LR-N16-0125, Response to RIS 2016-09, Preparation of Scheduling of Operator Licensing Examination

From kanterella
Jump to navigation Jump to search
Response to RIS 2016-09, Preparation of Scheduling of Operator Licensing Examination
ML16190A255
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 07/08/2016
From: Grover F
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N16-0125, RIS-16-009
Download: ML16190A255 (3)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 0 I>SEG Nucleat LLC 10 CFR 55.40 LR-N16-0125 JUL 0 8 2016 U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 2055-0001 Hope Creek Generating Station Unit 1 Renewed Facility Operating License Number NPF-57 Docket Number 50-354

Subject:

RESPONSE TO RIS 2016-09, PREPARATION AND SCHEDULING OF OPERATOR LICENSING EXAMINATIONS Attached is the completed FORM 536, Operator Licensing Examination Data, for Initial Licensed Operator Examinations through Calendar Year (CY) 2021 and Generic Fundamentals Examinations through CY 2018.

There are no regulatory commitments in this correspondence.

Should there be any questions regarding this matter, please contact Mark Shaffer, Hope Creek Operations Training Manager at 856-339-1820.

Sincerely, ako Attachment- Form 536, Operator Licensing Examination Data

USNRC Document Control Desk LR -N16-0125 Page 2 cc: Mr. Daniel Dorman, Regional Administrator- Region I, NRC Ms. Carleen Parker, Project Manager - US NRC Justin Hawkins, NRC Senior Resident Inspector- Hope Creek (X24)

Mr. Patrick Mulligan, Chief Bureau of Nuclear Engineering New Jersey Department of Environmental Protection PO Box 420 Trenton, NJ 08625 Mr. Thomas MacEwen, Hope Creek Commitment Tracking Coordinator (H02)

Mr. Lee Marabella - Corporate Commitment Tracking Coordinator (N21)

Mr. Robert Boesch - Manager, Hope Creek Training

NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3160-0131 EXPIRES: 10/31/2017 (05-2016) Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This


.:;:.0:VRFU$q(ll


** 4J! - - - -- -- ------ - - --

information collection is used to plan budgets and resources for operator examinations. Send

$ OPERATOR LICENSING comments regarding burden estimate to the FOIA, Privacy, and Information Collections Branch (T-5 EXAMINATION DATA F53), U.S. Nuclear Regulatory Commission, Washington, DC20555-0001, or by e-mail to lnfocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs,

\""" NEOB,10202, (3150-0131), Office of Management and Budget; Washington, DC 20503. If a means

      • ""+< used to impose an information collection does not display a currenlly valid OMB control number, the NRC may not conduct or sponsor, and a person Is not required to respond to, the information collection.

FACILITY NRC REGION Hope Creek Generating Station 1 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2018 CY2019 CY2020 CY2021 ESTIMATED NUMBER OF LICENSEE-PREPARED 1 1 0 1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0 0 0 0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2018 CY2019 CY2020 CY2021 NUMBER OF REACTOR OPERATORS 5 4 5 NUMBER OF SENIOR REACTOR OPERATORS- INSTANT 8 5 5 NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE 0 2 2 NUMBER OF SENIOR REACTOR OPERATORS- LIMITED PROPOSED DATES PRIMARY DATE 2/12/18 8/12/19 2/8/21 ALTERNATE DATE 2/19/18 8/19/19 2/15/21

c. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2017 CY 2018 PROPOSED -

NUMBER MARCH SEPTEMBER MARCH SEPTEMBER ESTIMATED NUMBER OF 13 CANDIDATES NRC FORM 536 (05-2016)