Hope Creek 2019 SRO Q#80 (Original Question)
Given:
Pressure transmitter BB-PT-N078A has failed its surveillance calibration check The failure is non-conservative Which one of the following describes the action(s) required by Technical Specifications?
A.
Trip the inoperable channel in one trip system within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
B.
Trip the inoperable trip system within one hour and be in at least HOT SHUTDOWN within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
C.
Trip the inoperable channel in one trip system within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
D.
Commence a normal shutdown within one hour and be in at least Startup within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, Hot Shutdown with 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and Cold Shutdown within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
Answer:
A