IR 05000456/2019003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000456/2019003 and 05000457/2019003
ML19312A525
Person / Time
Site: Braidwood  
(NPF-072, NPF-077)
Issue date: 11/08/2019
From: Hironori Peterson
Region 3 Branch 3
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
EA-19-116 IR 2019003
Download: ML19312A525 (31)


Text

November 8, 2019

SUBJECT:

BRAIDWOOD STATION, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000456/2019003 AND 05000457/2019003

Dear Mr. Hanson:

On September 30, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Braidwood Station, Units 1 and 2. On October 17, 2019, the NRC inspectors discussed the results of this inspection with the Plant Manager, Mr. J. Keenan, and other members of your staff. The results of this inspection are documented in the enclosed report.

One Severity Level IV violation without an associated finding is documented in this report. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Braidwood. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Hironori Peterson, Chief Branch 3 Division of Reactor Projects

Docket Nos. 05000456 and 05000457 License Nos. NPF-72 and NPF-77

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000456 and 05000457

License Numbers:

NPF-72 and NPF-77

Report Numbers:

05000456/2019003 and 05000457/2019003

Enterprise Identifier: I-2019-003-0059

Licensee:

Exelon Generation Company, LLC

Facility:

Braidwood Station, Units 1 and 2

Location:

Braceville, IL

Inspection Dates:

July 01, 2019 to September 30, 2019

Inspectors:

R. Baker, Senior Operations Engineer

B. Bergeon, Operations Engineer

R. Bowen, Illinois Emergency Management Agency

D. Kimble, Senior Resident Inspector

C. Phillips, Project Engineer

M. Porfirio, Illinois Emergency Management Agency

L. Rodriguez, Reactor Inspector

R. Ruiz, Project Engineer

P. Smagacz, Resident Inspector

Approved By:

Hironori Peterson, Chief

Branch 3

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Braidwood Station, Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure of the facility licensee to certify that a licensed senior operator with an inactive license completed the requirements of 10 CFR 55.53(f) before resuming functions authorized by a license.

Cornerstone Significance Cross-Cutting Aspect Report Section Not Applicable NCV 05000456,05000457/2019003-01 Open/Closed EA-19-116 Not Applicable 71111.11B The inspectors identified a Severity Level IV non-cited violation (NCV) of 10 CFR 55.53(f) for the failure of the facility to certify that a senior licensed operator with an inactive license completed the requirements to return the license to an active status before resuming functions authorized by the license. Specifically, a senior reactor operator whose license was no longer in an active status was permitted to relieve the unit supervisor watch. As this individual was no longer permitted to perform the functions of a senior operator, and subsequently was the only senior reactor operator in the control room for a period of time during the shift, the facility did not ensure a senior operator with an active license was present in the control room at all times when both units were in Mode 1.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period operating at full power. On July 23, 2019, power was reduced to approximately 30 percent to facilitate electrical repairs to a solenoid valve associated with the 1D Steam Generator (SG) Feedwater Regulating Valve (1FW540). Upon completion of the repair activities and associated post-maintenance testing, the unit returned to operation at full power on July 25, 2019. On September 18, 2019, the unit reached the end of the nuclear fuel cycle and entered planned power coast down operations in preparation for its 21st refueling outage. Late in the morning on September 23, 2019, the unit tripped while operating at approximately full power when the 1B SG Feedwater Regulating Valve (1FW520) unexpectedly failed to the closed position. Following the identification of failed digital control components associated with the 1FW520 valve, the unit was restarted and the reactor made critical on September 24, 2019. Synchronization of the main electrical generator to the power grid occurred later that same morning. The unit had reached approximately 90 percent power at the end of the inspection period with power coast down operations continuing.

Unit 2 began the inspection period operating at full power. With the exception of minor reductions in power to support scheduled testing activities or small load changes requested by the transmission system dispatcher, the unit remained operating at or near full power for the balance of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515 Appendix D, Plant Status and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04Q - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system conditions and configuration by conducting partial physical alignment verifications of the following systems/trains:

(1) The 1A Residual Heat Removal (RH) train with the 1B RH out of service for planned maintenance during the week ending July 27, 2019
(2) The 1B Safety Injection (SI) train with the 1A SI train out of service for planned maintenance during the week ending August 3, 2019
(3) The 1A SI train with the 1B SI train out of service for planned maintenance during the week ending August 24, 2019
(4) The 2A SI train with the 2B SI train out of service for planned maintenance during the week ending September 21, 2019

71111.04S - Equipment Alignment

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the configuration and condition of the Unit 2 SI system during a full system physical alignment verification during the weeks ending September 7 through September 14, 2019

71111.05Q - Fire Protection

Quarterly Inspection (IP Section 03.01) (8 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) The Division 11 Engineered Safety Feature (ESF) Switchgear Room, Fire Zone 5.2-1, during the weeks ending July 13 through July 20, 2019
(2) The Unit 1, Non-ESF Switchgear Room, Fire Zone 5.3-1, during the weeks ending July 13 through July 20, 2019
(3) The Division 12 ESF Switchgear Room, Fire Zone 5.1-1, during the weeks ending July 13 through July 20, 2019
(4) The Division 21 ESF Switchgear Room, Fire Zone 5.2-2, during the weeks ending July 13 through July 20, 2019
(5) The Division 22 ESF Switchgear Room, Fire Zone 5.1-2, during the weeks ending July 13 through July 20, 2019
(6) Unit 2 Non-ESF Switchgear Room, Fire Zone 5.3-2, during the weeks ending July 13 through July 20, 2019
(7) The Division 12 Miscellaneous Electrical Equipment Room and Battery Room, Fire Zone 5.4-1, during the weeks ending July 13 through July 20, 2019
(8) The Division 22 Miscellaneous Electrical Equipment Room and Battery Room, Fire Zone 5.4-2, during the weeks ending July 13 through July 20, 2019

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 02.02a.) (1 Sample)

The inspectors evaluated internal flooding vulnerability and mitigation for the following plant area:

(1) The Unit 1 Auxiliary Feedwater (AF) area, 383' Elevation, during the week ending September 28, 2019

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered from August 19, 2019 through September 20, 2019.

71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)

(1) Biennial Requalification Written Examinations

The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered on August 17, 2018.

Annual Requalification Operating Tests

The inspectors evaluated the adequacy of the facility licensees annual requalification operating test.

Administration of an Annual Requalification Operating Test

The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.

Requalification Examination Security

The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.

Remedial Training and Re-examinations

The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.

Operator License Conditions

The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.

Control Room Simulator

The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.

Problem Identification and Resolution

The inspectors evaluated the licensees ability to identify and resolve problems associated with licensed operator performance.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

The inspectors observed and evaluated licensed operator performance in the station's Main Control Room during the following activities:

(1) Various periods of high-tempo and/or risk-significant operations during the weeks ending July 27 through September 28, 2019

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (2 Samples)

The inspectors observed crews of licensed operators in the station's simulator during the following evaluated and graded casualty training scenarios:

(1) An evaluated and graded casualty scenario on July 9, 2019
(2) An evaluated and graded casualty scenario on September 18, 2019

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness Inspection (IP Section 02.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance activities associated with the following equipment and/or safety significant issues:

(1) The 2B Main Feedwater (FW) Pump lube oil system and performance issues as documented in Issue Report (IR) 426503 during the weeks ending August 3 through August 10, 2019
(2) The Unit 1 Main Control Room annunciator system and performance issues as documented in IR 4264965 during the weeks ending August 10 through August 31, 2019

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's risk assessments and planning for the following work activities:

(1) Emergent repairs to 125 volts direct current (Vdc) Bus 111 grounds as documented in Work Order (WO) 4920701 during the week ending July 27, 2019
(2) Emergent work to repair a Unit 1 annunciator logic error as documented in IR 4264965 during the weeks ending July 27 through August 3, 2019
(3) Troubleshooting and repairs to the 2B Main FW Pump lube oil system as documented in WO 4850789 during the week ending August 10, 2019
(4) Emergent repairs to the 1B Steam Generator Main Feedwater Regulating Valve (1FW520) as documented in WO 4962887 during the week ending September 28, 2019

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 02.02) (8 Samples)

The inspectors evaluated the following operability determinations and functionality assessments:

(1) The evaluation of a noisy and slowly increasing demand signal associated with the 1D Steam Generator FW Regulating Valve (1FW540) controller as documented in IR 4259918 during the week ending July 20, 2019
(2) The evaluation of an American Society of Mechanical Engineers Code nonconformance for Unit 1 replacement steam generators as documented in IR 4272501 during the weeks ending August 24 through August 31, 2019
(3) The evaluation of the functionality of the 2B Main FW Pump after foreign material was introduced into the pump's oil system as documented in IR 4270893 during the weeks ending August 17 through September 14, 2019
(4) The evaluation of the operability of direct current (DC) distribution panels following the identification of duct tape being used to secure spare fuse holders in the DC distribution panels as documented in IR 4273062 during the weeks ending August 24 through September 7, 2019
(5) The evaluation of the 1A Essential Service Water (SX) Pump strainer backwashing excessively as documented in IR 4274831 during the weeks ending August 31 through September 7, 2019
(6) The evaluation of Air Circuit Breaker (ACB) 1424 requiring multiple attempts to close during the Bus 142/242 cross-tie surveillance as documented in IR 4276343 during the weeks ending September 7 through September 14, 2019
(7) The evaluation of DC Bus 112 battery cell 2 low specific gravity as documented in IR 4272834 during the weeks ending September 7 through September 14, 2017
(8) The evaluation of the 2B AF Pump with a degraded engine fan coupling as documented in IR 4279078 during the week ending September 21, 2019

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following permanent modification to the facility:

(1) Permanent enhancements and upgrades to the cooling systems for the Unit 1 and Unit 2 Miscellaneous Electrical Equipment Rooms as documented in Engineering Changes (ECs) 624901 and 624903 during the weeks ending August 17 through September 14, 2019

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the following post maintenance testing activities and results:

(1) Electrical acceptance testing following repairs to 125 Vdc Bus 111 as documented in WO 4920701 during the week ending July 27, 2019
(2) Functional testing of the 1B RH Pump following planned maintenance as documented in WO 4917400 during the weeks ending July 27 through August 10, 2019
(3) Functional and operational testing of the 2A EDG following planned maintenance as documented in WOs 4943770, 4921630, and 4758895 during the week ending August 10, 2019
(4) Functional and operational testing of the 0B Diesel-Driven Fire Pump following replacement of the pump element as documented in WOs 04843529 and 04947232 during the weeks ending August 3 through August 17, 2019
(5) Functional and operational testing of the 2B Containment Spray (CS) Pump following planned maintenance as documented in WOs 4925636, 4654936, and 4671383 during the week ending August 17, 2019
(6) Functional and operational testing of the 1B SI Pump following planned maintenance as documented in WOs 1764793, 1843557, 1898770, 1914717, 4613459, and

===4680012 during the week ending August 24, 2019

(7) Functional and operational testing of the DC Bus 111 Battery Charger (1DC03E)following emergent repairs as documented in WO 46667971 during the week ending September 14, 2019

71111.22 - Surveillance Testing

.Surveillance Tests (other) (IP Section 03.01)===

The inspectors observed and evaluated the following licensee surveillance testing activities:

(1)2BwOSR 3.8.1.2-1, 2A Diesel Generator Operability Surveillance as documented in WO 4933550 during the week ending July 12, 2019 (2)0BwOS CW-1, U0 Circulating Water (CW) Blowdown Vacuum Breaker inspection as documented in WO 4943151 during the week ending August 10, 2019 (3)1BwOSR 3.7.5.4-2, 1B AF monthly surveillance as documented in WO 4943151 during the weeks ending August 17 through August 24, 2019 (4)2BwOSR 3.8.1.8-1, Station Auxiliary Transformer (SAT) 142-1 crosstie to Bus 241 18-Month Surveillance as documented in WO 4724064 during the week ending September 7, 2019

FLEX Testing (IP Section 03.02) (1 Sample)

The inspectors observed and evaluated the following licensee FLEX Testing activities:

(1) 0BwOS FX-9, 0FX3PA Low Head FLEX Pump testing as documented in WO

===4674064 during the weeks ending August 31 through September 7, 2019

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03)===

The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes:

(1) Evaluation 18-45; Exelon Nuclear Standardized Radiological Emergency Plan, Revision 30; 02/14/2019

This evaluation does not constitute NRC approval.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicator information by reviewing selected information for the periods listed below:

MS08: Heat Removal Systems (IP Section 02.07)===

(1) Unit 1 (July 1, 2018, through June 30, 2019)
(2) Unit 2 (July 1, 2018, through June 30, 2019)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (July 1, 2018, through June 30, 2019)
(2) Unit 2 (July 1, 2018, through June 30, 2019)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (July 1, 2018, through June 30, 2019)
(2) Unit 2 (July 1, 2018, through June 30, 2019)

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of their corrective action program (CAP) related to the following issues:

(1) Review of corrective actions for the 1D Steam Generator Main FW Regulating Valve (1FW540) DC grounds as documented in IRs 4209878, 4248185, and 4265545 during the weeks ending August 3, 2019, through September 28, 2019

===71153 - Follow-up of Events and Notices of Enforcement Discretion

The inspectors reviewed the licensee's response to the following event:

Event Follow-up (IP Section 03.01)===

(1) Response to the Unit 1 automatic reactor trip on September 23, 2019, due to a 1B Steam Generator Lo-Lo Level condition as documented in NRC Event Notification (EN)

INSPECTION RESULTS

Failure of the facility licensee to certify that a licensed senior operator with an inactive license completed the requirements of 10 CFR 55.53(f) before resuming functions authorized by a license.

Cornerstone Severity Cross-Cutting Aspect Report Section Not Applicable Severity Level IV NCV 05000456,05000457/2019003-01 Open/Closed EA-19-116 Not Applicable 71111.11B The inspectors identified a Severity Level IV non-cited violation (NCV) of 10 CFR 55.53(f) for the failure of the facility to certify that a senior licensed operator with an inactive license completed the requirements to return the license to an active status before resuming functions authorized by the license. Specifically, a senior reactor operator whose license was no longer in an active status was permitted to relieve the unit supervisor watch. As this individual was no longer permitted to perform the functions of a senior operator, and subsequently was the only senior reactor operator in the control room for a period of time during the shift, the facility did not ensure a senior operator with an active license was present in the control room at all times when both units were in Mode 1.

Description:

On August 20, 2019, the NRC identified a licensed senior operator who had been performing the functions of a senior operator with an inactive license. The licensed senior operator had been off-shift, in another department, for a few years and was not maintaining his license in an active status. The senior operator restored the active status of his license by completing 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> of shift functions under the direction of a proficient senior operator as of December 20, 2018 (4th quarter 2018), in accordance with 10 CFR 55.53(f)(2). The senior operator's reactivation record was not reviewed and approved until January 4, 2019. Subsequently, the senior operator was incorrectly entered into the facility's qualification system as having completed the requirements to return the license to an active status in the 1st quarter 2019.

As a result, the senior operator did not stand all of the required seven 8-hour or five 12-hour shifts in the 1st quarter 2019 and the license once again reverted to an inactive status as of April 1, 2019. The senior operator was then permitted to stand 12 watches during the 2nd and 3rd quarters of 2019, without a license in active status. This was the result of the facility licensee's failure to certify that a licensed senior operator with an inactive license completed the requirements of 10 CFR 55.53(f) before resuming functions authorized by the license.

Additionally, these actions resulted in the facility licensee not meeting the requirements of 10 CFR 50.54(m)(2)(iii) and Technical Specification 5.1.2, to have a person with a senior operator license, capable of performing the functions of that position, in the control room at all times and having a senior reactor operator responsible for the control room command function when either unit is in Mode 1, 2, 3, or 4, respectively. Since these 2 violations were the direct result of the violation of the licensed operator's license condition, they will be dispositioned as part of the Severity Level IV violation.

Corrective Actions: The facility immediately removed the licensed operator from the qualification tracking system and placed the individual on administrative hold from performing licensed duties. The facility also conducted a stand down with all Operations crews, the Operations Training department personnel, and the Department Training Coordinators on the issue, as well as performing an extent of condition review of all recently reactivated licenses in 2018 and 2019. No additional issues were identified with SROs or ROs standing shifts with an inactive license. An operation's Standing Order was issued for each licensed operator to verify qualifications and license restrictions for watch standing every shift prior to watch standing and audited by the Senior Operations Supervisor.

Corrective Action References: IR 04273460; OP-AA-105-102, Attachment 1 not complete for 1st quarter 2019; dated 8/21/2019. IR 04274629; EOC [Extent of Condition] of Operator License Maintenance Review; dated 8/27/2019.

Performance Assessment:

The inspectors determined that the facility incorrectly credited a senior operator's license reactivation in the calendar quarter following the quarter in which the under-direction watches were completed, and then subsequently permitted the senior operator to stand watch in the control room with an inactive license. This error constituted a performance deficiency that was within the facility's ability to foresee and correct and should have been prevented. The inspectors determined that Traditional Enforcement applied, as the issue had the potential to impact the NRC's ability to perform its regulatory function. The NRC may need to perform a review in consideration of a licensing action, if a licensed operator fails to meet the conditions of their license. If the information regarding the qualifications of an individual is not accurately presented, the NRC may potentially make an incorrect licensing decision based on the inaccurate information. Specifically, the facility did not certify that a licensed senior operator, whose license became inactive at the end of 1st quarter 2019, completed the requirements of 10 CFR 55.53(f) before resuming functions authorized by the license, and permitted the senior operator to stand watches in the 2nd and 3rd quarters of 2019. These actions violated a license condition as specified in 10 CFR 55.53

(e) and (f). No associated Reactor Oversight Program finding was identified, and no cross-cutting aspect was assigned.
Enforcement:

The ROPs significance determination process does not specifically consider the regulatory process impact in its assessment of licensee performance. Therefore, it is necessary to address this violation which impedes the NRCs ability to regulate using traditional enforcement to adequately deter non-compliance.

Severity: This issue is similar to the violation example 6.4.c.1(c) in the NRC Enforcement Policy, dated May 28, 2019, for a Severity Level III violation because it involved the noncompliance with a condition stated on an individuals license. However, since the amount of time that lapsed between consecutive watches was never more than a calendar quarter, and the length of time used to complete 5 consecutive watches was within the intent of the requirement, along with the fact that there were no adverse impacts to nuclear safety, the NRC has determined that this issue will be dispositioned as a Severity Level IV NCV in accordance with the NRCs Enforcement Policy.

Violation: Title 10, of the Code of Federal Regulations (CFR), 55.53(e) requires, in part, that if a licensee has not been actively performing the functions of an operator or senior operator, the licensee may not resume activities authorized by a license issued under this part except as permitted by paragraph

(f) of this section. Section 55.53(f) states, If paragraph
(e) of this section is not met, before resumption of functions authorized by a license issued under this part, an authorized representative of the facility licensee shall certify the following:
(1) That the qualifications and status of the licensee are current and valid; and
(2) That the licensee has completed a minimum of 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> of shift functions under the direction of an operator or senior operator as appropriate and in the position to which the individual will be assigned. The 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> must have included a complete tour of the plant and all required shift turnover procedures.

Title 10 CFR 50.54(m)(2)(iii) requires, in part, that when a nuclear power unit is in an operational mode other than cold shutdown or refueling, as defined by the units technical specifications, each licensee shall have a person holding a senior operator license for the nuclear power unit in the control room at all times.

The facility Technical Specification (TS) Section 5.1.2, states, in part, that a senior reactor operator shall be responsible for the control room command function while either unit is in Mode 1, 2, 3, or 4.

Contrary to the above, between April 1, 2019 and August 6, 2019, the facility licensee failed to certify that a licensed senior operator with an inactive license completed the requirements of 10 CFR Part 55.53(f) before resuming functions authorized by a license issued by the NRC.

Additionally, on June 18, 2019, for several periods totaling approximately 16 minutes and 47 seconds, there was not a Senior Reactor Operator in the control room with an active license. Therefore, the facility licensee failed to meet the requirements of 10 CFR 50.54(m)and TS 5.1.2 for minimum control room staffing. Because these violations were the result of the facility licensees failure to meet the requirements of 10 CFR Part 55.53(f) to certify that the senior reactor operator who was on shift had an active license, these violations will be dispositioned as part of the Severity Level IV violation.

Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Observation: Steam Generator (SG) 1D Main Feedwater Regulating Valve (FRV) 1FW540, DC Bus Grounds 71152 The inspectors performed detailed reviews of IR 4209878, DC Bus 111 Ground Coming in with 1PL01J Panel Check, IR 4248185, DC Bus 111 Ground, and IR 4265545, Unexpected Annunciator 1-21-D6: DC Bus 111 Ground. The licensees evaluation for this issue went back to the previous Unit 1 refueling outage (A1R20) that took place during April of 2018.

During that refuel outage, digital FRV positioners were installed on all applicable valves on Unit 1. As part of this upgrade, new solenoid valves were also installed on the associated FRV actuators. Licensee troubleshooting identified that a solid DC Bus 111 ground was located between terminal box 1JB080T and the A solenoid valve, 1FSV-FW540-A, on FRV 1FW540. Upon inspection, one of the lugs/screws for the solenoid wiring terminations was excessively long, significantly longer than the others used for the project, and eventually wore through the insulating tape that had been applied causing the electrical connection to short out against the conduit body.

The cause of the ground was determined by the licensee to have been poor worker craftsmanship. Contractor electricians performing the solenoid replacement for 1FSV-FW540-A did not use the hardware referenced in the work package material request as specified. The lug/screw for the solenoid wiring termination that was significantly longer than the others required a different taping/insulating technique, which was not utilized.

Furthermore, the taping/insulating procedure referenced in the work package was for the use of the hardware specified within the material request. The licensees investigation could not determine why one lug/screw utilized in making up the connection was significantly longer than the others. New hardware of a shorter dimension had been requested and associated with the work package, and was on site and available for use.

Although there were several errors associated with the FRV 1FW540 digital upgrade work that were reasonably within the licensees ability to foresee and that should have been prevented, the inspectors determined that the performance deficiency involved did not rise to the level of being of more than minor safety significance and, as such, did not constitute a documentable finding. Additionally, no violations of NRC requirements were identified by the inspectors. Following their review, the inspectors concluded that the licensees identification of the issue had been timely and that the actions the licensee had taken to troubleshoot the condition had been reasonable and appropriate. Additionally, the inspectors concluded that the licensee had established corrective actions to address the issue that were appropriate for its safety significance and that could reasonably be expected to resolve the issue.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 17, 2019, the inspectors presented the integrated inspection results to the Plant Manager, Mr. J. Keenan, and other members of the licensee staff.
  • On August 23, 2019, the inspectors presented the licensed operator requalification program inspection results inspection results to Ms. M. Marchionda, the Site Vice President, and other members of the licensee staff.
  • On October 3, 2019, the inspectors presented the Exit Meeting for EP Inspection per IP 71114, Attachment 4 inspection results to Mr. L. Baker, the Emergency Preparedness Fleet Programs Manager, and other members of the licensee staff.
  • On October 16, 2019, the inspectors presented the licensed operator requalification program inspection results and SLIV violation characterization inspection results to Ms. M. Marchionda, the Site Vice President, and other members of the licensee staff.

THIRD PARTY REVIEWS

As discussed in IMC 0611, Section 13.01, the inspectors completed a review of the report issued by the World Association of Nuclear Operators (WANO) for the most recent periodic plant evaluation performed at the Braidwood Station during April 2019.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04Q Corrective Action

Documents

1047235

346 V 21 Rust and Dry Deposits on Stair Stringer and Floor

03/24/2010

1047255

343-0 (+8 FT) V-23 Stains and Mineral Deposits on Hanger

03/24/2010

1047650

Dry Brown Stains and Deposits on Concrete Wall in U2 CWA 03/25/2010

1047660

Repair Grout Seal in 364-0 Slab Near X/23

03/25/2010

267934

Cannot Remove Breaker from 1A SI Pump Cubicle

07/30/2019

276875

2SI8807A has Evidence of Packing Leak

09/05/2019

278048

Braidwood LR W/O Commitments Require Tighter Scrutiny

09/20/2019

Corrective Action

Documents

Resulting from

Inspection

267077

MCC 131X2 Cubicle C Rear Door Found not Latched

07/25/2019

277092

2CV206 Dry Boric Acid Leakage

09/05/2019

Drawings

M-136

Diagram of Safety Injection Unit 2

BR

M-61

Diagram of Safety Injection Unit 1

BJ

M-62

Diagram of Residual Heat Removal

BR

Procedures

BwOP RH-5

RH System Startup for Recirculation

BwOP RH-E1

Electrical Lineup Unit 1 - 1ARH Train

BwOP RH-M1

Operating Mechanical Lineup Unit 1 - 1A RH Train

BwOP S1-M1

Operating Mechanical Lineup Unit 1

BwOP SI-1

Safety Injection System Startup

BwOP SI-E1

Electrical Lineup - Unit 1 Operating

BwOP SI-E2

Electrical Lineup - Unit 2 Operating

BwOP SI-M2

Operating Mechanical Lineup Unit 2

Work Orders

1746544

Unit 2 - Area 7 Maintenance Rule Inspection Aux Bldg. 346

06/15/2015

4898247

IST for 2SI8919A/B/8922A/8926 - ASME Surveillance

Requirements for 2SI01PA

05/31/2019

4906921

IST for 2SI8919A/B/8922B/8926 - ASME Surveillance

Requirements for 2SI01PB

06/20/2019

4931599

U2 ECCS Venting and Valve Alignment Quarterly

09/10/2019

71111.05Q Corrective Action

Documents

Resulting from

262586

Cable Tray Wires Exceed Cable Tray Boundary

07/08/2019

262586

Cable Tray Wires Exceed Cable Tray Boundary

07/08/2019

263390

Broken Conduit

07/11/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Inspection

263390

Broken Conduit

07/11/2019

263659

Scaffold Tie Off to Structure Broke - Div 12 ESF Room

07/11/2019

263659

Scaffold Tie Off to Structure Broke - Division 12 Engineered

Safety Features Switchgear Room

07/12/2019

263917

Degraded Fire Hose Station

07/13/2019

265224

NRC ID: Appendix R Light not Directed at Equipment

07/18/2019

Fire Plans

Pre-Fire Plan 41

SWGA 426 Division 12 ESF Switchgear Room FZ5.1-1

Pre-Fire Plan 42

SWGA 426 Division 22 ESF Switchgear Room FZ5.1-2

Pre-Fire Plan 43

SWGA 426 Division 11 ESF Switchgear Room - FZ 5.2-1

Pre-Fire Plan 44

SWGA 426 Division 21 ESF Switchgear Room

Pre-Fire Plan 45

SWGA 451 Unit 1, Non-ESF Switchgear Room - FZ 5.3-1

Pre-Fire Plan 46

Fire Zone 5.3-2, Unit 2 Non-Engineered Safety Features

Switchgear Room

Pre-Fire Plan 47

Fire Zone 5.4-1, Division 12 Miscellaneous Electrical

Equipment Room and Battery Room

Pre-Fire Plan 48

Fire Zone 5.4-2, Division 22 Miscellaneous Electrical

Equipment Room and Battery Room

Procedures

BwAP 1110-1

Fire Protection Program System Requirements

BwAP 1110-3

Plant Barrier Impairment Program

BwOP PBI-1

Plant Barrier Impairment Program Pre-Evaluated Barrier

Matrix

CC-AA-201

Plant Barrier Control Program

ER-AA-600-1069

High Risk Fire Area Identification

ER_BR-600-1069

Site List of High Risk Fire Areas - Braidwood Unit 1 and

Unit 2

OP-AA-104-101

Communications

OP-AA-201-004

Fire Prevention for Hot Work

OP-AA-201-007

Fire Protection System Impairment Control

OP-AA-201-008

Pre-Fire Plan Manual

OP-AA-201-009

Control of Transient Combustible Material

71111.06

Corrective Action

Documents

4033220

VC Room Floor Drain Backed Up

08/18/2017

Drawings

Auxiliary Plumbing Flow Diagram

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Procedures

BwMS 3350-004

Watertight Door Surveillance

Work Orders

4749961

Inspection of Watertight Doors

11/01/2018

71111.11B

Corrective Action

Documents

IR 4035408

TRNG: Performance EP Failure (DEP)

07/25/2017

IR 4114638

TRNG: Performance EP Failure (DEP)

03/14/2018

IR 4128714

Multiple Losses of ESF Bus 141 during 1A Diesel Generator

Sequence Testing in A1R20

04/19/2018

IR 4132886

Roll-up and ECAP Request for Fuel Handling Issues During

A1R20

05/01/2018

IR 4144070

Unit 1 Manual Reactor Trip due to Lowering Steam

Generator Level

06/04/2018

IR 4146837

LORT TSA Failure (Isolate WS Flooding)

06/13/2018

Ir 4173301

NRC Biennial Exam Answer Choice Distribution

09/14/2018

IR 4233266

Two DEP Failures of an Evaluated Simulator Scenario

03/26/2019

IR 4252314

Crew Failure During OBE

05/28/2019

IR 4259627

Missed NRC Notification Within 30-Day Requirement for

License Drop

06/26/2019

SWR 133280

Update Dispatch Spreadsheet for IC Resets

08/06/2017

SWR 133554

MST will not Reset

09/27/2017

SWR 134808

Tuning the Feed System for Ovation

11/28/2018

SWR 135325

Issues in CV System

06/20/2019

SWR 135413

Enhancements to the MFW System Responses

07/25/2019

Corrective Action

Documents

Resulting from

Inspection

AR 04274629

Extent of Condition of Operator License Maintenance

Review

08/27/2019

AR 4273460

OP-AA-105-102, Attachment 1 Not Complete for 1st Quarter

2019

08/21/2019

Miscellaneous

OP-AA-105-102,

2-

A.G.

Reactivation of License Log

05/11/2018

OP-AA-105-102,

2-

D.B.

Reactivation of License Log

04/07/2018

OP-AA-105-102,

2-

G.L.

Reactivation of License Log

2/14/2017

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OP-AA-105-102,

2-J.L.

Reactivation of License Log

04/06/2018

OP-AA-105-102,

2-J.P.

Reactivation of License Log

10/11/2017

OP-AA-105-102,

2-

M.N.

Reactivation of License Log

01/01/2018

Scenario Guide

BR-5

Respond to a MS Line Break Inside Containment with

Miscellaneous Malfunctions

08/13/2019

Scenario Guide

BR-8

Respond to an RCS LOCA with Miscellaneous Malfunctions

08/20/2019

Simulator

Scenario Based

Testing

Scenario Number 18-1 NRC 2

05/07/2019

Simulator

Scenario Based

Testing

Braidwood Post-Event Trip of MWP

2/15/2018

Simulator

Scenario Based

Testing

Reactivity Scenario 1 / 18-1

08/20/2018

Simulator

Scenario Based

Testing

Braidwood Moderator Temp. Coefficient of Reactivity Att. 10

of TQ-AA-306, Cycle 21 with Plant Data Added

07/15/2018

Simulator

Scenario Based

Testing

Braidwood Rod Worth Reactivity Att. 11 of TQ-AA-306,

Cycle 21 with Plant Data Added

07/15/2018

Simulator

Scenario Based

Testing

Braidwood PWR Boron Coefficient of Reactivity Att. 12 of

TQ-AA-306, Cycle 21 Testing

01/15/2018

Simulator

Scenario Based

Testing

Braidwood PWR Approach to Criticality Using Boric Acid, Att.

of TQ-AA-306, Cycle 21 Testing

01/15/2018

Simulator

Scenario Based

Braidwood PWR Xenon Worths Att. 13 of TQ-AA-306,

Cycle 21

07/15/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Testing

Simulator

Scenario Based

Testing

Braidwood PWR Approach to Criticality with Boric Acid Att.

of TQ-AA-306, Cycle 21

07/21/2018

Simulator

Scenario Based

Testing

Braidwood Approach to Critical with Rods Att. 17 of

TQ-AA-306, Cycle 21 Testing

01/06/2018

Simulator

Scenario Based

Testing

Braidwood 2019 Annual Operating Test Scenario BR-5

08/12/2019

Simulator

Scenario Based

Testing

Braidwood 2019 Annual Operating Test Scenario BR-18

08/12/2019

Simulator Test

PMT SWR 135325, Issue in CV System

06/18/2019

TQ-BR-302-0107

Braidwood Transient Test 2, Simultaneous Trip of All Main

Feedwater Pumps, Cycle 21 Testing

TQ-BR-302-0110

Braidwood Transient Test 5, Trip of Any Single Reactor

Coolant Pump, Cycle 21 Testing

TQ-BR-302-0113

Braidwood Transient Test 8, LBLOCA with LOOP, Cycle 21

Testing

TQ-BR-302-0115

Braidwood Transient Test 10, Slow Primary Depress due to

Open PORV W/out Charging Pumps, Cycle 21 Testing

Procedures

OP-AA-105-102

NRC ACTIVE LICENSE MAINTENANCE

OP-BR-102-106

Operator Response Time Program at Braidwood Station

Scenario Guide

BR-18

Respond to a Main Steam Header Break and Miscellaneous

Malfunctions

08/21/2019

Scenario Guide

BR-25

Respond to a Vapor Space LOCA and Miscellaneous

Malfunctions

08/14/2019

TQ-AA-150

Operator Training Programs

TQ-AA-155

CONDUCT OF SIMULATOR TRAINING AND EVALUATION

TQ-AA-201

EXAMINATION SECURITY AND ADMINISTRATION

Self-Assessments AR 4217716

Pre-NRC 71111.11 Inspection Licensed Operator

Requalification Training Assessment

07/18/2019

71111.11Q Corrective Action

255332

Main Control Room Alarm Sensitivity Review

06/07/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

266841

Unit 1 Power Ascension Delayed Due to Beacon

Uncertainties

07/25/2019

Miscellaneous

Reactivity

Maneuver Plan

BR1C21

Braidwood 1 Cycle 21 DC Ground Repair

07/23/2019

Reactivity

Maneuver Plan

BR1C21-09.0

Braidwood 1 Cycle 21 Coastdown

09/17/2019

Procedures

1BwGP 100-4

Power Decension

BwOP CD/CB-2

Condensate/Condensate Booster System Shutdown

BwOP FW-2

Shutdown of a Turbine-Driven Main Feedwater Pump

BwOP FW-30

Feedwater Regulating Valve Base Load Operation

OP-AA-101-111-

1001

Operations Standards and Expectations

OP-AA-101-113

Operator Fundamentals

OP-AA-101-113-

1006

4.0 Crew Critique Guidelines

OP-AA-103-102

Watch-Standing Proactices

OP-AA-103-102-

1001

Strategies for Successful Transient Mitigation

OP-AA-103-103

Operation of Plant Equipment

OP-AA-108-107-

1002

Interface Procedure Between BGE/COMED/PECO and

Exelon Generation (Nuclear/Power) for Transmission

Operations

OP-AA-111-101

Operating Narrative Logs and Records

OP-AA-300

Reactivity Management

OP-AA-300

Reactivity Management

TQ-AA-10

Systematic Approach to Training Process Description

TQ-AA-150

Operator Training Program

TQ-AA-155

Conduct of Simulator Training and Evaluation

TQ-AA-201

Examination Security and Administration

TQ-AA-306

Simulator Management

TQ-BR-201-0113

Braidwood Training Department Simulator Examination

Security Actions

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.12

Corrective Action

Documents

28777

Braidwood Lessons Learned from Byron Feedwater Pump

Trip

04/26/2005

0331256

A2R11LL - 2B Feedwater Pump Lube Oil System

Troubleshooting

05/03/2005

29045

2B Feedwater Pump Oil Pressure Up Light Anomaly -

2FW01PB

20/09/2008

29046

Lesson Learned - 2B Feedwater Pump Oil Pump Auto Start

10/09/2008

1059245

Anomalies Observed During the Start of the 2B TDFW Pump

Oil

05/14/2010

1071520

Replace 2B Feedwater Pump Lube Oil Pressure Switch

2PS-FW203

05/20/2010

1071521

Replace 2B Feedwater Pump Lube Oil Pressure Switch

2PS-FS205

05/20/2010

1660140

B4 Trend Code: 2PS-FW203 Reset Out of Tolerance High

05/14/2014

4192076

2B Feedwater Pump Emergency Oil Pump Auto Started

11/06/2018

264965

Erratic Annunciators During Shiftly Test

07/18/2019

266428

Unexpected Alarm

07/23/2019

267503

2B Feedwater Pump Emergency Oil Pump Auto Started

07/28/2019

267874

Annunciator Box 1-17 Does Not Test Correctly

07/29/2019

Drawings

20E-2-4030FW22

Schematic Diagram Steam Generator Feedwater Pump 2B

Turbine Oil Pumps 2FW01PB-A, 2FW01PB-B

J

20E-2-4030FW23

Schematic Diagram Steam Generator Feedwater Pump 2B

Tubine Emergency Oil Pump 2FW01PB-C

F

M-152

Manufacturers Supplemental Diagram Steam Generator

Feed Pump Turbine Oil System

Y

Procedures

BwOP DC-23-111 125V DC Bus 111/113 Ground Detection

BwOP FW-10

Operation of a Turbine Driven Main Feedwater Pump Lube

Oil System

BwOP FW-23

Swapping Feedwater Pumps

ER-AA-310-1002

Maintenance Rule Functions - Safety Significan

Classification

ER-AA-320

Maintenance Rule Implementation per NEI 18-10

ER-AA-320-1001

Maintenance Rule 18 - 10 - Scoping

ER-AA-320-1003

Maintenance Rule 18 - 10 - Failure Definitions

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

ER-AA-320-1004

Maintenance Rule 18 - 10 - Performance Monitoring and

Dispositioning Between (a)(1) and (a)(2)

Work Orders

0958686

Perform Post-Maintenance Disassembled Inspection of

Turbine Feed Pump

06/09/2008

1354739

Replace 2B Feedwater Pump Lube Oil Pressure Switch

2PS-FW205

11/08/2012

1354740

Replace 2B Feedwater Pump Lube Oil Pressure Switch

2PS-FW203

11/08/2012

71111.13

Corrective Action

Documents

209878

DC Bus 111 Ground Coming in with 1PL01J Panel Check

01/10/2019

248185

DC Bus 111 Ground

05/11/2019

264965

Erratic Annunciators During Shiftly Test

07/18/2019

265545

Unexpected Annunciator 1-21-D6: DC Bus 111 Ground

07/19/2019

266428

Unexpected Alarm

07/23/2019

267874

Annunciator Box 1-17 does not Test Correctly

07/29/2019

270540

DC System Trend IR (January 2014 - July 2019)

08/08/2019

270893

2TO5337A Inspection Revealed Foreign Material

08/10/2019

272352

Annunciator 1-2-E4 Did Not Clear as Expected

08/16/2019

274648

Unit 1 Annunciator Horn Troubleshooting Learnings

08/27/2019

281976

1FW520 Status on 1PL100J Status Needs Verification

09/25/2019

Drawings

20E-2-4030FW23

Steam Generator Feedwater Pump 2B Turbine Emergency

Oil Pump 2FW01PB-C

F

Procedures

1BwOSR 0.1-

1,2,3

Unit 1 Modes 1, 2, and 3 Shiftly and Daily Operating

Surveillance

1BwOSR

5.5.8.FW-1

Unit One Main and Bypass Feedwater Regulating Valves

and Tempering Flow Control Valves Fail Safe Test 18 Month

Surveillance

BwHP 4006-059

Operation of the Biddle/AVO Ground Fault Tracer

BwHP 4006-066

DC Bus Ground Location Using the Multi-Amp Battery

Ground-Fault Locator

BwIP 1FW520

Calibration of 1B Steam Generator Feedwater Flow

Regulating Valve (FW)

BwOP DC-E2

Electrical Lineup - Unit 1 Operating - 125V DC Division 11

MA-AA-716-004

Conduct of Troubleshooting

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

4850789

2B Feedwater Pump Oil Filter Differential Pressure High

08/09/2019

20701

DC Bus 111 Ground

07/23/2019

4962887

1FW520: Calibrate Feedback Unit, Positioner, and Perform

Flowscan

09/24/2019

4963345

1FW520: Replace Digital Valve Controller and Flowscan

Feedwater Regulating Valve

09/24/2019

71111.15

Calculations

2-7720-B140

Secondary Side Small Nozzles ASME Level A/B/C/D

Analysis

2-7720-SR-2

Byron and Braidwood Replacement Steam Generator

Transient Analysis Report - Section 5, 5% Power Uprate

(3600.6 MWt)

Calibration

Records

1464960

CCP: Tape on Spare Fuse Holders in 1DC12J

01/20/2013

Corrective Action

Documents

29453

Fukushima Walkdown Found Duct Tape on Fuse Holder

Covers

10/21/2012

1464956

CCP: Tape on Spare Fuse Holders in 1DC10J

01/20/2013

1464959

CCP: Tape on Spare Fuse Holders in 1DC11J

01/20/2013

1464959

CCP: Tape on Spare Fuse Holders in 1DC11J

01/20/2013

1464961

CCP: Tape on Spare Fuse Holder in 1DC13J

01/20/2013

1464962

CCP: Tape on Spare Fuse Holders in 2DC11J

01/20/2013

1464964

CCP: Tape on Spare Fuse Holders in 2DC12J

01/20/2013

1464965

CCP: Tape on Spare Fuse Holders in 2DC13J

10/20/2013

4016750

1A SX Pump Significantly Weaker than 1B SX Pump

05/31/2017

4155768

2B SX Strainer Stuck in Continuous Backwash

07/14/2018

4168621

Issues Closing 1SX046A

08/30/2018

25240

Review of Byron IR 4185973 Feedwater Regulating Valve

Travel Transducers

03/01/2019

250599

Request WR to Replace 1FW540 Travel Transducer During

Window

05/21/2019

257124

1A SX Pp Strainer is Backwashing Excessively

06/15/2019

259918

Noisy and Slowly Increasing Demand on 1FW540 Controller

06/27/2019

269369

1A SX Pp Strainer is Backwashing Excessively

08/03/2019

270893

FME: 2TO5337A Inspection Revealed FM

08/10/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

270913

FME: 2TO5313A Relief Valve Cap Gasket Missing

08/10/2019

272160

4.0 Critique 2B TDFWP Work Window

08/15/2019

272501

Notification of Code Nonconformance for Replacement

Steam Generators

08/16/2019

272834

DC 112 Specific Gravity Deviation High

08/18/2019

274831

1A SX Pp Strainer is Backwashing Excessively

08/27/2019

275530

Schedule WO to Perform Follow-up UT on Section of

1SX93AB

08/29/2019

276343

ACB 1424 Took Multiple Attempts to Close 1AP06EQ

09/03/2019

279078

2AF01PB - 2B Auxiliary Feedwater Pump Diesel - Abnormal

Noise While Running

09/13/2019

279222

Documentation of 2B Auxiliary Feedwater Pump Shaft

Condition

09/13/2019

279236

Lot Part - Woodruff Key for 2B Auxiliary Feedwater Pump

09/14/2019

279748

Extent of Condition Following IR 4279078

09/16/2019

Corrective Action

Documents

Resulting from

Inspection

273062

NRC Identified Duct Tape on Spare Fuses in 2DC11J

08/19/2019

Drawings

20E-0-3000P

Installation Notes for Electrical Equipment

V

20E-1-4004B

Synchronizing Diagram 4160 SWGR & Diesel Gen. 1A & 1B

J

20E-2-4257A

Internal Wiring Diagram 125V DC Fuse PNL 2DC11J-ESF-

Part 1

C

20E-2-4257B

Internal Wiring Diagram 125V DC Fuse PNL 2DC11J-ESF

- Part 2

D

20E001

Steam Generator Arrangement

20E214

Steam Drum Assemble - Stage 1

M-42

Diagram of Essential Service Water Units 1 & 2

BE

M152

Manufacturers Supplemental Diagram Steam Generator

Feed Pump Turbine Oil System

Y

Engineering

Changes

391045

Engineering Chang Evaluating Use of Non-Metallic Tie

Wraps on Spare Fuse Holders

29229

TCCP to Temporarily Jumper Out Cell 2 of ESF Battery 112

to Allow 125 VDC ESF Battery 112 Operation with 57 Cells

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

BRW-S-2019-58

Temporarily Jumper Out Cell #2 of ESF Battery 112 to Allow

25 VDC ESF Battery 112 Operation With 57 Cells

Engineering

Evaluations

396312

Evaluation for Determining RCFC Operability When SX

Discharge Header Pressure Low Alarm is in

29019

Lost Parts Evaluation 2B FW Turbine Oil System Foreign

Material

29021

Losst Part Evaluation for Adjustment Gasket Within

2TO5313A

PP_SX-10

2SX01PA - 2BwOSR 5.5.8SX.6A - IST Pump Evaluation

Form

09/22/2016

Procedures

1BwOA PRI-8

Essential Service Water Malfunction Unit 1

107

1BwOL 3.8.1

LCOAR AC Sources - Operating - Tech Spec LCO 3.8.1

1BwOSR 3.6.6.2

Reactor Containment Fan Cooler Surveillance

1BwOSR 3.7.8.1

Unit One Essential Service Water System Surveillance

1BwOSR 3.8.1.8-

SAT 242-2 Crosstie to Bus 142 and DG 1B Crosstie to Bus

2 Surveillance

1BwOSR 3.8.6.5-

Unit One 125V DC ESF Battery Bank 112 Operability

Surveillance

BRW-97-0384-

E/BYR97-204

25 VDC Battery Sizing Calculation Braidwood Only Key

Calc

BwAR 1-2-A2

SX Pump Discharge Header Pressure Low - Alarm No. 1-2-

A2

BWAR 1-2-C2

SX Trainer dP High - Alarm No. 1-2-C2

BwOP DC-2T1

Battery Capacity Talbe for 125V DC ESF Battery

BwOP DC-5-112

25 DC ESF Battery 112 Equalization

BYR97-

406/BRW-97-

0965-M

RCFC Performance Curve Calculation

ER-AA-2006

Lost Parts Evaluations

ER-AA-321

Administrative Requirements for Inservice Testing

ER-AA-600-1012

Risk Management Documentation

ER-AA-600-1045

Risk Assessments of Missed or Deficient Surveillances

MA-MW-726-605

25 Volt DC ESF Battery Cell Jumpering

0A

OP-AA-106-101-

Operational Decision Making Process

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1006

OP-AA-108-111

Adverse Condition Monitoring and Contingency Planning

OP-AA-108-115

Operability Determinations (CM-1)

Work Orders

1960165

U1 SX System Flow Balance Surveillance

01/16/2016

4849480

2B FW Pump Oil Filter dP High

11/02/2018

4850789

2B FW Pump OIl Filter dP High

08/10/2019

27972

LR-IST for 1SX002A - ASME Surveillance Requirements for

1A Essential Service Water Pump

08/27/2019

71111.18

Corrective Action

Documents

269037

0FP03PB Stuffing Box Leak

08/02/2109

272278

RD Project - U1 Condenser Cosmetic Damage

08/15/2019

278254

Intentionally Abbreviated Maintenance: 2P-VE001LOOP

CAL

09/11/2019

Engineering

Changes

24901

Augmented Cooling for Control Rod Drive Cabinets Unit 1 -

50.59 Screening No. BRW-S-2018-82

24903

Augmented Cooling for Control Rod Drive Cabinets Unit 2 -

50.59 Screening No. BRW-S-2018-66

71111.19

Corrective Action

Documents

4107548

Erratic Reading on 0TI-FP8023

2/23/2018

266039

GOCAR BwAP 1110-1A2 Past 7 Days for -B DDFP

07/22/2019

269424

Diesel Fire Pump Battery Connection

08/03/2019

270013

0TI-FP8047 Reading Erratic and Inaccurate

08/06/2019

270088

2DG5228A Missing Plug Resulted in Small Air Leak

08/07/2019

270279

Flange Leak at Discharge of 0FP775B on Return to Service

08/07/2019

270387

Small Leak Found at FP03PB Fitting

08/08/2019

273569

1SX2080B Valve Difficult to Operate - Unable to Fully Close

08/21/2019

Procedures

0BwOS FP.2.1.E-

1B

0B Fire Protection Pump Flow and Pressure Test

0BwOS

FP.2.2.M-2

Diesel Driven Fire Pump Surveillance

0BwOS FP.3.3.E-

0B Fire Pump NFPA Test

1BwOSR

5.5.8.SI-10B

Group A IST Requirements for 1B Safety Injection Pump

(1SI01PB)

1BwOSR

Test Operation of ECCS Motor Operated Valves

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

5.5.8.SI-12

Surveillance

2BwOSR

5.5.8.CS-3B

Comprehensive Full Flow Test for 2B Containment Spray

Pump (2CS01PB) and Check Valves 2CS003B, 2CS011B

BwAP 1110-qA2

Fire Suppression Water Supply Required Compensatory

Measures Action Response

BwAR 0-38-C7

Fire Pump Diesel Trouble

BwOP CS-5

Containment Spray System Recirdulation to the RWST

BwOP SI-1

Safety Injection System Startup

BwOP SI-2

Safety Injection System Shutdown

Work Orders

1764793

Change Greae in Coupling and Perform Inspection of

Coupling Internals

08/2/2019

1843557

Grease Inspection Grade of Grease 3 - 1SI8923B

08/21/2019

1898770

1SI01PB-M Perform Static Barrier Testing

08/21/2019

1914717

1SI01PB Weeping Oil Leak on Oil Return Line

08/21/2019

4613459

1SI01PB Replace Oil Breathers and Mark Oil Level S/G

08/21/2019

4654936

Rebuild Actuator, Reg/Replace Elastomers

08/15/2019

4671383

2FSV-CS010B Replace Solenoid Valve

08/15/2019

4680012

Weeping Oil Leak at 1TE-SI002D

08/21/2019

4758895

Failed PMTS: 2A DG Fuel Leak 3-5 DPM

08/07/2019

4843529

Overhaul DDFP per Pump & Motor Plan in 2019

08/06/2019

4917400

IST-1RH01PB ASME Group A Test & CC-1SI8958B

07/26/2019

20701

DC Bus 111 Ground

07/23/2019

21630

2A DG - 2019 Pre 2 Year Work Window Engine Analysis

Results

08/07/2019

25636

IST - For 2CS003B/11B ASME Surveillance Requirements

for 2CS01PB & Check Valves

07/15/2019

4943770

LR-IST-2A D/G Operability Monthly

08/07/2019

4947232

LR-0B Fire Protection Pump Flow and Pressure Test

08/07/2019

71111.22

Corrective Action

Documents

269965

Water Found in Vacuum Breaker #3 Vault, No Active Leak

08/06/2019

269970

Water Found in Vacuum Breaker #11 Vault, No Active Leak

08/06/2019

275218

Corrosion Found Inside Radiator Opening of 0FX03PA

08/28/2019

275829

0BwOS FX-9 Improvement Opportunity

08/30/2019

276486

Work Request Needed to Fabricate Flex Discharge Manifold

09/03/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Operability

Evaluations

BwOP DG-1

Diesel Generator Alignment to Standby Condition

Procedures

0BwOS CW-1

Unit Common Circulating Water System Blowdown Line

Inspection

0BwOS FX-9

Flex Pump Flow Surveillance

1BwOSR 3.7.5.4-

Unit One Diesel Driven Auxiliary Feedwater Pump

Surveillance

2BwOSR 3.8.1.2-

2A Diesel Generator Operability Surveillance

2BwOSR 3.8.1.8-

SAT 142-1 Crosstie to Bus 241 and Diesel Generator 2A

Crosstie to Bus 141 Surveillance

BwOP AF-7

Auxiliary Feedwater Pump _B (Diesel) Startup on Recirc

BwOP AF-7T1

Diesel Driven Auxiliary Feedwater Pump Operating Log

BwOP AF-8

Auxiliary Feedwater Pump _B (Diesel) Shutdown

BwOP DG-11

Diesel Generator Startup and Operation

BwOP DG-12

Diesel Generator Shutdown

Work Orders

4674064

Perform 3 Y Inspection/Maintenance on #1 Flex Pump

08/29/2019

24690

SAT 142-1 Crosstie to Bus 241 18-Month Surveillance

09/04/2019

4933550

2A EDG Operability Monthly

07/10/2019

4943151

LR-1B AF Pump Monthly Surveillance Run

08/16/2019

4947149

U0 CW Blowdown Vacuum Breaker Inspection

08/06/2019

71114.04

Miscellaneous

Evaluation 18-45

Exelon Nuclear Standardized Radiological Emergency Plan,

Revision 30

2/14/2019

71151

Miscellaneous

NRC

Performance

Indicator Data;

Mitigating

Systems

Mitigating System Performance Index for Heat Removal

Systems

07/01/2018 -

06/30/2019

NRC

Performance

Indicator Data;

Mitigating

Systems

Mitigating System Performance Index for Residual Heat

Removal Systems

07/01/2018 -

06/30/2019

NRC

Mitigating System Performance Index for Cooling Water

07/01/2018 -

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Performance

Indicator Data;

Mitigating

Systems

Systems

06/30/2019

Procedures

LS-AA-2001

Collecting and Reporting of NRC Performance Indicator Data 15

LS-AA-2200

Mitigating System Performance Index Data Acquisition and

Reporting

PI-AA-125-1001

Root Cause Analysis Manual

71152

Corrective Action

Documents

209878

DC Bus 111 Ground Coming in with 1PL01J Panel Check

01/10/2019

248185

DC Bus 111 Ground

05/11/2019

265545

Unexpected Annunciator 1-21-D6: DC Bus 111 Ground

07/19/2019

Procedures

NO-AA-10

Quality Assurance Topical Report (QATR)

PI-AA-120

Issue Identification and Screening Process

PI-AA-125

Corrective Action Program (CAP) Procedure

PI-AA-125-1003

Corrective Action Program Evaluation Manual

Work Orders

4659603

Install EC 620239: Upgrade Feedwater Regulating Valve

Positioner to Digital

04/11/2018

71153

Corrective Action

Documents

281429

Unit 1 Reactor Trip on Lo-2 Steam Generator Level in 1B

Steam Generator

09/23/2019

281460

Unit 1 - N-36 Reading Higher than Expected

09/23/2019

281465

Unit 1 Post-Accident Neutron Monitor 1NI-NR006A Failed

Low

09/23/2019

281521

Various Radiation Monitors Spiking During Reactor Trip

09/23/2019

281548

4.0 Critique for Unit 1 Reactor Trip

09/23/2019

281624

1ZC-FW520 Unable to Communicate with Digital Valve

Controller

09/24/2019

Procedures

OP-AA-108-114

Post Transient Review

13