ML19210E060

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000456/2019002 and 05000457/2019002
ML19210E060
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 07/26/2019
From: Hironori Peterson
Division Reactor Projects III
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2019002
Download: ML19210E060 (19)


See also: IR 05000456/2019002

Text

July 26, 2019

Mr. Bryan C. Hanson

Senior VP, Exelon Generation Company, LLC

President and CNO, Exelon Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT:

BRAIDWOOD STATION, UNITS 1 AND 2INTEGRATED INSPECTION

REPORT 05000456/2019002 AND 05000457/2019002

Dear Mr. Hanson:

On June 30, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

Braidwood Station, Units 1 and 2. On July 2, 2019, the NRC inspectors discussed the results of

this inspection with Ms. M. Marchionda, Site Vice President, and other members of your staff.

The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for

Withholding.

Sincerely,

/RA/

Hironori Peterson, Chief

Branch 3

Division of Reactor Projects

Docket Nos. 05000456 and 05000457

License Nos. NPF-72 and NPF-77

Enclosure:

As stated

cc: Distribution via LISTSERV

ML19210E060

x

SUNSI Review

x

Non-Sensitive

Sensitive

x

Publicly Available

Non-Publicly Available

OFFICE

RIII

RIII

NAME

NShah:bw

HPeterson

DATE

7/25/2019

7/26/2019

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Numbers:

05000456 and 05000457

License Numbers:

NPF-72 and NPF-77

Report Numbers:

05000456/2019002 and 05000457/2019002

Enterprise Identifier: I-2019-002-0059

Licensee:

Exelon Generation Company, LLC

Facility:

Braidwood Station, Units 1 and 2

Location:

Braceville, Illinois

Inspection Dates:

April 01, 2019 to June 30, 2019

Inspectors:

D. Kimble, Senior Resident Inspector

J. Robbins, Reactor Inspector

P. Smagacz, Resident Inspector

Approved By:

Hironori Peterson, Chief

Branch 3

Division of Reactor Projects

2

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at Braidwood Station, Units 1 and 2 in

accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs

program for overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type

Issue Number

Title

Report Section

Status

URI

05000456,05000457/2

018012-01

Qualification of Conduit Seal

Removal for 2RY456 Limit

Switch

71111.21N

Closed

3

PLANT STATUS

Unit 1 began the inspection period operating at full power. With the exception of minor

reductions in power to support scheduled testing activities or small load changes requested by

the transmission system dispatcher, the unit remained operating at or near full power for the

entire inspection period.

Unit 2 began the inspection period operating at full power. With the exception of minor

reductions in power to support scheduled testing activities or small load changes requested by

the transmission system dispatcher, the unit remained operating at or near full power for the

entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors performed plant status activities described in

IMC 2515 Appendix D, Plant Status and conducted routine reviews using IP 71152, Problem

Identification and Resolution. The inspectors reviewed selected procedures and records,

observed activities, and interviewed personnel to assess licensee performance and compliance

with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Summer Readiness Sample (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated summer readiness of offsite and alternate alternating

current (AC) power systems during the week ending June 22, 2019

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial alignment verifications of the

following systems/trains:

(1)

1B Emergency Diesel Generator (EDG) with 1A EDG out of service for maintenance

during the week ending April 6, 2019

(2)

1A Containment Spray (CS) with 1B CS out of service for planned maintenance

during the week ending June 22, 2019

4

71111.05Q - Fire Protection

Quarterly Inspection (IP Section 03.01) (4 Samples)

The inspectors evaluated fire protection program implementation in the following selected

areas:

(1)

Fuel Handling Building, Fire Zone 12.1-0 during the week ending April 6, 2019

(2)

2A Residual Heat Removal (RH) Pump Room, Fire Zone 11.2A-2 during the week

ending April 27, 2019

(3)

Unit 1 Containment Pipe Penetration Area, Fire Zone 11.3-1 during the week ending

April 27, 2019

(4)

2A EDG Room, Fire Zone 18.2-2 during the week ending June 22, 2019

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 02.02a.) (1 Sample)

The inspectors evaluated internal flooding mitigation vulnerability and protection for the

following plant area:

(1)

Unit 2 'B' Essential Service Water (SX) Pump Room, Auxiliary Building Elevation 330'

during the weeks ending May 18 through June 1, 2019

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1)

The inspectors conducted an evaluation of licensed operator performance in the

Control Room during various observations of on-watch Operations shift crews during

the weeks ending April 27 through June 29, 2019

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1)

The inspectors observed and evaluated a graded simulator scenario for a crew of

licensed operators on June 25, 2019

71111.12 - Maintenance Effectiveness

Quality Control (IP Section 02.02) (1 Sample)

The inspectors evaluated the licensee's maintenance and quality control activities

associated with the following equipment performance issue:

(1)

The failure of control power fuses for the 2A EDG as documented in Issue Report (IR)

4252176 during the weeks ending June 8 through June 29, 2019

5

Routine Maintenance Effectiveness Inspection (IP Section 02.01) (2 Samples)

The inspectors evaluated the effectiveness of routine maintenance activities associated with

the following equipment and/or safety significant functions:

(1)

A 1B Auxiliary Feedwater (AF) Pump performance issue associated with diesel fuel

oil seepage into the crankcase oil system as documented in IR 4238259 during the

weeks ending April 20 through June 29, 2019

(2)

An issue with the cubicle cooler fan motor bearing service life and run times for the

chemical and volume control pump cubicle coolers as documented in IRs 4244994,

4244974, and 4244975 during the weeks ending May 4 through June 29, 2019

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's assessment of risk associated with the following

planned and emergent work activities:

(1)

Planned 2-year maintenance on the 1A EDG as document in Work Order (WO)

4692594 during the week ending April 6, 2019

(2)

Emergent maintenance on the 1B AF Pump as documented in WO 4908688 during

the week ending April 13, 2019

(3)

Starting battery capacity maintenance and testing for the 2B AF Pump as

documented in WO 1836579 during the weeks ending April 20 through April 27, 2019

(4)

Unit 1 System Auxiliary Transformer (SAT) 142-1 maintenance inspections as

documented in WO 1945815 during the week ending May 11, 2019

(5)

Ground isolation activities on direct current (DC) Bus 111 as documented in WO 4920701 during the weeks ending May 18 through June 29, 2019

(6)

Emergent maintenance activities surrounding the failure of DC control power fuses for

the 2A EDG as documented in IR 4252176 during the week ending June 1, 2019

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 02.02) (6 Samples)

The inspectors performed evaluations of the following issues with respect to equipment

operability and/or functionality:

(1)

The licensee's decision to isolate primary water to the 1C Reactor Coolant Pump

(RCP) seal package standpipe as documented in IR 4224618 during the weeks

ending April 20 through April 27, 2019

(2)

Evaluation of excessive run time hours for the bearings on the 1B CV Cubicle Cooler

fan motor as documented in IR 4244994 during the weeks ending May 4 through

June 29, 2019

(3)

Evaluation of the minimum bus voltages for the Unit 1 SAT outage window as

documented in IR 4247579 during the week ending May 11, 2019

(4)

Evaluation of intermittent grounds on DC Bus 111 as documented in IR 4248185

during the weeks ending May 18, 2019 through June 29, 2019

(5)

Evaluation of degraded conditions for the valve 2AF005G manual loader (2HK-

AF036B) as documented in IR 4249077 during the week ending May 18, 2019

6

(6)

Evaluation of degraded performance associated with valve 2SX124A as documented

in IR 4253330 during the weeks ending June 8 through June 15, 2019

71111.19 - Post-Maintenance Testing

Post Maintenance Test Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the adequacy of the following post maintenance testing activities:

(1)

Functional and operational testing for 1B SX Pump following planned oil cooler

maintenance during the weeks ending May 18 through May 25, 2019

(2)

Functional and operational testing for check valve 2CC070B following disassembly

and inspection as documented in WO 1939834 during the weeks ending May 18

through May 25, 2019

(3)

Functional testing following investigation and repair of a high temperature connection

associated with 1AP27E, Division 1, during the week ending May 25, 2019

(4)

Functional testing following repairs on the cubicle cooler flow indicator sensing line for

the 1B CS pump during the week ending June 22, 2019

71111.21N - Design Bases Assurance Inspection (Programs)

The inspectors conducted the following activities:

Select Sample Components to Review - Risk Significant/Low Design (Inside/Outside

Containment) (IP Section 02.01) (1 Partial)

(1)

(Partial)

The inspectors reviewed actions to close Unresolved Item

05000456,05000457/2018012-01; "Qualification of Conduit Seal Removal for 2RY456

Limit Switch." These reviews by the inspectors did not constitute a separate stand-

alone inspection sample. Rather, they were an integral part of the original inspection

sample for this previously documented item.

71111.22 - Surveillance Testing

The inspectors evaluated the performance and conduct of the following surveillance testing

activities:

Surveillance Tests (other) (IP Section 03.01) (3 Samples)

(1)

2BwOSR 3.8.1.2-1: 2A Diesel Generator Semiannual Operability Surveillance - Timed

Fast Start during the week ending April 13, 2019

(2)

1BwOS MS-Q1: Unit 1 Main Condenser Steam Dump Operability Surveillance -

Timed Fast Opening during the week ending April 13, 2019

(3)

2BwOSR5.5.8.SI-10B: Group A Inservice Test (IST) Requirements for 2B Safety

Injection Pump during the week ending June 22, 2019

7

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors conducted a verification of the performance indicators listed below through a

sample of the licensee's submitted data:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04) (2 Samples)

(1)

Unit 1 (April 1, 2018, through March 31, 2019)

(2)

Unit 2 (April 1, 2018, through March 31, 2019)

MS06: Emergency AC Power Systems (IP Section 02.05) (2 Samples)

(1)

Unit 1 (April 1, 2018, through March 31, 2019)

(2)

Unit 2 (April 1, 2018, through March 31, 2019)

MS07: High Pressure Injection Systems (IP Section 02.06) (2 Samples)

(1)

Unit 1 (April 1, 2018, through March 31, 2019)

(2)

Unit 2 (April 1, 2018, through March 31, 2019)

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1)

The inspectors reviewed the licensees corrective action program for potential

adverse trends involving multiple issues with the loose parts monitoring systems on

both units that might be indicative of a more significant safety issue during the weeks

ending May 3, 2019, through June 29, 2019.

INSPECTION RESULTS

Observation: Loose Parts Monitoring System Reliability

71152

The inspectors performed a review of plant issues, particularly those entered into the

licensees CAP, associated with issues and failures of the loose parts monitoring systems on

both units. The loose parts monitoring system is described in Section 4.4.6.4 of the stations

Updated Final Safety Analysis Report (UFSAR) as a system that detects and alarms upon

sensing unusual noises that might indicate a metallic loose part within the reactor coolant

system. Operability requirements for the system in operational Modes 1 and 2 are set forth in

Section 3.3.d of the stations Technical Requirements Manual (TRM).

During their review, the inspectors noted that there have been several loose parts monitoring

system failures during the current operating cycles on both units. Currently, each unit has

three (of a total of twelve available) loose parts monitoring system channels in a degraded

and unavailable status, and due to accessibility issues with the equipment locations in

containment each degraded channel will remain unavailable for the remainder of the units

operating cycle. Given the systems overall significance, as indicated by its UFSAR and TRM

descriptions and requirements, additional review of system maintenance practices may be

warranted.

8

Additionally, during the course of the most recent inspection period, the inspectors noted that

a spurious Unit 1 loose parts monitoring system alarm was frequently being received at the

same time each morning on most days of the week over a several week period. Following

discussions with licensee management regarding the vulnerabilities associated with spurious

alarms causing the operating crews to become desensitized, this particular loose parts

monitoring system problem was traced to a computer coding issue within the systems

software and eliminated.

Unresolved Item

(Closed)

Qualification of Conduit Seal Removal for 2RY456 Limit

Switch

05000456,05000457/2018012-01

71111.21N

Description: The inspectors identified an unresolved Item concerning the removal of the

conduit seal of a NAMCO EA180 limit switch for the 2RY456 Pressurizer Power Operated

Relief Valve (PORV). Position indication of PORVs is a requirement outlined in NUREG-

0737, Clarification of TMI Action Plan Requirements, Enclosure 1, Post-TMI Requirements

for Operating Reactors, Item II.D.3, Valve Position Indication. These requirements were

incorporated prior to license issuance and are part of Braidwoods current licensing basis.

These switches are located in containment and could be exposed to a high temperature

steam environment during an accident. These switches were originally qualified for this

environment by Westinghouse. As documented in the Regulatory Guide 1.89 discussion in

UFSAR, Appendix A, (Page A1.89-1), For Westinghouse Nuclear Steam System Supplier

Class lE equipment, Westinghouse has met the requirements of IEEE-323-1974, IEEE

Standard for Qualifying Class lE Equipment for Nuclear Power Generating Stations including

the Nuclear Power Engineering Committee (NPEC) Position Statement of July 24, 1975, and

Regulatory Guide 1.89, Revision 0, by providing an appropriate combination of the following:

type testing, operating experience, qualification by analysis, and on-going qualification. This

commitment has been satisfied by NRC review and approval of Westinghouse Topical Report

WCAP-8587.

Subsequently, the licensee performed an analysis that supported the removal of seals

associated with the conduit attachment to the limit switch without affecting its environmental

qualification. The inspectors were concerned that the subsequent analysis did not align with

detailed guidance located within IEEE-323-1974.

Initially, the inspectors viewed this lack of alignment as a potential performance deficiency.

After discussions with NRR technical staff and legal staff, the inspectors determined that no

performance deficiency existed. The basis for this conclusion was that 10 CFR 50.49,

Environmental Qualification of Electric Equipment Important to Safety for Nuclear Power

Plants, does not currently invoke any specific standard. The information contained within the

licensee's UFSAR, when viewed as a historical reference, includes information about IEEE- 323-1974 because this information describes how equipment was originally qualified.

However, the requirements pertaining to IEEE-323-1974 were sunset upon the issuance of

the Final Rule, 50.49 (see Federal Register (FR), 48 FR 2733, Jan. 21, 1983, as amended at

49 FR 45576). As a result, no performance deficiency was identified.

Corrective Action Reference(s): AR 4120790 - NRC Question on Environment Qualification

Binder Evaluation of Limit Switches

9

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On July 2, 2019, the inspectors presented the integrated inspection results to

Ms. M. Marchionda, Site Vice President, and other members of the licensee staff.

On July 10, 2019, the inspectors presented the closure of Unresolved Item 2018012-01

to Mr. S. MacArtney, General Design Engineering Manager, and other members of the

licensee staff.

10

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

0BwOA ENV-1

Adverse Weather Conditions Unit 0

124

OP-AA-102-102

General Area Checks and Operator Field Rounds

16

OP-AA-108-107-

1001

Station Response to Grid Capacity Conditions

7

OP-AA-108-111-

1001

Sever Weather and Natural Disaster Guidelines

18

OP-BR-102-102-

1001

Augmented Operator Field Rounds

3

WC-AA-107

Seasonal Readiness

21

71111.04

BwOP CS-E1

Electrical Lineup - Unit 1 Containment Spray system

Electrical Lineup

4

BwOP CS-M1

Operating Mechanical Lineup Unit 1

12

BwOP DG-E2

Electrical Lineup - Unit 1, 1B Diesel Generator

6

BwOP DG-M2

Operating Mechanical Lineup Unit 1, 1B Diesel Generator

17

71111.05A

Fire Plans

No. 104; Fire

Zone 11.2A-2

Auxiliary Building 364' Elevation RHR Pump 2A Room

1

No. 114; Fire

Zone 11.3-1

Auxiliary Building 364' Elevation Unit 1 Containment Pipe

Penetration Area

1

71111.05Q

No. 104; Fire

Zone 11.2A-2

Auxiliary Building 364' Elevation Residual Heat Removal

Pump 2A Room

1

No. 114; Fire

Zone 11/3-1

Auxiliary Building 364' Elevation Unit 1 Containment Pipe

Penetration Area

1

No. 178; Fire

Zone 12.1-0

Fuel Handling Building 401' Elevation

1

No. 179; Fire

Zone 12.1-0

Fuel Handling Building 426' Elevation

1

No. 200; Fire

Zone 18.2-2

Auxiliary Building 401' Elevation Diesel Generator 2A &

Switchgear Room Air Shaft

0

Procedures

BwAP 1110-1

Fire Protection Program System Requirements

42

BwAP 1110-3

Plant Barrier Impairment program

38

BwOP PBI-1

Plant Barrier Control program

12

CC-AA-201

Plant Barrier Control Program

12

11

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

ER-AA-600-1069

High Risk Fire Area Identification

4

ER-BR-600-1069

Site List of High Risk Fire Areas - Braidwood Unit 1 and Unit

2

0

OP-AA-201-004

Fire Prevention for Hot Work

16

OP-AA-201-007

Fire Protection System Impairment Control

0

OP-AA-201-009

Control of Transient Combustible Material

23

71111.06

0BwOA PRI-8

Auxiliary Building Flooding Unit 0

9

BwAP 1110-3

Plant Barrier Impairment Program

38

BwOP PBI-1

Plant Barrier Impairment Program Pre-Evaluated Barrier

Matrix

3

CC-AA-201

Plant Barrier Control Program

12

71111.11Q

ER-AA-600

Risk Management

7

OP-11-101-113-

1006

4.0 Crew Critique Guidelines

10

OP-AA-101-111-

1001

Operations Standards and Expectations

22

OP-AA-101-113

Operator Fundamentals

13

OP-AA-103-102

Watch Standing Practices

18

OP-AA-103-102-

1001

Strategies for Successful Transient Mitigation

2

OP-AA-103-103

Operation of Plant Equipment

1

OP-AA-104-101

Communications

4

OP-AA-108-107-

1002

Interface Procedure Between BGE/COMED/PECO and

Exelon Generation (Nuclear/Power) for Transmission

Operations

12

OP-AA-111-101

Operating Narrative Logs and Records

15

OP-AA-300

Reactivity Management

13

TQ-AA-10

Systematic Approach to Training Process Description

5

TQ-AA-150

Operator Training Programs

18

TQ-AA-155

Conduct of Simulator Training and Evaluation

9

TQ-AA-201

Examination Security and Administration

17

TQ-AA-306

Simulator Management

9

TQ-BR-201-0113

Braidwood Training Department Simulator Examination

22

12

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Security Actions

71111.12

Corrective Action

Documents

0881124

Long Range Planning for 1VA06CD Motor Refurbishment

02/16/2009

4238259

1AF01PB Crankcase Oil Analysis Degrading Trend

04/10/2019

4244974

1VA06SA Vibration Reading Results

04/30/2019

4244975

2VA06SA Vibration Reading Results

04/302019

4244994

1VA06CD Exceeds Run Time Threshold for Motor Bearings

04/30/2019

Procedures

ER-AA-310-1002

Maintenance Rule Functions - Safety Significant

Classification

3

ER-AA-320

Maintenance Rule Implementation per NEI 18-10

0

ER-AA-320-1001

Maintenance Rule 18-10 - Scoping

0

ER-AA-320-1004

Maintenance Rule 18-10 - Performance Monitoring and

Dispositioning Between (a)(1) and (a)(2)

1

71111.13

Calculations

BRW-97-0340-E

Battery Duty Cycle and Sizing for the Braidwood Diesel

Driven Auxiliary Feedwater Pumps

3

Corrective Action

Documents

2667064

Lessons Learned - Unit 1 System Auxiliary Transformer

(SAT) Outage Temporary State Estimator Alarm Setpoint

05/09/2016

4235979

Coating Repairs Needed for the 1DG01KA-X2 Lower

Stationary Head

04/03/2019

4235981

Coating Repairs Needed for the 1DG01KA-X2 Lower Pact

End Channel Head

04/03/2019

4235983

Coating Repairs Needed for the 1DG01KA-X1 Upper Pact

End Channel Head

04/03/2019

4235987

Debris Found Inside Stationary Head and Tubesheet

1DG01KA-X2

04/03/2019

4235988

Degradation Found During Inspection of 1DG01KA-X1

Upper Stationary Head

04/03/2019

4236145

Significant Amount of Oil in Air Sensing Line

04/04/2019

4236908

1A Diesel Generator South Fuel Rack Positioner Cable

Broke

04/06/2019

4236938

1A Diesel Generator Butterfly Valve Sticking

04/06/2019

4238259

1AF01PB Crankcase Oil Analysis Degrading Trend

04/10/2019

4240057

Battery Charger Lugs are Distorted on 2AF01EB-A Battery

04/16/2019

4247173

ACB 1441 Would Not Close Following SAT Restoration

05/02/2019

13

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4247555

Ground Connections Corroded

05/08/2019

4247567

Unit 1 SAT LCO 4.0 Critique

05/08/2019

4247579

Braidwood SAT Outage Restoration Delays

05/08/2019

4248106

SAT 142-1 Received Unsatisfactory Doble Test on X3

Bushing

05/10/2019

4248185

Direct Current Bus 111 Ground

05/11/2019

Engineering

Evaluations

620474

Evaluation of Single SAT Operation on Unit 1 for 2019

0

Procedures

1BwOSR 3.8.1.1

Unit 1 Offsite AC Power Availability Surveillance

5

2BwHS 384-6

24 Volt ESF Auxiliary Feed Diesel Battery BT2 and BT2

Performance Test

0

2BwHSR 3.7.5-

BA

2B Diesel Auxiliary Feed Pump Battery Bank B Battery A

(2AF01EB-A) Capacity Test

3

2BwOS DC-Q4

24V DC Auxiliary Feed Pump 2B Battery Bank A and B

Quarterly Surveillance

6

BwHP 4006-023

Bus Disconnect Link Relocation on 6900 V SAT Buses

8

BwHP 4006-059

Operation of the Biddle/AVO Ground Fault Tracer

3

BwHP 4006-066

DC Bus Ground Location Using the Multi-Amp Battery

Ground-Fault Locator

1

BwHP 4006-074

Bus Disconnect Link Relocation on 4160 V SAT Buses

4

BwHS 4002-084

System Auxiliary Transformer Preventative Maintenance

Inspection

15

BwMP 3100-022

Diesel Generator 2 Year Inspection

38

BwMP 3200-014

Auxiliary Feedwater Pump Diesel Drive Unit Inspection and

Maintenance

22

BwOP AP-15

Isolating System Auxiliary Transformer (SAT) 142-1 with Unit

1 Unit Auxiliary Transformer (UAT) Energized

27

BwOP AP-20

Restoring System Auxiliary Transformer (SAT 142-2) with

Unit 1 UAT Energized

21

BwOP AP-54

With SAT 142-1 Isolated, Isolate SAT 142-2 and Restore

SAT 142-1 with Unit 1 UAT Energized

11

BwOP DC-E2

Electrical Lineup - Unit 1 Operating - 125 Vdc Division 11

9

ER-AA-330-009

ASME Section XI Repair/Replacement Program

16

ER-AA-335-015-

VT-2 Visual Examination in Accordance with ASME 2013

0

14

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2013

ER-AA-600-1042

On-Line Risk Management

11

MA-AA-716-230-

1004

Lubricant Sampling Guideline

5

MA-BR-EM-4-

09070

Diesel Generator Electrical Inspection

16

OP-AA-108-117

Protected Equipment Program

5

WC-AA-101-1006

On-Line Risk Management and Assessment

2

WC-AA-104

Integrated Risk Management

25

Work Orders

1836579

24 Volt Auxiliary Feed Battery Bank Capacity Test

(2AF01EB)

04/15/2019

1945815

1AP02E: Preventative Maintenance Inspection of SAT 142-1

05/07/2019

4692594

1DG01KA: 24 Month Inspection of the Diesel Generator

04/01/2019

4693700

1DG01EA: Diesel Generator Exciter Inspection (1A EDG)

04/01/2019

4908688

1AF01PB Crank Case Oil and Filter Change

04/12/2019

4920701

DC Bus 111 Ground

05/13/2019

71111.15

Corrective Action

Documents

2667064

Lessons Learned - Unit 1 SAT Outage Temporary State

Estimator Alarm Setpoint

09/09/2016

4194175

1PL01J Alarms Generate DC Bus 111 Ground Alarm

11/12/2018

4209879

DC Bus 111 Ground Coming in with 1PL01J Panel Check

01/10/2019

4223051

1RF008 Flowrate Trend Anomaly

02/24/2019

4224618

1CV179 Cycling Excessively

02/28/2019

4228652

1RF009 Elevated Reading

03/12/2019

4229675

Unit 1 Floor Drain Sump Channel A Failed - PC002

03/15/2019

4244974

1VA06SA Vibration Reading Results

04/30/2019

4244975

2VA06SA Vibration Reading Results

04/30/2019

4244994

1VA06CD Exceeds Run Time Threshold for Motor Bearings

04/30/2019

4247579

Braidwood SAT Outage Restoration Delays

05/08/2019

4248185

DC Bus 111 Ground

05/22/2019

4249077

2HK-AF036B: Manual Loader for 2AF005G Failed - WO 1893938

05/15/2019

4253330

2SX124A is Very Difficult to Operate

05/31/2019

4254702

Erratic 2A CV Pump Cubicle Cooler SX Flow Rate

06/05/2019

15

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Changes

EC 628126

Performance of Cubicle Coolers 1VA06SA and 2VA06SA

with One or Two Fans in Operation

0

Procedures

1BwOS DC-1a

AAR-125 Vdc ESF Bus Ground

8

BwOL 3.8.4

LCOAR

DC Sources - Operating Technical Specification LCO 3.8.4

8

BwOP DC-23-111 125 Vdc Bus 111/113 Ground Detection

4

ER-AA-321

Administrative Requirements for Inservice Testing

13

ER-AA-600-1012

Risk Management Documentation

14

ER-AA-600-1045

Risk Assessments of Missed or Deficient Surveillances

7

OP-AA-106-101-

1006

Operational Decision Making Process

21

OP-AA-108-111

Adverse Condition Monitoring and Contingency Planning

13

OP-AA-108-115

Operability Determinations (CM-1)

21

71111.19

Corrective Action

Documents

4257536

2SI8804B Mechanical and Grease Inspection

06/17/2019

4257539

2SI8912B has Inactive Packing Leak

06/17/2019

Procedures

2BwOSR

5.5.8.SI-10B

Group A IST Requirements for 2B Safety Injection Pump

(2SI01PB)

10

BwOP SX-1

Essential Service Water Pump Startup

23

BwOP SX-7

Swapping Essential Service Water Pumps

27

ER-AA-330-001

Section XI Pressure Testing

16

ER-AA-335-015-

2013

VT-2 Visual Examination in Accordance with ASME 2013

0

Work Orders

1938834

Disassemble and Inspect 2CC070B

05/14/2019

1939833

2CC9520B Disassemble and Inspect

05/14/2019

1955970

EQ Motor Containment Spray Pump 1B

06/18/2019

4615529

1SX01AB Cooler Inspection and Cleaning

05/16/2019

4838800

Flow Indicator Containment Spray Pump Room Cooler 1B

Outlet

06/18/2019

4889939

ESF Switchgear Room Division 12 Ventilation System Vent

Fan Motor

05/22/2019

4906923

IST for 1CS003B/11B - ASME Surveillance Requirements

for 1CS01PB & Check Valves

06/18/2019

71111.22

Corrective Action

4238267

Valve Handle Not Moving Valve Stem Properly

04/10/2019

16

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

4238279

Fuel Oil Leak From Left Bank Fuel Rail

04/10/2019

4238284

2PI-DG030A Turbo Air Inlet Pressure Indication is Suspect

04/10/2019

4238291

2A EDG Fuel Rack Trip Level Pushbutton Fell off During

EDG Run

04/10/2019

Procedures

1BwOS MS-Q1

Main Steam Dump Valve Stroke Surveillance

11

2BwOSR 3.8.1.2-

1

2A Diesel Generator Operability Surveillance

47

BwOP DG-1

Diesel Generator Alignment to Standby Condition

30

BwOP DG-11

Diesel Generator Startup and Operation

51

BwOP DG-12

Diesel Generator Shutdown

30

Work Orders

4836509

2A Diesel Generator Operability Semi-Annual Surveillance

04/10/2019

4876995

Unit 1 Steam Dump Valve Quarterly Surveillance (Tave

Mode and Above P-8)

04/11/2019

4898251

2A Diesel Generator Operability Monthly Surveillance

04/10/2019

71151

Corrective Action

Documents

4236155

Unexpected Unit 2 Loose Parts Alarm

04/04/2019

Miscellaneous

NRC Performance Indicator Data; Mitigating Systems -

Safety System Functional Failures

04/01/2018 -

03/31/2019

NRC Performance Indicator Data; Mitigating Systems -

Mitigating System Performance Index for Emergency

Alternating Current Power

04/01/2018 -

03/31/2019

NRC Performance Indicator Data; Mitigating Systems -

Mitigating System Performance Index for High Pressure

Injection

04/01/2018 -

03/31/2019

Procedures

LS-AA-2001

Collecting and Reporting of NRC Performance Indicator

Data

15

LS-AA-2080

Monthly Data Elements for NRC Safety System Functional

Failures

7

LS-AA-2200

Mitigating System Performance Index date Acquisition and

Reporting

6

71152

Corrective Action

Documents

4209142

Unit 2 Loose Parts Alarm

01/08/2019

4210587

Unexpected Alarm, Loose Parts

01/14/2019

4211151

Trend in Loose Parts Monitoring Issues

07/15/2019

4212438

Unexpected Annunciator 2-13-E9, Loose Parts Monitoring

01/20/2019

17

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

System Trouble

4213338

Received Unexpected Annunciator 2-13-E9, Loose Parts

01/23/2019

4216074

Unit 2 Loose Parts Alarm

01/31/2019

4217622

Unit 1 Loose Parts Alarm

02/05/2019

4219216

Unexpected Annunciator: 2-13-E9

02/12/2019

4227893

Unit 2 Loose Parts Monitoring System Impact Noise Alarm

Channel 4

03/08/2019

4228922

Loose Parts Alarm - Channel 1, 3, 14 - No Abnormal Noises

03/13/2019

4232957

Metallic Noise Unit 1 Loose Parts Monitoring System at 1C

SC Lower Narrow Range Level Tap

03/25/2019

4233318

Reactor Vessel Head Loose Parts Monitoring System Alarm

Disabled 2VE-LM002

03/26/2019

4236155

Unexpected Unit 2 Loose Parts Alarm

04/04/2019

4236932

Unexpected Annunciator: 2-13-EP

04/06/2019

4237724

Unexpected Unit 1 Loose Parts Alarm

04/09/2019

4242027

Unexpected Unit 2 Loose Parts Alarm

04/22/2019

4245172

Unexpected Annunciator 1-13-E9

05/01/2019

4248952

Need Work Request to Troubleshoot Unit 1 Loose Parts

Monitoring System Channel 1

05/14/2019

4250626

Re-Evaluate Loose Parts Monitoring System Oversight

05/21/2019

Miscellaneous

ER-AA-320-1003

Maintenance Rule 18-10 - Failure Definitions

0

Procedures

BwOP LM-10

Loose Parts Monitoring System Operation and Alarm

Response

4

BwOP LM-10A1

Loose Parts Monitoring System Alignment

3

NO-AA-10

Quality Assurance Topical Report (QATR)

7

OP-AA-108-117

Protected Equipment Program

5

OP-AA-201-008

Pre-Fire Plan Manual

4

PI-AA-=125-1001

Root Cause Analysis Manual

3

PI-AA-120

Issue Identification and Screening Process

8

PI-AA-125

Corrective Action Program (CAP) Procedure

6

PI-AA-125-1003

Corrective Action Program Evaluation Manual

4