Perry Nuclear Power Plant FENC10 FENOC-PO. Box 97 Center Road FirstEnergy Nuclear Operating Company Perry Ohio 44081 Ernest J. Harkness 440-280-5382 Vice President Fax: 440-280-8029 August 15, 2014 L-14-254 10 CFR 71.95 Mr. Mark Lombard, Director Director, Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTN: Document Control Desk

SUBJECT:

Perry Nuclear Power Plant Docket No. 50-440, License No. NPF-58 10 CFR 71.95 Report on the TN-RAM Package

Reference:

AREVA TN letter to NRC, dated June 18, 2014, Report Pursuant to 10CFR71.95(a)(3) and (b) of As-Built Discrepancies in the TN-Ram Packaging Relative to Certificate of Compliance No. 9233 (ML14171A358)

By the referenced letter, Areva TN Americas submitted a report to the NRC providing information required by 10CFR71.95(a)(3) and (b) with respect to Certificate of Compliance (CoC) No. 9233, Revision 11, for the Model No. TN-RAM Package, Docket No. 71-9233. The circumstances described were applicable to licensed users of the package.

FirstEnergy Nuclear Operating Company (FENOC) was notified by Areva TN Americas of the as-built discrepancies by letter dated June 19, 2014. FENOC is reporting pursuant to 10 CFR 71.95(a)(3) and (b) instances in whi6h the conditions of approval in CoC 9233 for the TN-RAM packaging may not have been observed when making shipments from the Perry Nuclear Power Plant (PNPP). FENOC records show that PNPP made a total of 6 shipments using the TN-Ram packaging in the time period October 3, 2007, through January 15, 2008, to ship spent fuel pool cleanout waste without incident. These shipments are listed in Attachment 1.

Areva TN Americas has evaluated the identified discrepancies and determined they were non-safety significant. Areva TN Americas has submitted a CoC revision request to include revisions necessary to correct the as-built discrepancies. The NRC approved this request by letter dated July 3, 2014 (ML14188A896).

Perry Nuclear Power Plant L-14-254 Page 2 of 2 There are no regulatory commitments contained in this letter. If there are any questions or if additional information is required, please contact Mr. Nicola Conicella, Manager, Regulatory Compliance at 440-280-5415.

Sincerely, Ernest J. Harkness

Attachment:

List of PNPP shipments using the TN-RAM Packaging cc: NRC Regional Administrator NRC Resident Inspector NRC Project Manager

Attachment 1 L-14-254 List of PNPP shipments using the TN-RAM Package

List of PNPP Shipments Using The TN-RAM Package Shipment Date Cask COC User Shipment Id User Manifest Id 10/03/2007 USA/9233/B(U) 1007-13478 07-1037 10/12/2007 USA/9233/B(U) 1007-13490 07-0001 10/26/2007 USA/9233/B(U) 1007-13498 07-0002 12/03/2007 USA/9233/B(U) 1207-13532 07-0003 12/12/2007 USA/9233/B(U) 1207-13540 07-0004 01/15/2008 USA/9233/B(U) 0108-13557 08-0000 Note: All shipments were made to Barnwell Waste Management Facility; Operated by Chem-Nuclear Systems LLC; Barnwell SC