L-19-234, Transmittal of Emergency Plan, Revision 54

From kanterella
Jump to navigation Jump to search
Transmittal of Emergency Plan, Revision 54
ML19294A045
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 10/09/2019
From: Payne F
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML19294A052 List:
References
L-19-234
Download: ML19294A045 (2)


Text

FENOC' Perry Nuclear Power Plant P.O. Box 97 10 Center Road Perry, Ohio 44081 FirstEnergy Nuclear Operating Company Frank Payne 440-280-5382 Vice President October 9, 2019 10CFR50.4, 10CFR50.54(q), 10CFR72.44(f)

L-19-234 United States Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555-0001 Perry Nuclear Power Plant Docket No. 50-440, License No. NPF-58 EMERGENCY PLAN FOR PERRY NUCLEAR POWER PLANT DOCKET No. 50-440 Pursuant to 10CFR50.4, enclosed is a summary of changes for the Perry Nuclear Power Plant (PNPP) Emergency Plan Revision 54.

The changes have been reviewed in accordance with 10CFR50.54(q), and it has been determined that the changes do not result in a reduction of the effectiveness of the Emergency Plan. It has also been determined that the Plan, as changed, continues to meet the standards of 10CFR50.47(b) and 10CFR50 Appendix E.

There are no regulatory commitments contained in this submittal. If there are any questions or if additional information is required, please contact Mr. Glendon Burnham, Manager, Site Regulatory Compliance, at (440) 280-7538.

SincerJ /1 t r-Rrr-Frank R. Payne Vice President

Enclosure:

Summary of Changes

Perry Nuclear Power Plant L-19-234 Page 2 cc: NRC Document Control Desk NRC Resident Inspector NRC Projeqt Manager . -

Llnited States Environmental Protection Agency, Mr. Steve Ostrodka, Chief.

Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards NRC Regional Response Center NRC Region Ill Regional Administrator - Incident Response Center