Report of Facility Changes, Tests and Experiments for the Period of June 1, 2012 to May 31, 2014
ML14182A573
Person / Time
Site: Beaver Valley
Issue date: 07/01/2014
From: Emily Larson
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-14-202
Download: ML14182A573 (1)


Text

Beaver Valley Power Station FENOC' P.O. Box4 Shippingport, PA 15077 FirstEnergy Nuclear Operating Company Eric A. Larson 724-682-5234 Site Vice President Fax: 724-643-8069 July 1, 2014 L-14-202 10 CFR 50.59(d)(2)

ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

SUBJECT:

Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 Report of Facility Changes, Tests and Experiments In accordance with 10 CFR 50.59(d)(2), that requires a report of facility changes, tests, and experiments, FirstEnergy Nuclear Operating Company reports that there were no evaluations completed pursuant to 10 CFR 50.59 during the reporting period of June 1, 2012 to May 31, 2014 for the Beaver Valley Power Station, Unit No. 1.

There are no regulatory commitments contained in this letter. If there are any questions or if additional information is required, please contact Mr. Thomas A. Lentz, Manager-Fleet Licensing, at (330) 315-6810.

Sincerely, rr;t--

Eric A. Larson cc: NRC Region I Administrator NRC Senior Resident Inspector NRR Project Manager Director BRP/DEP Site BRP/DEP Representative