Forwards BVPS Unit 1,Cycle 13 Startup Physics Test Rept. Rept Summarizes Applicable Physics Testing Performed to Verify Adequacy of Cycle 13 Reload Core Design
ML20216J950
Person / Time
Site: Beaver Valley
Issue date: 04/13/1998
From: Jain S
DUQUESNE LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20216J954 List:
References
L-98-070, L-98-70, NUDOCS 9804220042
Download: ML20216J950 (1)


Text

e 4

- s gg Beave Valley Power Station Shippingport. PA 15077-0004 SUSHIL C. JAIN (412) 393-5512 Senior Vice President Fax (724) 643-8069 Nuclear Services Nuclear Power Division April 13, 1998 L-98-070 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001

Subject:

Beaver Valley Power Station, Unit No.1 Docket No. 50-334, License No. DPR-66 Cycle 13 Startup Test Report Enclosed is a copy of the Cycle 13 Stanup Test Repon provided in accordance with Technical Specification 6.9.1.3. This repon summarizes the applicable physics testing performed to verify the adequacy of the Cycle 13 reload core design. The results of each test performed indicate that the measured parameters are within the specified acceptance criteria.

Sincerely, Sushil C. Jain c: Mr. D. M. Kern, Sr. Resident inspector Mr. H. J. Miller, NRC Region I Administrator Mr. D. S. Brinkman, Sr. Project Manager Mr. W. P. Dornsife, Director BRP/DEP Mr. M. P. Murphy (BRP/DEP)

,..C1 \ \

9804220042 980413 PDR ADOCK 05000334 ,9 DEllVERillG PDR s Q QUALIT.Y

~

ENER6Y I