IR 05000445/1990043

From kanterella
Jump to navigation Jump to search
Insp Repts 50-445/90-43 & 50-446/90-43 on 901113-16. Violations Noted.Major Areas Inspected:Qa Manual & Licensee Overview of Engineering Contractor Activities
ML20058K395
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 12/07/1990
From: Barnes I, Mcneill W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20058K370 List:
References
50-445-90-43, 50-446-90-43, NUDOCS 9012170210
Download: ML20058K395 (7)


Text

- -..

.

.

.

_.

.

.

)

.:

APPENDIX B l

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

l NRC Inspection Report: 50-445/90-43 Operating License: NPF-87 l

50-446/90-43 Construction Permit: CPPR-127

'

,

Dockets: 50-445 l

50-446 I

i

,

Licensee: TV Electric Skyway Tower 400 North ~011ve, L.B. 81-

,

Dallas, Texas 75201

.

Facility Name:

Comanche Peak Steam Electric Station (CPSES)

'

Inspection At: CPSES, Glen _ Rose, Somervell County, Texas Inspection Conducted: November 13-16, 1990 Inspector: [ I 3 w

/2

- 9o W. M. McNeill, Reactor Inspector, Materials Date and Quality Programs Section, Division of Reactor Safety Approved

/3

/a

-1o

%

I. Barnes, Chief, Naterials and Quality Date Programs Section Division of Reactor Safety Inspection Summary Inspection Conducted November 13-16. 1990 (Report 50-445/90-43)

l Areas Inspected: No inspection of Unit I was conducted.

Results: Not apr11 cable.

Inspection Conducted November 13-16, 1990 (Report 50-446/90-43)

Areas Inspected:

Routine, unannounced inspection of the quality assurance manual j

and licensee's overview of engineering contractor activities.

,

.;

"

'

9012170210 901212 PDR ADOCK 0D000445l

PDR ~

,

- -..

.

.

-2-Results: The Quality Assurance (QA) program appeared to be adequately defined and requirements were satisfactorily identified in lower tier procedures for Unit 2.

In review of the licensee's overview of engineering contractor activities, a deviation was identified (paragraph 3.2.?) pertaining to the failure to perform Engineering Assurance (EA) evaluations and surveillance of Unit 2 engineering contractor activities, as committed to by TV Electric letter TXX-88373 to the NRC dated April 14, 1988. This deviation relates to a reorganization in June 1989, in which the EA Surveillance unit was transferred to 0A, thereby eliminating the separate EA surveillance of contractor engineering activities, it was noted that a Unit 2 Engineering organization was in place which was responsible for performing oversight and evaluations of contractor engineering performance. Weaknesses were noted with respect to the adequacyandimplementationofproceduresforcontractorengineering) oversight, for which an inspector followup item was identified (paragraph 3.2.3. QA wcs found to be satisfactorily implementing its program for audits and surveillances of engineering contractors.

I i

'

s

,. I

-_-

.

.

.

..

.

.

3-DETAILS

,

1.

PERSONS CONTACTED 1.1 TV ELECTRIC

.

J.L. Barker, Manager,IndependentSafetyEngineeringGroup1(ISEG)

,

  • 0. Chatty, Issue Interface Coordinator

R. W. Braddy, Project Engineering Manager

'

  • H. D. Bruner, Senior Vice President

,

  • R. D. Calder, Manager of Design Basis Engineering ) Manager
  • H. M. Carmichael, Unit 2 Engir.eering Assurance (EA
  • W. G. Guldemond, Manager Site Licensing S. W. Harrison, Unit 2 Engineering Manager T. L. Heatherly, Licensing Engineer
  • C. R. Hooton, Deputy Project Engineering Manager
  • J. C. Hicks, Licensing Manager i

S. V. Lakdawala. Engineering Supervisor L. N. Johnson, Trend Analyst

  • D. M. McAfee, Manager, Quality Assurance (QA )

}

  • D. E._Pendleton, Assistant Project Manager i

W. J. Sturtz, Lead QA Auditor

W. R. Syfrett, Senior Engineer

'

  • C, L. Terry, Director, QA J. E. Thomson, Senior Engineer
  • J. E. Wren, QA Construction Manager
  • L. G. Yeager, Unit 1 Manager EA

.

J. P. Ziemian, Procurement Quality Engineer

!

1.2 CASE

  • E. F. Ottney, Program Manager 1.3 NRC
  • D. D. Chamberlain, Project Section Chief.

!

  • R. M. Latta Senior Resident inspector Unit 2
  • Denotes those attending the exit interview conducted on November 16, 1990.

The inspector alsn interviewed other TV Electric personnel during the

,

inspection.

'

i a

ss -

~

..

..

-

.

.

.

P.

REVIEW OF QA MANUAL (35100)

2.1 Objective The objective of this inspection was to determine whether QA plans, instructions, and procedures for safety-related activities have been established in accordance with the QA manual and whether these documents conform to the progtam described in Chapter 17.1 of the Final Safety Anclysis Report (FSAR).

P.2 Organization Structure and Personnel The inspector ascertained that it was planned to reorganize the QA Department on November 19, 1990, into a Nuclear Overview Department. The Director of 0A will be retitled Director of Nuclear Overview with five se:ctions reporting to-him. The Independent Safety Engineering Group (ISEG) which was originally part of the Technical Interface Department will be moved into the Nuclear Overview Department and reorganized to consist of two subunits (i.e., surveillance and assessment).

In addition, the Plant Evaluation Department will be relocated to

>

the Nuclear Overview Department and become the Trending and Analysis Section.

This section will consist of two subunits. (i.e., trending analysis and event analysis). The staffing size will rerain the same for Trending and Analysis and increase for ISEG because it will assume responsibility for surveillance l

,

functions previously performed by Operations QA.

l The remaining three sections [ Construction Quality Control (QC), Operations QC, andQA]willremainthesameexceptfortheQASection. The QA Section will be

'

>

reorganized from four subunits (Quality Operations, Quality Program, Quality

,

Construction, and Quality. Technical Support)- to three subunits (Construction QA, l

OperationsQA,andProcurementQA). Procurement QA has been a subunit reporting directly to the Director, QA. The staffing of the QA section will be slightly reduced with the moving of. staff to the new ISEG Section.

2.3 Program The QA program description in Chapter 17.1 was implemented by Nuclear Engineering and Operations Policy Statements, Nuclear Engineering and

Operations Procedures, " Site-Wide" Procedures, and a CPSES QA Manual. The QA Department's activities were further implemented in lower tier documents by a Nuclear QA Procedures Manual and Nuclear Quality Instructions. The Construction QC Section was found to be ' staffed by Stone & Webster personnel which worked to the CPSES QA program and its own Construction Quality Procedures. A Drown and Root group was matrixed to the Construction QC Section which worked to its own QA program. This program was described by a QA Manual-as well as administrative, construction, and quality procedures for ASME Section III activities.

-.

.

,.

.

.

-5-Within the Quality Construction subunit of the QA Section, an Ebasco Services

'

Inc. group was matrixed which worked to its own program. This program was

>

described by a OA I4anual and implementing procedures. This group was known as the code control group.

No violations or deviations were identified in this area of the inspection.

3.

LICENSEE'S OVERVIEW 0F ENGINEERING CONTRACTOR ACTIVITIES (35020},

l 3.1 Objective The objective of this inspection was to determine whether the lic m ee's implementation of its responsibilities relating to overview of engineering contractors is consistent with the status of the nuclear project and the QA program described in the FSAR and other commitments.

3.2 Overview Program The responsibilities for review of engineering) contractors were found to have been assigned to QA, Engineering Assurance (EA, and Unit 2 Engineering.

The inspector performed a review of program requirements and implementation for each of these groups.

3.2.1 g The QA overview requirements were found to be defined in the following procedures:

flQA 3.07, " Quality Assurance Audit Program." Revision 6 NQA 3.23, " Surveillance Program," Revision 4

NQA 3.14, " Control of Vendor Activities," Revision 6

HQA 1.16-1.01, " Indoctrination Training and Certification of Auditors and

Lead Auditors," Revision 3 NQA 1.16-4.01, " Indoctrination Training, and Qualification of Quality

Assurance Surveillance Personnel," Revision 2 The OA audits and surveillances of engineering-activities were reviewed, it was found that Procurement QA had performed a QA program audit (QAA-90-276) of Dechtel's offsite engineering office in order to remove an Approved Vendor List restriction. Quality Construction had performed two surveillances of the three engineering contractors (Bechtel, Stone & Webster, and ABB 1mpo11)

pertaining to specification commitments (QAS-90-552) and the post construction hardwarevalidationprogram(QAS-90-540).

In addition, Quality Construction had performed three surveillances of Stone & Webster pertaining to electrical device walkdowns (QAS-90-524), electrical separation (QAS-90-550), and penetration walkdowns-(QAS-90-562). Two audits had been performed by Quality Construction

,

.

.

.. _ _

,

.

.

-6-i of Stone & Webster and ABB Irpell. Audit QAA-90-056 on the Integrated Nuclear

.

Data Management System reviewed both Stone & Webster's and ABB 1mpell's onsite engineering activities. Audit QAA-90-055 was in-process as of this inspection j

and pertained to the ABB Impell QA program for its onsite engineering. The

'

above surveillances and audits were found to have been performed to a schedule, were preplanned, and were executed by qualified personnel in accordance with the established procedures.

Followup and close out of findings could not be verified because the surveillances and audits were recent activities.

,

3.2.2 Engineering Assurance j

The EA overview requirements were found to be defined in the following

,

procedures, l

2PP-1.01, " Organization and Responsibilities of the Unit 2 Project i

Organization " Revision 0 f

2EP-3.23. " Engineering Activities Overview and Evaluation Procedure,"

Revision 0 During review of EA activities, the inspector noted that establishment of this function was documented in TU letter TXX-4946 dated August 4, 1986, to the NRC as corrective action in response to escalated enforcement violations 86-09 and 86-63.

It was further "oted that a la%r letter, TXX-88373 dated April 14, 1988, provided a respon; e to an NRC s'.aff request for an explanation of the applicability of the Cor *ctive Action Program to CPSES Unit 2.

Attachment A to this letter states that the EA organization "... maintains design control procedures and provides necessary training in their use, and conducts technical evaluations and surveillance of engineering activities to assure technical adequacy and compliance with design control procedures and licensing commitments."

Attachment A additionr11y identified that the audit responsibilities of the Technical Audit ';roup would be assumed by the permanent audit and surveillance sections withir. the QA Department with expanded capabilities, including transferred personnel f rom the Technical Audit Group or acquired personnel with the requisite education, experience, and training.

l The inspector observed that Procedure 2PP-1.01 identified that EA was I

responsible for training and coordinating procedures and audits, but did not identify that EA was responsible for performing evaluations and surveillances.

Procedure 2EP-3.23 identified, however, that the Unit 2 EA Manager was L

responsible for performing or participating in evaluations. The inspector ascertained that EA had not performed any evaluations or surveillances and,

,

'

including the manager, had a staff of four.

it was additionally ascertained from licensee personnel that the licensee had transferred the EA surveillance unit to QA in June 1989, thereby eliminating the separate EA surveillance of contractor engineering activities. The failure to perform EA evaluations and surveillances of Unit 2 contractor engineering activities is an apparent deviation from commitments made in TV Electric letter TXX-88373 dated April 14, 1988, to the NRC.

(446/9043-01)

l

.

.-

-.

....

-7

j 3.2.3 Unit 2 Engineering The inspector noted that Procedures 2PP-1.01 and 2EP-3.23 identified Unit 2 Engineering as being responsible for performing oversight and evaluations of

L contractor engineering performance. As of this inspection, Unit 2 Engineering had performed and issued 11 tvaluations of Stone & Webster, completed but not issued 2 evaluations of Bechtel, and was in the process of performing an evaluation of ABB 1mpell.

The inspector found that procedural requirements for evaluations were not fully implemented. For example, only 3 of the 11 Stone & Webster evaluations had prepared assessment plans required by paragraph 6.3 of Procedure 2EP-3.P3.

Assessment plans are utilized for defining the scope of the evaluation and listing of the attributes to be assessed.

It was also found that the two Bechtel evaluatlons did not have assessment plans.

It was edditionally noted that the 11 Stone & Webster evaluations had resulted in 33 Discrepancy Reports, 31 of which dealt with drawing and drafting control problems.

EA had not established this as a trend as required by paragraph 5.2.2 of Procedure 2PP-1.01. QA who were on the distribution for evaluation reports did issue an Analysis of Repetitive Concerns (ARC 90-11-01) after this condition was highlighted by the inspector.

It was also noted that the procedures were weak in that they did not ensure timely review of corrective actions to findings. One report was noted which had four findings for which corrective action responses had been submitted.

Although 45 days had elapsed since the responses were issued, the evaluation

'

and acceptance of the corrective actions had not been performed. -Another report with seven findings did not have evaluation and acceptance of the corrective actions, although 21 days had elapsed since the responses were issued.

In regard to these observations, the licensee identified that corrective actions would be taken to strengthen the affected procedures. A review of the effectiveness of the above actions is considered an inspector followup I

item (446/9043-02).

l

EX1T INTERVIEW An exit interview was held November 16, 1990, with those personnel indicated in paragraph 1 in which the inspection findings were summarized, llo information was presented to the inspector that was identified by the licensee as proprietary.

The licensee was subsequently infomed on December 6,1990, during the exit.

_

,

interview for NRC Inspection Report 50-445/90-42; 50-446/90-42 that the failure to perform EA evaluations and surveillances would be identified as a deviation frem commitments.

l