ML022670133

From kanterella
Jump to navigation Jump to search
August 2002 Exam 50-400/2002-301 Final Written RO Exam
ML022670133
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 03/22/2002
From: Ernstes M
Division of Reactor Safety II
To: Scarola J
Carolina Power & Light Co
References
50-400/02301 50-400/02301
Download: ML022670133 (123)


See also: IR 05000400/2002301

Text

Final Submittal

(Blue Paper)

Reactor Operator Written Examination

SHEARON HARRIS

EXAM 2002-301

50-400

AUGUST 26 - 29, 2002

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 1

Given the following conditions:

"* The Main Turbine is operating at 1800 rpm in preparation for synchronizing to the

grid.

"* Reactor power is being maintained at approximately 12% using the Condenser Steam

Dumps.

  • Condenser Vacuum Pump 'A' is under clearance.
  • Condenser Vacuum Pump 'B' trips.

Assuming NO operator actions, condenser vacuum degrades until ...

a. the turbine and the reactor trip, and condenser steam dump operation is blocked

b. the turbine trips, and condenser steam dump operation is blocked, but the reactor

remains critical

c. condenser steam dump operation is blocked, but vacuum stabilizes above the

turbine trip setpoint

d. the turbine and reactor trip, but vacuum stabilizes above the steam dumps

interlock setpoint

ANSWER:

a. the turbine and the reactor trip, and condenser steam dump operation is blocked

5/o

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 2

Given the following conditions:

A reactor trip and safety injection have occurred.

Steam Generator parameters have decreased to the following values:

SG LEVEL PRESSURE

A 32% 870 psig

B 12% 420 psig

C 34% 830 psig

NO operator actions have been taken.

Which of the following components is mispositioned?

a. LFCV-2051B, MDAFW FCV to B SG, CLOSED

b. lFCV-2051C, MDAFW FCV to C SG, OPEN

c. 1MS-70, MS B SG to AFW Turbine, CLOSED

d. 1MS-72, MS C SG to AFW Turbine, OPEN

ANSWER:

d. 1MS-72, MS C SG to AFW Turbine, OPEN

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 3

If a Containment Ventilation Isolation (CVI) signal occurred, which of the following

Containment Ventilation fans would NOT trip directly from the CVI signal, but would

trip as a result of being interlocked with other fans?

a. Normal Purge Supply fans (AH-82 A & B)

b. Pre-Entry Purge Makeup fans (AH-81 A & B)

c. Airborne Radioactivity Removal fans (S-lA & B)

d. CNMT Pre-entry Purge Exhaust fans (E-5 A & B)

ANSWER:

b. Pre-Entry Purge Makeup fans (AH-81 A & B)

&2 aý3. 0/

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 4

Hydrogen concentration in the Waste Gas System, downstream of the catalytic

recombiners, is limited to 4% to ...

a. maintain levels below flammability limits.

b. ensure proper operation of the recombiner.

c. limit the volume of waste gas generated.

d. minimize the radioactive content of the waste gas decay tanks.

ANSWER:

a. maintain levels below flammability limits.

//t, 07/71, ;,  ; J7

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 5

Given the following conditions:

  • A large break LOCA has occurred.
  • Containment pressure peaked at 15 psig and has decreased to 6 psig.

accordance with

  • Actions are being taken to place the plant in cold leg recirculation in

EPP-010, "Transfer to Cold Leg Recirculation."

Pumps are

running.

recirculation and is in

  • The crew has just completed alignment of Safety Injection for

the Reactor Operator

the process of verifying Containment Spray alignment when

notes Containment Sump level is 25%.

Which of the following actions should be taken?

a. * Stop both trains of Containment Spray

  • Maintain both trains of RHR Pumps and CSIPs operating

b. * Stop both trains of Containment Spray

  • Stop one (1) train of RHR Pumps and CSIPs

c. * Stop one (1) train of Containment Spray

  • Stop one (1) train of RHR Pumps and CSIPs

d. * Stop both trains of Containment Spray

  • Stop both trains of RHR Pumps and CSIPs

ANSWER:

d. * Stop both trains of Containment Spray

  • Stop both trains of RHR Pumps and CSIPs

/4 b&,2641/t ,5

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 6

Given the following conditions:

  • The plant is operating at 93% power.
  • Condensate Pump 1B trips on motor overcurrent.
  • Condensate Booster Pump 1B trips as a result of the trip of Condensate Pump lB.

Which of the following describes the effect of these events on the Main Feed Pumps

AND the required operator action?

a. * Main Feed Pumps IA and lB remain running

  • Trip the reactor and go to PATH- I

b. * Main Feed Pumps 1A and lB remain running

0 Verify a turbine runback occurs

c. * Main Feed Pump 1B trips

  • Trip the reactor and go to PATH-1

d. * Main Feed Pump lB trips

  • Verify a turbine runback occurs

ANSWER:

c. * Main Feed Pump lB trips

  • Trip the reactor and go to PATH-1

656 0,

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 7

Given the following conditions:

  • The plant is solid in Mode 5 with one (1) RCP in operation.
  • RHR Pump A-SA is providing letdown flow with PK-145.1, LTDN PRESSURE

1CS-38, in MAN.

  • CSIP A-SA is providing RCS makeup and seal injection.

If instrument air is lost to 1CS-38 (PCV-145), the operator should ...

a. trip CSIP A-SA.

b. trip RHR Pump A-SA.

c. maintain letdown flow using HC-142.1, RHR Letdown 1CS-28.

d. open one PRZ PORV.

ANSWER:

a. trip CSIP A-SA.

/9 04 S ,2 -0,?

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 8

Given the following conditions:

"* An I&C technician reports that both of the Control Room Normal Outside Air Intake

Isolation radiation monitors have failed detectors.

"* It will take somewhere between four (4) and eight (8) hours to replace the detectors.

Which of the following states the action which must be taken within one (1) hour, in

accordance with Technical Specification 3.3.3.1 ?

a. Establish operation of the Control Room Emergency Filtration System in the

Recirculation Mode of Operation

b. Initiate the preplanned alternate method of radiation monitoring

c. Return the monitors to service, or be in Hot Standby within the next six (6) hours

d. Perform a surveillance test on the Control Room Emergency Filtration System, or

be in Hot Standby within the next six (6) hours

ANSWER:

a. Establish operation of the Control Room Emergency Filtration System in the

Recirculation Mode of Operation

'1/2 ý,-,7

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 9

Given the following conditions:

  • A reactor trip occurred from 75% power approximately 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> ago.
  • The operating crew is attempting to close the Reactor Trip Breakers.
  • All controls and switches are in their normal alignment for plant conditions.

Assuming all other conditions are met for closing the Reactor Trip Breakers, which of the

following sets of conditions would physically allow the breakers to close when the

REACTOR TRIP BREAKERS TRAINS A&B switch is taken to the CLOSE position?

a. * SG 'A' level is 18%

  • IR channel N-36 is failed high

b. * SG 'A' level is 18%

  • RCP 'A' is secured

c. * IR channel N-36 is failed high

  • PRZ pressure is 1920 psig

d. * PRZ pressure is 1920 psig

  • RCP 'A' is secured

ANSWER:

d. * PRZ pressure is 1920 psig

  • RCP 'A' is secured

A14 m/ & //I

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 10

The plant is in Mode 1.

and what

When entering the Personnel Air Lock, how is the inside door checked closed

would be the consequences of attempting to enter with the inside door open?

a. * The outside door contains a visual indication (red/green light) of the inside

door's position

  • Technical Specifications would be violated

b. * The equalizing valve will NOT open if the inside door is open

  • Technical Specifications would be violated

c. * The outside door contains a visual indication (red/green light) of the inside

door's position

  • An interlock will prevent entry if the inside door is open

d. * The equalizing valve will NOT open if the inside door is open

  • An interlock will prevent entry if the inside door is open

ANSWER:

inside

c. * The outside door contains a visual indication (red/green light) of the

door's position

0 An interlock will prevent entry if the inside door is open

kl' )- / )g

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 11

Given the following conditions:

  • Containment Pressure Channel I, PT-950A, is in TEST for surveillance testing

purposes.

  • Containment Pressure Channel III, PT-952A, is failed low.
  • A large break LOCA occurs and actual Containment Pressure reaches 21 psig.

Which of the following describes the response of the Containment Spray system?

a. NEITHER train of Containment Spray will automatically actuate

b. ONLY Train 'A' of Containment Spray will automatically actuate

c. ONLY Train 'B' of Containment Spray will automatically actuate

d. BOTH trains of Containment Spray will automatically actuate

ANSWER:

d. BOTH trains of Containment Spray will automatically actuate

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 12

Given the following conditions:

on both trains have

  • Several Fuel Handling Building (FHB) area radiation monitors

reached the high alarm setpoint.

the operator to verify that the

  • AOP-005, "Radiation Monitoring System," has directed

lineup.

FHB ventilation has shifted to the emergency exhaust

are RUNNING.

  • Both FHB Emergency Exhaust Fans, E-12 and E-13,

1FV-4 SB, are OPEN

  • FHB Emergency Exhaust Fan Inlets, 1FV-2 SA and

Which of the following additional alignments is expected?

AH-59)

a. * FHB Operating Floor Supply Fans (AH-56, AH-57, AH-58,

SECURED

FL-D21, FL-D22)

  • FHB Normal Exhaust Isolation Dampers (FL-D4, FL-D5,

OPEN

AH-58, AH-59)

b. * FHB Operating Floor Supply Fans (AH-56, AH-57,

RUNNING

FL-D21, FL-D22)

  • FHB Normal Exhaust Isolation Dampers (FL-D4, FL-D5,

OPEN

AH-58, AH-59)

c. * FHB Operating Floor Supply Fans (AH-56, AH-57,

RUNNING

FL-D21, FL-D22)

  • FHB Normal Exhaust Isolation Dampers (FL-D4, FL-D5,

SHUT

AH-57, AH-58, AH-59)

d. * FHB Operating Floor Supply Fans (AH-56,

SECURED

FL-D21, FL-D22)

  • FEB Normal Exhaust Isolation Dampers (FL-D4, FL-D5,

SHUT

ANSWER:

AH-58, AH-59)

d. o FHB Operating Floor Supply Fans (AH-56, AH-57,

SECURED

FL-D21, FL-D22)

  • FHB Normal Exhaust Isolation Dampers (FL-D4, FL-D5,

SHUT

3/4ý ý,) ,/

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 13

Given the following conditions:

  • A loss of offsite power has occurred with the plant at 100% power.
  • The operating crew is performing the actions of EOP-EPP-001, "Loss of AC Power to

LA-SA and 1B-SB Buses."

  • A SGTR has been identified in SG 'C'.
  • SGs 'A' and 'B' are being depressurized to 180 psig.

Which of the following describes the method used AND the bases for depressurizing SGs

'A' and 'B' to 180 psig?

a. e Method - Operate the SG PORVs 'A' and 'B' from the MCB

  • Bases - Lower RCS pressure below ruptured SG pressure to backfill from SG

'C' to the RCS

b. * Method - Operate the SG PORVs 'A' and 'B' locally

  • Bases - Lower RCS pressure below ruptured SG pressure to backfill from SG

'C' to the RCS

c. * Method - Operate the SG PORVs 'A' and 'B' from the MCB

  • Bases - Minimize RCP seal damage and RCS inventory loss

d. * Method - Operate the SG PORVs 'A' and 'B' locally

  • Bases - Minimize RCP seal damage and RCS inventory loss

ANSWER:

d. * Method - Operate the SG PORVs 'A' and 'B' locally

  • Bases - Minimize RCP seal damage and RCS inventory loss

it21X 05 .2,C p

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 14

(DEI-131) activity has exceeded

Chemistry reports that the RCS Dose Equivalent Iodine

the limit and a shutdown is required.

than 5000 F to ...

The plant is to be placed in Hot Standby with T-avg less

fission products in

a. enhance the ability of the mixed bed demineralizers to remove

the event of a small break LOCA.

products on the core

b. minimize the deposition of fission products and activation

surfaces in the event of a large break LOCA.

in the event of a large

c. prevent additional fuel cladding oxidation from occurring

break LOCA.

in the event of a SGTR.

d. prevent the release of radioactivity to the environment

ANSWER:

in the event of a SGTR.

d. prevent the release of radioactivity to the environment

ty/ o7$AV/Yp

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 15

Given the following conditions:

  • The plant is operating at 50% power.
  • All control systems are in automatic and at program values.
  • The Median Select AT Circuit output has failed high.

Which of the following will occur?

a. ALB-020-2-1, TURBINE AUTOMATIC LOADING STOP, alarms

b. ALB-013-8-3, BANK LO-LO INSERTION LIMIT, alarms

c. Bank 'D' Control Rods step inward

d. Charging flow increases

ANSWER:

b. ALB-013-8-3, BANK LO-LO INSERTION LIMIT, alarms

1-14 /6t'/(//S9

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 16

some selected 480-V

Which one of the following statements describes the reason why

MCC loads have two supply breakers in series?

a. The loads are safety-related, requiring redundant train protection

for the

b. The loads are in Containment, requiring redundant overcurrent protection

penetration

with different

c. The loads are safety-related, requiring redundant protection

overcurrent trip setpoints

redundant

d. The loads are capable of being operated from the ACP, requiring

control functions

ANSWER:

protection for the

b. The loads are in Containment, requiring redundant overcurrent

penetration

1//1 ) 22 ./ 2 7

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 17

Given the following conditions:

Which of the following RWMU Flow Controller potentiometer settings will result in the

HIGHEST ACCEPTABLE total automatic Primary Makeup System flow rate for these

conditions?

a. 5.63

b. 6.25

C. 6.88

d. 7.50

ANSWER:

C. 6.88

z./ A5

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 18

Given the following conditions:

  • The site has experienced a loss of offsite power.
  • EDG 'A' has started and sequenced all loads.
  • A valve misalignment has isolated ESW cooling to EDG 'A'.

How long can the EDG operate at full load under these conditions with NO adverse

effects?

a. One (1) minute

b. Five (5) minutes

c. Until Jacket Water Cooler Outlet temperature exceeds 185 0 F

d. Until Lube Oil Cooler Outlet temperature exceeds 1850 F

ANSWER:

a. One (1) minute

3/4)0,40z ,. ,

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 19

The plant is operating at 100% power with the following conditions:

Time Ambient Temp CT Basin Temp

1200 35 OF 64 OF

1600 20 OF 60 OF

2000 10 OF 58 OF

Which of the following describes the correct CT Deicing Gate Valve alignment for these

conditions?

1600 2000

a. Full Open Full Open

b. Full Open Half Open

c. Half Open Full Open

d. Half Open Half Open

ANSWER:

b. Full Open Half Open

WW z)7

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 20

Given the following conditions:

  • A fire has occurred in cable spread Room A - RAB 286 which requires a plant

shutdown.

  • 'A' SG pressure is 1000 psig.
  • 'A' SG wide range level is 78%.
  • 'A' SG narrow range level is unavailable.
  • AFW flow is being supplied to 'A' SG.

Which of the following actions should be taken?

a. Decrease AFW flow to lower 'A' SG wide range level to < 75%

b. Decrease AFW flow to lower 'A' SG wide range level to < 57%

c. Increase AFW flow to raise 'A' SG wide range level to > 57%

d. Increase AFW flow to raise 'A' SG wide range level to > 75%

ANSWER:

a. Decrease AFW flow to lower 'A' SG wide range level to < 75%

x14 -- ,

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 21

Given the following conditions:

  • The plant is operating at 30% power.
  • All control systems are in automatic.
  • T-ref fails low.

Which of the following describes the INITIAL response of the rod control system?

a. Step in at 8 steps per minute to reduce Tavg to 553TF

b. Step in at 8 steps per minute to reduce Tavg to 557fF

0

c. Step in at 72 steps per minute to reduce Tavg to 553 F

d. Step in at 72 steps per minute to reduce Tavg to 557'F

ANSWER:

d. Step in at 72 steps per minute to reduce Tavg to 557fF

A 0o/At/A5-'

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 22

While establishing a bubble in the PRZ per GP-002, "Normal Plant Heatup From Cold

Solid to Hot Subcritical MODE 5 to MODE 3," letdown pressure control valve 1CS-38

(PK-145.1), Low Pressure Letdown Pressure Controller, opens.

Which of the following describes why PK-145.1 opens?

a. Thermal expansion of liquid in the pressurizer /

b. Change in CCW heat load

c. Spray valves are shut while drawing a bubble

d. Switchover of letdown to orifices from RHR-CVCS cross-connect

ANSWER:

a. Thermal expansion of liquid in the pressurizer

f/A 016X1 do4

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 23

Given the following conditions:

Valves

  • Feed water flow is being transferred from the Main Feed Regulating Bypass

to the Main Feed Regulating Valves.

  • All six (6) valves are in MANUAL control and are open.

Regulating Valves

Which of the following describes the expected status of the Main Feed

and the Main Feed Regulating Bypass Valves?

a. * Main Feed Regulating Valves OPEN

  • Main Feed Regulating Bypass Valves OPEN

b. * Main Feed Regulating Valves OPEN

0 Main Feed Regulating Bypass Valves CLOSED

c. * Main Feed Regulating Valves CLOSED

  • Main Feed Regulating Bypass Valves OPEN

d. * Main Feed Regulating Valves CLOSED

0 Main Feed Regulating Bypass Valves CLOSED

ANSWER:

C. Main Feed Regulating Valves CLOSED

Main Feed Regulating Bypass Valves OPEN

e9S

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 24

Given the following conditions:

  • The plant is being heated up with RCS temperature at 280TF.
  • Containment pressure is indicating (-) 0.8 inches WG.

Assuming NO operator actions, which of the following will automatically occur?

a. 1CB-2 & CB-D51 SA will open when Containment pressure decreases to (-) 1.0

inches WG; 1CB-6 & CB-D52 SB will open if Containment pressure continues to

decrease to (-) 2.25 inches WG

b. 1CB-6 & CB-D52 SB will open when Containment pressure decreases to (-) 1.0

inches WG; 1CB-2 & CB-D51 SA will open if Containment pressure continues to

decrease to (-) 2.25 inches WG

c. 1CB-2 & CB-D51 SA and 1CB-6 & CB-D52 SB will both open when

Containment pressure decreases to (-) 1.0 inches WG

d. 1CB-2 & CB-D51 SA and 1CB-6 & CB-D52 SB will both open when

Containment pressure decreases to (-) 2.25 inches WG

ANSWER:

d. 1CB-2 & CB-D51 SA and 1CB-6 & CB-D52 SB will both open when

Containment pressure decreases to (-) 2.25 inches WG

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 25

A loss of 125 VDC bus DP-1B-SB has just occurred.

Which of the following AFW Pumps, if any, are considered inoperable?

a. NO AFW pumps are inoperable

b. ONLY MDAFW Pump lB-SB is inoperable

c. ONLY the TDAFW Pump is inoperable

d. BOTH MDAFW Pump 1B-SB and the TDAFW Pump are inoperable

ANSWER:

d. BOTH MDAFW Pump lB-SB and the TDAFW Pump are inoperable

03 /ýý O0

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 26

Given the following conditions:

  • The plant is being maintained at 1900 psig.
  • RCS temperature is 500'F and stable.

~Csm lctdownt ztnd nor-mal letdown are both in zzrVmz.

c" C) dLý 14vr~-ma Lýcet-t&,ýs tCt

The following indications are noted:

"* Normal letdown is 67 gpm

"* RCP IA seal injection flow is 9 gpm

"* RCP 1B seal injection flow is 7 gpm

"* RCP 1C seal injection flow is 8 gpm

"* RCP 1A seal leakoff flow is 2.5 gpm

"* RCP 1B seal leakoff flow is 2.0 gpm

"* RCP IC seal leakoff flow is 2.5 gpm

In order to maintain pressurizer level constant, charging flow should be adjusted to

indicate ...

a. 36 gpm.

b. 43 gpm.

c. 50 gpm.

d. 74 gpm.

ANSWER:

c. 50 gpm.

d4A

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 27

Which of the following describes the start sequence of the Fire Pumps?

a. The Motor Driven Fire Pump will only start after a 30 second time delay if the

Diesel Driven Fire Pump has received a start signal and is not maintaining Ž 100

psig.

b. The Motor Driven Fire Pump will start at * 93 psig and the Diesel Driven Fire

Pump will start at * 83 psig.

c. The Diesel Driven Fire Pump will start at * 93 psig and the Motor Driven Fire

Pump will start at * 83 psig.

d. The Diesel Driven Fire Pump will only start after a 30 second time delay if the

Motor Driven Fire Pump has received a start signal and is not maintaining Ž 100

psig.

ANSWER:

b. The Motor Driven Fire Pump will start at * 93 psig and the Diesel Driven Fire

Pump will start at * 83 psig.

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 28

Given the following conditions:

  • An operator is required to complete a valve lineup in an area where the radiation level

is 50 mrem/hour.

  • The operator's current annual Total Effective Dose Equivalent (TEDE) is 1450 mrem.
  • All of the operator's dose has been received while working at Harris Nuclear Plant.

What is the MAXIMUM time that the operator may work in this area and still remain

within CP&L's Annual Administrative Dose Limit?

a. One (1) hour

b. Eleven (11) hours

c. Fifty-one (51) hours

d. Seventy-one (71) hours

ANSWER:

b. Eleven (11) hours

fAI &04,/

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 29

Given the following:

"* The unit is at 45% power.

"* RCP 'B' trips.

"* All SG level controllers are in AUTO.

"* NO operator action is taken.

Which of the following describes the response of SG 'B' level?

a. Increases to approximately 70% and stabilizes without any significant decrease in

level during the transient

b. Decreases to approximately 30% and stabilizes without any significant increase in

level during the transient

c. Increases to approximately 70% and then decreases to approximately 30% before

stabilizing

d. Decreases to approximately 30% and then increases to approximately 70% before

stabilizing

ANSWER:

d. Decreases to approximately 30% and then increases to approximately 70% before

stabilizing

b1 DS0/ 7 /9//I , De

4/i

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 30

Given the following conditions:

Shortly following a loss of offsite power, the following indications are noted on Train

'A' Emergency Safeguards Sequencer (ESS) light box:

CNMT FAN CNMT FAN CNMT FAN CNMT FAN SW BSTR PUMP

HIGH AH-2B LOW AH-2A LOW AH-2B START A

HIGH AH-2A

OFF OFF OFF LIT

LIT

  • Prior to AUTO ACT COMPLETE MAN LOAD PERMITTED (Load Block 9)

lighting, a steam break occurs inside Containment, causing a Safety Injection.

Following completion of the sequencer, which of the following indications would be

expected on the Train 'A' ESS light box?

CNMT FAN CNMT FAN CNMT FAN CNMT FAN SW BSTR PUMP

HIGH AH-2B LOW AH-2A LOW AH-2B START A

HIGH AH-2A

LIT OFF OFF LIT

a. LIT

b. LIT LIT OFF OFF OFF

OFF LIT OFF LIT

c. OFF

OFF LIT OFF OFF

d. OFF

ANSWER:

c. OFF OFF LIT OFF LIT

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 31

Given the following conditions:

  • A reactor trip and safety injection occurred several minutes ago.
  • A loss of offsite power has just occurred.
  • Both 6.9 KV buses IA-SA and lB-SB are being supplied by the diesel generators.

Which of the following components has NO power available?

a. Containment Fan Cooler AH-1

b. Containment Fan Coil Unit AH-37A

c. Primary Shield Cooling Fan S-2A

d. Reactor Support Cooling Fan S-4A

ANSWER:

b. Containment Fan Coil Unit AH-37A

2 /U . 0/

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 32

Given the following plant conditions:

  • The plant is operating at 100% power.
  • 1CS-7, 45 GPM Letdown Orifice A, and lCS-8, 60 GPM Letdown Orifice B, are

closed.

  • 1CS-9, 60 GPM Letdown Orifice C, is open.
  • The Reactor Makeup System is setup properly and is in AUTO.
  • VCT level transmitter, LT- 112, fails high.

Assuming NO operator action, which of the following describes the plant response?

a. Charging Pump suction is eventually lost as VCT level decreases

b. 1CS-120 (LCV- 15A), Letdown VCT/Hold Up Tank, aligns to the VCT and NO

automatic makeup will occur

c. ICS-120 (LCV-1 15A), Letdown VCT/Hold Up Tank, aligns to the HUT and a

CONTINUOUS makeup to the VCT will occur

d. 1CS-120 (LCV- 15A), Letdown VCT/Hold Up Tank, aligns to the HUT and

INTERMITTENT makeups at normal setpoints will occur

ANSWER:

d. 1CS-120 (LCV-115A), Letdown VCT/Hold Up Tank, aligns to the HUT and

INTERMITTENT makeups at normal setpoints will occur

St o611, 6 (0

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 33

Given the following conditions:

  • CCW Pump 'A' needs to be removed from service for motor replacement.
  • CCW Pump 'C' is being aligned to replace CCW Pump 'A'.

Which of the following design features is associated with this evolution AND what is the

basis for this design feature?

a. A key-operated interlock is used to prevent aligning CCW Pumps 'A' and 'C' to

6.9 KV Bus 1A-SA simultaneously

b. A key-operated interlock is used to prevent aligning CCW Pump 'C' to 6.9 KV

Buses lA-SA and 1B-SB simultaneously

c. A common breaker is used to prevent aligning CCW Pumps 'A' and 'C' to 6.9 KV

Bus 1A-SA simultaneously

d. A common breaker is used to preVent aligning CCW Pump 'C' to 6.9 KV Buses

1A-SA and lB-SB simultaneously

ANSWER:

a. A key-operated interlock is used to prevent aligning CCW Pumps 'A' and 'C' to

6.9 KV Bus 1A-SA simultaneously

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 34

Given the following conditions:

  • The plant is currently operating at 30% power.
  • Core bumup is 300 EFPD.
  • Control Bank 'D' rods are inadvertently withdrawn from 135 steps to 155 steps.

BEFORE RCS temperature increases in response to the rod withdrawal, reactor power

will increase from 30% to approximately ...

a. 32%.

b. 36%.

c. 40%.

d. 44%.

ANSWER:

b. 36%.

bo l l SV

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 35

Given the following conditions:

  • The plant is operating at 68% power.
  • Control Bank D, Group 1, step counter indicates 187 steps.
  • Control Bank D, Group 2, step counter indicates 187 steps.
  • Control Bank D rod heights are as follows:

Group 1 Rod Steps

H2 186

B8 186

H14 192

P8 180

Group 2 Rod Steps

F6 186

F1O 198

K10 186

K6 180

Which of the following describes the Technical Specification action, if any, that must be

taken within one (1) hour for these conditions?

a. NO actions are required

b. Realign rods F1O and K6 within 12 steps of each other

c. Reduce power below 50%

d. Determine the position of the rods using the movable incore detectors

ANSWER:

a. NO actions are required

Ii/

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 36

Given the following conditions:

  • The AutoLog is NOT functioning.
  • The Reactor Operator is maintaining a manual log.

The following log entries have been made:

  • 0956 B-SB CSIP trip
  • 1011 Established normal letdown

At 1030, the Reactor Operator realizes he forgot to make a 0957 entry that letdown had

been isolated.

Which of the following entries would be a proper entry in accordance with OMM-0 16,

Operator Logs?

a. * 1030 Isolated normal letdown

b. L.E. 1030 Isolated normal letdown

c. *0957 Isolated normal letdown

d. L.E. 0957 Isolated normal letdown

ANSWER:

d. L.E. 0957 Isolated normal letdown

k1 C"ý)" 1,2ý

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 37

Given the following conditions:

"* Following a large break LOCA, a transition has been made from EPP PATH- I to

EPP-010, "Transfer to Cold Leg Recirculation."

"* The operator attempts to open 1RH-25, RHR A to Charging Pump Suction Valve, and

1RH-63, RHR B to Charging Pump Suction Valve.

Which of the following describes a condition that prevents 1RH-63 from opening AND

the actions that should be taken?

a. * 1CS-752, CSIP 'B' Alternate Miniflow, failed to close.

  • Maintain RHR Train 'B' aligned for Cold Leg Injection until RWST level

decreases to 3% and then secure RHR Train 'B'.

b. a 1SI-301, CNMT Sump to RHR Pump 'B' Suction, failed to open.

  • Maintain RHR Train 'B' aligned for Cold Leg Injection until RWST level

decreases to 3% and then secure RHR Train 'B'.

c. * 1CS-752, CSIP 'B' Alternate Miniflow, failed to close.

  • Close lCS-753, CSIP 'B' Alternate Miniflow Isolation, and open 1RH-63,

RHR B to Charging Pump Suction Valve.

d. * 1SI-301, CNMT Sump to RHR Pump 'B' Suction, failed to open.

RHR B to Charging Pump Suction Valve.

ANSWER:

c. * 1CS-752, CSIP 'B' Alternate Miniflow, failed to close.

  • Close 1CS-753, CSIP 'B' Alternate Miniflow Isolation, and open 1RH-63,

RHR B to Charging Pump Suction Valve.

3/4 b0 k koq,

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 38

Given the following conditions:

  • The plant is operating at 100% power.
  • Spent fuel is being moved in Spent Fuel Pool 'B'.
  • The suction pipe from Spent Fuel Pool 'B' to the Spent Fuel Pool Cooling Pump

completely severs.

Level in the Spent Fuel Pool will decrease and stabilize at ...

a. 18 feet above the fuel assemblies. Makeup should be initiated using AOP-013,

"Fuel Handling Accident."

16,

b. 18 feet above the fuel assemblies. Makeup should be initiated using OP-1

"Fuel Pool Cooling System."

c. 21 feet above the fuel assemblies. Makeup should be initiated using AOP-013,

"Fuel Handling Accident."

OP-1 16,

d. 21 feet above the fuel assemblies. Makeup should be initiated using

"Fuel Pool Cooling System."

ANSWER:

above

18 feetPool Cooling assemblies. Makeup should be initiated using OP-1 16,

the fuelSystem."

"Fuel

A/A D336),2CD3

o

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 39

Given the following conditions:

"* The plant has tripped from 100% power due to a trip of B'RCP.

"* 'A' and 'C' RCPs are running.

Which of the following is the expected RVLIS Dynamic Head indication?

a. 36%

b. 41%

c. 63%

d. 100%

ANSWER:

c. 63%

-P,/,4t 0

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 40

Given the following conditions:

  • The plant is operating at 40% power.
  • AOP-005, "Radiation Monitoring System," has been entered.
  • REM-1WC-3544, WPB CCW HX Inlet Monitor, is in HIGH alarm.

As a result of the high alarm, which of the following will automatically close?

a. 1CC-252, RCP Thermal Barrier Flow Control Valve

b. 3WC-4, WPB CCW Surge Tank Overflow Valve

c. 1CC-304, CCW to Gross Failed Fuel Detector

d. 3WC-7, WPB CCW Surge Tank Drain Valve

ANSWER:

b. 3WC-4, WPB CCW Surge Tank Overflow Valve

'1/4 ~l o

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 41

RCS

The following post-SGTR cooldown procedures all cooldown and depressurize the

to RHR conditions:

  • EPP-017, "Post SGTR Cooldown Using Backfill"
  • EPP-018, "Post SGTR Cooldown Using Blowdown"
  • EPP-019, "Post SGTR Cooldown Using Steam Dump"

in EPP-017

Which of the following describe how the depressurization and cooldown

differs from that in EPP-018 and EPP-019?

a. * EPP-017 maintains RCS pressure above the ruptured SG pressure

  • EPP-018 and EPP-019 maintain RCS pressure the same as the ruptured SG

pressure

b. * EPP-017 maintains RCS pressure below the ruptured SG pressure

  • EPP-018 and EPP-019 maintain RCS pressure the same as the ruptured SG

pressure

c. * EPP-017 maintains RCS pressure below the ruptured SG pressure

SG pressure

  • EPP-018 and EPP-019 maintain RCS pressure above the ruptured

d. * EPP-017 maintains RCS pressure the same as the ruptured SG pressure

  • EPP-018 and EPP-019 maintain RCS pressure below the ruptured SG pressure

ANSWER:

b. * EPP-017 maintains RCS pressure below the ruptured SG pressure

  • EPP-018 and EPP-019 maintain RCS pressure the same as the ruptured SG

pressure

4 C.'. y7

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 42

Given the following conditions:

  • A Control Bank 'D' rod has dropped into the core while operating at 100% power.
  • The operating crew has reduced power to 74%.
  • Three (3) hours later, they are attempting to withdraw the dropped rod.

In accordance with AOP-001, "Malfunction of Rod Control and Indication System," to

maintain programmed Tavg while recovering the dropped rod ...

a. raise turbine load.

b. reduce turbine load.

c. borate the RCS.

d. dilute the RCS.

ANSWER:

a. raise turbine load.

3/4,d

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 43

The plant is in Mode 1.

VCT pressure has decreased to 8 psig.

Which of the following is the effect on the plant?

a. VCT water flashes to steam

b. Insufficient cooling is available to the No. 2 RCP seals

c. Insufficient seal injection is available to the RCPs

d. CSIPs begin cavitating due to gas binding

ANSWER:

b. Insufficient cooling is available to the No. 2 RCP seals

4b116 . D00

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 44

Given the following conditions:

  • A plant startup is being performed per GP-005, "Power Operation (MODE 2 to

MODE 1)."

  • The SG PORVs controllers are set at 87%.
  • The Steam Dump Controller has been incorrectly set at 89%.

While preparing to latch the Main Turbine, RCS temperature will be maintained at

approximately ...

a. 553TF.

b. 557 0F.

c. 562TF.

d. 5640 F.

ANSWER:

c. 5620 F.

4K/4 03M6

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 45

Given the following conditions:

"* The plant is operating at 100% power when a high radiation condition occurs inside

containment.

"* RC-3561A, Containment Ventilation Isolation radiation monitor (Train A), goes into

high (RED) alarm.

"* RC-3561B, Containment Ventilation Isolation radiation monitor (Train B), is out-of

service for testing.

"* RC-3561C, Containment Ventilation Isolation radiation monitor (Train A), does

NOT respond to the high radiation condition.

"* RC-3561D, Containment Ventilation Isolation radiation monitor (Train B), goes into

high (RED) alarm.

Which train(s) of Containment Ventilation Isolation will actuate, if any?

a. NEITHER Train 'A' NOR 'B'

b. Train 'A' ONLY

c. Train 'B' ONLY

d. BOTH Train 'A' AND 'B'

ANSWER:

d. BOTH Train 'A' AND 'B'

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 46

Given the following conditions:

  • The unit is in Mode 4, performing a cooldown on RHR.
  • Both trains of CCW are in service.
  • NSW Pump 'A' is operating.
  • NSW Pump 'B' is in standby.
  • Both ESW Pumps are available, but are NOT running.
  • NSW Pump 'A' experiences a sheared shaft.

Which of the following automatically occurs AND what is the effect on the plant

cooldown?

a. * ESW aligns on a low flow signal to cool Train 'A' CCW ONLY

  • Train 'B' RHR and CCW must be secured.

b. * ESW aligns on a low flow signal to cool BOTH trains of CCW.

  • Neither train of RHR and CCW must be secured.

c. * ESW aligns on a low pressure signal to cool Train 'A' CCW ONLY.

  • Train 'B' RHR and CCW must be secured.

d. * ESW aligns on a low pressure signal to cool BOTH trains of CCW.

  • Neither train of RHR and CCW must be secured.

ANSWER:

d. * ESW aligns on a low pressure signal to cool BOTH trains of CCW.

  • Neither train of RHR and CCW must be secured.

4 NV6AA6t t O/

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 47

per EOP

Which of the following conditions would permit securing Containment Spray

PATH-1 Guide?

a. * Actuation caused by a LOCA

  • Time since LOCA occurred is 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />
  • Containment pressure is 9 psig

b. * Actuation caused by a LOCA

  • Time since LOCA occurred is 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />
  • Containment pressure is 5 psig

c. * Actuation caused by a Steam Line Break

  • Time since Steam Line Break occurred is 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />
  • Containment pressure is 5 psig

d. * Actuation caused by a Steam Line Break

  • Time since Steam Line Break occurred is 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />
  • Containment pressure is 9 psig

ANSWER:

c. * Actuation caused by a Steam Line Break

"* Time since Steam Line Break occurred is 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />

"* Containment pressure is 5 psig

41A 0.X( d6'OY0

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 48

Given the following conditions:

"* The plant is in Mode 3 with Tavg at 557F.

"* All systems are in their normal alignment.

"* Safety Injection is manually actuated inadvertently.

Which of the following describes the impact on Instrument Air inside Containment?

a. e IA-819, Containment Instrument Air, closes

  • SI and Phase A must BOTH be reset to allow opening IA-819

b. * IA-819, Containment Instrument Air, closes

  • ONLY SI must be reset to allow opening IA-819

c. * IA-819, Containment Instrument Air, closes

  • ONLY Phase A must be reset to allow opening IA-819

d. e IA-819, Containment Instrument Air, remains open

  • NO actions are required to be taken to restore IA to Containment

ANSWER:

c. * IA-819, Containment Instrument Air, closes

  • ONLY Phase A must be reset to allow opening IA-819

114 02k/o

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 49

Given the following conditions:

  • The unit is operating at 100% power.
  • All automatic actions occur, EXCEPT one (1) Throttle Valve fails to close.

Assuming NO operator actions, which of the following describes the expected FINAL

to

CONDITION of SG pressure and Turbine First Stage Impulse Pressure as compared

the 100% power conditions?

a. * SG pressure INCREASES

  • Turbine First Stage Impulse Pressure INCREASES

b. * SG pressure INCREASES

  • Turbine First Stage Impulse Pressure DECREASES

c. * SG pressure DECREASES

  • Turbine First Stage Impulse Pressure INCREASES

d. * SG pressure DECREASES

  • Turbine First Stage Impulse Pressure DECREASES

ANSWER:

b. * SG pressure INCREASES

  • Turbine First Stage Impulse Pressure DECREASES

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 50

Given the following conditions:

  • The plant is being cooled down on RHR per EPP-006, "Natural Circulation

Cooldown with Steam Void in Vessel with RVLIS."

  • RCS cold leg temperatures are 190TF.
  • RVLIS upper range indicates greater than 100%.
  • Three CRDM fans have been running during the entire cooldown.

Steam should be dumped from all SGs to ensure ...

a. boron concentration is equalized throughout the RCS prior to taking a sample to

verify cold shutdown boron conditions.

b. all inactive portions of the RCS are below 200TF prior to complete RCS

depressurization.

c. RCS and SG temperatures are equalized prior to any subsequent RCP restart.

d. RCS temperatures do not increase during the required 29 hour3.356481e-4 days <br />0.00806 hours <br />4.794974e-5 weeks <br />1.10345e-5 months <br /> vessel soak period.

ANSWER:

b. all inactive portions of the RCS are below 200TF prior to complete RCS

depressurization.

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 51

Given the following conditions:

"* During a reactor startup, power has been stabilized at 10-8 amps.

"* Main Feed Pump 'A' is operating and maintaining SG levels at program level.

"* Main Feed Pump 'B' is secured.

"* Subsequently, SG 'B' level increases to 85%.

Which of the following is the expected status of the following pumps?

a. e Main Feed Pump 'A' RUNNING

  • Motor Driven AFW Pumps OFF
  • Turbine Driven AFW Pump OFF

b. * Main Feed Pump 'A' OFF

  • Motor Driven AFW Pumps RUNNING
  • Turbine Driven AFW Pump OFF

c. . Main Feed Pump 'A' OFF

  • Motor Driven AFW Pumps OFF
  • Turbine Driven AFW Pump RUNNING

d. * Main Feed Pump 'A' OFF

  • Motor Driven AFW Pumps RUNNING
  • Turbine Driven AFW Pump RUNNING

ANSWER:

b. * Main Feed Pump 'A' OFF

"* Motor Driven AFW Pumps RUNNING

"* Turbine Driven AFW Pump OFF

1/4 059Kw0

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 52

Given the following conditions:

0 A loss of offsite power has occurred.

Both Emergency Diesel Generators are loaded.

ALB-024-3-2, DIESEL GENERATOR A TROUBLE, alarms.

0 An operator is sent to investigate and reports the following conditions:

Turbo Oil Press 28 psig and stable

Lube Oil Press 30 psig and stable

Fuel Oil Press 1.5 psig and stable

Day Tank Level 56% and slowly decreasing

Starting Air Pressure 227 psig and slowly decreasing

Jacket Water Pressure 17 psig and stable

Control Air Pressure 53 psig and stable

Which of the following compone nts should have automatically started based on these

conditions?

a. Lube Oil Circulating Pump

b. Auxiliary Lube Oil Pump

c. Fuel Oil Transfer Pump

d. Starting Air Compressor

ANSWER:

b. Auxiliary Lube Oil Pump

// 15(o 19Ai-

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 53

Given the following conditions:

  • PRZ pressure is 1685 psig.
  • PRT pressure is 15 psig.

Which of the following indications support a diagnosis that a PRZ PORV is stuck open?

TEMP

DOWNSTREAM

PRZ LEVEL OF PORV

a. Increasing 613 0 F

b. Increasing 250 0 F

c. Decreasing 613 0F

d. Decreasing 2500 F

ANSWER:

b. Increasing 2500 F

3/411

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 54

Given the following conditions:

  • A Reactor Startup is being performed.
  • Initial Source Range Count Rate was 200 count per second (cps).
  • 2500 pcm has been inserted into the core by withdrawing control rods and Source

Range Count Rate has increased to 400 cps.

  • Rod withdrawal is continued, and an additional 1250 pcm is added to the core.

Which of the following identifies the approximate condition of the core?

a. The reactor is subcritical with a stable count rate of 500 cps

b. The reactor is subcritical with a stable count rate of 600 cps

c. The reactor is subcritical with a stable count rate of 800 cps

d. The reactor is critical with an increasing count rate

ANSWER:

c The reactor is subcritical with a stable count rate of 800 cps

//A5/ DA

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 55

During a plant cooldown and depressurization in preparation for a refueling, the SIS

Accumulators are depressurized and then drained.

The normal drain path for the SIS Accumulators is through the Reactor Coolant Drain

Tank ...

a. to the Recycle Holdup Tank.

b. to the Waste Holdup Tank.

c. via the Spent Fuel Pool Cooling System to the Refueling Water Storage Tank.

d. via the Spent Fuel Pool Cooling System to the Transfer Canal.

ANSWER:

a. to the Recycle Holdup Tank.

3/4oNS /,/ 07

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 56

Given the following conditions:

"* The plant is in Hot Standby.

"* Letdown flow is 105 gpm.

"* CSIP 'B' is operating.

"* A loss of 125 VDC Emergency Bus DP-1B-SB occurs.

With NO operator actions, which of the following is the response of the plant?

a. Seal injection will be lost

b. Charging pump suction will shift to the RWST

c. Letdown line flashing will occur

d. RCS inventory will be lost

ANSWER:

d. RCS inventory will be lost

414 oggn/q vý'o9s

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 57

Which of the following sets of conditions would require that the Reactor Coolant Pumps

be secured?

a. * RCS is currently at 5250 F during a plant heatup

  • Operating CSIP has tripped
  • CCW Heat Exchanger outlet temperature is 95 0 F

b. * RCS is currently at 375 0 F during a plant heatup

  • Operating CSIP has tripped

0

  • CCW Heat Exchanger outlet temperature is 11 2 F

c. * RCS is currently at 525°F during a plant heatup

  • CSIP 'A' is operating

& CCW Heat Exchanger outlet temperature is 108TF

d. * RCS is currently at 375 0 F during a plant heatup

  • CSJP 'A' is operating
  • CCW Heat Exchanger outlet temperature is 122 0 F

ANSWER:

b. * RCS is currently at 3750 F during a plant heatup

"* Operating CSIP has tripped

"* CCW Heat Exchanger outlet temperature is 1120 F

"* ALB-5-1-2B, RCP THERM BAR HDR LOW FLOW, is alarming

S0o9f3. oS

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 58

Given the following conditions:

  • A loss of offsite power has occurred.
  • SG levels are being maintained constant using AFW in manual control.
  • ERFIS is out-of-service.
  • SG pressures are at 885 psig and decreasing slowly.
  • RCS pressure is 1935 psig and stable.

0

  • RCS hot leg temperatures are 605TF and stable.

0

  • RCS cold leg temperatures are 532 F and decreasing slowly.

The operator is verifying natural circulation flow in EPP-004, "Reactor Trip Response."

EPP

Which of the following describes the status of natural circulation flow criteria per

004?

a. The natural circulation criteria of EPP-004 has been met

b. RCS cold leg temperature criteria has NOT been met

c. RCS hot leg temperature criteria has NOT been met

d. RCS subcooling criteria has NOT been met

ANSWER:

d. RCS subcooling criteria has NOT been met

4/ 0 /7f3.e0/

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 59

Which of the following would require that Independent Verification be performed in

accordance with OPS-NGGC-1303, "Independent Verification?"

a. During Mode 5, a valve in the Containment Spray system is being repositioned for

testing and the OP lineup will be completed prior to Mode 4 entry

b. During Mode 1, a valve in the Main Steam system is being placed under clearance

and the valve is only accessible with a manlift

c. During Mode 4, a valve in CVCS inside containment is being positioned for

draining and the valve is located in an area where the temperature is 134°F

d. During Mode 3, a valve in CVCS is being placed under clearance and the valve is

located in a radiation field of 175 mRem/hr with an estimated verification time of

6 minutes

ANSWER:

b. During Mode 1, a valve in the Main Steam system is being placed under clearance

and is only accessible with a manlift

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 60

Given the following conditions:

o Train 'A' RHR has just been placed in service in accordance with GP-007, "Normal

Plant Cooldown MODE 3 to MODE 5."

  • Train 'B' RHR is still aligned for ECCS Mode.
  • Interlock P-12 has been bypassed and the Condenser Steam Dumps are in operation.
  • Train 'A' equipment is in operation.
  • Both CSIPs are still available.
  • RCP 'C' has been secured for the cooldown.

A loss of 6.9 KV Bus 1A-SA occurs and EDG 1A-SA fails to start.

Which of the following describes the impact of the loss of Bus 1A-SA on the plant?

a. TDAFW Pump becomes inoperable

b. RCPs 'A' and 'B' must be secured

c. RHR cooling capability is temporarily lost

d. Condenser steam dump capability is lost

ANSWER:

c. RHR cooling capability is temporarily lost

414 667113,02

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 61

Given the following conditions:

"* FRP-P. 1, "Response to Imminent Pressurized Thermal Shock," is being performed.

"* Safety Injection CANNOT be terminated due to inadequate RCS subcooling.

"* However, RCS subcooling is adequate to start an RCP.

Which of the following describes the bases for RCP operation under these conditions?

a. Provide additional RCS subcooling

b. Provide mixing of injection water and reactor coolant

c. Supply additional heat input into the RCS

d. Provides normal sprays for the depressurization

ANSWER:

b. Provide mixing of injection water and reactor coolant

hi-ocf d,02

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 62

Given the following conditions:

  • REM-3502A, Containment RCS Leak Detection Radiation monitor, is in service.
  • REM-3502B, Containment Pre-Entry Purge Radiation monitor, is in service.

Which of the following describes the effect on these monitors if a Containment Isolation

Phase 'A' actuation occurs?

a. * REM-3502A remains in service

  • REM-3502B remains in service

b. * REM-3502A remains in service

  • REM-3502B is isolated

c. e REM-3502A is isolated

  • REM-3502B remains in service

d. o REM-3502A is isolated

  • REM-3502B is isolated

ANSWER:

c. e REM-3502A is isolated

  • REM-3502B remains in service

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 63

Given the following conditions:

"* A LOCA has occurred inside Containment, resulting in a reactor trip and a safety

injection.

"* A transition has just been made from EPP PATH- I to FRP-P. 1, "Response to

Imminent Pressurized Thermal Shock."

  • Containment pressure is 7 psig and increasing slowly.
  • All RCPs have been secured.
  • Pressurizer level is off-scale low.
  • RVLIS Full Range indicates 88%.

0

  • RCS cold leg temperatures are 230'F and decreasing.
  • RCS pressure is 285 psig and stable.

0

  • ERFIS indicates subcooling is 177 F.
  • SG levels are as follows:

SG LEVEL

A 32%

B 10%

C 26%

Which of the following actions should be taken in accordance with FRP-P. 1, "Response

to Imminent Pressurized Thermal Shock?"

a. Maintain total AFW flow >210 KPPH until at least one (1) SG is >40% level

b. Secure AFW flow to all SGs

c. Maintain cold leg injection flow, but secure one (1) CSIP

d. Return to EOP-PATH-1

ANSWER:

a. Maintain total AFW flow >210 KPPH until at least one (1) SG is >40% level

4 /

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 64

Given the following conditions:

  • A loss of secondary heat sink has occurred.
  • Attempts are made to restore main feedwater using FRP-H. 1, "Response to Loss of

Secondary Heat Sink."

  • All RCPs are stopped.
  • SG level wide range levels are all below 5%.
  • PRZ pressure is 2180 psig and increasing rapidly.

Which of the following describes the sequence of actions to be taken?

a. * Actuate Safety Injection

  • Verify all PRZ PORVs automatically open when pressure increases

b. e Actuate Safety Injection

  • Open all PRZ PORVs after verifying Safety Injection flowpath

c. * Open all PRZ PORVs

  • Verify Safety Injection automatically actuates when pressure decreases

d. * Open all PRZ PORVs

  • Actuate Safety Injection after verifying the PRZ PORVs are open

ANSWER:

b. * Actuate Safety Injection

  • Open all PRZ PORVs after verifying Safety Injection flowpath

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 65

Given the following conditions:

  • Reactor power is 8%.
  • The turbine is at 1800 rpm, in preparations for synchronizing to the grid.

Which of the following describes why the Main Turbine must be tripped under these

conditions?

a. Prevent an uncontrolled RCS cooldown

b. Generate an additional reactor trip signal

c. Minimize the depletion of SG inventory

d. Minimize the pressure increase in the RCS

ANSWER:

a. Prevent an uncontrolled RCS cooldown

3/4l 0D 7 E/X,

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 66

Given the following conditions:

  • PRZ pressure is being controlled in automatic at 2235 psig.
  • Pressure transmitter PT-444 fails high.
  • Approximately 10 seconds after the failure, the operator places PK-444A in

MANUAL.

Which of the following actions is the operator required to take to restore PRZ pressure to

2235 psig?

a. Raise controller output to cause heaters to energize and spray valves to close

b. Raise controller output to cause spray valves to open and heaters to deenergize

c. Lower controller output to cause heaters to energize and spray valves to close

d. Lower controller output to cause spray valves to open and heaters to deenergize

ANSWER:

c. Lower controller output to cause heaters to energize and spray valves to close

A/14 0, Z

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 67

The plant is in Mode 3 with the Shutdown Banks withdrawn when the following events

occur:

  • ALB-15-2-2, PIC 1-2-3-4-9-10-13-14 POWER FAILURE, alarms.
  • ALB-15-4-3, PIC 17-18 POWER FAILURE, alarms.
  • Most lights in the top row of Trip Status Light Boxes are energized.
  • Several lights in each of the other rows of Trip Status Light Boxes are energized.
  • ALB-15-1-4, 60 KVA UPS TROUBLE, remains clear.
  • ALB-15-1-5, 7.5 KVA UPS TROUBLE, remains clear.
  • ALB-15-3-2, PIC 5-6-7-8-11-12-15-16 POWER FAILURE, remains clear.
  • ALB-15-5-3, PIC 19 POWER FAILURE, remains clear.

Which of the following buses have been lost?

a. Instrument Bus S-I

b. Instrument Bus S-II

c. UPS Bus UPP-1A

d. UPS Bus UPP-1B

ANSWER:

a. Instrument Bus S-I

PA )57/9 d /5

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 68

Given the following conditions:

  • The crew diagnosed a SG tube leak.
  • In response to the alarm on REM-1BD-3527, the crew performed the required actions

of AOP-016, "Excessive Primary Plant Leakage," Attachment 1, "Primary-To

Secondary Leak."

Which of the following describes the expected indicated trend on REM- 1BD-3527 after

the completion of Attachment 1?

a. Stabilizes and then decreases

b. Stabilizes and remains constant

c. Increases and stabilizes at full scale

d. Stabilizes and then increases

ANSWER:

a. Stabilizes and then decreases

/i/ 037/J ,41 13

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 69

Given the following conditions:

"* FRP-C. 1, "Response to Inadequate Core Cooling," is being performed following a

small break LOCA.

"* Containment pressure is 8.5 psig.

"* Core exit thermocouples are >1400'F.

"* All efforts to establish SI flow have failed.

"* The crew has started RCP 'C' in an attempt to lower core exit temperatures, but

temperatures have remained above 1300'F.

"* SG 'C' level is 55%.

"* SGs 'A' and 'B' are off-scale low.

Which of the following actions should be taken?

a. Open the PRZ PORVs and RCS vent valves

b. Start RCPs 'A' and 'B' one at a time

c. Close any open PRZ PORVs and RCS vent valves

d. Refill and repressurize the SI Accumulators for continued injection

ANSWER:

a. Open the PRZ PORVs and RCS vent valves

/V, o0YE , v5

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 70

Given the following conditions:

"* The unit is in the Source Range during a reactor startup.

"* Power is lost to Instrument Bus S-III.

Which of the following signals caused the reactor trip?

a. Source Range High Count Rate

b. Intermediate Range High Flux

c. Power Range Neutron Flux (Low Setpoint)

d. Turbine Trip

ANSWER:

d. Turbine Trip

hA o,;,¢ý,-

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 71

After plant control is completely shifted to the Auxiliary Control Panel in accordance

with AOP-004, "Remote Shutdown", which of the following actions will the operators

have to manually perform?

a. Align CSIP suction to the RWST

b. Transfer control of the EDGs to the local control panels

c. Open the reactor trip breakers

d. Block SIAS to the Emergency Sequencers

ANSWER:

a. Align CSIP suction to the RWST

I/pt

ý)6214 ý /I -,-/

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 72

Given the following conditions:

"* During a plant startup, Main Feed Water is aligned to the SGs through the Feed Reg

Valve Bypass FCVs.

"* The controller for FCV-479, SG 'A' Feed Reg Valve Bypass FCV (FK-479. 1), has

just been placed in AUTO.

"* The controller for FCV-489, SG 'B' Feed Reg Valve Bypass FCV (FK-489.1), is still

in MANUAL.

"* The controller for FCV-499, SG 'C' Feed Reg Valve Bypass FCV (FK-499.1), is still

in MANUAL.

"* FCV-479 begins going open.

Which of the following failures could have caused the response of FCV-479?

a. SG 'A' Feed Flow Channel FT-475 failing low

b. SG 'A' Steam Flow Channel FT-476 failing high

c. SG 'A' Level Channel LT-476 failing high

d. Power Range Channel N-44 failing high

ANSWER:

d. Power Range Channel N-44 failing high

,/63.-q ,0 /

-j/3

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 73

Which of the following describes why RCP trip criteria is included in PATH-2?

a. Protect against operator misdiagnosis since RCS pressure should not decrease to

the trip criteria during a SGTR

b. Decrease leakage from the RCS since the total leakage for the duration of the

SGTR is less than it would have been with the RCPs in service

in

c. Prevent heatup of the RCS since a heatup of the RCS due to the RCPs being

service increases leakage to the ruptured SG

one RCP

d. Protect the RCPs from operating with inadequate AP across the number

seal as a result of the RCS depressurization from the SGTR

ANSWER:

to

a. Protect against operator misdiagnosis since RCS pressure should not decrease

the trip criteria during a SGTR

1/2 )c38FK3, /9

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 74

Which of the following describes how the Emergency Sequencer is reset following a loss

of AC power to 6.9 KV Bus 1A-SA which results in actuation of the Sequencer UV

Program?

a. The operator resets the program by turning the SI Reset switch to RESET at least

2.5 minutes after Load Block 9 is completed

b. The operator resets the program by placing both Reactor Trip Breaker A-SA and

Reactor Trip Breaker B-SB to the closed position momentarily after all actuation

signals have been cleared

c. The program automatically resets when Auxiliary Bus D To Emergency Bus A

SA Breaker 104 and Emergency Bus A-SA To Aux Bus D Tie Breaker 105 SA are

closed during the restoration of offsite power

d. The program automatically resets when Diesel Generator A-SA Breaker 106 SA is

opened during the restoration of offsite power

ANSWER:

c. The program automatically resets when Auxiliary Bus D To Emergency Bus A

SA Breaker 104 and Emergency Bus A-SA To Aux Bus D Tie Breaker 105 SA are

closed during the restoration of offsite power

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 75

Given the following conditions:

  • FRP-S. 1, "Response to Nuclear Power Generation / ATWS," is being performed.
  • The operating crew is about to exit FRP-S.1.

Boration should continue even after exiting FRP-S. 1 to ensure ...

a. adequate shutdown margin is established since the criteria for exiting FRP-S. 1 is

only that the reactor be subcritical.

b. the reactor becomes subcritical since the criteria for exiting FRP-S. 1 is only that

the power range channels indicate < 5%.

c. cold shutdown boron concentration is achieved since additional boron, beyond that

needed to make the reactor subcritical, is required to compensate for the cooldown

portion of the recovery.

d. refueling boron concentration is achieved since additional boron, beyond that

needed to make the reactor subcritical, is required to allow for core offloading to

inspect for fuel damage.

ANSWER:

a. adequate shutdown margin is established since the criteria for exiting FRP-S.1 is

only that the reactor be subcritical.

A D2.g

O

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 76

Given the following conditions:

"* Spent resin is being sluiced from the Cation Demineralizer to a Spent Resin Storage

Tank.

"* The operator reports that it appears that a pipe in the overhead of a hallway is plugged

with resin.

"* HP reports the results of a radiation survey as follows:

& 2500 mr/hr on contact with pipe

  • 1200 mr/hr @ 18 inches from the pipe
  • 5 mr/hr at floor level below the pipe

Which one of the following describes the required radiological postings?

a. NO postings are required because a ladder is required to access the pipe area

b. Very High Radiation Area with red flashing light

c. High Radiation Area with a red flashing light

d. High Radiation Area, but NO red flashing light required

ANSWER:

c. High Radiation Area with a red flashing light

6ý >0- ) 3

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 77

Given the following conditions:

Which of the following signals will automatically terminate the PRT makeup AND how

will the valves respond?

a. * ONLY a Phase A signal

0 1RC-161, RMW TO CNMT, closes

b. * ONLY a Phase A signal

c. * EITHER a Phase A signal OR a Phase B signal

d. * EITHER a Phase A signal OR a Phase B signal

S1RC-161, RMW TO CNMT, remains open

ANSWER:

a. * ONLY a Phase A signal

"* 1RC-161, RMW TO CNMT, closes

"* 1RC-167, RMW TO PRT, remains open

1161

SOD4,T

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 78

Given the following conditions:

Emergency Boration is required.

0 1CS-278, Emergency Boric Acid Addition, is failed CLOSED.

Which of the following alignments will provide adequate boric acid flow?

1CS-155 1CS-291 1CS-292 1LCS-165 1CS-166

1CS-283 1CS-156

CSIP CSIP VCT VCT

Boric Makeup Makeup

Suction Suction Outlet Outlet

Acid to to CSIP to VCT

from from LCV LCV

Boric Suction FCV

114A RWST RWST 115C 115E

Acid FCV

Blender 113B LCV LCV

FCV 115B 115D

113A

CLOSED OPEN

a. CLOSED OPEN CLOSED CLOSED CLOSED

OPEN CLOSED CLOSED OPEN CLOSED

b. OPEN CLOSED

OPEN OPEN

C. CLOSED OPEN CLOSED CLOSED CLOSED

OPEN CLOSED OPEN CLOSED

d. OPEN CLOSED CLOSED

ANSWER:

d. OPEN CLOSED CLOSED OPEN CLOSED OPEN CLOSED

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 79

The compensating voltage on Intermediate Range (IR) channel N-35 is set too low,

resulting in N-35 stabilizing at 2 x 10.10 amps during a reactor shutdown.

If IR channel N-36 fails low ...

a. BOTH SR NIs will automatically energize.

b. ONLY SR channel N-31 will automatically energize.

c. ONLY SR channel N-32 will automatically energize.

d. NEITHER SR NI will automatically energize.

ANSWER:

d. NEITHER SR NI will automatically energize.

I// 033/9XIe /

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 80

Which of the following is an acceptable condition in accordance with AOP-010,

"Feedwater Malfunctions?"

a. * Power level at 65%

& No (0) Heater Drain Pumps operating

  • One (1) train of Feed Water Pumps (FWP, CBP, CP) operating

b. * Power level at 98%

  • One (1) Heater Drain Pump operating
  • Two (2) trains of Feed Water Pumps (FWP, CBP, CP) operating

c. * Power level at 92%

  • No (0) Heater Drain Pumps operating
  • Two (2) trains of Feed Water Pumps (FWP, CBP, CP) operating

d. * Power level at 70%

  • One (1) Heater Drain Pump operating
  • One (1) train of Feed Water Pumps (FWP, CBP, CP) operating

ANSWER:

b. * Power level at 98%

"* One (1) Heater Drain Pump operating

"* Two (2) trains of Feed Water Pumps (FWP, CBP, CP) operating

/0 05q/9/1,03

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 81

Which of the following describes the automatic operation of 1SA-506, Service Air

Header Isolation Valve?

a. Opens if Instrument Air pressure decreases to < 90 psig

b. Closes if Service Air pressure decreases to < 90 psig

c. Opens if Service Air pressure decreases to < 90 psig

d. Closes if Instrument Air pressure decreases to < 90 psig

ANSWER:

d. Closes if Instrument Air pressure decreases to < 90 psig

1614 079A1/40~o/

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 82

Given the following conditions:

  • PATH-2 is being performed in response to a tube rupture on SG 'C'.
  • SI termination criteria is being checked.

Over the last several minutes:

"* RCS subcooling has gone from 60'F to 63TF.

"* Levels in SG 'A' and 'B' have increased from 45% to 50%.

"* PRZ level has increased from 43% to 47%.

"* RCS temperature has gone from 472TF to 4680 F.

"* RCS pressure has gone from 885 psig to 880 psig.

The Unit-SCO asks if "RCS pressure is stable or increasing."

Which of the following describes how the operator should respond AND what actions

should be taken?

a. * RCS pressure is still decreasing.

  • The cooldown must be stablized to determine if RCS pressure has stabilized.

b. e RCS pressure is still decreasing.

  • SI cannot be terminated and a transition to the appropriate procedure must be

made.

c. o RCS pressure is stable.

  • The cooldown must be stabilized in order to verify the trend.

d. * RCS pressure is stable.

  • SI can be terminated.

ANSWER:

d. o RCS pressure is stable.

  • SI can be terminated.

k1~4 9, , V/?

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 83

Given the following conditions:

  • A large break LOCA has occurred.
  • Containment hydrogen concentration is 1.2%.
  • Containment pressure is 6 psig.
  • Electric Hydrogen Recombiner (EHR) 1A-SA was placed in service two (2) hours

ago.

Which of the following describes the expected status of EHR lB-SB and the

Containment Hydrogen Purge System?

CONTAINMENT

HYDROGEN

EHR 1B-SB PURGE

a. In Standby Operating

b. In Standby Secured

c. In Service Operating

d. In Service Secured

ANSWER:

b. In Standby Secured

tie3z.

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 84

Given the following conditions:

  • The plant is operating at 100% power.
  • The Condenser Zone 1 low-pressure turbine boot seal ruptures, causing a turbine trip

and reactor trip.

  • A complete loss of Zone 1 and Zone 2 vacuum occurs.

Which of the following will automatically actuate to stabilize RCS temperature instead of

Condenser Steam Dumps AND why does C-9 prevent Condenser Steam Dump

operation?

a. . Steam Generator PORVs

  • Ensure the condenser does NOT reach saturation conditions

b. * Steam Generator PORVs

  • Protect the condenser from an overpressure condition

c. * Atmospheric Steam Dumps

  • Ensure the condenser does NOT reach saturation conditions

d. * Atmospheric Steam Dumps

  • Protect the condenser from an overpressure condition

ANSWER:

b. * Steam Generator PORVs

  • Protect the condenser from an overpressure condition

/dVf bslAI 3/b .

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 85

Which of the following sets of conditions would require that AOP-022, "Loss of Service

Water," be performed?

a. * ALB-002-1-1, EMER SERV WTR PMPS HDR STR HIGH AP OR LOSS OF

PWR, in alarm

0 Local strainer AP indicating 20 psid

b. * ALB-002-3-2, SW BSTR PUMP A AUTO START FAIL/OVERRIDE, in

alarm

  • ALB-002-3-3, SW BSTR PUMP A O/C TRIP OR CLOSE CKT TROUBLE,

in alarm

  • SI actuated

c. * ALB-002-6-2, SERV WTR PUMPS DISCHARGE VLV NOT FULL OPEN,

in alarm

o NSW Pump 'A' has been started in Priming Mode

  • NSW Pump discharge valve 10% open

d. * ALB-002-7-5, COMPUTER ALARM SERVICE WATER, in alarm

  • Main Reservoir temperature indicating 94°F
  • Aux Reservoir temperature indicating 88 0 F

ANSWER:

a. o ALB-002-1-1, EMER SERV WTR PMPS HDR STR HIGH AP OR LOSS OF

PWR, in alarm

"* Local strainer AP indicating 20 psid

"* ESW header pressure indicating 51 psig

O762 ,Z/ /1

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 86

Given the following conditions:

  • The plant is operating at 60% power.
  • RCS Tavg is on program.
  • PRZ level is on program.
  • The Median Tavg input to PRZ level fails high.
  • The operator places LK-459, PRZ Master Level Controller, in MANUAL.

In order to control PRZ level at program level, the operator should be directed to control

PRZ level at ...

a. 36%.

b. 41%.

c. 46%.

d. 51%.

ANSWER:

c. 46%.

// , I,izt

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 87

Given the following conditions:

  • The plant is operating at 90% power.
  • Control Bank 'C' Rod D-4, located at the edge of the core near PR NI N-43, has

slipped to approximately 6 steps off the bottom of the core and appears to be stuck.

Which of the following parameters would be the LEAST AFFECTED by this rod

misalignment?

a. Quadrant Power Tilt Ratio calculations

b. Power Range Nuclear Instrument indications

c. Axial Flux Difference indications

d. Core Exit Thermocouple temperature indications

ANSWER:

c. Axial Flux Difference indications

IZ-1 9 D5S fi //,

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 88

Given the following conditions:

  • The unit is in a Refueling Outage.
  • A spent fuel assembly is attached to the manipulator crane.
  • A failure of the Reactor Vessel permanent cavity seal ring causes cavity level to drop

approximately 3" every minute.

  • The Refueling Crew is in the process of placing the assembly in the Reactor Vessel

when a Loss of Off-Site Power occurs.

Upon the loss of off-site power there is NO means for ...

a. making up to the cavity.

b. monitoring radiological levels inside Containment.

c. monitoring the reactivity condition of the core.

d. placing this fuel assembly in the vessel.

ANSWER:

d. placing this fuel assembly in the vessel.

07 6,3664P/9/."

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 89

FRP-J. 1, "Response to High Containment Pressure," monitors the status of the ESW

Booster Pumps.

Which of the following is the concern if ESW Booster pumps fail to start while high

containment pressure conditions exist?

a. ESW Pump runout

b. Flooding of safety equipment in containment

c. Loss of containment cooling capability

d. Radioactivity release to the environment

ANSWER:

d. Radioactivity release to the environment

&ý WV/E/VE/K-3VA92

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 90

Given the following conditions:

  • A plant cooldown is in progress.
  • All three (3) RCPs are operating.
  • ALB-010-8-5A, "CMPTR ALARM RX COOLANT," is in alarm and investigation

reveals RCP 'C' Radial Bearing Temp has exceeded the warning alarm setpoint and

is approaching the alarm limit of 2200 F.

  • Seal injection to each RCP is approximately 10 gpm.

Which of the following conditions would direct opening the RCP No. 1 seal bypass valve

in accordance with OP-100, "Reactor Coolant System?"

a. * RCS pressure 850 psig

  • RCP 'A' No. 1 seal leakoff 1.2 gpm

o RCP 'B' No. 1 seal leakoff 0.9 gpm

  • RCP 'C' No. 1 seal leakoff 1.3 gpm

b. o RCS pressure 1060 psig

  • RCP 'A' No. 1 seal leakoff 0.7 gpm
  • RCP 'B' No. 1 seal leakoff 0.9 gpm
  • RCP 'C' No. 1 seal leakoff 0.8 gpm

c. * RCS pressure 640 psig

o RCP 'A' No. 1 seal leakoff 1.2 gpm

  • RCP 'B' No. 1 seal leakoff 1.1 gpm
  • RCP 'C' No. 1 seal leakoff 1.1 gpm

d. e RCS pressure 1110 psig

o RCP 'A' No. 1 seal leakoff 1.2 gpm

  • RCP 'B' No. 1 seal leakoff 0.8 gpm
  • RCP 'C' No. 1 seal leakoff 0.9 gpm

ANSWER:

a. e RCS pressure 850 psig

"* RCP 'A' No. 1 seal leakoff 1.2 gpm

"* RCP 'B' No. 1 seal leakoff 0.9 gpm

"* RCP 'C' No. 1 seal leakoff 1.3 gpm

/4/ 0 63 K/, m

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 91

Which of the following sets of conditions would NOT permit waiving the Independent

Verification (IV) requirement for a clearance removal?

TIME TO AREA

DOSE RATE PERFORM IV TEMPERATURE

a. 120 mRem/hr 6 minutes 105°F

b. 180 mRem/hr 3 minutes 115 0F

c. 90 mRem/hr 4 minutes 125 0F

d. 60 mRem/hr 3 minutes 135 0F

ANSWER:

b. 180 mRem/hr 3 minutes 115°F

/,,ý q

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 92

Which of the following is the basis for the Technical Specification limit of 31 gpm on

Controlled Leakage?

a. Sufficiently low to ensure early detection of additional leakage

b. Allows limited known leakage with the ability to detect additional leakage

c. Ensures safety injection flow is greater than that analyzed for a LOCA

d. Keeps dose to a small fraction of limits in the event of a SGTR or steam line break

ANSWER:

c. Ensures safety injection flow is greater than that analyzed for a LOCA

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 93

The unit is operating at 100% power.

If 125 VDC Bus 1A-SA deenergizes due to a fault on the bus ...

a. the reactor will trip due to an undervoltage (UV) trip of Train SA reactor trip

breaker.

the reactor will trip due to a shunt trip of Train SA reactor trip breaker.

b.

an undervoltage trip signal will NOT be capable of opening Train SA reactor trip

breaker.

d. a shunt trip signal will NOT be capable of opening Train SA reactor trip breaker.

ANSWER:

d. a shunt trip signal will NOT be capable of opening Train SA reactor trip breaker.

LOD / /<t D,

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 94

A waste gas release is in progress when the WPB Stack 5 PIG radiation monitor, REM

lWV-3546, exceeds the high alarm setpoint.

Which of the following describes how the release will be automatically terminated?

a. Key-operated 3WG-229, Waste Gas Decay Tanks E & F to Plant Vent, CLOSES

b. 3WG-230, Gas Decay Tanks to Plant Vent Isolation Valve, CLOSES

c. Filtered Exhaust Fans, E-46, E-47, E-48, and E-49 TRIP

d. Running Waste Gas Compressor TRIPS

ANSWER:

a. Key-operated 3WG-229, Waste Gas Decay Tanks E & F to Plant Vent, CLOSES

0 06b 0A 2, (6

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 95

Given the following conditions:

"* The plant is at 22% power during a Technical Specification 3.0.3 required shutdown.

"* Source Range Channel N-31 has been declared inoperable as a result of failing to

meet Operational Test Criteria of MST-I0169.

"* The LEVEL TRIP switch has been placed in the BYPASS position per OWP-RP-19,

"Source Range N-3 1."

"* The I&C Supervisor states that both control and instrument power must be removed

from the N-31 drawer to replace a bistable module.

Should the control and instrument power fuses be removed AND why or why not?

a. NO, because removing both fuses will cause the reactor to trip when the fuses are

removed.

b. YES, provided only the instrument power fuses are removed or the reactor will

trip when power is reduced below P-10.

c. NO, because removing both fuses will cause the reactor to trip when power is

reduced below P-6.

d. YES, because removing both fuses will NOT cause a reactor trip to occur.

ANSWER:

c. NO, because removing both fuses will cause the reactor to trip when power is

reduced below P-6.

SD/5, S 0o3

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 96

1CS-50, Letdown to VCT/Demin, automatically bypasses the CVCS Demineralizers

when ...

0

a. TE-143, LP Letdown Temperature, exceeds 135 F to prevent an inadvertent

dilution event

b. TE-143, LP Letdown Temperature, exceeds 135 0 F to prevent damage to the

demineralizer resin

0

c. TE-144, Letdown HX Outlet Temperature, exceeds 135 F to prevent an

inadvertent dilution event

0

d. TE-144, Letdown HX Outlet Temperature, exceeds 135 F to prevent damage to

the demineralizer resin

ANSWER:

b. TE-143, LP Letdown Temperature, exceeds 135°F to prevent damage to the

demineralizer resin

1-11

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 97

Given the following conditions:

  • During Mode 3 operations, a large break LOCA occurred concurrently with a loss of

offsite power.

  • Both EDGs started and loaded.
  • The BOP operator secured all running AFW pumps with all SG levels at 55%.
  • SI has NOT been reset and offsite power has NOT been restored.

If SG narrow range levels decrease to the following levels,

SG LEVEL

A 22%

B 17%

C 27%

which of the following describes the expected AFW pump operation?

a. * MDAFW Pump 1A-SA running

b. * MDAFW Pump lA-SA running

& MDAFW Pump lB-SB running

c. * MDAFW Pump 1A-SA secured

d. * MDAFW Pump 1A-SA secured

ANSWER:

c. e MDAFW Pump lA-SA secured

"* MDAFW Pump lB-SB secured

"* TDAFW Pump running

,c14 D06/,U,0 ,2-

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 98

Given the following conditions:

"* A small break LOCA occurred and SI has been terminated in accordance with EPP

008, "SI Termination."

"* SI Reinitiation criteria has been met.

Which of the following are the correct order of actions to be taken?

a. Close the BIT valves, open the charging line isolation valves, and verify the

normal miniflow isolation valves open

b. Open the BIT valves, close the charging line isolation valves, and verify the

normal miniflow isolation valves open

c. Close the charging line isolation valves, open the BIT valves, and verify the

normal miniflow isolation valves closed

d. Open the charging line isolation valves, close the BIT valves, and verify the

normal miniflow isolation valves closed

ANSWER:

c. Close the charging line isolation valves, open the BIT valves, and verify the

normal miniflow isolation valves closed

/10 kA// fDAt/ 1 t 6 0

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 99

In accordance with the EOP User's Guide, which of the following is an approved

pre-emptive action?

a. Isolating AFW to a ruptured SG and closing the Main Steam Isolation Valve from

the ruptured SG immediately upon completion of the Immediate Actions of

PATH-1

b. Throttling AFW to supply all three (3) SGs at 100 KPPH per SG with one AFW

pump during the performance of EPP-FRP-S. 1, "Response to Nuclear Power

Generation - ATWS," with all SG narrow range levels below 5%

c. Restoring AFW to a faulted SG after it has been isolated to establish the maximum

cooldown rate available during the performance of PATH-2

d. Throttling AFW flow to all three (3) SGs at 50 KPPH per SG to maintain intact

SG levels between 25% and 50% immediately upon completion of the Immediate

Actions of PATH- I

ANSWER:

d. Throttling AFW flow to all three (3) SGs at 50 KPPH per SG to maintain intact

SG levels between 25% and 50% immediately upon completion of the Immediate

Actions of PATH- 1

Harris Nuclear Plant

August 2002 - RO Exam

ANSWER KEY

QUESTION: 100

Given the following conditions:

"* Following a large break LOCA, SI has been reset.

"* The crew has just completed the performance of EPP-010, "Transfer to Cold Leg

Recirculation," and have transitioned back to PATH-1.

"* A loss of offsite power occurs following the transition to PATH- 1.

Core cooling will be ...

a. automatically re-established when the Emergency Diesel Generator output breaker

closes.

b. automatically re-established upon completion of the Sequencer loading.

c. lost until the operator re-opens the RHR suction valves after the Emergency Diesel

Generator output breaker closes.

d. lost until the operator restarts the RHR pumps after the Emergency Diesel

Generator output breaker closes.

ANSWER:

d. lost until the operator restarts the RHR pumps after the Emergency Diesel

Generator output breaker closes.

0 3f3/4 o'-

Harris Nuclear Plant

RO Written Reference

RO SUPPLIED REFERENCES

AOP-036, Attachment 6 ............ SG Wide Range Level vs. SG Pressure

OP- 107, Attachment 19 ............. Makeup Concentration Limits

OP- 141, Attachment 5 ............... Cooling Tower Cold Weather Operation

Curves A- 11-6 through -I I ......... Differential and Integral Rod Worth Curves

Curves C-I1-I through -3 ........... Power Defect Curves

Steam Tables

SAFE SHUTDOWN FOLLOWING A FIRE

Attachment 6

Sheet 1 of 1

SG Wide Range Level vs. SG Pressure

1Im

85

I

8 70

2 KA

t5

2(0

300 2E 4D] wo w0O 90a O(0 103 11w0 12Ei

0 O

SG Pressre PSIG)

-END ATTACHMENT 6

AOP-036 Rev. 19 Page 99 of 105

Attachment 19

Sheet 1 of 9

Makeup Concentration Limits

These tables were derived per calculation HNP-I/INST-1056 using the equations of

Attachment 3 and provide a means to select an appropriate RWMU Total

Makeup Flow Rate (Q) which will yield a desired blended flow boron concentration when

matched to the BAT concentration and the Boric Acid Flow Rate span of 1 to 30 gpm.

It is necessary to select lower RWMU Total Makeup Flow Rates when high boron

concentrations are required because the Boric Acid Flow is limited by system configuration to

a maximum of 33 gpm. This maximum Boric Acid Flow capability however is not used as the

basis for these tables because it is necessary to allow some margin for possible system

performance degradation. Therefore a maximum Boric Acid Flow of 30 gpm is used as the

basis for the following tables.

Each sheet of the tables is applicable to a specific RWMU Total Makeup Flow Rate (Q).

The maximum ppm results have been rounded down to the nearest whole number and the

minimum ppm results have been rounded up to the nearest whole number.

OP-107 Rev. 42 Page 245 of 256

Attachment 19

Sheet 2 of 9

Makeup Concentration Limits for: RWMU Total Makeup Flow Rate Q = 120gpm

To determine the maximum boron concentration for which makeup will be

reliable at 120 gpm total flow, select the BAT boron concentration which is equal

to or lower than current BAT boron concentration.

2. To determine the minimum boron concentration for which makeup will be reliable

at 120 gpm total flow, select the BAT boron concentration which is equal to or

higher than current BAT boron concentration.

BAT BORON MAXIMUM PPM FOR 120 GPM MINIMUM PPM FOR 120 GPM

CONCENTRATION (PPM) MAKEUP MAKEUP

(30 GPM BA FLOW) (1 GPM BA FLOW)

7000 1750 59

7050 1762 59

7100 1775 60

7150 1787 60

7200 1800 60

7250 1812 61

7300 1825 61

7350 1837 62

7400 1850 62

7450 1862 63

7500 1875 63

7550 1887 63

7600 1900 64

7650 1912 64

7700 1925 65

7750 1937 65

OP-107 Rev. 42 Page 246 of 256

Attachment 19

Sheet 3 of 9

Makeup Concentration Limits for: RWMU Total Makeup Flow Rate Q = 10Ogpm

1. To determine the maximum boron concentration for which makeup will be

reliable at 110 gpm total flow, select the BAT boron concentration which is equal

to or lower than current BAT boron concentration.

2. To determine the minimum boron concentration for which makeup will be reliable

at 110 gpm total flow, select the BAT boron concentration which is equal to or

higher than current BAT boron concentration.

BAT BORON MAXIMUM PPM FOR 110 GPM MINIMUM PPM FOR 110 GPM

CONCENTRATION (PPM) MAKEUP MAKEUP

(30 GPM BA FLOW) (1 GPM BA FLOW)

7000 1909 64

7050 1922 65

7100 1936 65

7150 1950 65

7200 1963 66

7250 1977 66

7300 1990 67

7350 2004 67

7400 2018 68

7450 2031 68

7500 2045 69

7550 2059 69

7600 2072 70

7650 2086 70

7700 2100 70

7750 2113 71

OP-107 Rev. 42 Page 247 of 256

Attachment 19

Sheet 4 of 9

Makeup Concentration Limits for: RWMU Total Makeup Flow Rate Q = 100qpm

To determine the maximum boron concentration for which makeup will be

reliable at 100 gpm total flow, select the BAT boron concentration which is equal

to or lower than current BAT boron concentration.

2. To determine the minimum boron concentration for which makeup will be reliable

at 100 gpm total flow, select the BAT boron concentration which is equal to or

higher than current BAT boron concentration.

BAT BORON MAXIMUM PPM FOR 100 GPM MINIMUM PPM FOR 100 GPM

CONCENTRATION (PPM) MAKEUP MAKEUP

(30 GPM BA FLOW) (1 GPM BA FLOW)

7000 2100 70

7050 2115 71

7100 2130 71

7150 2145 72

7200 2160 72

7250 2175 73

7300 2190 73

7350 2205 74

7400 2220 74

7450 2235 75

7500 2250 75

7550 2265 76

7600 2280 76

7650 2295 77

7700 2310 77

7750 2325 78

OP-I07 Rev. 42 Page 248 of 256

Attachment 19

Sheet 5 of 9

Makeup Concentration Limits for: RWMU Total Makeup Flow Rate Q = 90.pm

1. To determine the maximum boron concentration for which makeup will be

reliable at 90 gpm total flow, select the BAT boron concentration which is equal

to or lower than current BAT boron concentration.

2. To determine the minimum boron concentration for which makeup will be reliable

at 90 gpm total flow, select the BAT boron concentration which is equal to or

higher than current BAT boron concentration.

BAT BORON MAXIMUM PPM FOR 90 GPM MINIMUM PPM FOR 90 GPM

CONCENTRATION (PPM) MAKEUP MAKEUP

(30 GPM BA FLOW) (1 GPM BA FLOW)

7000 2333 78

7050 2350 79

7100 2366 79

7150 2383 80

7200 2400 80

81

2416

7250

7300 2433 82

7350 2450 82

7400 2466 83

7450 2483 83

7500 2500 84

7550 2516 84

7600 2533 85

7650 2550 85

7700 2566 86

7750 2583 87

IOP-107 Rev. 42 Page 249 of 256

Attachment 19

Sheet 6 of 9

Makeup Concentration Limits for: RWMU Total Makeup Flow Rate Q = 80opm

1. To determine the maximum boron concentration for which makeup will be

reliable at 80 gpm total flow, select the BAT boron concentration which is equal

to or lower than current BAT boron concentration.

2. To determine the minimum boron concentration for which makeup will be reliable

at 80 gpm total flow, select the BAT boron concentration which is equal to or

higher than current BAT boron concentration.

BAT BORON MAXIMUM PPM FOR 80 GPM MINIMUM PPM FOR 80 GPM

CONCENTRATION (PPM) MAKEUP MAKEUP

(30 GPM BA FLOW) (1 GPM BA FLOW)

7000 2625 88

7050 2643 89

7100 2662 89

7150 2681 90

7200 2700 90

7250 2718 91

7300 2737 92

7350 2756 92

7400 2775 93

7450 2793 94

7500 2812 94

7550 2831 95

7600 2850 95

76501 2868 96

7700 2887 97

7750 2906 97

Page 250 of 256 1

OP-107 Rev. 42

Attachment 19

Sheet 7 of 9

Makeup Concentration Limits for: RWMU Total Makeup Flow Rate Q = 70pm

1. To determine the maximum boron concentration for which makeup will be

reliable at 70 gpm total flow, select the BAT boron concentration which is equal

to or lower than current BAT boron concentration.

2. To determine the minimum boron concentration for which makeup will be reliable

at 70 gpm total flow, select the BAT boron concentration which is equal to or

higher than current BAT boron concentration.

BAT BORON MAXIMUM PPM FOR 70 GPM MINIMUM PPM FOR 70 GPM

CONCENTRATION (PPM) MAKEUP MAKEUP

(30 GPM BA FLOW) (1 GPM BA FLOW)

7000 3000 100

7050 3021 101

7100 3042 102

7150 3064 103

7200 3085 103

7250 3107 104

7300 3128 105

7350 3150 105

7400 3171 106

7450 3192 107

7500 3214 108

7550 3235 108

7600 3257 109

7650 3278 110

7700 3300 110

7750 3321 111

OP-107 Rev. 42 Page 251 of 256

Attachment 19

Sheet 8 of 9

Makeup Concentration Limits for: RWMU Total Makeup Flow Rate Q = 60rm

1. To determine the maximum boron concentration for which makeup will be

reliable at 60 gpm total flow, select the BAT boron concentration which is equal

to or lower than current BAT boron concentration.

2. To determine the minimum boron concentration for which makeup will be reliable

at 60 gpm total flow, select the BAT boron concentration which is equal to or

higher than current BAT boron concentration.

BAT BORON MAXIMUM PPM FOR 60 GPM MINIMUM PPM FOR 60 GPM

CONCENTRATION (PPM) MAKEUP MAKEUP

(30 GPM BA FLOW) (1 GPM BA FLOW)

7000 3500 117

7050 3525 118

7100 3550 119

7150 3575 120

7200 3600 120

7250 3625 121

7300 3650 122

7350 3675 123

7400 3700 124

7450 3725 125

7500 3750 125

7550 3775 126

7600 3800 127

7650 3825 128

7700 3850 129

7750 3875 130

I OP-107 Rev. 42 Page 252 of 256

Attachment 19

Sheet 9 of 9

Makeup Concentration Limits for: RWMU Total Makeup Flow Rate Q = 50qpm

1. To determine the maximum boron concentration for which makeup will be

reliable at 50 gpm total flow, select the BAT boron concentration which is equal

to or lower than current BAT boron concentration.

2. To determine the minimum boron concentration for which makeup will be reliable

at 50 gpm total flow, select the BAT boron concentration which is equal to or

higher than current BAT boron concentration.

BAT BORON MAXIMUM PPM FOR 50 GPM MINIMUM PPM FOR 50 GPM

CONCENTRATION (PPM) MAKEUP MAKEUP

(30 GPM BA FLOW) (1 GPM BA FLOW)

7000 4200 140

7050 4230 141

7100 4260 142

7150 4290 143

7200 4320 144

7250 4350 145

7300 4380 146

7350 4410 147

7400 4440 148

7450 4470 149

7500 4500 150

7550 4530 151

7600 4560 152

7650 4590 153

7700 4620 154

7750 4650 155

OP-107 Rev. 42 Page 253 of 256

Attachment 5

Sheet I of 1

Cooling Tower Cold Weather Oreration

90

0

w

w 80

(5

a:

a. 70

wH

0

w 60

n

Ia:

w

a 50

z

0

-J

0

0

C- 40

32

30

-30 -20 -10 0 10 20 30 32 40

AMBIENT AIR TEMPERATURE (DEGREES F)

NORMAL OPERATION - COOLING TOWER DEICING GATE VALVES OPEN

U AS IS - COOLING TOWER DEICING GATE VALVES REMAIN AS IS

HALF OPEN - COOLING TOWER DEICING GATE VALVES HALF OPEN

K ABNORMAL OPERATION-'NO CONDENSER HEAT LOAD AREA. IN THIS AREA PERFORM

SECTION 8.6.

Rev. 17 Page 38 of 40

OP-141

HARRIS UNIT 1 CYCLE 11

DIFFERENTIAL AND INTEGRAL

ROD WORTH CONTROL BANKS D and C

MOVING WITH 103 STEP OVERLAP

BOL (0*5 EFPD < 161), HZP, WITH NO XENON

  • - - -r-iIr rr -i--rr i-i-I--F I LA I I I I ill I I

-18

-1800 ---

I i i i

I

I i

i

I t I I '

II

'

O * m m I L m I I m * m I B * * F m l k T p m L F i m m I m m m m i

-17

-1700 I

. ; .* . i l l- -( - - - -

16

rI&

-1600 t

q . . .

.... . . . . . *m I* Jm Jm .I ,. ) I q * i I r !  !

+/-

-15

-1500 I

-1400

£ J - -

4: -14

-1300 SL  ! -13

-lJ0n

-12

-1200 m

-11 *m

"0 -1100

I -10

-1000

-9 0

-900

C3

0 0

-8

.~ -800 --4

-7

(5 -700

a I

i

LLJ

I-_z -600 I -6

-500 A

-i 1' .5

-400

TFFY El al -4

-300

EFlI

........ -3

F-Tf-F-Til

. -2

-200 1 42l

__ -T-

ILhjiv4 - = I -1

-100

25 PCM/DIV

Im _

I- I

m

I

m

- m

_i_

.11111

m m i

-

I

I___tt-41

I I Im I-

0

0

-0 180 200 220 240

0

5 STEPS/DIV

20 40 [ 1-4-ý 60 80 100 120 140 160

0 103 231

BANK D

128 231

BANK C

CURVE NO. A-11-6 REV NO. 0

ORIGINATOR - a.C,.,P DATE 10/1;2/0

SUPERVISOR DATE

SUPERINTENDENT - ( e0/1'

SHIFT OPERATIONS DATE

HARRIS UNIT 1 CYCLE 11

DIFFERENTIAL AND INTEGRAL

ROD WORTH CONTROL BANKS D and C

MOVING WITH 103 STEP OVERLAP

MOL (161 < EFPD < 334), HZP, WITH NO XENON

-1800 - * -18

-1700

ml F -17

4-4-4-ýi i

Zn' -16

-1600 I LL23J ....L..L. I - I - J- J-4--S -4-441-4-4--h.- I-4- -4-4 -H--t-r- I -t- t- - I -,r-t- I r--r I -r-r-r 1-rr-1-- U

I +/-tzttt

. .

t-

.

I E

I ]

I J

I JI II I II

-15

-1500

-1400 Ia I J I d I I * d I * I I I I 1 * I I

-14

-1300

C-)

a

-1200

-1100

m

t -12

-11

-n

m

I.

0

-1000 fl 1111- IN+

-10

-10

r

0

-9 0

-900

-8 0

-800 4 F :1: 1 -

n t-i -J z

-700 *WT T Z I

H:I+/-H:FNHTh2Th. -7

w

tflhiVTIiTI7IIVEIIEBIZIFI+/-Effl+/-EH

I I

I

z -600 Sm

I E i i i {

- f+M-+-* L -5

-500

+ThATh-VMYW 11 -4

-400

J4-1-H sd-M-4-H -3

-300

-k , -f--f- f

-2

-200

-1

-100

25 PCMIDIV

0

0 20 40 60 80 100 120 140 160 180 200 220 240

5 STEPS/DIV

0 103 231

BANK D

128 231

BANK C

CURVE NO. A-11-7 REV NO. 0

ORIGINATOR t. _, DATE /Q/;S7O/"5

SUPERVISOR DATE /, -zt-o\

SUPERINTENDENT

SHIFT OPERATIONS DATE -

HARRIS UNIT 1 CYCLE 11

DIFFERENTIAL AND INTEGRAL

ROD WORTH CONTROL BANKS D and C

MOVING WITH 103 STEP OVERLAP

EOL (334 < EFPD -507), HZP, WITH NO XENON

-2000 I--.' ZZ IZIt I

r -20

FI -'U.-) r -19

-1900 f I I

it 1r

-1800 I -18

a

I

  • WflV -17

-1700

iii i-tm

I-- ffi

i-4-4-H-1-h- -- 16

-1600

-- 15

-1500'

--14 "m

-1400'

E -1300

TF1]T[TLLWiI I! I

11

I -13'::

m

0

CL

I -1200 H U-

4-4:1 H-+++/-+/-+/-A--

-d

H I

-12 -z z

o -1100. q II* II I I r Z I *

--o00

III".'

o *1000* tI

0 09

O

-900. 3: t rt 3! L

--4

S-800

a 1 mm J

-8

w

z -700

. . I11.1 '-7 (

-6

-600 ÷

S-L -i - -

--5

-500

-400 4Z1 17 I Ii'

--3

-300 -4

-i-i--V A- "-2

-200 1 *  ! I I L ,

4 ----**

  • I

9 T . Cl -;. . I i I 1

-1

-100

25 PCMIDIV

0

-lit- t27Z

  • 0

0 20 40 60 80 100 120 140 160 180 200 220 240

5 STEI

103 231

0

BANK D

231

128

BANK C

CURVE NO. A-11-8 REV NO. 0

ORIGINATOR DATE /0/25?/0O

SUPERVISOR DATE ,z/.t/o4

SUPERINTENDENT- D

SHIFT OPERATIONS LDATE 16SLA

HARRIS UNIT 1 CYCLE 11

DIFFERENTIAL AND INTEGRAL

ROD WORTH CONTROL BANKS D and C

MOVING WITH 103 STEP OVERLAP

BOL (O:5 EFPD - 161), RFP, EQUILIBRIUM XENON

-1700 -17

-1600 -16

-1500 -15

I I

-1400

-1300

4 14 a, 4

-14

-13

-1200 -12 2

"1

-11 m

m:

E -1100

z

"I

0 -1000 -10~

CL

I-"

-900 0

0 -9

-8

r'C -800 0

1 4V I~, 4-+ 1c 11 ti f-+ -i

I-

-700 4 +-~ I

z-

Z II I 1 4+44H

I I I

-600 -4II-f -6

-500

-400 -4

-300 -3

-200 -2

-100 -1

25 PCMIDIV

0 0

0 20 40 60 80 100 120 140 160 180 200 220 240

5 STEPS/DIV

0 103 231

aaa

BANK D

128 231

BANK C

CURVE NO. A-11-9 REV NO. 0

ORIGINATOR " it, DATE /O/Z5/0/

SUPERVISOR DATE T

SUPERINTENDENT- DATE/ 1/0/

SHIFT OPERATIONS DATE /

HARRIS UNIT 1 CYCLE 11

DIFFERENTIAL AND INTEGRAL

ROD WORTH CONTROL BANKS D and C

MOVING WITH 103 STEP OVERLAP

MOL (161 < EFPD 5 334), HFP, EQUILIBRIUM XENON

-1800 18

.1'

T I ] + I I I I I F J. J* r

. . I

.. p I

II 111111;

!l I I I f I 4 -.

-1700

-1600 I t I .. I1 - JLL. I WA.... .1 - ....L...A..d

rnsmmmmm *4

SI- I -

IIj'!i,

  • 11 -1-ti--nm
  • -16

Fj!fII:K7TJILJ IJULJJIL

I r I I I t F I I I I I I I P . i

-1500

-1400

I I

711 111

I

VLLIJAA...LLIJIIIL

T I I

StJ

171ThT1Z2U1D2Z122ZF1

I

"-15

-14

-1300 -13

3i 1--

-1200 r7 HIfmn:i:H14izlAH -12 m

7i TYI.IAAJILLIIIILL

m

- (a

0. 4-TTT44444 -1 z

! 1 ! 1T-HH

I [ 1

-1100

' ' ll1 -

i I I I * I I E I

I' EXiiIH iii~i *-10 r

0 -1000

Aq K

0

C

-900

Ft . -9 0

C

cc * -8 0

-n

_j -800 -4

< K

r

cc

w

-700

zI

z -600 -

-500 I

t --7

--6

t 1T_IiI

T.............LI ni, .

-400 Z

-300 IaT _ _ _ _~~~~

Th*

I

--2

-200 wT__.J

7j:j -1

-100

25 PCM/DIV St -- I

- -

1-i--K-i-il

1**'-"t

--

'II

0

0

0 20 40 60 80 100 120 140 160 180 200 220 240

5 STEPS/DIV

0 103 231

BANK D

128 231

BANK C

CURVE NO. A-11-10 REV NO. 0

ORIGINATOR a-, DATE /./:Tht/0o1

SUPERVISOR DATE /z,/z V'

SUPERINTENDENT

SHIFT OPERATIONS ,DATEI

HARRIS UNIT 1 CYCLE 11

DIFFERENTIAL AND INTEGRAL

ROD WORTH CONTROL BANKS D and C

MOVING WITH 103 STEP OVERLAP

i

EOL (334 < EFPD < 507), HFP, EQUILIBRIUM XENON

jt -21

-2100

-2000. - -20

H-P -H- H -f-f-H I-i--I- -- 19

-1900 -

Hqq:q YE -- 18

-1800 I f-I-i-i- IFT117}71111111[IL.hI.t1li.1JLJ Hcizi+/-tzrr;

-1700

fl I 1! I A-H -17

-li I

-16

-1600

S

F l

SrI I I * & I I I I

w~I I I I I * I I I I

................I I I

I I -

m

-1500

E -1400

  • l ** l I I I I I a T1TVYIIIIII]I[I]III!.......LLLLLIILLLLLLLIJItIt

I I, I I I ] l I I } I I ---I I I-I-tm-

Il I q i l

I "-152

a 1/2ttrtr -14m

.i -13z

&-1300 ----- - - - -- - - - - - - - - -

--I

-1200 -8

0

3: -1100

H-

H -110

O -1000 -0 -7

--9 -.

-j

.< -900

cr

a -800 ----------------------- ~~J-- t-.z

$


1!I -8 "*

C

LLI

--7 :33

z -700 7:- l


op

I I I --6 *

-600 -t--- _l

-500 m - I ....-. I I . Err

--5

'-4

-400

I 'I --3

-300 I I

-2

-200

EFF ---- -r t

--1

-100 1W#

JZ~fz4 fz22 m-i it

25 PCM/DIV

0"

0 20 40 60 80 100 120 140 160 180 200 220 240

5 STEPS/DIV

0 103 231

BANK D

128 231

BANK C

CURVE NO. A-11-11 REV NO. 0

ORIGINATOR 6 /9,/L DATE 10125101

SUPERVISOR c DATE /Z?,,

SUPERINTENDENT

SHIFT OPERATIONS DATE / k

HARRIS UNIT 1 CYCLE 11

POWER DEFECT vs. POWER LEVEL

for VARIOUS BORON CONCENTRATIONS

BOL (05 EFPD < 161)

0

-200

-400

-600

-800

E

0

a.

F

CL -1000

U

' -1200

0_

0

-1400

.-j

I,-

-1600 2100 ppm

1800 ppm

1500 ppm

-1800

1200 ppm

-2000

900 ppm

-2200

20 PCMIOIV

-2400

0 20 40 60 80 100

1 0/ 0/DIV

POWER LEVEL (PERCENT)

CURVE NO. C-11-1 REV NO. 0

0

ORIGINATOR DATE 1 /-)5-/o/

SUPERVISOR DATE ZZ,2/29y,/

SUPERINTENDENT

SHIFT OPERATIONS DATE 16 Q

HARRIS UNIT 1 CYCLE 11

POWER DEFECT vs. POWER LEVEL

for VARIOUS BORON CONCENTRATIONS

MOL (161 < EFPD - 334)

0

-200

-400

-600

-800

E

I-. -1000

uJ

U.

u,

a

-1200

Lu

0

a -1400

-1

0I-

-1600

-1800

1800 ppm

1500 ppm

-2000

1200 ppm

900 ppm

-2200

20 PCMI]IV 600 ppm

-2400

0 20 40 60 80 100

1 %mIV

POWER LEVEL (PERCENT)

C-11-2 REV NO. 0

CURVE NO.

ORIGINATOR -,.,, 2-&. DATE /0. -? -/5

SUPERVISOR DATE

SUPERINTENDENT

SHIFT OPERATIONS, j DATE

HARRIS UNIT 1 CYCLE 11

POWER DEFECT vs. POWER LEVEL

for VARIOUS BORON CONCENTRATIONS

EOL (334 < EFPDP 507)

0

-200

-400

-600

-800

-1000

E -1200

-1400

w

LA

-1600

0

CLl -1800

0

a

-2000

I

0

-2200

-2400

-2600

1200 ppm

-2800 900 ppm

600 ppm

-3000 300 ppm

0 ppm

-3200

20 PCMJDIV

-3400

0 20 40 60 80 100

1 %/DIV

POWER LEVEL (PERCENT)

CURVE NO. C-11-3 REV NO. 0

ORIGINATOR - DATE /O/a?5-/01

SUPERVISOR c-DATE ,o/-?/oi

SUPERINTENDENT

SHIFT OPERATIONS - DATE

Attachment 5

Sheet 1 of 1

loolina Tower Cold Weather Oneration

90

U

w

w 80

(9

UJ 70

w

0

0 60

Iz

0

CD

z 50

0

-J

L

0 40

0

C,

32

30

-30 -20 -10 0 10 20 30 32 40

AMBIENT AIR TEMPERATURE (DEGREES F)

Li NORMAL OPERATION - COOLING TOWER DEICING GATE VALVES OPEN

U AS IS - COOLING TOWER DEICING GATE VALVES REMAIN AS IS

H HALF OPEN - COOLING TOWER DEICING GATE VALVES HALF OPEN

ABNORMAL OPERATION-"NO CONDENSER HEAT LOAD" AREA. IN THIS AREA PERFORM SECTION 8.6.

ac_

AfptQ

OP-141 Rev. 17 Page 38 of 40