Original Question for Modified Question 80
ML21041A173
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/01/2019
From: Thomas Setzer
Operations Branch I
To:
Public Service Enterprise Group
Shared Package
ML19007A361 List:
References
EPID L-2019-OLL-0016
Download: ML21041A173 (1)


Text

Hope Creek 2019 SRO Q#80 (Original Question)

Given:

  • Pressure transmitter BB-PT-N078A has failed its surveillance calibration check
  • The failure is non-conservative Which one of the following describes the action(s) required by Technical Specifications?

A. Trip the inoperable channel in one trip system within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

B. Trip the inoperable trip system within one hour and be in at least HOT SHUTDOWN within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

C. Trip the inoperable channel in one trip system within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

D. Commence a normal shutdown within one hour and be in at least Startup within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, Hot Shutdown with 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and Cold Shutdown within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Answer: A