 20, 2020 River Bend Station NRC Inspection Report 05000458/2020412 ML18135A1072018-05-15015 May 2018 RBS Draft Response (RAI 4.3.1-2a_Class 1 Fatigue w-header-footer-watermark_received on 051318 CNRO-2016-00024, Entergy - Form 10-K for Fiscal Year Ended December 31, 20152016-12-20020 December 2016 Entergy - Form 10-K for Fiscal Year Ended December 31, 2015 ML15219A6672015-09-0404 September 2015 Tables 1 and 2 ML13322A8332013-11-25025 November 2013 Final ASP Analysis - River Bend Station ML12056A0522012-03-12012 March 2012 Enclosure 6 - List of Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML1032600152010-11-22022 November 2010 Category 1 Public Meeting with Entergy Operations, Inc. to Discuss River Bend Preliminary Enforcement Attendees List ML1018304562010-06-29029 June 2010 Attachment Re :Clinton Sample Bases Page ML1019304602010-03-25025 March 2010 List of Historical Leaks and Spills at Us Commercial Nuclear Power Plants ML1002209442009-03-30030 March 2009 Data Sheet for River Bend Station, Checklist for Step 1 Review ML1002209452009-03-30030 March 2009 Data Sheet for River Bend Station, Checklist for Step 1 Review ML0906404472009-03-0909 March 2009 Enclosure 13: Case Study 9: River Bend Shutdown as an Alternative to Other Actions - Meeting Summary of the January 27 & 28 Meeting with Nrc/Tstf ML0732400242007-10-25025 October 2007 Examples of Max Thermal Power License Conditions CNRO-2007-00038, Entergy Operations, Inc. - Proof of Financial Protection (10 CFR 140.15)2007-09-24024 September 2007 Entergy Operations, Inc. - Proof of Financial Protection (10 CFR 140.15) ML0726303192007-09-14014 September 2007 P. Paquin Ltr Amendment to Certificate of Compliance No. 6574 for the Model No. 3-82B Package (TAC L24116)/ Register User List ML0726301142007-09-14014 September 2007 / P. Paquin Ltr Amendment to Certificate of Compliance No. 9208 for the Model No. 10-142B Package (TAC L24117)/S121170 ML0722504332007-08-14014 August 2007 Corrected Facility Operating License Pg 6a 8/2/2007 Conforming License Amendment to Incorporate Mitigation Strategies Required by Section B.5.b of Commission Order EA-02-026 ML0721104332007-07-25025 July 2007 Questions from 1 Through 8 ML0717700952007-05-10010 May 2007 Draft, Attachment to 5/10/07 E-Mail from Rwbyrd, Entergy, to Bvaidya, Nrr/Dorl/Lpliv, Enclosing Draft Response to Request for Additional Info Re LAR to Update LOCA Methodology ML0429905442004-09-23023 September 2004 RB-09-2004 - Final - Written Exam - RO ML0411703752004-04-0909 April 2004 Fire Area PT-1 Summary Table E. F & G Tunnels ML0329400652003-10-0707 October 2003 Fire Protection Issue at River Bend ML0329400672003-10-0707 October 2003 Fire Protection Issue at River Bend ML0329401042003-10-0707 October 2003 Riv Backfit Status ML0329400982003-03-27027 March 2003 Riv Backfit Status ML0230501072002-07-19019 July 2002 Attachment 4, River Bend, Executive Summary ML0230501062002-07-18018 July 2002 Attachment 3, River Bend, Human Performance Questions, 1.7% Power Uprate 2021-12-20
[Table view] |
Text
S-n /5F HUMAN PERFORMANCE QUESTIONS RIVER BEND STATION 1.7% POWER UPRATE
- 1. Describe how the proposed power uprate will change the plant emergency and abnormal operating procedures, if known at this time. Discuss if your operating procedure change control process requires the identification and update of the affected operating procedures associated with a modification. Discuss if the procedures that impact plant operation have been identified and if they will be revised prior to operation above the current licensed thermal power level.
- 2. Describe any changes the proposed power uprate will have on the operator interfaces for control room controls, displays, and alarms. For example, what zone markings (e.g.,
normal, marginal, and out-of-tolerance ranges) on meters will change? What setpoints will change? How will the operators know of the change? Describe any controls, displays, and alarms that will be upgraded from analog to digital instruments as a result of the proposed power uprate and how operators were tested to determine they could use the instruments reliably.
- 3. Describe any changes the proposed power uprate will have on the Safety Parameter Display System. How will the operators know of the changes?
4.a. With regard to operator training, the licensee stated that no additional training (apart from normal training) is required to operate the plant in the uprated condition. For the uprated condition, operator response to transient, accident, and special events are not affected. Operator actions for maintaining safe shutdown, core cooling, containment cooling, etc., do not change for the power uprate. Minor changes to the power/flow map, Technical Specifications, and the like, will be communicated through normal operator training.
Please indicate the implementation schedule for the training/changes discussed above (i.e., prior to operation above the current licensed thermal power level).
4.b. With regard to the control room simulator, the licensee stated that simulator changes and validation for the power uprate will be performed in accordance with ANSI/ANS 3.5-1985.
Please describe the simulator changes (hardware and software) to the extent that they are known at this time, and provide the implementation schedule for making the changes (i.e., prior to operation above the current licensed thermal power level).
Attachment 3