November 21, 2017 FENOC'

~

FirstEnergy Nuclear Operating Company Richard D. Bologna Site Vice President L-17-114 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

SUBJECT:

Beaver Valley Power Station, Unit No. 2 Docket No. 50-412, License No. NPF-73 Report of Facility Changes, Tests and Experiments Beaver Valley Power Station P.O. Box 4 Shippingport, PA 15077 10 CFR 50.59(d)(2) 724-682-5234 Fax: 724-643-8069 FirstEnergy Nuclear Operating Company hereby provides notice that for Beaver Valley Power Station, Unit No. 2, there are no evaluations to report in accordance with 10 CFR 50.59(d)(2), for the period of April 2, 2016 to October 4, 2017.

There are no regulatory commitments contained in this letter. If there are any questions or if additional information is required, please contact Mr. Thomas A. Lentz, Manager -

Fleet Licensing, at (330) 315-6810.

Sincerely, Richard D. Bologna cc: