IR 05000456/2019002

From kanterella
Jump to navigation Jump to search
Reissue - Braidwood Station, Units 1 and 2 - Integrated Inspection Report 05000456/2019002 and 05000457/2019002
ML19266A637
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 09/20/2019
From: Karla Stoedter
NRC/RGN-III
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
Shared Package
ML19266A656 List:
References
IR 2019002
Download: ML19266A637 (19)


Text

September 20, 2019

SUBJECT:

REISSUEBRAIDWOOD STATION, UNITS 1 AND 2INTEGRATED INSPECTION REPORT 05000456/2019002 AND 05000457/2019002

Dear Mr. Hanson:

The U.S. Nuclear Regulatory Commission (NRC) identified the need to reissue NRC Inspection Report 05000456/2019002 and 05000457/2019002 dated July 26, 2019 (ADAMS Accession Number ML19210E060). Specifically, the basis for closing the unresolved item regarding the qualification of Limit Switch 2RY456 following the removal of a conduit seal required clarification to better describe the NRCs basis for closing the item. This unresolved item appears in the Inspection Findings section of this report. As a result, the NRC has reissued the report in its entirety with that section revised to correct the error.

On June 30, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Braidwood Station, Units 1 and 2. On July 2, 2019, the NRC inspectors discussed the results of this inspection with Ms. M. Marchionda, Site Vice President, and other members of your staff.

The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Karla Stoedter, Chief Engineering Branch 2 Division of Reactor Safety

Docket Nos. 05000456 and 05000457 License Nos. NPF-72 and NPF-77

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000456 and 05000457

License Numbers:

NPF-72 and NPF-77

Report Numbers:

05000456/2019002 and 05000457/2019002

Enterprise Identifier: I-2019-002-0059

Licensee:

Exelon Generation Company, LLC

Facility:

Braidwood Station, Units 1 and 2

Location:

Braceville, Illinois

Inspection Dates:

April 01, 2019 to June 30, 2019

Inspectors:

D. Kimble, Senior Resident Inspector

J. Robbins, Reactor Inspector

P. Smagacz, Resident Inspector

Approved By:

Karla Stoedter, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Braidwood Station, Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000456,05000457/2 018012-01 Qualification of Conduit Seal Removal for 2RY456 Limit Switch 71111.21N Closed

PLANT STATUS

Unit 1 began the inspection period operating at full power. With the exception of minor reductions in power to support scheduled testing activities or small load changes requested by the transmission system dispatcher, the unit remained operating at or near full power for the entire inspection period.

Unit 2 began the inspection period operating at full power. With the exception of minor reductions in power to support scheduled testing activities or small load changes requested by the transmission system dispatcher, the unit remained operating at or near full power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515 Appendix D, Plant Status and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Summer Readiness Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated summer readiness of offsite and alternate alternating current (AC) power systems during the week ending June 22, 2019

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial alignment verifications of the following systems/trains:

(1)1B Emergency Diesel Generator (EDG) with 1A EDG out of service for maintenance during the week ending April 6, 2019 (2)1A Containment Spray (CS) with 1B CS out of service for planned maintenance during the week ending June 22, 2019

71111.05Q - Fire Protection

Quarterly Inspection (IP Section 03.01) (4 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Fuel Handling Building, Fire Zone 12.1-0 during the week ending April 6, 2019 (2)2A Residual Heat Removal (RH) Pump Room, Fire Zone 11.2A-2 during the week ending April 27, 2019
(3) Unit 1 Containment Pipe Penetration Area, Fire Zone 11.3-1 during the week ending April 27, 2019 (4)2A EDG Room, Fire Zone 18.2-2 during the week ending June 22, 2019

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 02.02a.) (1 Sample)

The inspectors evaluated internal flooding mitigation vulnerability and protection for the following plant area:

(1) Unit 2 'B' Essential Service Water (SX) Pump Room, Auxiliary Building Elevation 330' during the weeks ending May 18 through June 1, 2019

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors conducted an evaluation of licensed operator performance in the Control Room during various observations of on-watch Operations shift crews during the weeks ending April 27 through June 29, 2019

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a graded simulator scenario for a crew of licensed operators on June 25, 2019

71111.12 - Maintenance Effectiveness

Quality Control (IP Section 02.02) (1 Sample)

The inspectors evaluated the licensee's maintenance and quality control activities associated with the following equipment performance issue:

(1) The failure of control power fuses for the 2A EDG as documented in Issue Report (IR)

4252176 during the weeks ending June 8 through June 29, 2019 Routine Maintenance Effectiveness Inspection (IP Section 02.01)

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:

(1) A 1B Auxiliary Feedwater (AF) Pump performance issue associated with diesel fuel oil seepage into the crankcase oil system as documented in IR 4238259 during the weeks ending April 20 through June 29, 2019
(2) An issue with the cubicle cooler fan motor bearing service life and run times for the chemical and volume control pump cubicle coolers as documented in IRs 4244994,

===4244974, and 4244975 during the weeks ending May 4 through June 29, 2019

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01)===

The inspectors evaluated the licensee's assessment of risk associated with the following planned and emergent work activities:

(1) Planned 2-year maintenance on the 1A EDG as document in Work Order (WO)

===4692594 during the week ending April 6, 2019

(2) Emergent maintenance on the 1B AF Pump as documented in WO 4908688 during the week ending April 13, 2019
(3) Starting battery capacity maintenance and testing for the 2B AF Pump as documented in WO 1836579 during the weeks ending April 20 through April 27, 2019
(4) Unit 1 System Auxiliary Transformer (SAT) 142-1 maintenance inspections as documented in WO 1945815 during the week ending May 11, 2019
(5) Ground isolation activities on direct current (DC) Bus 111 as documented in WO 4920701 during the weeks ending May 18 through June 29, 2019
(6) Emergent maintenance activities surrounding the failure of DC control power fuses for the 2A EDG as documented in IR 4252176 during the week ending June 1, 2019

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 02.02)===

The inspectors performed evaluations of the following issues with respect to equipment operability and/or functionality:

(1) The licensee's decision to isolate primary water to the 1C Reactor Coolant Pump (RCP) seal package standpipe as documented in IR 4224618 during the weeks ending April 20 through April 27, 2019
(2) Evaluation of excessive run time hours for the bearings on the 1B CV Cubicle Cooler fan motor as documented in IR 4244994 during the weeks ending May 4 through June 29, 2019
(3) Evaluation of the minimum bus voltages for the Unit 1 SAT outage window as documented in IR 4247579 during the week ending May 11, 2019
(4) Evaluation of intermittent grounds on DC Bus 111 as documented in IR 4248185 during the weeks ending May 18, 2019 through June 29, 2019
(5) Evaluation of degraded conditions for the valve 2AF005G manual loader (2HK-AF036B) as documented in IR 4249077 during the week ending May 18, 2019
(6) Evaluation of degraded performance associated with valve 2SX124A as documented in IR 4253330 during the weeks ending June 8 through June 15, 2019

71111.19 - Post-Maintenance Testing

Post Maintenance Test Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the adequacy of the following post maintenance testing activities:

(1) Functional and operational testing for 1B SX Pump following planned oil cooler maintenance during the weeks ending May 18 through May 25, 2019
(2) Functional and operational testing for check valve 2CC070B following disassembly and inspection as documented in WO 1939834 during the weeks ending May 18 through May 25, 2019
(3) Functional testing following investigation and repair of a high temperature connection associated with 1AP27E, Division 1, during the week ending May 25, 2019
(4) Functional testing following repairs on the cubicle cooler flow indicator sensing line for the 1B CS pump during the week ending June 22, 2019

===71111.21N - Design Bases Assurance Inspection (Programs)

The inspectors conducted the following activities:

Select Sample Components to Review - Risk Significant/Low Design (Inside/Outside Containment) (IP Section 02.01) (1 Partial)

(1)

(Partial)

The inspectors reviewed actions to close Unresolved Item 05000456,05000457/2018012-01; "Qualification of Conduit Seal Removal for 2RY456 Limit Switch." These reviews by the inspectors did not constitute a separate stand-alone inspection sample. Rather, they were an integral part of the original inspection sample for this previously documented item.

71111.22 - Surveillance Testing

The inspectors evaluated the performance and conduct of the following surveillance testing activities:

Surveillance Tests (other) (IP Section 03.01)===

(1)2BwOSR 3.8.1.2-1: 2A Diesel Generator Semiannual Operability Surveillance - Timed Fast Start during the week ending April 13, 2019 (2)1BwOS MS-Q1: Unit 1 Main Condenser Steam Dump Operability Surveillance - Timed Fast Opening during the week ending April 13, 2019 (3)2BwOSR5.5.8.SI-10B: Group A Inservice Test (IST) Requirements for 2B Safety Injection Pump during the week ending June 22,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors conducted a verification of the performance indicators listed below through a sample of the licensee's submitted data:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (April 1, 2018, through March 31, 2019)
(2) Unit 2 (April 1, 2018, through March 31, 2019)

MS06: Emergency AC Power Systems (IP Section 02.05) (2 Samples)

(1) Unit 1 (April 1, 2018, through March 31, 2019)
(2) Unit 2 (April 1, 2018, through March 31, 2019)

MS07: High Pressure Injection Systems (IP Section 02.06) (2 Samples)

(1) Unit 1 (April 1, 2018, through March 31, 2019)
(2) Unit 2 (April 1, 2018, through March 31, 2019)

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends involving multiple issues with the loose parts monitoring systems on both units that might be indicative of a more significant safety issue during the weeks ending May 3, 2019, through June 29,

INSPECTION RESULTS

Observation: Loose Parts Monitoring System Reliability 71152 The inspectors performed a review of plant issues, particularly those entered into the licensees CAP, associated with issues and failures of the loose parts monitoring systems on both units. The loose parts monitoring system is described in Section 4.4.6.4 of the stations Updated Final Safety Analysis Report (UFSAR) as a system that detects and alarms upon sensing unusual noises that might indicate a metallic loose part within the reactor coolant system. Operability requirements for the system in operational Modes 1 and 2 are set forth in Section 3.3.d of the stations Technical Requirements Manual (TRM).

During their review, the inspectors noted that there have been several loose parts monitoring system failures during the current operating cycles on both units. Currently, each unit has three (of a total of twelve available) loose parts monitoring system channels in a degraded and unavailable status, and due to accessibility issues with the equipment locations in containment each degraded channel will remain unavailable for the remainder of the units operating cycle. Given the systems overall significance, as indicated by its UFSAR and TRM descriptions and requirements, additional review of system maintenance practices may be warranted.

Additionally, during the course of the most recent inspection period, the inspectors noted that a spurious Unit 1 loose parts monitoring system alarm was frequently being received at the same time each morning on most days of the week over a several week period. Following discussions with licensee management regarding the vulnerabilities associated with spurious alarms causing the operating crews to become desensitized, this particular loose parts monitoring system problem was traced to a computer coding issue within the systems software and eliminated.

Unresolved Item (Closed)

Qualification of Conduit Seal Removal for 2RY456 Limit Switch 05000456,05000457/2018012-01 71111.21N

Description:

The inspectors identified an unresolved item concerning the removal of the conduit seal from a NAMCO EA180 limit switch for 2RY456 Pressurizer Power Operated Relief Valve (PORV). Position indication of PORVs is a requirement outlined in NUREG-0737, Clarification of TMI Action Plan Requirements, Enclosure 1, Post-TMI Requirements for Operating Reactors, Item II.D.3, Valve Position Indication. These requirements were incorporated prior to license issuance and are part of Braidwoods current licensing basis.

The NAMCO EA 180 switch in question is located in containment and could be exposed to a high temperature steam environment during an accident. These switches were originally qualified for this environment by Westinghouse. As documented in the Regulatory Guide 1.89 discussion in Braidwood UFSAR, Appendix A, (Page A1.89-1): For Westinghouse Nuclear Steam System Supplier Class lE equipment, Westinghouse has met the requirements of IEEE Std 323-1974, "IEEE Standard for Qualifying Class lE Equipment for Nuclear Power Generating Stations" including the Nuclear Power Engineering Committee (NPEC) Position Statement of July 24, 1975, and Regulatory Guide 1.89, Revision 0, by providing an appropriate combination of the following: type testing, operating experience, qualification by analysis, and on-going qualification. This commitment has been satisfied by NRC review and approval of Westinghouse Topical Report WCAP-8587.

Subsequently, the licensee performed an analysis supporting removal of seals without affecting the environmental qualification.

Initially, the inspectors identified differences in the licensees analysis and the IEEE Std 323-1974 guidance and viewed this as a potential performance deficiency. After discussions with NRR technical staff and legal staff, the inspectors determined that no performance deficiency existed based on the following information:

In November 1974, Regulatory Guide 1.89, Qualification of Class IE Equipment for Nuclear Power Plants, was issued. Within this document it states:

The procedures described in IEEE Std 323-1974, "IEEE Standard for Qualifying Class IE Equipment for Nuclear Power Generating Stations,"' dated February 28, 1974, for qualifying Class IE equipment for service in light-water-cooled and gas-cooled nuclear power plants are generally acceptable and provide an adequate basis for complying with design verification requirements of Criterion III of Appendix B to 10 CFR Part 50 to verify adequacy of design under the most adverse design conditions subject to the following:

This regulatory guide was revised in 1984, following issuance of 10 CFR 50.49, Environmental Qualification of Electric Equipment Important to Safety for Nuclear Power Plants. The revised guide contains a similar statement:

The procedures described by IEEE Std 323-1974, "IEEE Standard for Qualifying Class IE Equipment for Nuclear Power Generating Stations,"' are acceptable to the NRC staff for satisfying the Commission's regulations pertaining to the qualification of electric equipment for service in nuclear power plants to ensure that the equipment can perform its safety functions subject to the following:

Currently, Regulatory Guide 1.89 remains available for use and the view that IEEE Std 323-1974 represents an acceptable method for satisfying the Commission's regulations pertaining to the qualification of electric equipment for service in nuclear power plants remains unchanged.

The guidance found in IEEE Std 323-1974 is detailed and prescriptive. One issue that arose during inspection was not if IEEE Std 323-1974 represented an acceptable approach, but rather is it possible to meet requirements set forth in 50.49 and deviate from the guidance contained in IEEE Std 323-1974. With respect to meeting regulatory requirements, while IEEE Std 323-1974 has been endorsed by the NRC with clarification, 50.49 does not invoke any standard directly; i.e. a deviation from the guidance found in IEEE Std 323-1974 does not necessarily mean that a component is non-compliant with 10 CFR 50.49.

The requirements associated with environmental qualification can be found in 10 CFR 50.49. Multiple methods for qualification are identified in 10 CFR 50.49(f) including:

(f) Each item of electric equipment important to safety must be qualified by one of the following methods:
(1) Testing an identical item of equipment under identical conditions or under similar conditions with a supporting analysis to show that the equipment to be qualified is acceptable.
(2) Testing a similar item of equipment with a supporting analysis to show that the equipment to be qualified is acceptable.
(3) Experience with identical or similar equipment under similar conditions with a supporting analysis to show that the equipment to be qualified is acceptable.
(4) Analysis in combination with partial type test data that supports the analytical assumptions and conclusions.

The inspectors concluded that the information provided by the licensee was sufficient to address the inspectors concerns with both 10 CFR 50.49 and 10 CFR 50.59.

Corrective Action Reference(s): AR 4120790 - NRC Question on Environment Qualification Binder Evaluation of Limit Switches

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 2, 2019, the inspectors presented the integrated inspection results to Ms. M. Marchionda, Site Vice President, and other members of the licensee staff.
  • On July 10, 2019, the inspectors presented the closure of Unresolved Item 2018012-01 to Mr. S. MacArtney, General Design Engineering Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

0BwOA ENV-1

Adverse Weather Conditions Unit 0

24

OP-AA-102-102

General Area Checks and Operator Field Rounds

OP-AA-108-107-

1001

Station Response to Grid Capacity Conditions

OP-AA-108-111-

1001

Sever Weather and Natural Disaster Guidelines

OP-BR-102-102-

1001

Augmented Operator Field Rounds

WC-AA-107

Seasonal Readiness

71111.04

BwOP CS-E1

Electrical Lineup - Unit 1 Containment Spray System

Electrical Lineup

BwOP CS-M1

Operating Mechanical Lineup Unit 1

BwOP DG-E2

Electrical Lineup - Unit 1, 1B Diesel Generator

BwOP DG-M2

Operating Mechanical Lineup Unit 1, 1B Diesel Generator

71111.05A

Fire Plans

No. 104; Fire

Zone 11.2A-2

Auxiliary Building 364' Elevation RHR Pump 2A Room

No. 114; Fire

Zone 11.3-1

Auxiliary Building 364' Elevation Unit 1 Containment Pipe

Penetration Area

71111.05Q

No. 104; Fire

Zone 11.2A-2

Auxiliary Building 364' Elevation Residual Heat Removal

Pump 2A Room

No. 114; Fire

Zone 11/3-1

Auxiliary Building 364' Elevation Unit 1 Containment Pipe

Penetration Area

No. 178; Fire

Zone 12.1-0

Fuel Handling Building 401' Elevation

No. 179; Fire

Zone 12.1-0

Fuel Handling Building 426' Elevation

No. 200; Fire

Zone 18.2-2

Auxiliary Building 401' Elevation Diesel Generator 2A &

Switchgear Room Air Shaft

Procedures

BwAP 1110-1

Fire Protection Program System Requirements

BwAP 1110-3

Plant Barrier Impairment Program

BwOP PBI-1

Plant Barrier Control Program

CC-AA-201

Plant Barrier Control Program

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

ER-AA-600-1069

High Risk Fire Area Identification

ER-BR-600-1069

Site List of High Risk Fire Areas - Braidwood Unit 1 and

Unit 2

OP-AA-201-004

Fire Prevention for Hot Work

OP-AA-201-007

Fire Protection System Impairment Control

OP-AA-201-009

Control of Transient Combustible Material

71111.06

0BwOA PRI-8

Auxiliary Building Flooding Unit 0

BwAP 1110-3

Plant Barrier Impairment Program

BwOP PBI-1

Plant Barrier Impairment Program Pre-Evaluated Barrier

Matrix

CC-AA-201

Plant Barrier Control Program

71111.11Q

ER-AA-600

Risk Management

OP-11-101-113-

1006

4.0 Crew Critique Guidelines

OP-AA-101-111-

1001

Operations Standards and Expectations

OP-AA-101-113

Operator Fundamentals

OP-AA-103-102

Watch Standing Practices

OP-AA-103-102-

1001

Strategies for Successful Transient Mitigation

OP-AA-103-103

Operation of Plant Equipment

OP-AA-104-101

Communications

OP-AA-108-107-

1002

Interface Procedure Between BGE/COMED/PECO and

Exelon Generation (Nuclear/Power) for Transmission

Operations

OP-AA-111-101

Operating Narrative Logs and Records

OP-AA-300

Reactivity Management

TQ-AA-10

Systematic Approach to Training Process Description

TQ-AA-150

Operator Training Programs

TQ-AA-155

Conduct of Simulator Training and Evaluation

TQ-AA-201

Examination Security and Administration

TQ-AA-306

Simulator Management

TQ-BR-201-0113

Braidwood Training Department Simulator Examination

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Security Actions

71111.12

Corrective Action

Documents

0881124

Long Range Planning for 1VA06CD Motor Refurbishment

2/16/2009

238259

1AF01PB Crankcase Oil Analysis Degrading Trend

04/10/2019

244974

1VA06SA Vibration Reading Results

04/30/2019

244975

2VA06SA Vibration Reading Results

04/302019

244994

1VA06CD Exceeds Run Time Threshold for Motor Bearings

04/30/2019

Procedures

ER-AA-310-1002

Maintenance Rule Functions - Safety Significant

Classification

ER-AA-320

Maintenance Rule Implementation per NEI 18-10

ER-AA-320-1001

Maintenance Rule 18-10 - Scoping

ER-AA-320-1004

Maintenance Rule 18-10 - Performance Monitoring and

Dispositioning Between (a)(1) and (a)(2)

71111.13

Calculations

BRW-97-0340-E

Battery Duty Cycle and Sizing for the Braidwood Diesel

Driven Auxiliary Feedwater Pumps

Corrective Action

Documents

2667064

Lessons Learned - Unit 1 System Auxiliary Transformer

(SAT) Outage Temporary State Estimator Alarm Setpoint

05/09/2016

235979

Coating Repairs Needed for the 1DG01KA-X2 Lower

Stationary Head

04/03/2019

235981

Coating Repairs Needed for the 1DG01KA-X2 Lower Pact

End Channel Head

04/03/2019

235983

Coating Repairs Needed for the 1DG01KA-X1 Upper Pact

End Channel Head

04/03/2019

235987

Debris Found Inside Stationary Head and Tubesheet

1DG01KA-X2

04/03/2019

235988

Degradation Found During Inspection of 1DG01KA-X1

Upper Stationary Head

04/03/2019

236145

Significant Amount of Oil in Air Sensing Line

04/04/2019

236908

1A Diesel Generator South Fuel Rack Positioner Cable

Broke

04/06/2019

236938

1A Diesel Generator Butterfly Valve Sticking

04/06/2019

238259

1AF01PB Crankcase Oil Analysis Degrading Trend

04/10/2019

240057

Battery Charger Lugs are Distorted on 2AF01EB-A Battery

04/16/2019

247173

ACB 1441 Would Not Close Following SAT Restoration

05/02/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

247555

Ground Connections Corroded

05/08/2019

247567

Unit 1 SAT LCO 4.0 Critique

05/08/2019

247579

Braidwood SAT Outage Restoration Delays

05/08/2019

248106

SAT 142-1 Received Unsatisfactory Doble Test on X3

Bushing

05/10/2019

248185

Direct Current Bus 111 Ground

05/11/2019

Engineering

Evaluations

20474

Evaluation of Single SAT Operation on Unit 1 for 2019

Procedures

1BwOSR 3.8.1.1

Unit 1 Offsite AC Power Availability Surveillance

2BwHS 384-6

Volt ESF Auxiliary Feed Diesel Battery BT2 and BT2

Performance Test

2BwHSR 3.7.5-

BA

2B Diesel Auxiliary Feed Pump Battery Bank B Battery A

(2AF01EB-A) Capacity Test

2BwOS DC-Q4

24V DC Auxiliary Feed Pump 2B Battery Bank A and B

Quarterly Surveillance

BwHP 4006-023

Bus Disconnect Link Relocation on 6900 V SAT Buses

BwHP 4006-059

Operation of the Biddle/AVO Ground Fault Tracer

BwHP 4006-066

DC Bus Ground Location Using the Multi-Amp Battery

Ground-Fault Locator

BwHP 4006-074

Bus Disconnect Link Relocation on 4160 V SAT Buses

BwHS 4002-084

System Auxiliary Transformer Preventative Maintenance

Inspection

BwMP 3100-022

Diesel Generator 2 Year Inspection

BwMP 3200-014

Auxiliary Feedwater Pump Diesel Drive Unit Inspection and

Maintenance

BwOP AP-15

Isolating System Auxiliary Transformer (SAT) 142-1 with Unit

Unit Auxiliary Transformer (UAT) Energized

BwOP AP-20

Restoring System Auxiliary Transformer (SAT 142-2) with

Unit 1 UAT Energized

BwOP AP-54

With SAT 142-1 Isolated, Isolate SAT 142-2 and Restore

SAT 142-1 with Unit 1 UAT Energized

BwOP DC-E2

Electrical Lineup - Unit 1 Operating - 125 Vdc Division 11

ER-AA-330-009

ASME Section XI Repair/Replacement Program

ER-AA-335-015-

VT-2 Visual Examination in Accordance with ASME 2013

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2013

ER-AA-600-1042

On-Line Risk Management

MA-AA-716-230-

1004

Lubricant Sampling Guideline

MA-BR-EM-4-

09070

Diesel Generator Electrical Inspection

OP-AA-108-117

Protected Equipment Program

WC-AA-101-1006

On-Line Risk Management and Assessment

WC-AA-104

Integrated Risk Management

Work Orders

1836579

Volt Auxiliary Feed Battery Bank Capacity Test

(2AF01EB)

04/15/2019

1945815

1AP02E: Preventative Maintenance Inspection of SAT 142-1

05/07/2019

4692594

1DG01KA: 24 Month Inspection of the Diesel Generator

04/01/2019

4693700

1DG01EA: Diesel Generator Exciter Inspection (1A EDG)

04/01/2019

4908688

1AF01PB Crank Case Oil and Filter Change

04/12/2019

20701

DC Bus 111 Ground

05/13/2019

71111.15

Corrective Action

Documents

2667064

Lessons Learned - Unit 1 SAT Outage Temporary State

Estimator Alarm Setpoint

09/09/2016

4194175

1PL01J Alarms Generate DC Bus 111 Ground Alarm

11/12/2018

209879

DC Bus 111 Ground Coming in with 1PL01J Panel Check

01/10/2019

23051

1RF008 Flowrate Trend Anomaly

2/24/2019

24618

1CV179 Cycling Excessively

2/28/2019

28652

1RF009 Elevated Reading

03/12/2019

29675

Unit 1 Floor Drain Sump Channel A Failed - PC002

03/15/2019

244974

1VA06SA Vibration Reading Results

04/30/2019

244975

2VA06SA Vibration Reading Results

04/30/2019

244994

1VA06CD Exceeds Run Time Threshold for Motor Bearings

04/30/2019

247579

Braidwood SAT Outage Restoration Delays

05/08/2019

248185

DC Bus 111 Ground

05/22/2019

249077

2HK-AF036B: Manual Loader for 2AF005G Failed - WO 1893938

05/15/2019

253330

2SX124A is Very Difficult to Operate

05/31/2019

254702

Erratic 2A CV Pump Cubicle Cooler SX Flow Rate

06/05/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Changes

EC 628126

Performance of Cubicle Coolers 1VA06SA and 2VA06SA

with One or Two Fans in Operation

Procedures

1BwOS DC-1a

AAR-125 Vdc ESF Bus Ground

BwOL 3.8.4

LCOAR

DC Sources - Operating Technical Specification LCO 3.8.4

BwOP DC-23-111 125 Vdc Bus 111/113 Ground Detection

ER-AA-321

Administrative Requirements for Inservice Testing

ER-AA-600-1012

Risk Management Documentation

ER-AA-600-1045

Risk Assessments of Missed or Deficient Surveillances

OP-AA-106-101-

1006

Operational Decision Making Process

OP-AA-108-111

Adverse Condition Monitoring and Contingency Planning

OP-AA-108-115

Operability Determinations (CM-1)

71111.19

Corrective Action

Documents

257536

2SI8804B Mechanical and Grease Inspection

06/17/2019

257539

2SI8912B has Inactive Packing Leak

06/17/2019

Procedures

2BwOSR

5.5.8.SI-10B

Group A IST Requirements for 2B Safety Injection Pump

(2SI01PB)

BwOP SX-1

Essential Service Water Pump Startup

BwOP SX-7

Swapping Essential Service Water Pumps

ER-AA-330-001

Section XI Pressure Testing

ER-AA-335-015-

2013

VT-2 Visual Examination in Accordance with ASME 2013

Work Orders

1938834

Disassemble and Inspect 2CC070B

05/14/2019

1939833

2CC9520B Disassemble and Inspect

05/14/2019

1955970

EQ Motor Containment Spray Pump 1B

06/18/2019

4615529

1SX01AB Cooler Inspection and Cleaning

05/16/2019

4838800

Flow Indicator Containment Spray Pump Room Cooler 1B

Outlet

06/18/2019

4889939

ESF Switchgear Room Division 12 Ventilation System Vent

Fan Motor

05/22/2019

4906923

IST for 1CS003B/11B - ASME Surveillance Requirements

for 1CS01PB & Check Valves

06/18/2019

71111.22

Corrective Action

238267

Valve Handle Not Moving Valve Stem Properly

04/10/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

238279

Fuel Oil Leak From Left Bank Fuel Rail

04/10/2019

238284

2PI-DG030A Turbo Air Inlet Pressure Indication is Suspect

04/10/2019

238291

2A EDG Fuel Rack Trip Level Pushbutton Fell off During

EDG Run

04/10/2019

Procedures

1BwOS MS-Q1

Main Steam Dump Valve Stroke Surveillance

2BwOSR 3.8.1.2-

2A Diesel Generator Operability Surveillance

BwOP DG-1

Diesel Generator Alignment to Standby Condition

BwOP DG-11

Diesel Generator Startup and Operation

BwOP DG-12

Diesel Generator Shutdown

Work Orders

4836509

2A Diesel Generator Operability Semi-Annual Surveillance

04/10/2019

4876995

Unit 1 Steam Dump Valve Quarterly Surveillance (Tave

Mode and Above P-8)

04/11/2019

4898251

2A Diesel Generator Operability Monthly Surveillance

04/10/2019

71151

Corrective Action

Documents

236155

Unexpected Unit 2 Loose Parts Alarm

04/04/2019

Miscellaneous

NRC Performance Indicator Data; Mitigating Systems -

Safety System Functional Failures

04/01/2018 -

03/31/2019

NRC Performance Indicator Data; Mitigating Systems -

Mitigating System Performance Index for Emergency

Alternating Current Power

04/01/2018 -

03/31/2019

NRC Performance Indicator Data; Mitigating Systems -

Mitigating System Performance Index for High Pressure

Injection

04/01/2018 -

03/31/2019

Procedures

LS-AA-2001

Collecting and Reporting of NRC Performance Indicator

Data

LS-AA-2080

Monthly Data Elements for NRC Safety System Functional

Failures

LS-AA-2200

Mitigating System Performance Index date Acquisition and

Reporting

71152

Corrective Action

Documents

209142

Unit 2 Loose Parts Alarm

01/08/2019

210587

Unexpected Alarm, Loose Parts

01/14/2019

211151

Trend in Loose Parts Monitoring Issues

07/15/2019

212438

Unexpected Annunciator 2-13-E9, Loose Parts Monitoring

01/20/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

System Trouble

213338

Received Unexpected Annunciator 2-13-E9, Loose Parts

01/23/2019

216074

Unit 2 Loose Parts Alarm

01/31/2019

217622

Unit 1 Loose Parts Alarm

2/05/2019

219216

Unexpected Annunciator: 2-13-E9

2/12/2019

27893

Unit 2 Loose Parts Monitoring System Impact Noise Alarm

Channel 4

03/08/2019

28922

Loose Parts Alarm - Channel 1, 3, 14 - No Abnormal Noises

03/13/2019

232957

Metallic Noise Unit 1 Loose Parts Monitoring System at 1C

SC Lower Narrow Range Level Tap

03/25/2019

233318

Reactor Vessel Head Loose Parts Monitoring System Alarm

Disabled 2VE-LM002

03/26/2019

236155

Unexpected Unit 2 Loose Parts Alarm

04/04/2019

236932

Unexpected Annunciator: 2-13-EP

04/06/2019

237724

Unexpected Unit 1 Loose Parts Alarm

04/09/2019

242027

Unexpected Unit 2 Loose Parts Alarm

04/22/2019

245172

Unexpected Annunciator 1-13-E9

05/01/2019

248952

Need Work Request to Troubleshoot Unit 1 Loose Parts

Monitoring System Channel 1

05/14/2019

250626

Re-Evaluate Loose Parts Monitoring System Oversight

05/21/2019

Miscellaneous

ER-AA-320-1003

Maintenance Rule 18-10 - Failure Definitions

Procedures

BwOP LM-10

Loose Parts Monitoring System Operation and Alarm

Response

BwOP LM-10A1

Loose Parts Monitoring System Alignment

NO-AA-10

Quality Assurance Topical Report (QATR)

OP-AA-108-117

Protected Equipment Program

OP-AA-201-008

Pre-Fire Plan Manual

PI-AA-=125-1001

Root Cause Analysis Manual

PI-AA-120

Issue Identification and Screening Process

PI-AA-125

Corrective Action Program (CAP) Procedure

PI-AA-125-1003

Corrective Action Program Evaluation Manual

4