IR 05000445/1986022

From kanterella
Jump to navigation Jump to search
Confirms That Review of Encl Insp Repts 50-445/86-22 & 50-446/86-20 Completed,Per Jm Taylor 860626 Memo.Concurrence in Rept Provided on 870210
ML20245A119
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 02/10/1987
From: Spessard R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML20238B208 List:
References
FOIA-87-428 NUDOCS 8702180081
Download: ML20245A119 (62)


Text

ArH.'

pj

.

'

.

"" 1 ' I Docket Nos. 50-445 and 50 4',6 FEMORANDUM FOR:

Eric H. Johnson, Director Division of Reactor Safety and Projects Region IV

'

FROM:

R. Lee Spessard, Deputy Director Division of Inspection Programs Office of Inspection and Enforcement SUBJECT:

INSPECTION REPORT REVIEW ASSISTANCE - COMANCHE PEAK

.

This will confirm the completion of our review of Inspection Report 50-445/86-22; 50-446/86-20 4, 6crordance with J. M. Taylor's memorandum to R. D. Martin dated

]

June 26, 1965.

{

l As a part of our re i ew process, we' provided copies of the report to NRR i

(Trammell) and OGC (r.izuno) for comment.

Both NRR and 0GC had several comments; these have been coordinated and resolved through discussions with I. Barnes.

Our concurrence in the report was provided on February 10, 1987, as noted on the enclosed report.

"Oricir'l '

-/ I'

'

a

-

!

R. Lee Spessard, Deputy Director Division of Inspection Programs Office of Inspection an8 Enforcement

Enclosure:

Inspection Report

REGION IV==

]

NRC' Inspection Report:

50-445/86-22

Permits:

CPPR-126

50-446/86-20

CPPR-127

Dockets:

50-445

Category:

A2

50-446

Licensee:

Texas Utilities Electric Company

Construction Permit:

Expiration Dates:

j

Unit 1: August 1, 1988

Unit 2: August 1, 1987

.

i

Applicant: Texas Utilities Electric Company

Skyway Tower

400 North Olive Street

Lock Box 81

!

i

Dallas, Texas 75201

Facility Name:

Comanche Peak Steam Electric Station (CPSES),

Units I & 2.

'

Inspection At:

Glen Rose, Texas

Inspection Conducted: July 1 through August 31, 1986

!

~

Inspectors:

l

L. E. Ellershaw, Reactor Inspector, Region IV

Date

j

CPSES Group

(paragraphs 2.n, 2.v-z, 2.0, 4 b-c, 4.f-h,

6.1, 7, 8, and 9)

'

i

C J. Hale, Reactor Inspector, Region IV

Date

C6;ES Group

(paragraphs 2.a 2.m

2.0, 4.b-c, 4.f-h,

6.a, 7, 8, and 9)

P. C. Wagner, Reactor Inspector, Region IV

Date

CPSES Group

(paragraphs z.b.-1, 2.p-u, 4.1, 5.1, and 6.b)

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _. __ _ ________

.

'

.

-2-

I

i

Consultants:

EG&G - J. Dale (paragraphs 2.z, 3, 4.j, and 5.j)

A. Maughan (paragraphs 2.b-1, 2.p-u, and 5.a)

W. Richins (paragraphs 2.n, 2.v-y, 4.d 5.e)

V. Wenczel (paragraphs 8 and 9)

Parameter - J. Birmingham (pardgraphs 4.b-c, 4.f-h, and 7)

K. Graham (paragraphs 4.3, L.c-d, 5.f, 5.1 and 5.b)

i

D. Jew (paragraphs 4.1, and 5. g-h)

Reviewed by:

/

.24 * d

-

P7

'

R. L. Spessard, Seputy Director, Division of

Date

Inspection Programs, Office of Inspection

and Enforcement

Approved:

1. Barnes, Chief, Region IV CPSES Group

Date

Inspection Summary

Inspection Conducted:

July 1 through August 31, 1986 (Report 50-445/86-22;

50-446/86-20)

~

Areas Inspected:

Nonroutine, unannounced inspection of applicant actions on

previous inspection findings; employee protection posting; assessment of

allegations; Comanche Peak Response Team (CPRT) issue-specific action

plans (0 SAPS); CPRT central and working files; ERC overview inspection program;

dnd procurement, receiving, and storage.

Results:

Within the seven areas inspected, four violations (stainless steel

and carbon steel were stored in outside areas with improper protective end

coverings, paragraph 6.1; records of heat treatment were not available for disc

,

l

inserts and spares for main steam safety valves, nor was it apparent that

proper source and receipt inspections were performed, paragraph 4.6;

'

nonconformance reports (NCRs) dea'..ng with installed valve bonnets were

incorrectly dispositioned, paragraph 4.1; and a correct assessment was not

provided regarding adequacy of design with respect to. square groove welds in

HVAC duct supports, paragraph 2.z) and six deviations (objectivity forms and

evaluations had not been completed for certain members of the CPRT staff,

paragraph 2.a; and Evaluation Research Corporation (ERC) documentation package

review failed to identify four inspectors ano two welders involved in the

package being reviewed, paragraph 4.h; ERC overview inspection failed to

_ - _ _ - _ - _ _ _ _ - _ _ _ _

.... _ -. _ -

_

~

_

.

-

'

-3-

identify deviating conditions and unsatisfactory decisions made by the initial

ERC inspector, paragraph 4.j and 5.g; ERC identified eight deviations on a pump

but did not tag the pump, paragraph 5.c; diaphragm valves were purchased to an

earlier version of the ASME Code than that consnitted in the Final Safety

Arialysis Report (FSAR), paragraph 4.1; and ERC engineering did not identify all

sdfety signifiCant attributes on the inspection checklist for mechanical

equipment inst 611ation, paragraph 5.c) were identified.

_

.

.

\\

.

h

_

'~

_.....

.

.

-

DETAILS

I

1.

Persons Contacted

    • J. W. Audas, Senior Licensing Engineer, Texas Utilities

Generating Company, (TUCCo)

    • J.,L. Barker, Engineering Assurance Manager TUGCo

L. B. Barker, Executive Assistant TUGCo

  • R. T. Bentley, Technical Assistant, CPRT
      • C. T. Brandt, Quality Engineering Supervisor, TUGCo
    • R. E. Camp, Project General Manager, Unit 1. TUGCo

,

  • W. G. Counsil, Executive Vice President, TUGCo

B. DuBois, Quality Assurance (QA) Manager, TERA

P. E. Halstead, Site Quality Control (QC) Manager, TUGCo

M. Keathley, Lead Electrical QC Inspector, ERC

    • J. Krechting, Director of Engineering, TUGCo
  • J. Mallanda, Electrical Review Team Leader, CPRT
      • J. T. Merritt, Jr., Director of Construction, TUGCo

C. K. Moehlman, Project Mechanical Engineer, TUGCo

      • J. T. Merritt, Jr., Director of Construction, TUGCo

C. K. Moehlman, Project Mechanical Engineer, TUGCo

      • L. D. Nace, Vice President, TUGCo

0. Nevins, Training Coordinator. TERA

A. A. Patterson, Reinspection Engineering Supervisor, ERC

  • F. L. Powers, Assistant Unit 1 Project Manager, TUGCo

P. Pussalugo, Equipment Qualification Engineer, TUGCo

F. Schafer, Systems Engineering Manager, TERA

B. Shair, Lead Electrical Engineer, ERC

!

~

P. Stevens, Electrical Engineer, TUGCo

  • J. F. Streeter, Director of QA, TUGCo

T. G. Tyler, CPRT Program Director, TUGCo

R. F. Wright, Manager, Warehouse and Material Control, TUGCo

'

The NRC inspectors also interviewed other CPRT and applicant employees

during this inspection period.

  • Denotes persunnel present at the August 7, 1986, exit interview.
    • Denotes personnel present at the September 5, 1986, exit

interview.

      • Denotes personnel present at both of the above exit interviews.

2.

Applicant Action on Previous Inspection Findings

a.

(Closeri) Deviation (445/8511-D-02):

An issue coordinator that had

been previously involved with CPSES activities had not been

_ _ _ _ _ _ _ _ - _

_

.

.

-5-

identified to the NRC, nor had the CPRT provided justification

regarding his objectivity as required by Section VII of the CPRT

Program Plan.

Revision 3 to the CPRT Program Plan deleted the commitment from

Section VII to identify.and provide justification to the NRC when

third party personnel were found to have had prior CPSES involvement.

By letter to the NRC dated April 1,1986, (Counsil to Johnson), it

was further committed that all CPRT personnel would complete

objectivity questionnaires (Attachment 7 of the CPRT Program Plan).

When completed questionnaires identified prior CPSES involvement or

l

association of an individual, further evaluation was required by the

l

Senior Review Team (SRT) for Review Team Leaders (RTLs) and by the

RTL for their assigned personnel.

In such cases evaluation forms

were to be completed documenting the basis of the SRT or RTL

conclusions concerning the objectivity of such an individual. These

objective and evaluation forms were to be completed by the end of

April 1986.

The NRC inspector verified the implementation of these revised

'

commitments by:

(1) a review of a sample of the ERC and TERA files

on objectivity of personnel (the TERA records were in Bethesda,

Maryland, and QA branch personnel from the Office of Inspection and

Enforcement conducted this review); (2) review of all the objectivity

l

records of the testing and electrical personnel; and (3) review of a

I

objectivity questionnaires and their evaluations by the appropriate

l

authority were found to be in compliance with the revised commitments

with the following exceptions.

'

The technical support staff (two individuals) of the CPRT Program

Director had not completed objectivity questionnaires nor had the

personnel on the records review committee. The CPRT Program _ Director

did not believe the revised commitment applied to these individuals;

however, the commitment states that these documents had been

completed for the SRT, RTL, and support staff.

Further, a commitment

was made to document an evaluation of the objectivity forms for all

CPRT personnel by April 1986; however, such an evaluation was not

made for the CPRT Program Director and the TERA RTL evaluation was

not completed until July 17, 1986. These findings represent ~a.

!

deviation from commitment (445/8622-D-01; 446/8620-D-01).

'

b.

(Closed)OpenItem(445/8511-0-01):

Incorrect electrical pull box

location.

Further NRC review established that the ERC determir.6 tion

of incorrect box location was based on a drawing which was for

guidance only and did not contain mandatory location requirements.

The NRC inspector verified that the box had been properly installed

and met all of the required quality procedure checklist items.

Further NRC review fo @und that NRC Inspection R

(Closed) Open Item (445/8511-0-09): i

cable trap edges and cable

&

c.

jacket damage.

l

50-445/86-01; 50-446/86-01 hud incorrectly associated NCR ES5-100831

i

l

.

_____________m______w

-. _ _ _ _ _ _ _ _ _ _

.

.

-6-

with this open item. The correct NCR (i.e., E85-100844) was found to

h6ve been dis ositioned and closed.

The disposition stated that

6-

since the s op edges were not inside the cable tray but were on the

troy's lip, a ove the cable jacket, the conditions were acceptable.

The NRC inspector performed a reinspection of the cable tray and

found that the NCR had been properly dispositioned.

d.

(Closed) Open Item (445/8511-0-11:

Loose splice plate bolt.

Further

NRC review found NCR E85-100988 had been dispositioned and closed.

The disposition stated that the nut was jammed and could neither be

tightened or removed.

The condition was determined to be acceptable

since Design Change Authorization (DCA) 3883, Revision 2, requires

only six bolts per -plate and there are eight bolts in this plate.

-

The NRC inspector performed a reinspection of the splice plate for

this NCR and found that the NCR had been properly dispositioned.

e.

(Closec) Open Item (445/8511-0-21): Missing fire seals. The

findings that fire stop sealing material was not present in the

conduit stubs which entered a control room panel was evaluated during

!!k

a review of the ERC deviation report (DR). A review of the

dpplicable project requirements by the NRC inspector showed that the

seal material can be installed in either end of the conduit and an

inspection revealed that it was installed in the opposite end of

these conduits.

.

f.

(Closed) Open Item (445/8511-0-22):

Improper electrical separation.

The condition of conduit C13016035 ending just under tray T030CCQ64

instead of ending 10" above the tray was identified during a

witnessed ERC inspection.

Further review by the NRC showed that

Drawing 2323-El-1702, Note Sc, allowed this type of installation

provided 2" of slack was maintained.

Reinspection by the NRC of the

installation found it to be acceptable,

g.

(Closed) Open Item (445/8511-0-23):

Group of cables bearing on

single cable,

Further review by the NRC found NCR E85-101047X had

been dispositioned and closed.

The disposition stated that the

indentation of the cable outer jacket was minor and would not affect

conductor performance.

The NRC inspector performed a reinspection of

the cable and found that the NCR had been properly dispositioned.

h.

(0 pen) Open Item (445/8511-0-24):

Lack of cable slack. This item

pertained to a lack of the required 2" of cable slack at the cable

tray (T130SC65) to conduit (C13015570) transition for cable E010C091.

Further review by the NRC showed NCR E85-101211SX had been written

for this deficiency.

This item remeins open pending disposition of

the hCR.

i.

(0 pen) Open Item (445/8511-0-31):

Cable with cut outer jacket. This

item pertained to a two conductor cable with a cut outer jacket which

was located at the floor penetration for motor control center (MCC)

_ _... _ _ _.

r

l

.

l

'

-7-

l

IEB1-1.

Further review by the NRC showed NCR E85-101048X had been

written for this finding. This item remains open pending disposition

of the NCR.

j.

(0 pen)OpenItem(445/8511-0-32):

Incorrect tray to conduit

I

separation. This item pertained to less than the required 1" of

l

separation between a cable tray (T030 SCC 68) and a lighting conduit.

Further review by the NRC shoed NCR E85-1001805 had been written for

this finding. This item remains open pending disposition of the NCR.

k.

(Closed)OpenItem(445/8511-0-38): This item perteined to the lack

of CPRT quality instructions governing ISAP I.1.5 activities.

'

Further review by the NRC of the required tasks, redispositioning of. -

NCRs and obtaining a vendor analysis report, showed that the

,

activities were already governed by acceptable existing site

procedures.

1.

(Closed) Violation (445/8511-V-01):

Inspector failed to write NCR.

During an NRC witnessed reinsperb on, a TUGCo QC inspector failed tot

document nonconforming conditions and process an NCR in a prompt

manner relative to out-of-scope ERC inspection findings. The

inspector involved was retrained to Procedure CP-QP-16-0,

"Nonconformances," on September 16. 1985.

For the nonconforming

conditions identified, TUGCo has issued NCR E85-100993X.

In addition

to the above actions, ERC Procedure CPP-020 "Out-of-Scope

Observations," Revision 0, was issued on August 23, 1985, to provide

a procedure to third party inspectors to follow in documenting

out-of-space observations.

,

m.

(Closed) Open Item (445/8511-0-37):

Prior to the development of the

design adequacy procedures (DAPs), TERA personnel used informal work

instructions to control their activities.

The DAPs manual was issued in October 1985. This manual is fully

developed, presently containing 23 procedures.

NRC inspectors from

the QA branch in the Office of Inspection and Enforcement have

inspected the adequacy and implementation of these procedures at

TERA's office in Bethesda, Maryland, and Berkeley, California.

The

_

results of these inspections are documented in NRC Inspection Reports

50-445/86-17; 50-446/86-14 and 50-445/86-19; 50-446/86-16.

]

NRC personnel involved in these inspections observed that very little

i

work was performed by TERA prior to March 1986 that would have

required these procedures being in place. Therefore, the DAP manual

was issued before substantive TERA work was conducted.

n.

(Closed) Deviation (446/8513-D-11): This deviation addressed field

-l

reinspection of a containment liner packages that included weld seams

i

between materials of unequal thickness. Change Notice 001 to QI-031,

l

Revision 2, provided guidelines for measuring reinforcement of welds

w_- -_-_

_

- - _ _ _ - _ _ _ - _ _ - _ _

.

_

e

{

'

.

-8-

using a contour gauge for weld seams between materials of unequal

p"

thickness. Approximately 38 containment liner packages were

reinspected. Two new DRs were issued, ten were superseded, and six

"

were invalidated. The NRC inspector inspected containment liner

Verifiu. tion Package I-S-LINR-061 using Change Notice 001 to QI-031,

Revision 2, and found the weld reinforcement to be acceptable. A

sample of the results of the' additional reinspection by ERC for weld

reinforcement was reviewed by the NRC inspector. The committed

corrective actions were found to by the NRC inspector to have been

correctly implemented.

o.

(Closed)'Open Item (445/8513-0-01): TERA identified a potentially

reportable condition on August 27, 1985. This open item was to track

its disposition.

Discrepancy / Issue Resolution Report (DIR) D-0004 was initiated by

TERA on August 27, 1985, concerning the evaluation of an air gap

deviation using methodology in apparent conflict with FSAR

commitments. On Vuly 26, 1985, a significant deficiency analysis

report was issued (CP85-27) and the NRC was notified that the matter

was.potentially reportable under paragraph 50.55(e) of 10 CFR Part 50.

On December 17, 1985, this item was determined to be

reporteble and e report was submitted to the NRC. This matter is

I

included in the CPRT's assessment under ISAP II.c, which the NRC is

monitoring on a continuing basis. Accordingly, this item is closed,

p.

(Clesed) Open Item (445/8513-0-25):

Conduit separation and loose

fittings. This item pertained to two loose conduit couplings'and

separation between two conduits being less than the required 1".

These conaitions were identified during a witnessed ERC inspectier,

and were' additionally addressed in NRC Inspection Report

50-445/86-01; 50-446/86-01. NRC review during this report period

found that NCR E85-101496SX had been dispositioned and closed. The

disposition of the NCR required the couplings to be tightened and the

conduits reworked to meet the 1" requirement. The NRC performed an

inspection of the conduits and found the reworked condition

acceptable,

q.

(Closed) Open Item (445/8513-0-28):

Incorrect tray node

identification. This item pertained to a trey section identification

tag not located as shown on Drawing 2323-El-0500-15.

Further NRC

review of Drawing 23E3-El-0500-16 found that note 1 is used only to

identify the location of the tray segment, not its identification.

Review of TUGCo Instruction QI-QP-11.3-24, " Class IE Cable Tray

Raceway Inspections," by the NRC inspector found that the tray

identification tag was properly installed.

r.

(0 pen) Open Item (45/8513-0-38): Misaligned torque indicators.

This item pertaint:0 to anti-torque.

Indicators on flexible hose

connections wicch were misaligned.

Further NRC review found that

DR-I-E-ININ-005-DR01 and NCR 175-101251SX had been written for this

condition. This item remains open pending disposition of the NCR.

_ _ - - - _ - _ -

-

.

>

'

.

-g-

l

(0 pen)OpenItem-(445/8513-0-39):

L % lighting switch box. This

3.

item pertained to a lighting circu t. switch box which was loose.

I

'

Further NRC review found that NCR E86-101053X had been written for.

this condition. This item remains open pending disposition of the

NCR.

t.

(0 pen) Open Item (445/8514-0-03): Cable routing and conduit

H

,

identification. The conditions of incorrect routing for cable

j

'

EG113538 end two through-wall conduit. sleeves with the same

identification number were noted during a witnessed ERC inspection.

.)

Review of ERC Verification Package I-E-CABL-078 by the NRC inspector

showed that DR I-E-CAB-078-DR01 and NCR E85-101382SX had been written

!

for these conditions. This item remains open pending disposition of

.

the NCR.

i

u.

(Closed) Open Item (445/8514-)-11):

Incomplete procedure. The

i

condition that an ERC procedure (Q0-009) did not reference the

!

specific procedures for plant Class IE lighting conduits was resolved

i

by the initiation of e new population for lighting circuits.

The new

population covered all aspects of the plant lighting circuits,

including the conduits, and resulted in the removal of lig~nting

circuits from the other populations;

i.e., conduit, cables,

equipment. Therefore, the new population eliminated the need to

,

incorporate lighting conduit procedures in the conduit inspection

'

procedures.

v.

(Closed) Deviation (445/8516-D-41):

This deviation

addressed:

(1) an inconsistency regarding measurement of liner

contour between ERC QI-031, Revision 0, for containment liner

reinspection and Gibbs & Hill (G&Fi) Containment Liner

Specification 2323-55-14, Revision 4; and (2) a failure to provide

comprehensive instructions far reinspection of containment liner

contour using a 10' straight edge.

l

The committed corrective action involved the revision of the

applicable paragraphs in QI-031.

ERC conducted a review of each QI

,

for clarity and discussed changes to QI-031 with the ERC inspectors.

'

QI-031 was revised and Revisior. I was issued on January 15, 1986. A

review of inspection packages completed prior to this date was

i

l

reviewed by the NRC inspector.

The committed corrective actions have

I

been made to determine if any package was inappropriately marked

"N/A" for Attribute A.1.b.

In addition, ERC determined that previous

inspections using the 10' straight edge (Attribute 1.1.d) were

correctly performed.

The NRC inspector reviewed the changes made to Q0-031 to assure

consistency with G&H Specification 2323-SS-14 and that adequate

instructions were provin d for the measurement of containment liner

contour. The NRC inspector also discussed with the ERC population

engineer and inspectnrs, the methods used for inspection of these

ettributes prior to January 15, 1986.

The NRC inspector reviewed an

- _ - _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ - - -

_ _ _ _ _ - - - _ _ - - -.

- - _ - - _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

-10-

additional ten containment liner reinspection packages and determined

that the original ERC reinspection conformed to Attributes A.1.b. and

A.I.d of QI-031, Revision 1.

The committed corrective actions were

verified to have been implemented.

(Closed) Deviation (445/8516-D-42): This deviation addressed field

w.

reinspection of containment liner packages by ERC that were not

performed in accordance with approved instructions.

The ERC

inspector entered "N/A" for not applicable and " dome only" in the

remarks column for Attribute A.1.a on the checklists for three

,

containment liner packages.

These verification packages involved the

!

cylindrical liner and Attribute A.1.a did, in fact, apply.

l'

.

The committed corrective actions involved the revision of ERC QI-031

and a review of reinspection packages.

In addition to the 3 noted

verification packages,14 other packages initially reinspected by the

same ERC inspector were identified as having "N/A" and " dome only"

entered for Attribute A.1.a.

These packages were reinspected for

Attribute A.1.a and two new DRs were issued regarding liner contour.

The NRC inspector has reviewed the corrections made to QI-031, the

results, of the ERC reinspection of Verification

Packages I-S-LINR-08, I-S-LINR-12, and I-S-LINR-61, and three of the

additional packages reinspected by ERC for Attribute A.I.a.

The

committed corrective actions have been verified by the NRC to have

been implemented.

!

(Closed) Deviation (445/8516-D-47): This deviation addressed the

I

x.

completeness and accuracy of an ERC checklist for a concrete

l

'

placement reinspection. Attribute 3.1 of the completed checklist for

Verification Package I-2-CONC-015 was neither accepted nor rejected;

i.e., not signed off, and actual reinspection for this attribute

j

could not be. verified. The checklist was approved and signed by both

!

the lead inspector and the lead discipline engineer.

l

.

The committed corrective actions were the' reinspection of this

l

verification package for Attribute 3. A. and ERC management meetings

,

with all ERC inspectors and leads to emphasize the importance of

providing complete and accurdte information. The overview inspection

,

l

program has also been implemented to reinspect a sample of each

l

inspector's work.

The NRC inspector reviewed ERC's reinspection of

l

Verification Package I-S-CONC-015 and established from record review

j

that training meetings were held with ERC inspectors and leads. A

,

review of the overview inspection program is ongoing.

The committed

corrective actions have been implemented.

y.

(Closed) Devi6 tion (445/8516-D-48):

[ Note:

This deviation was

incorrectly identified as 445/8516-D-47 in the Notice of Deviation,

NRC Inspection Report 50-445/85-16; 50-446/85-13. Appendix D of that

report correctly identified the deviation as 445/8516-D-48]. This

deviation addressed field reinspection of a concrete placement

packege by ERC that was not performed in accordtnce with approved

f

l

_

)

I

.

.

-11-

instructions.

The ERC inspector entered "N/A" for not applicable and

" coated" in the remarks column for Attribute 3.A'on the checklist for

Verification Package I-S-CONC-057. A subsequent NRC inspector,

however, identified that the surface was not coated.

i

The committed corrective actions involved discussions with the

inspector and a historical review of the inspector's activity by the

ERC overview inspection program.

No additional errors were

identified. The ERC inspector stated that reinspection was made on a

-

blockout immediately adjacent to theLdesignated blockout. The NRC

inspector has reinspected Verification Package I-S-CONC-057, verified

)

ERC's reinspection of the correct blockout, and reviewed the results

J

of the ERC overview inspection program. The committed corrective

-)

'

actions have been implemented.

z.

(Closed)' Unresolved Item (446/8602-U-12):

It was not apparent that

inspection of square groove weld penetration conditions had been

considered in the Corporate Consulting & Development Company, Ltd.

(CCL) reanalysis of HVAC supports.

q

Further review of this item identified Memorandum No. BSC-2156, which

i

references Section 6.2 of Revision 8 to Bahnson Service Company (BSC)

'

Procedure DFP-TUSI-003 and states, "The following shall-be considered

a part of the subject procedure:

All groove welds on the seismic

duct hanger detail drawings shall be shown as square groove welds.

Unless otherwise stated the weld shall be considered partial

penetration.

No size will be shown.

Per the attached test results a

penetration of not less than 1/8" (0.125") is achieved. These tests

results with coupons are retained in DCC."

.

This 1/8" penetration has been used in CCL's reanalysis of HVAC

supports in Unit 2.

However, the available documentation for the

original test program did not assure that the test results were fully

representative of minimum penetration conditions that could occur

during field welding; i.e., the position dsed to weld the samples was

not recorded and etching was performed on weld sample ends rather

than on sections cut from samples.

Further, the tests coupons were

not retained in the Document Control Center (DCC) and could not be

,

located.

L

(

Additional welded samples were prepared and sections macroetched,

with the NRC inspector witnessing the activities.

The samples were

welded with a 3/32" electrode in the vertical position using BSC

Welding Procedure Specification BSC-20. Macroetching of sections

revealed a maximum partial penetration of 0.047", which is 0.078"

less than the claimed penetration used for reanalysis.

i

_

i

/k l &*f.2.$YW

/

W W

Y

i

!

.

-12-

,

3.

Employee Protection Posting

The unresolved item has been closed and replaced by a violation, as a

result of the failure to provide an appropriate test basis for assumptions

used in the design analysis (446/8620-V-02).

Paragraph (e) in 10 CFR Part 50.7, " Employee Protection," requires the

applicant to post Form NRC-3 " Notice of Employees" on its premises.

Posting must be at locations sufficient to permit employees to observe a

copy on the way to or from their place of work.

As a result of recent relocations and modifications to entrances and

exits, the NRC inspector performed an inspection to determined if TUGCo

was in compliance with the above requirements. The inspection revealed

l

that TUGCo was in compliance in that Form NRC-3 had been conspicuously

l

'

posted at all entrances and exits to the job site, and at various

locations within Units I and 2.

No violations or deviations were identified.

Action Request (MAR) 85-0757 as implemented by Operation Traveler

EE85-11348-2203.

No violations or. deviations were identified.

4.

CPRT ISAPs (Excluding ISAP VII.c)

a.

Butt Splice Qualification ISAP I.a.3

'

The NRC inspector participated, with representatives of NRR and the

applicant, in an inspection of selected Unit 1 panels known to

contain the AMP splices thet are the subject of this ISAP.

The

panels (i.e., control room relay panel CR-03, cable spreading room

termination cabinets TC 41 and TC 42, and auxiliary building MCC

CEB 4-1) were inspected to familiarize the NRR representative with

the type of installations and configurations in which the splices are

installed.

During this inspection, the NRC inspector noted wrappings of

electrical tape on a conductor in control room panel CP1-ECPRCR-03.

l

The green conductor of cable E0112530 was subsequently identified as

having had its insulation repaired and inspected by Maintenance

Action request (MAR) 85-0757 as implemented by Operation Traveler

EE85-11348-2203.

No violations or deviations were identifiad.

i

!

- _ _ _ _ _ _ _ _

l

.

-13-

b.

QC Inspector Qualifications (ISAP I.d.1)

During this report period, the activities identified by NRC Reference

No 01.d.01.04 were inspected as follows:

Phase III Sample Selection and Reinspection (NRC Reference No.,

-01.d.01.04

The NRC inspector reviewed four reinspection matrices approved by the

ERC Discipline Level III inspector. These matrices were used to

evaluate the performance of those inspectors placed into Phase'III

due to documentation difficulties with their. qualifications.

The

reinspection matrices were for TUGCo Instructions QI-QP-11.2-1,

.

.

Revision 16, " Installation of Drilled-in Hilt! Bolts"; QO-QP-11.14-8,

Revisions 1 and 2, " Verification of Installation of Richmond Insert

Bolts"; QI-QP-11.0-15. The NRC inspector verified that the

reinspection matrices identified the inspection procedures and

designated the inspection attributes as recreatable/nonrecreatable

and subjective / objective as defined in ERC QI-005, " Evaluation of-

Inspector Performance."

The NRC. inspector witnessed the ERC Phase III reinspection of TUGCo

l

Inspection Reports (irs) 2-0010162 and 2-0020136.- Subsequent NRC

review of the completed ERC reinspection matrices for these two irs

found them to be complete and to properly reflect the actual field

conditions.

No violations or deviations were noted during this inspection.

~

c.

Craft Personnel Training ISAP I.d.3)

During this report period, the ISAP activities identified by NRC

Reference Nos 01.d.03.02, 01.d.03.03, 01.d.03.04, 01.d.03.05,

01.d.03.06, and 01.d.03.07 were inspected as follows:

,

Interview Personnel (NRC Reference No 01.d.03.02)

The NRC inspector reviewed the documentation from the interviews of

site personnel conducted by ERC.

Thirty-seven interview of personnel

were conducted, with the selection of personnel interviewed ranging

from general superintendents to craft journeymen and helpers

The NRC inspection was performed to determine if' the attributes

listed in Section 4.1.2 of the ISAP were included. Since no

established list of questions was utilized.in the ERC interviews, the

NRC inspector reviewed the interviews to assure that each attribute

was included.

It was found that the interviews in total did address

-

each attribute, although not every attribute was applicable or

addressed in each interview; e.g., attributes applicable to

management were only addressed in the management interviews.

_ _ _ _ _ -

.

...

..

.......

..

..

..

._

..

.

.

.

'

From review of interviews, the NRC inspector determined that specific

areas of NRC Technical Review Team (TRT) concern, such as knowledge

of criteria used for lifting of heavy. loads and installation of

electrical supports were addressed in interviews of the

representative craft personnel.

Separate NRC interviews of personnel are planned to be conducted

during a subsequent inspection.

No violations or deviations were noted.

Observe Training and Field Activities (NRC Reference No. 01.d.03.03

.

The NRC inspector reviewed the records of ERC's observations of

training and field activities.

These records showed that one class

each of mock up training, classroom training, and procedural training

were observed. The lesson plan for each class was reviewed by the

NRC inspector. The ERC observations were.found by the NRC inspector

,

to be in agreement with the lesson plans..The records'of field

'

activities observed showed that 11 field activities were observed

which included inst 611ation of Hilti bolts and pipe hanger rework in

the mechanical discipline, cable termination and pulling in the-

electrical discipline and installation of a duct and a duct hanger

for HVAC. The field observations lists were noted by the NRC

inspector to attributes that would be found in the applicable

procedures, but did not give either a direct reference to the

procedure in most cases, or provide specific evidence of craft

compliance with these attributes.

The ERC observers were determined

by the NRC inspector from file review to have previously reviewed the

craft procedures to familiarize themselves with the craft activities.

l

to be observed. The NRC inspector verified that the listed

procedures were applicable to the field activities observed.

Additional assessment of the adequacy of field activity observations

will be made during a subsequent NRC inspection.

,

No violations or deviations were identified during this inspection.

Recommendations for Improvement and Evaluation of Changes (NRC

Reference Nos. 01.d.03.04 and 01.d.03.05)

~

The NRC inspector verified performance of the following ERC

activities by inspection of documents in the working files for this

ISAp.

.

!

ERC addressed through implementation of this ISAp the specific TRT

.

concerns for conduit supports, lifting of heavy loads, and the

i

general concern of craft training.

ERC found by interviews of

electrical personnel and observation of a conduit support

installation that craft were aware of necessary documents of

installation, but did not always recall the formal name of the

documents.

ERC found by review of the training procedure, interviews

._--___-__a

- _ _ _ _ _ _ _ _ _ _ _ _ _

i

.

-15-

-

of rigging personnel, using records, and a field observation that

training related to lifting of heavy loads was adequate. ERC also

found as e result of interviews, procedure review, and field

i

observations that the training programs of Brown & Root (B&R) and BSC

craft personnel were adequate and therefore recommendations for

l

improvement or evaluation of changes were not applicable.

The NRC inspection inspected the current training procedure of B&R

i

and found that it met the requirements of ANSI N45.2, 1971, and the

l

guidelines on training given by Section D of the Gray Book, " Guidance

i

on Quality Assurance During Design and Procurement Phase of Nuclear

Power Plants." The NRC inspector verified a portion of the training

records listed in the ERC working files by reviewing the signed

j

attendance sheets in the TUGCo training files. The NRC inspector

l

inspected the lesson plans for the training classes that were

monitored by ERC and found that the lesson plans support the ERC

observations of mockup, classroom, and procedural training adequacy.

!

l

The ERC review of Corrective Action Requests (CARS) was related to

l

'

craft training inspected by the NRC inspector.

A sample of the CARS reviewed by ERC was inspected in detail.

These

CARS were found by the NRC inspector to support ERC's determination

that most craft training related CARS pertained to documentation,

administrative, and clerical deficiencies rather than craft training

program or implementation deficiencies.

NRC inspection of the BSC

training program will be reported in a subsequent inspection report.

No violations or deviations were identified.

)

l

Qualification of Personnel (NRC Reference No. 01.d.03.06)

l

l

The NRC inspector verified the qualification of personnel associated

I

'

with the evaluation of this ISAP.

The resumes and objectivity

l

questionnaires from the personnel files were reviewed and found to

l

meet the requirements of the CPRT Program, Plan.

No violations or deviations were noted during this inspection.

No

further NRC inspection is planned for this reference area.

Root Cause Determined from VII.c Results (NRC Reference

ho. 01.d.03.07

The results report for ISAP I.d.3 was approved by the SRT on

August 27, 1986,

ho program deviations or deficiencies were

identified by ERC; therefore, root cause and generic implication

analyses were determined by ERC to be not applicable.

NRC evaluation

of this determination will be reported when inspection of I.d.3

activities is completed.

Craft training may be determined to be the

root cause of construction deficiencies or adverse trends found

during implementation of other ISAPs, including VII.c.

If this

occurs, the Collective Evaluation Group is responsible for evaluation

f

i

-

_ - _. _ _ -. - _. ~ _ _ _ _ - - _ _. _ - - - - - - - - - _ - - -

i

.

-16-

-

!

-

of that determination. NRC inspection of the Collective Evaluation

Group activities for this ISAP reference area (01.d.03.07) will be

'

reported when the collective evaluation is completed.

No violations or deviations were noted during this inspection.

'

d.

Maintenance of Air Gap Between Concrete Structures (ISAP II.c)

l

The following activities for ISAP II.c were reviewed by the NRC

inspector during this report period:

!

Reinspect and Assess As-Built Condition (NRC Reference No. 02.c.01.00

The NRC inspector reviewed Unit 1 and Unit 2 work in progress on

single wall, secondary wall, and basemat gap initial clean out and

inspection.

These activities are complete for single wall gaps.

The

initial clean out of foam to allow for gap inspection has started for

secondary wall gaps with approximately 70% of the work complete. The

initial clean out of foam and inspection of the as-built condition

has also started for gaps associated with the basemat.

Initial clean out and inspection of double wall gaps is essentially

complete with the exception of several areas at or near the basemat

that are not accessible through existing access points. Two

blockouts, approximately 6' x

5', have been cut through the auxiliary

building walls to provide access to the gaps between the auxiliary

dnd safeguards buildings for both Units 1 and 2 at the 790' level.

Five additional blockouts are planned.

No violations or deviations were identified.

,

Removal of Debris or Rotofoam (NRC Reference No. 02.c.02.00

The NRC inspector witnessed ongoing cleaning and repair activities of

air gaps between structures in Units 1 and 2 during this report

period. These activities included use of,a high pressure water jet

system, concrete removal from single walled gaps, grinding of

concrete in secondary wall gaps to increase the gap dimensions, and

removal of debris through the blockouts discussed above.

NRC inspections were not performed on other activities during this

report period.

l

No violations or deviatiuns were identified.

e.

Plug Weld ISAP V.d)

The following activities for ISAP V.d were reviewed by the NRC

inspector during this report period:

-

_ - - - _ - - - _ _ - -

.

-

.

.

.

..

..

..

..

-

...

__. - - - - _ - - - _ - - -

.

t

-17-

.

Determine Effects of Plug Welds on Quality of Supports (NRC Reference

No. 05.d.09.03

)

I

A concern relative to the effect of plug weld on the quality of

j

supports is the influence on weld properties of the slag removal

i

i

method used during welding. To address this concern, a program was

established by the CPRT in which 3/4" diameter plug welds were made

in 3/8" think predrilled plates.

Three welders were randomly

i

J

selected from a list of all welders qualified to make plug welds.

Each welder was provided with eight test plates and instructed to

make plug welds and remove slag with a chipping hammer and wire brush

on the first four test plates, and a grinding tool on the remaining

four test plates.

Each of the 24 test plates was radiographer per

AWS 01.1.

Three test plates were selected from each slag removal

l

process used by each welder (i.e.,18 plates) and tensile test

(

'

coupons were prepared and tested per ASTM E8.

The two remaining coupons prepared by each of the the three welders

!

were sectioned, polished, and acid etched for macroscopic testing.

The NRC inspector will review all test results and associated

l

documentation during a subsequent report period.

No other activities in this ISAP were inspected during this report

!

period.

{

l

No violations or deviations were identified.

l

J

f.

Periodic Review of the QA Program (ISAP VII.a.5)

'

During this report period, the ISAP activities identified by NRC

Reference Nos. 07.1.05.01 and 07.1.05.02 were inspected as follows:

Develop Criteria for Review of the QA Program (NRC Reference

No. 07.a.05.01

,

i

ERC considered information obtained from INP0 and guidance from the

USNRC Standard Review Plan in developing the review criteria to

assess the current management review of the QA program.

The review

criteria specified that a policy statement of management objectives

for the QA program be published and that specific details be

developed to assure program management's review of progress in meeting

those objectives.

In addition, the review criteria required

management review of:

current QA status reports, including any

deficiencies from all departments; trend' analysis reports; audit

reports; notices and bulletins from externa.1 sources; construction

progress reports; and other typical sources.

The ERC review criteria

further specified that the methods should be detailed by which

management would:

respond to reported information, track deficiencies

and assure that followup and closecut is performed, and provide for an

_ _ _ _ - _ -

)

-

i

-18-

.l

-

annual review of management's actions in meeting the published

l

objectives. The NRC inspector verified that the applicable elements

of the USNRC Standard Review Plan were incorporated in the ERC review

' '

criteria.

The NRC inspector determined that the ERC, review criteria

would provide an adequate basis to perform an evaluation of management

review of the QA program required in paragraph 4.1.2.4 of the ISAP.

j

ERC's development of review criteria is coniplete. No violations or

. I

'

deviations were identified and no further NRC inspection is planned

for this reference area.

I

Evaluation of the prrent QA Program Review Versus the Developed

l

Criteria (NRC Refers nce No. 07.a.05.02

The NRC inspector reviewed the ERC issue coordinator's evaluation of

the current QA program review.

The ERC evaluation reviewed Policy

Statement No.2, Revision 0, issued by the Executive Vice President

for Nuclear Engineering and Operations (NEO). This policy statement

details the QA program objectives and defines the responsibilities of

I

the Director of QA and the organizational vice presidents. The

policy specifies that the vice presidents shal'1 meet periodically to

assess the status and adequacy of the QA program and at least=

annually provide a written assessment of the QA program to the

l

Executive Vice President, NE0. The Executive Vice President, NE0, is

l

l

responsible to assure that an annual independent assessment of the

l

,

TUGCo QA program is performed.

NE0 Procedure 2.20, Revision 1,

" Senior Management QA Overview Program," details the methods by which

the objectives of the policy statement are to be implemented.

The

issue coordinator reviewed NE0 2.20, Revision 1, and attended the

first two meetings of the Senior Management Quali);y Assurance

Overview Committee.

The notes and recommendations of the issue

l

coordinator and the minutes of the overview committee meetings were

,

l

reviewed by the NRC inspector.

The results of this review showed

'

l

that the issue coordinator had evaluated the meetings against the

objectives of Policy Statement No. 2 and the ERC developed criteria.

NRC's review of these notes and Revision 1 of NEO 2.20 showed that

recounendations of the issue coordinator.had been incorporated.

No violations or deviations were identified and no further NRC

inspection is planned for this reference area.

g.

Receipt and Storage of Purchased Material and Equipment (ISAP VII.a.9

Receipt Inspection Report (RIR) 13686 was inspected by the NRC as a

sample of the implementation of ISAP VII.a.9.

During this

inspection, a disc insert for main steam safety valve CP2-2MS-021 and

two spare disc inserts were found not to have required records of

heat treatment available in the documentation package.

The NRC

inspector noted that implenientation if ISAP VII.a.9, Revision 0,

would not have identified the deficiency.

For this and other

_-_-_

_

_-

.-

-19-

-

reasons, ISAP VII.a.9 is undergoing revision. The failure to have

heat treatment records for the indicated disc inserts is a violation

(445/8622-V-02;446/8620-V-03).

h.

Onsite Fabrication ISAP VII.b.1

j

During this report period, the ISAP' activities' identified by NRC

Reference Nos. 07.b.01.01 and 07.b.01.03 were inspected as follows:

)

Review and Evaluate Procedures for Onsite Fabrication (NRC Reference

]

No. 07.b.01.01)

The NRC inspected the review performed by ERC of material storage,

)

fabrication, and inspection procedures applicable to both ASME and

non-ASME onsite fabrication. The ERC review listed the attributes

i

necessary for control of material traceability, _ fabrication

processes, and item inspection for acceptability. The ERC review

then identified where the attributes existed in the historical and

the current procedures.

NRC inspection of the attributes found them

to reflect the requirements of 10 CFR Part 50, Appendix B,

l

Criteria VIII and XIII; ANSI N45.2; and the Comanche Peak FSAR.

The

.

NRC inspector selected several of the attributes for inspection and

verified that the attributes were included in the procedures for the

j

tir.es specified (historical and current) by the ERC review.

{

No violations or deviations were noted in this area and no further

NRC inspection is planned for the reference item.

Review Fabrication Packages (NRC Reference No. 07.b.01.03)

The ERC sample selection and review of ASME-related fabrication

packages were inspected by the NRC inspector.

ERC reviews of

non-ASME packages are near completion and will be inspected and

reported when complete. The 73 ASME-related package reviews were

inspected for overall completeness and adherence to the guidelines of

the ISAP and the review checklists. The following nine ERC package

reviews were selected for inspection in detail:

CC-1-195-015-C42R

SI-1-101-011-C41R

CH-1-206-703-E23R

RH-1-063-010-522R

SI-1-031-033-732K

CH-1-206-703-E23R

PS-2-RB-011-003-2

SW-1-102-066-543R

These package reviews were compared to the hanger packages and other

applicable documents to determine their completeness and accuracy.

NRC inspection showed that eight of the nine package reviews were

complete and accurate for all review criteria, such as welder or

inspector qualifications, all required inspections complete, required

documentation complete and legible, documentation consistent and in

proper sequence, and traceability requirements met. One package was

noted to have failed to record four inspectors and two welders.

This

_

- _ - _ _

.

'

-20-

deficiency was corrected at the time of discovery and all reviews

performed by the responsible document reviewer were repeated.

NRC

inspection of the repeated reviews found them to be satisfactory.

This deficiency has been identified as a deviation (445/8622-0-03;

446/8620-D-04).

No other violetiuns or deviations were noted.

i.

ValveDisa"1bly(ISAPVII.b.2)

t-

Review Cons t etion and QC Procedures to Determine if They Provide

Adequate Controls of Materials During Disassembly / Reassembly (NRC

ReferenceNo.07.b.02.03)

y

NRC Inspection Report 50-445/86-07; 50-446/86-05 documented by

Deviation 445/8607-D-26 the failure of CPRT to identify that B&R did

not have an implementing procedure in existence for a portion of 1983

to control the disassembly / reassembly of valves. The CPRT

investigated to determine the reason (s) for not having a procedure in

effect for the five month time span anc what effect it had on the

valve disassembly / reassembly process.

The CPRT's response is

documented in a memorandum dated May 23, 1986, from Counsil tu

Noonan.

Based on review of the above memorandum, the NRC inspector concurs

with the CPRT finding that with the appropriate portions of QA

Procedure QI-QAP-11-1.26, Revisions 9 thru 12, still in effect, and

the use of an operation traveler similar in format and content to

those utilized prior to the procedural omission, adequate control of

valve disassembly / reassembly existed during this time frame. This

activity is complete.

No violations or deviations were identified.

Perform an Analysis to Determine the Safety Consequences of

Improperly Assembled Valves (NRC Reference No. 07.b.02.03

y

An analysis was performed by CPRT to determine the safety

consequences and f ailure modes of improperly assembled generic

valves.

Generic valves ore those which required disassembly of all

valves of that type and included ITT Grinnell diaphragm valves and

Borg-Warner check valves.

All possible combinations of reassembling generic valve bodies and

bonnets of the same size and type were evaluated in this analysis.

CPRT concluded that improper reassembly could possibly result in a

loss of valve function for Borg-Warner check valves.

For ITT

Grinnell diaphragm valves, it was determined that improper reassembly

would result in ASME Code violations, but not a loss of valve

function.

The NRC inspector reviewed this analysis for v61idity and

completeness, factoring into the review ASME Code requirements and

_ _ _ _ _ _ _ - _ _ _ _ - _ _ _ __

. _ - _ _

_ _ - _ _ _ _ _ _

'

.

q

-21-

)

information received from the' valve vendors.

However, a satisfactory

i

response is required with respect to a previously identified

unresolved item: 445/8607-U-28 before a final. evaluation of this

ISAP element can be made.

This unresolved item deals with the lack-

of consideration in the results report, after stating there was a

potential for switching ASME and non-ASME' bonnets, of the

significance of differences in QA requirements for non-ASME and ASME

Code bonnets.

No violations or deviations were identified.

Additional NRC Findings

'

As a result of DRs identifying the lack of traceability between the

installed bonnet and the vendor supplied NPV-1 form for Valve Tag

Nos. 1-7046 and XSF-179, NCRs were issued by B&R.

NCRs.M-23175N,

Revision 1, and M-23178N were initiated on February 25, 1986, and

were dispositioned and closed out by TUGCo on July 15, 1986.

To-

assess the applicant's review of these nonconformances, the NRC

inspector reviewed the NCR dispositions.

The dispositions stated that documentation, except'for hydrostatic

testing, was received from the vendor-indicating that the bonnet

material met all applicable requirements of ASME Section II and

Section III, ND-2000. The dispositions, hcwever, stated that an

acceptable bonnet hydrostatic test was performed-during the

system / subsystem hydrostatic test, as allowed by-the ASME: Code.

In

order to reconcile the fact that the valve bonnet heat numbers did

not correspond with those specified on the vendor's Nuclear

Valves / Heat Code Identification, the dispositions' stated that the

)

bonnets shall be considered as replacement parts and documented as

such on an NIS-2 form, which is an Owner's Report for Repair and

Replacement.

i

As a result of this review, the NRC inspeotor identified the

following:

(1) The disposition was incorrect with respect to an acceptable

bonnet hydrostatic test being performed during the system /

subsystem hydrostatic test. When a' diaphragm valve is

'

hydrostatic tested as a complete assembly, the diaphragm

isolates the bonnet from any hydrostatic pressures, Therefore,

there is still no evidence of the required hydrostatic test

having been properly performed.

This incorrect disposition of

the NCRs is a violation (445/8622-V-04).

(2) The NRC questions the validity of utilizing an~NIS-2 form to

document as-installed components. This matter is-an unresolved

item pending the applicant providing the NRC with adequate bases

for using the NIS-2 forms (445/8622-U-05).

.

._

-

_

l

l

]

.

^i

'

,

-22-

-

)

(3) Table 3.2-1 in Section 3 of Amendment 56 to the CPSES FSAR-

)

requires that Class 2 and 3 valves shall meet the requirements

I

of the 1974 Edition of Section III of the ASME Code,

Westinghouse P0 546-CCA-1919000-XN, which deals with Class 2 and

f

3 valves, specifies, however, the applicable Code requirement to

)

be Section III, 1971 Edition, Summer 1972 Addenda, Receipt of

'

valves in accordance with this criteria is evidenced by the

NPV-1 form for Valve Tag No. 1-7046 which states, "The material,

design, construction, and workmanship complies with ASME Code,

~

Section III, Class 3,1971 Edition, Summer 1972 Addenda." The

failure to comply with FSAR commitments is a deviation

(445/8622-D-06),

i

i

j.

Pipe Support Inspections (ISAP VII.b.3)

(1) Status of CPRT Activity

The reinspection being performed under ISAP VII.b.3 deal with

pipe supports located in Room 77N and the 42 pipe supports

previously inspected by the RTR. All other pipe support

populations and their samples are being reinspected under

ISAP-VII.c.

Room 77N Pipe Supports

i

Reinspection of the 178 pipe supports identified as being

i

nonconforming by TRT has been completed.

Of the 252 deviations

'

identified, 248 have been evaluated to date, with 99 determined

to be valid.

i

.

TRT Issues - 42 Pipe Supports

Of the 42 pipe supports identified by TRT as being nonconform-

.

'

ing, 40 have been reinspected. Of the 103 deviations

identified, 99 have beer, evaluated to date, with 67 determined

to be valid.

(2) Status of NRC Inspection Activity

Room 77N Pipe Supports

To date, nine NRC inspectors of ERC verification packages have

_

i

been performed with the following one being performed during

this report period:

Verification

Support No.

System *

Unit

Package No.

I-S-PS7N-146

SI-1-001-015-542R

SI

SI - Safety Injection Systen

- - ___-_ _ -__

l

q

-

l

-23-

)

i

)

While performing this inspection, the following conditions were

identified.

)

!

The initial ERC inspector inspected and signed off Attribute 3

J

on the inspection checklist regarding spherical bearing gap and

I

noted.that a gap of 1/32 existed.

Subsequently, the Overview

i

signed Inspector (01) performed the required overview inspection

!

and signed off Attribute 3 on the inspection checklist and noted

that a resultant gap of 0" existed.

During the NRC inspection,

I

however, it was observed that an excessive amount of paint

precluded the ability to measure the resultant gap,'in that

paint filled the gap and masked the bearing assembly. The

acceptance of this attribute by both the ERC inspector and the

>

01, and the failure of the 01 to identify an unsatisfactory ).

decision by the ERC inspector, is a aeviation (445/8622-D-07

l

As a result of this deviation being identified, ERC determined

,

that reinspection of six verification packages which had

previously been inspected by the ERC inspector would be

performed. The reinspected packages are as follows:

I-S-LBSN-048

I-S-LBSR-009

I-S-SBPS-033

I-S-PS7N-001

I-S-PS7N-136

I-S-PS7N-145

The reinspection, which were witnessed by the NRC inspector,

resulted in the identification of out-of-scope observations

pertaining to paint on the spherical bearings for packages

I-S-PS7N-001, I-S-PS7N-135, and I-S-PS7N-145.

Disposition of these out-of-scope observations is an open item

(445/8622-0-08)

TRT Issues - 42 Pipe Supports

There were no NRC inspections perfonded in this area during this

report period.

No NRC inspections were performed in other ISAP VII.b.3

activities.

5.

ISAP VII.c

a.

Electrical Equipment

,

Status of CPRT Activity

ERC has completed 98 reinspection and 98 documentation review

packages of sampled electrical equipment as of August 31, 1986.

- - - _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _

!

"

"

-24-

,

Status of NRC Inspection Activity

,

The status of NRC inspection activity remains unchanged for the ERC

population sample from the previous inspection report; i.e., the NRC

inspectors have witnessed 14 ERC reinspection, performed separate

reviews of 15 documentation packages, and performed 6 separate

reinspection of sampled electrical equipment. The NRC inspectors

i

I

did, however,. perform the following inspection during this report

period.of electrical equipment which was not included in the ERC

population sample:

(1) The NRC inspectors performed an inspection of the four

safety-related refrigeration. units to verify proper

installation. The. inspections included observations that:

.

,

(a) components were properly installed and identified as

indicated on the latest design documents, (b) supports and

,

attachments were properly mounted and secured, (c) protective

j

'

coatings were as specified, (d) electrical separation and

independence were maintained, and (e) provisions related to

environmental qualification of the components were maintained.

The following refrigeration units cool the safety chilled water

system (SCW)-which provides cooling water to various engineered

safety features (ESF) components' room coolers:

Equipment No.

S_ystem

Unit

CP1-CHCICE-05

SCW

CP1-CHCICE-06

SCW

i

CP2-CHCICE-05

SCW

,

CP2-CHCICE-06

SCW

I

~

During the above inspections, the following conditions, which

appeared to deviate from CPSES electrical erection specification

requirements, were identified.

CP1-05

(a) Bolts on the compressor discharge flange were not installed

<

as shown on Drawing 376-09121E;

(b)

Paint on the underside of the compressor was peeling;

(c) Some of the devices inside the control panel had wires

terminated using slide-on, tab type connectors;

(d) A number of wires inside the control panel had a short bend

radius;

(e) A number of connectors had two conductors crimped inside

one connector's barrel;

,

i

_________m______

_ _ ___ _ _ _ _ _ _ _ _ _ _. _. _ _ _ _ _ -. _ - _

,

!

'

,

"

-25-

.

(f)

Fitting No. OPG, inside the control panel, was leaking oil

<

onto relay SG and its associated wiring, which had resulted

in damage to the insulation of one of the wires;

(g) The flexible conduit for switch PRV had the outer jacket

split and falling off; and

(h) Cap type, inline splice connectors were used to terminate

instruments and limit switches.

CP1-06

)

This unit had the same conditions as identified in (a), (c),

<

(d), (c), (f) and (h) above for CPI-05, and.

)

(a) Some splices used to terminate instruments and limit

switches were made using Thomas and Betts (T&B) RC-6

j

'

connectors, which are usually only used for lighting

circuits; and

(b) A cap type, inline splice was installed on a wire in the

control panel.

CP2-05

i

This unit had the same conditions as identified in (a), (c),

(d), (e), (f), and (h) for CP1-05.

CP2-06

.

This unit had the same conditions as identified in (a), (c),

(d), (e), (f), and (h) for CP1-05 and one of the auxiliary oil

pump motor leads was also terminated using a wire nut.

The above findings are an unresolved' item pending the completion

of an NRC review of the applicable requirements for these pieces

of equipment (445/8622-U-09; 446/8620-U-05).

(2)

In addition to the above inspection efforts, the NRC inspector

noted, during a tour of the Unit I cable spreading room, feeder

cable splices and a cable jacket repair inside distribution

snel CPX-ECDPEC-02.

The cover had been removed from this

panel, as well as another panel, to facilitate some plant

modifications;thecableinquestion(EG205704) was, however,

unaffected by those modifications.

The NRC inspector noted that the outer jacket of one of the two

conductors of cable EG205704 had been repaired by wrappings of

electrical tape and that both conductors had been reduced in

size from AWG 4/0 to AWG #2 through the use of reduction

splices. A review of the applicable records showed:

,.

~...

.

. -

y

,

I

.:

.

-26-

(a) The damage to the cable jacket had been. reported in NCR

I

E84-01095, was repaired and the-results recorded in

IR E-1-0036473.

(b) The reduction splices we're installed in accordance wi.th.

construction operation traveler EE83-3520-2-02CT.. The

reduction consisted of installing a terminal lug of the

proper size on'each of the conductors and then bolting the

.,

lugs of one-of the 4/0 and one of the #2.together. These

i

connections were then covered with heat shrinkable tubing.

insulation.

The conductor size reduction was necessary for connection-

-

to the circuit breaker in the panel.

Since the circuit-

breaker was rated for 100 amperes, and a review of the'

applicable plant drawing (2323-El-1701) showed the smaller

'

(#2 AWG) conductor was rated for-116 amperes,. sufficient

current carrying capability was maintained by the

reduction.

No violations or deviations were identified.

b.

Documentation Review of NIS Cable Terminations

Status of CPRT Acti<, g

ERC completed the review 1 the 60 sampled nuclear instrumentation

system (NIS) cable termination verification packages prior to

August 31, 1986.

Because the attributes effecting these connectors

are not inspectable without completely reworking the c~onnectors, no

physical inspections were required.

ERC is continuing the evaluation

of the deviations which were noted during the documentation reviews;

Status of NRC Inspection Activity

,

(1) Procedures Review

The NRC inspector initiated the review of this population during

,

this report period. A review of the procedure which was

<

utilized by ERC (QI-074, Revision 0, dated March 10, 1986,

i

" Documentation Review of NIS Cable Terminations /R-E-NIST").

showed that it required checking five attributes. The ERC

reviewer was required to verify that:

(a) all attributes on the

IR for the connector were indicated to be satisfactory, (b) all-

IR attributes for insulation and resist 6nce measuring were

satisfactory, (c) all IR attributes for the coupling of the

connector were satisfactory, (d) all IR attributes for soldered

connections were satisfactory, and (e) the QC inspector who

verified the above four connection attributes was certified to

the applicable procedure. The NRC inspector also reviewed the

latest revision of the QC installation inspection procedure for

_

_--_-___- _

-

-

!

^

-27-

j

.

NIS connectors, QI-QP-11.3-43, Revision 20. dated February 18,

1986, " Verify Testing and Installation of NIS Triaxial Cable

!

Connectors."

(2) CPRT Records Review

Ten of the completed ERC verification packages were selected at

random and reviewed by the NRC inspector. A total of nine DRs

were noted to have been written by the ERC inspectors for

findings made during their documentation reviews of these ten

packages.

Each package consisted of one NIS connector. Of the

nine DRs, four were written because the heat shrink tubing (H5T)

had not been installed over the completed connection. A

'

!

subsequent review of the applicable requirements by ERC showed

that HST need only be applied to those NIS connectors at the

l

containment penetrations and at the detector wells.

Since all

!

of the connectors in question were equipment connections, HST

!

was not required. One DR was written because the test date was

l

not included in the package; however, the data sheet was

!

subsequently located. Another DR was written because the "0"

l

ring seal between connector halves had not been installed;

!

'

however, the connector in question was, a spare connector which

was coyered with HST and not mated with another connector half.

A seventh DR was written because a procedure step for insulaticn

and resistance measurements had been marked "N/A"; however,

since the connector was not a penetration connection, these

measurements were not required.

The remaining two DRs were

!

written because other steps in the procedure had been marked

!

"NA."

Further review determined that the steps marked "hA" were

not required for the particular application.

ERC, therefore,

determined that all of the nine DRs were invalid.

The NRC inspector questioned the appropriateness of some of the

above determinations with CPRT personnel and the applicant

personnel responsible for the prepar4 tion and implementation of

'

the QC procedure. The inspector was informed that all

connectors located inside the containment were covered with HST;

i

l

the invalidated DRs on this subject were for connectors located

I

outside the containment.

In addition, the entire length of the

j

cable run, excluding active devices, was subjected to an

insulation and resistance measurement test after final

I

installation.

The NRC inspector found no reason to disagree

with the above determinations.

!

l

.

!

!

I

!

_

_ _ _ _ _ _

-_

-

-28-

,

(3) TUCCo Documentation Review

The NRC inspector performed reviews of TUGCo documentation for

the following four verification packages for Unit 1 NIS cables:

Verification

Cable No.

Package No.

R-E-NIST-002

EW-140610

R-E-NIST-003

EY-140308

R-E-NIST-004

ER-140490Z

R-E-NIST-008

EW-140601

i

The results of the NRC inspector's review, which included

-

verification of the QC inspector's certification, were

j

compared to the ERC review findings with no differences

being identified.

!

I

No violations or deviations were identified.

l

c.

Mechanical Equipment Installation

Status of CPRT Activity

ERC has completed 168 reinspection of mechanical equipment

installation items from a total random and engineered sample size of

171.

Two hundred and fifteen valid DRs were issued as a result of

l

the above reinspection.

ERC has completed all documentation reviews of the total sample of 84

documentation review packages.

Two valid DRs have been issued.

Slatus of NRC Inspection Activity

To date, nine inspections have been completed of sample items

previously inspected by ERC. The NRC inspector performed the

following inspections during this report period:

Verification

Equipment Tag No.

System

Unit

Package No.

I-M-MEIN-107

TBX-CSAPPD-01

CS

Connon (1)

1-M-MEIN-019

CP1-CCAHHX-02

CC

I-M-MEIN-263

CP1-VAAUSE-11

VA

CS - Chemical and Volume Control;

CC - Component Cooling Water-

l

VA - Containment Ventilation

l

The NRC inspector identified that ERC engineering during their review

l

of historical data pertaining to Verification Package I-M-MEIN-017,

_ _ _ _ _ _ - _ _ _ _ _

.

-29-

'

'

i

faileo to provide ERC inspectors with accept / reject criteria for the

following work activities described by construction operation

travelers (C0Ts):

(1) COT NE78-101-4901 identified the use of Richmond inserts for

equipment anchoring.

No inspection instruction were provided to

verify adequacy of stud bolt thread engagement.

(2) C0T ME83-1532-4900 identified torquing requirements for Cylinder

Head Cover No.9.

No inspection instructions were provided to

verify satisfactory performance of the torquing operation.

(3)

COT ME78-101-4901 identified a requirement to install the oil

cooler and its associated piping.

No inspection instructions

i

were provided to verify satisfactory performance of the work

activities required for installation.

Subsequent to the NRC inspection, ERC engineering issued inspection

instructions to resolve (2) and (3) above. The failure to include

the preceding work activities in the scope of the reinspection effort

is a deviation (445/8622-D-10).

As a result of the additional inspection activities performed by ERC

inspection personnel with respect to (2) and (3) above, eight

deviations pertaining to nonconforming torque and coupling / alignment

specifications were identified.

However, NRC subsequent inspection

revealeo that the equipment was not tagged to identify the

nonconforming conditions as required by ERC Procedure CPP-010. This

failure to tag)the nonconforming equipment is a deviation

(445/8622-D-11.

.

d.

Pipe Welds / Materials

{

Status of CPRT Activity

l

The Pipe Welds / Material (PIWM) population,was created by combining

j

two previous populations referred to as Large Bore Pipe

l

Welds / Material and Small Bore Piping and Instrument Tubing / Piping

Welds / Material.

In addition, tubing welds were excluded and placed

.

in their own population, and mechanical equipment pressure boundary

j

welds were added as PIWM welds.

The PIWM population was then

i

categorized into two subsets: Large Bore Pipe Welds / Material (LBWM)

subset and Small Bore Pipe Welds / Material (SBWM) subset.

This

.

categorization has been done for the purpose of utilizing the

!

existing inspection QIs and corresponding verification packages.

ERC has completed all of the planned random and engineered sample of

!

180 reinspection packages and the 182 documentation review packages.

Of the five valid DRs which were issued, four have been evaluated, to

date, and determined to be nonsafety significant.

i

l

I

____ _.. _ _

l

- _ _ _ - _ _ _ _ _ _ _ _ - _ _

_ __.

.

-30-

'

.

' Status of NRC Inspection Activity

(1) To date, the NRC inspector has witnessed 15 ERC reinspection

and performed 6 separate inspections of ERC verification

packages. The following three inspections were performed during

this report period:

Verification

Drawing No.

Weld No.

System *

Unit

Package No.

I-M-SBWM-029

BRP-MS-2-RB-044

WE-15

MS

l

I-M-LBWM-054

BRP-BR-2-SB-014

WE-7

BR

I-M-LBWM-038

BRP-MS-2-SB-056

FW-3A

MS

MS - Main Steam; BR - Boron Recycling

No violations or deviations were identified.

(2) The NRC inspector performed a documentation review of the following

four ERC population samples:

i

Verification

Drawing No.

Weld

System * Unit

Package No.

No.

.

R-M-PIWM-174

BRP-BR-2-014

WE-7

BR

R-M-PIWM-046

BRP-MS-2-RB-044

WE-15

MS

R-M-PIWM-110

BRP-MS-2-SB-056

FW-3A

MS

R-M-PIWM-2004 TNE-12-2107-04-B-01-1Q2 FW-14

CS

"

BR - Boron Recycling; MS - Main Steam; CS'- Chemical and Volume

Control

No violations or deviations were identified.

e.

Equipment Supports

Status of CPRT Activity

j

ERC reinspection of equipment supports is complete with 70 support

packages reinspected and 128 DRs issued.

Eighty-nine DRs have been

determined to be valid. Documentation review is also complete with

225 DRs issued.

No safety significant deviations have been

identified.

Status of NRC Inspection Activity

(1) Two ERC equipment support inspections were witnessed by the NRC

,

inspector during March 1986.

The discussion of the following

_ _ _ _ - _ - _ _ _ - _ _ - _ _ _ _ _ _ - _ _ - _ - _

- _.

. _ _.

<

=

'

-31-

.

witnessed inspections was inadvertently left out of NRC

Inspection Report 50-445/86-03; 50-446/86-02:

Verification

Equipment No.

Building *

Unit

,

Package No.

I-S-EQSP-002

CP2-EPBCED-03

AB

Connon

I-S-EQSP-010

CP2-ECDPED-01

CR

Common

AB - Auxiliary Building, CR - Control Room

During the above reinspection, ERC identified the following

conditions to the NRC inspector as subject to evaluation as

.

potential deviations:

I-S-EQSP-002: A channel was incorrectly located by 1/4" and a

weld length was undersized for 1 3/4".

I-S-EQSP-010: The support location was not in accordance with

the installation drawing.

The gap between the panel and the

concrete wall exceeded the allowable of 1/2".

In addition, a

Hilti bolt spacing violdtion was identified.

Dispositions of the above findings are open items (445/8622-0-12

and 445/8622 0-13).

(2) The following seven equipment supports were separately

reinspected during this report period:

Verification

Equipment No.

Building *

Unit

Package No.

I-S-EQSP-008

CP1-VAFNAV-32

DG

I-S-EQSP-023

CP2-ELDPEC-04

DG

I-S-EQSP-027

CP2-VAFNAV-27

DG

1-S-EQSP-038

ILCS5691A

DG

I-S-EQSP-045

ILCS5803

AB

I-S-EOSP-049

CPX-EPTRET-04

CR

Common

I-S-EQSP-052

CP2-ELDPEC-14

CR

Conrnon

DG - Diesel Generator, AB - Auxiliary Building,

CR - Control Room

The above seven equipment supports had been previously inspected

by the ERC 01.

The initial ERC reinspection of Verification

Package I-S-EQSP-023 was evaluated as unacceptable by the

ERC 01.

The initial ERC inspector rejected Attribute 6F(i)

because nuts and washt'rs were not installed on two Hilti bolts.

Note 10 of DCA 3273 states, "If Hilti violations occur between

existing Hilti Kwik bolts ono new added Hiltis, remove nut

permanently from existing Hilti Kwik bolts." Note 5 of DCA

.

~

- _ _ _ _ _ _ _

..

.

-32-

.

20659 states that the Hilti bolts inside the panel.are not

necessa ry. The 01 determined that a DR saould not have been

. issued. Upon evaluation of this finding by the overview

supervisor, a decision was made to accept the initial ERC

inspector's DR, since the identity of the new verses existing

Hilti bolts could not be determined. Thus, Note 5 of DCA.20659

was not opplied.

The initial ERC reinspection of VeHfication

Package I-S-EQSP-052 was evaluated as unacceptable by the

ERC 01. Two additional DRs were issued. Attribute 3,

configuration, was rejected by the ERC OI.

The_ bottom of the

panel was 5/8" from the wall whereas DCA 14811 allowed 1/2"-

maximum. Attribute 6F(ii), anchor bolt nut engagement and

bearing, was alsu rejected by the ERC 01. One Hilti bolt was

installed without a required washer.

ERC Overview inspection results agreed with the initial ERC

reinpsections for the remaining five packages listed above.

No violations or deviations were identified.

f.

Fuel Poor Liner

Stetus of CPRT Activity

ERC has completed 62 reinspection of the fuel poor liner from a

population sample size of 62. ' Ten valid DRs were issued as a result

of the above reinspection.

ERC has completed 100 documentation reviews from a total sample size

of 100.

Forty-four valid DRs have been issued as a result of the

above documentation reviews.

Status of NRC Inspection Activity

,

(1) The NRC inspector witnessed the following ERC inspection during

December 1905, the discussion of which was inadvertently omitted

from NRC Inspection Report 50-445/85-18; 50-446/85-15:

Verification

Weld

Unit

Package No.

I.Do.

I-S-FPLR-163

1161

No deviating conditions were identified during this inspection.

-_

_ _ _ _ _ _ _ _ - _ - _

-

.

33-

-

.

(2) To date, the NRC inspector has performed the following

inspections of ERC inspected ~ packages:

Verification

Weld

Unit

Tackage No.

I.F~"~Ro.

I-S-FPLR-004

969

I-S-FPLR-111

1748

I-S-FPLR-029

1052

Common (1)

I-S-FPLR-072

1049

I-S-FPLR-058

1015

Common'(1)

No violations or deviations were identified.

g.

Small Bore Piping Configuration

Status of CPRT Activity

ERC has completed all reinspection of small bore piping

configurations from the planned random and engineered sample of 99.

Seventy-nine' valid DRs have been identified and issued.

Status of NRC Inspection Activity

(1) To date, the NRC inspector has witnessed seven ERC reinspection

and performed seven separate inspection of ERC. inspected

packages, of which the following three separate inspections

occurred during this report period:

Verification

Drawing No.

System *

Unit

Package No.

1-M-SBC0-023

BRP-GH-X-AB-068

GH

Conmon

I-M-SBC0-097

BRP-RC-1-RB-039

RC

1-M-SBC0-121

BRP-RH-1-SB-011,

RH

GH - Gaseous Waste Processing System;

RC - Reactor. Coolant System; RH - Residual

Heat Removal System

(2) With respect to Verification Package I-M-SBC0-121, the.01

identified that in the northwest corner of Room No. 67, the

inspected line and the floor grating angle iron did not meet the

separation criteria of Section 5.2 of QI-026. The deviation was

not identified by the original ERC inspector.

Disposition of

the above item is an open item (445/8622-0-14).

(3) During the inspection of Verification Package I-M-SBC0-121, the

NRC inspector identified two instances where the separation

criteria of paragraph 5.2.6.2 in 01-026 was violated.

QI-026

requires that for pipes operating at 200 degrees Fahrenheit or

- - _ - _ - _ _ _

___

- _ _

_ - _ _ _ _.-__

.

I

-34-

i

i

-

l

greater, a minimum of 1", including insulation, shall be

maintained between the pipe and nc.n,ers. Attribute 1.f

(separation) of the ERC reinspection checklist for this

verification package was accepted by the ERC inspector. lThe.

subsequent overview inspection failed to identify the. deviating

q

conditions; thus resulting in a failure to identify

i

unsatisfactory. decisions made by the ERC inspector. These

failures constitute a deviation (445/8622-D-15).

,

i

These conditions existed between a vertical run of pipe (5' 7

1/2" west of wall D-S and 3' 4" south of wall 5-S at elevation

789'6") and and structural tubing of pipe support

,

RH-1-025-004-S22R, and at elevation 791' 2" with the snubber

rear bracket of Pipe Support No. RH-2-013-008-S32K.

-

h.

Large Bore Piping Configuration

l

l

Status of CPRT Activity

I

ERC has completed all reinfections of large bore piping.

configurations from the planned random and engineered sample of.98.

Sixty-three valid DRs have been identified and issued.

I

Status of NRC Inspection Activity

To date, the NRC inspection has witnessed seven ERC reinspection and

l

performed seven separate inspections of ERC inspected packages, of

'

which the following separate inspections occurred during this report -

period:

~

Verification

Drawing No.

System *

Unit

,

Package No.

I

l

l

I-M-LBC0-087

BRP-CT-1-RB-020

CT

I-M-LBC0-025

CRP-CC-1-RB-057

CC

,

CT - Containment Spray; CC - Component Cooling Water

l

No violations or deviations were identified.

1.

Reinspection of Tubing Welds / Materials

Status of CPRT Activity

ERC has completed all reinspection of tubing welds / materials from

the total random and engineered sample of 99.- Seventeen valid DRs

were issued as a result of the above reinspection.

i

l

ERC has also completed all documentation reviews from the sample of

98 packages.

Fourteen valid DRs have been generated as a result of

l

the above documentation review.

,

L______________._____

_

i

I

J

.-

.

-35-

.

Status of NRC Inspection Activity

Review of this population identified that documentation of NRC

inspection activity had been deferred pending attempted resolution of

i

questions concerning the adequacy of instruction to inspectors in

>

0!-070, Revision 1.

The questions, which 'are somewhat judgmental in

nature, are described in paragraph (3) below.

(1) The NRC inspector has, to date, witnessed the following three

inspections:

j

,

Verification

Drawing No.

System *

Unit

Package No.

I-M-TUWM-024

FSI-0043-17

NI

I-M-TUWM-034

FSI-00043-56

NI

J

I-M-TUWM-036

FSI-00043-54

NI

i

NI - Nuclear Instrumentation

>

I

During these inspections, no deviating conditions were

identified by the ERC inspector.

No violations or deviations

were identified by the NRC inspector.

.

(2) The NRC inspector has, to date, performed the following four

separate inspections of ERC inspected packages:

Verification

Drawing No.

System *

Uni t

Package No.

,

]

..

I-M-TUWM-002

FSI-1-500

MS

I-M-TUWM-008

FSI-1-601-01

RC

I-M-TUWM-016

FSI-1-601-01

RC

I-M-TUWM-025

FSI-1-528

RC

MS - Main Stream; RC - Reactor 8colant

No violations or deviations were identified.

(3) The NRC inspector questioned ERC engineering concerning the

odequacy of QI-070, Revision 1, relative to instructions not

being provided for weld size inspection when the edge of tubing

fittings had either been consumed by welding.or subjected to

grinding. An additional related question was asked concerning

the QI not requiring verification of socket weld fitting sizes.

In the NRC inspector's judgement, fitting size verification

would have permitted more accurate assessment of weld size when

the edge of the fitting was not identifiable.

In attempting o

suitably resolve these questions, TUGCo Quality Engineering was

contracted relative to original inspection criteria used for

weld acceptance. TUGCo Quality Engineering issued NCRs

!

- __-_-_----_

.

-36-

.

M-86-103363 (for Unit 1) and M-86-201978 (for Unit 2) to obtain

suitable resolution of these questions. This subject is

considered unresolved pending disposition of the NCRs and the

NRC review (445/8622-U-16; 446/8620-U-06).

J.

Category I Conduit Supports

Status of CPRT Activity

Reinspection of Category I Conduit supports is complete with 161

support pack 6ges reinspected. A total of 80 valid deviations were

identified. Documentation review is also complete with 160 packages

reviewed. A total of 186 valid deviations were identified.

Status of NRC Inspection Activity

The NRC inspector has, to date, performed the following eight

separate inspections of ERC inspected packages, all of which occurred

during this report period:

Verification

Support No.

Unit

Package No.

I-S-COSP-071

C14W-13102-05

I-S-COSP 073

C140-06419-01

I-S-COSP!046

C03G09956-04

I-S-COSP-003

EAB9-5

I-S-COSP-017

ESB2-21

I-S-COSP-024

ESB8-6

1

1-S-COSP-042

C12G-16958-08

-

I-S-COSP-009

C146-20047-01

No violations or deviations were identified,

k.

Inspection of Nonpressure Boundary Welds for a Supplementary

Evaluation of Visual Weldino Inspection T6thniques

StatusofCPRTActivity

All inspection activity is complete.

Status of NRC Inspection Activity

(1) All inspection activity is comp'ete.

- _ - _ _ _ _ _ _

.. _.

..

.

-_

'

.

F

~

-37-

(2) The NRC inspector witnessed the.following inspection during

March 1986 which was documented in NRC Inspection

Report 50-445/86-03; 50-446/86-02:

Verification

Equi 3 ment

System *

Unit

Package No.

Tag

Vo.

I-S-NPBW-004

FW-1-017-908-C77W

FW

4 - Steam Generator Feedwater System

An open item was identified during the inspection; however, its

discussion was inadverte.ntly left out of the NRC inspection

-

report. The following is a discussion of that open item.

During the second phase inspection (after removal of coating),

,

the NRC inspector identified what appeared to be an unacceptable

weld surface condition; i.e., not suitable for nondestructive

-1

examination (NDE). This open item was resolved by the

J

performance of a magnetic particle examination (MT) of the' weld

by a Brown & Root (B&R) Level III NDE examiner on June 30, 1986,

)

using NDE Procedure'QI-QAP 10.2-2, Revision 4.

The result of

j

the MT was documented on MT Report No. 22583, and showed that

the weld surface condition was suitable for NDE.

No rejectable

indications were observed.

No violations or deviations were identified.

)

6.

Assessment of Allegations

,

a.

AQ-148 (4-05-A-15), AQ-155, and AQ-157 (4-85-A-30):

It was alleged

that the construction start-up/ turnover surveillance (CSTS) group

performed a QA surveill6nce of the warehouse and bulk material

storage (laydown) areas and found deficiencies.

The QC group had

performed a similar surveillance in the sdme areas, yet the QC

surveillance did not detect or record any deficiencies (AQ-148 and

i

Althou

AQ-157).

shop (fab shop) gh the QC group had reported the iron fabrication

had satisfactorily implemented corrective action for

previously identified deficiencies, CSTS surveillance found that the

'

same type deficiencies continued.

Also, the QC surveillance of the

feb shop did not detect or record the continuing deficiencies

(AQ-155).

These three allegations were assessed in common since they concern

departures from procedural requirements pertaining to surveillance

of the segregation, protection, and storage of bulk materials.

The NRC inspector reviewed the CSTS QA Surv

' nce Report 85-002

dated January 14, 1985, for the fab shop a'

d that the report

"

identified several deficiencies regarding i

'al storage and one

'

"

deficiency that QC surveillance required by,

cedures were not

'l

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - - _ _.

.

R

-38-

j

i

j

i

documented. The CSTS record package contained documentation of

'

satisfactory corrective action that was implemented by CAR 039 dated

January 16, 1985, which addressed surveillance not being documented.

The NRC inspector reviewed CSTS QA surveillance reports through

.

April 1985.

These reports identified deficiencies in the warehouse

areas that related to maintenance records for stored in place items;

however, no deficiencies similar to those previously identified in

the fab shop were noted. The CSTS record packages contained

documentation of the satisfactory implementation of corrective action

of the maintenance record deficiencies noted. A walkdown ir.spection

by the NRC inspector did not identify any continuing deficiencies or

a

deficiencies similar to previous findings in the fab shop.

j

I

-

All allegers referred to a QC surveillance of the warehouse area

which did not identify any deficiencies; however, a CSTS QA

surveillarme of the same area conducted one day later uncapped pipe

and deteriorated tape on pipe ends. The NRC inspector found that a

QC surveillance report of bulk material storage outside Warehouse C

was performed on April 30, 1985.

On the following d6y, May 1, 1985,

j

the CSTS QA surveillance group performed a random (unscheduled, not

utilizing a prepared QA checklist) surveillance of the same area.

The random surveillance resulted in the issuance of surveillance

deficiency reports concerning pipe end caps missing or damaged. The

deficient items were corrected and the deficiency reports closed.

'

The NRC inspector considered further the differences in the results

of the April 30 survey, which was satisfactory, and the May 1 survey

which identified the deficiencies.

Based on interviews with

personnel involved and review of documentation, it was determined

that the April 30 survey was a visual only inspection of the stored

condition of the items in the laydown yard. The May 1 survey was 6

hands on inspection of protective coverings which identified

deficiencies that would not necessarily be identified during a visual

only inspection.

This difference in inspection technique could

6ccount for the different survey results. #

'

In discussions with the manager, Warehouse and Material Control, the

NRC inspector found that warehouse and receiving QC personnel conduct

weekly and monthly surveillance of all storage areas. While the

requirement for these surveillance are not clearly documented in

procedures, the surveillance results are documented for each area

inspected, a result of implementation of CAR-039.

In addition,

periodic surveys and audits are conducted by personnel from the CSTS

group and the Dallas-based QA audit group. The NRC inspector

reviewed the results of the following surveillance and audits of the

pipe laydown area outside Warehouse C.

,

(2) Monthly surveillance are conducted in 14 areas by receiving QC

personnel. The January through June surveillance reports were

reviewed.

The February report identified seven items not stored

_ _ _ - _ _ _ - _ _ _ - _ _ _ _ _ _ - _ _ _ _ _ _

l

-

)

.

-39-

v

.

properly in areas outside Warehouse C, which were subsequently

corrected. All other reports found conditions satisfactory in this

)

same area.

<

l

(3) CSTS Report No.86-170, conducted the end of March 1986, was

reviewed. This survey of warehousing included the pipe laydown areas

j

outside Warehouse C.

Checklist item #4, based on CP-CPM-8.1,

!

Revision 3, was to verify piping and components were capped and

protected. This item was documented as satisfactory.

I

(4) The Dallas QA group conducted an audit (TCP-86-08) of the warehousing

l

at the site, including the laydown areas outside Warehouse'C..during

l

the weeks of March 3-17, 1986.

No unsatisfactory conditions were

i

noted in the audit report concerning outside pipe storage,

i

!

The NRC inspector discussed the above findings with both the CSTS

surveillance inspector and the Dallas QA auditor. Each confirmed

that the outside pipe storage areas were in compliance with

i

requirements during their inspections.

This is potentially accurate

since the monthly surveillance conducted February 28, 1986, had

l

'

identified seven nonconforming items which had been corrected.

Further, no audits or surveillance since the end of February had

identified nonconforming conditions in the outside pipe storage

areas.

On July 10, 1986, accompained by the manager, Warehouse and Material

.

l

Control, the NRC inspector conducted an inspection of outside storage

at Warehouse C, including pipe storage.

Four pieces of stainless

steel pipe were found with damapeo or deteriorated end covers, which

is a violation of Procedure MCP 10. Revision 9, " Storage and Storage

Maintenance of Mechanical and Electrical Equipment." The manager,

Warehouse and Material Control, initiated immediate corrective

action.

The NRC inspector found several pieces of carbon steel pipe

with end crps in place. When asked why, the manager Warehouse and

Material Control, stated that when carbon + steel pipe is received with

end caps in place they were not required to remove them. This also

is contrary to MCP-10 which states, in part, " Carbon steel piping

'

material or structural tubing shall not be capped."

These conditions are considered a violation (445/8622-V-17;

446/8620-V-07).

/.

Based on the assessment of these allegations, the NRC inspector /

substantiated that the weekly and perhaps the monthly surveHTances

~'

were not completely effective in identifying storace dy M ciencies nor

in preventing ident<ified deficiencies fromtreceivinD The NRC

findings above and those identified in paragraph.7.c of this report

I

are indicative that the alleged ineffectiveness'of the surveillance

l

continues to exist.

The NRC findings concerning material storage

outside was the only example of receiving deficiencies that was

_ _ _ _ _ _ _ _ _ _ - _ _

.

-40-

]

'

-

l

identified that is indicative of ineffective preventive measures

l

while several examples of effective preventive measures, such as

{

CAR-039 were noted.

!

b.

4-86-A-026:

Improper Drilling on Cable Trays

i

l

An allegation was made to the NRC inspectors that craft personnel had

drilled holes through solid bottom cable trays while electrical

cables were installed.

The holes were drilled so that cable ties

could be installed in the bottom of the tray to hold the electrical

l

cables in proper separation positions, The concern was that the

j

drilling through the tray could cause damaage to the electrical

{

cable (s).

.

An NRC inspector identified a similar concern in NRC Inspection

!

Report 50-445/86-14; 50-446/86-11, in that holes were being drilled

through cable trays (paragraph 10.d).

The failure of the applicant

to control the drilling of holes through cable trays containing

,

electrical cables was determined to be o violation of Criterion V of

Appendix B to 10 CFR Part 50 (445/8614-V-03; 446/8611-V-10).

.

,

Therefore, this allegation has been substantiated and the NRC will

follow the corrective actions proposed by the applicant in response

to the above violation.

'

7.

Procurement, Receiving, and Storage

Durir.g this report period, an inspection of TUGCo procurement, receiving,

l

and onsite storage activities was made by the NRC inspector.

The

j

activities of subcontractors that perform safety-related procurement were

{

l

also inspected.

Review of safety-related contracts revealed that BSC is

!

the only subcontractor currently performing onsite safety-related

procurement.

l

a.

TUGCo Onsite Procurement

o

l

Onsite procurement is the responsibility of TUGCo as committed in the

FSAR and the TUGCo/TUSI QA Manual.

Details of organization ore in

TUGCo Procedure CP-SP-1, Revision 0.

A review of the site

procurement procedures found that they include the requirements of

ANSI N45.2.13 (1986).

l

To verify TUGCo implementation of onsite procurement requirements,

the NRC inspector selected ten safety-related P0s issued in the last

i

!

6 months for inspection. The P0sselected were:

(1) CPF-12901-S,

(2) CPF-12913-S, (3) CPF-12971-S, (4) CPF-13022-S, (5) CPF-13114-S,

(6) CPF-13141-S, (7) CPF-13172-S, (8( CPF-13210-S, (9) CPF-13257-5,

(10) CPF-13313-5.

For all of the P0s, the purchasing documents

specified and imposed the applicable technical requirements; i.e.,

codes 6nd standards.

_-

_

.

__

__

.

'

l

-41-

,

The NRC inspector verified chat the PCs were placed-with suppliers

j

from the approved suppliers list or that the items were purchased

j

commercial grand and the required engineering evaluations performed.

The adequacy of the vendor surveillance program was previously

'

inspected and reported in NRC Inspection Report 50-445/86-03;.

50-446/86-02. As a further review, ten vendors were selected and a

verification made that a current audit or evaluation had been

performed. Two of these audits were reviewed in depth.

.

'j

Audit TBBC-3/T of BBC Brown Boveri Inc., was performed by Gilbert

j

Commonwealth for TUGCo, an approved supplier for conducting these

audits. Nuclear Supplier Quality Assurance System Evaluation

i

Checklist developed by the Coordinating Agency for Supplier

]

Evaluation. Audit TWH-34 of Westinghouse Nuclear Components Division

l

was performed by the TUGCo Dallas audit group utilizing their own

prepared checklist. Both vendors QA programs were evaluated as

'

acceptable.

No violations or deviations'were found in this area of the

inspection.

b.

TUGCo Receipt Inspection

The system for conducting receipt inspection was examined for

procedural compliance.

Procedures utilized were-

CP-QP-8-0, Revision 5, " Receiving Inspection"

i

.

CP-QP-8-0-2, Revision 1, " Receiving Inspection Instruction"

i

.

CP-QP-2-1, Revision 21, " Training of Inspection Personnel"

.

QI-QAP-2.1-5, Revision 9, " Training and Certification of

.

'

Mechanical Inspection Personnel."

The qualifications of six receipt inspectors were inspected and found

to be proper with appropriate supporting documentation in the

qualification file.

,

I

The area used for receipt inspection provided controlled access, a

clean and protectet inspection area, a hold area for nonconforming

material, calibrated measuring equipment in current calibration, and

j

an area with controlled temperature and humidity available for

'

receipt inspection of environmentally sensitive material.

Eleven RIRs and supplemental data were inspected to determine if the

requirements of the receiving procedures and purchasing

specification were met. The R0Rs selected were #27448, #26274,

  1. 27699, #27737, #27738, #27698, #27650. #27672, #27857, #27735, and

'

  1. 27734. The receiving requirements were met for all of these RIRs

and no violations or deviations were identified.

)

J

,

_ _ - _ _ _ _ _ _ _ _ _. _ _ _ _ _ _ - _ _ _ _ - - _ _ _ _ _ _. _ _ _ _. _ _. _ _ _ - _ _ - _ _ _ _ _ _

...

,

.

.

..

.

..

-.

.........

.......

.. -......

..

....

.

.

- - - - - - - -

-

.

.

-42-

.

c.

TUGCo Storage

The site storage and laydown areas were inspected for compliance to.

B&R Procedure MCP-10, Revision 9,." Storage and Storage Maintenance of.

Mechanical and Electrical Equipment." Areas inspected were

Warehouse's A and B, Welders Qualification Training Center (WQTC), the-

Pipe Fabrication Shop, Millwrights Shop, and the pipe, steel, and

'

electrical laydown areas. Also, items " stored inplace" inside Unit 2

reactor building were inspected.

The following areas of.

noncompliance were noted:.two level transmitters " stored inplace"

were not protected from overhead grinding activity; electrical cable

in cable trays in Unit 2 were not properly protected from nearby

welding activity; stainless steel tubing with the ends not capped or

capped with tape in degraded condition was found outside in the area

-

behind the WQTC and the layout area north of Warehouse C.

Violations

<

for the unprotected level transmitters and electrical cable was

'

reported in NRC Inspection Report 50-445/86-15; 50-446/6G-12. The

improperly capped tubing was identified as violation of

a

445/8622-V-17; 446/8620-V-07 in this report during the assessment of

-

an allegation.

'

The NRC inspector reviewed Procedures CP-QAP-14-1, Revision 6,

j

" Inspection of Storage and Maintenance of Permanent' Plant Equi

I

CP-QP-19.0, Revision 4," Construction, Start-up/ Turnover (CST)pment";

)

Surveillance"; and MCP-10. These procedures describe storage levels

]

anc' inspection requirements for storage.and maintenance. The-

prc;edures meet the requirement of ANSI-N45.2.2, Sections 2.7 and

6.1.2 for storage levels, and Section 6.4.1, for inspection

requirements.

No other violations or deviations were noted in this area of

inspection.

d.

Subcontractor Onsite Safety-Related Procurement Activity

To determine the procurement, receipt, and storage requirements for

BSC, the NRC inspector reviewed the terms of the BSC contract with

TUGCo.

The contract imposed the requirements of 10 CFR Part 50,

Appendix B; ANSI N45.2, 1971; and ASME,Section III, 1977.

The

!

following BSC procedures for procurement, receipt, and storage of

safety-related materials were reviewed to determine if they

incorporated these requirennents:

Procedure

Ti tle

QFP-4.003-CP1

Procurement of Material and Service from

General Contractor'/0wner

QFP-4.002-CP1

Procurement of Welding and Brazing Material

_ - _ _ _ - _ _ _

_ _ _

.

-

.

-43-

.

!

Procedure

. Title

QFP-4.001-CP1

Procurement Document Control for Nuclear

Projects

QFP-7.002-CPI

Receiving and Storage

QFP-8.001-CP1

Identification and Control of Materials,

)

Parts, and Components

y

<

QCI-CPSES-004

Receiving Inspection and Identification

~ Procedure

l

'

These procedures were found to adequately incorporate-the above

standards and requirements for procurement, receipt, and storage

activities.

j

BSC P0s 1769, 1776, and 1864 and BSC RIRs 511 and 517 were compared

with the criteria of the procurement and receipt inspection

.l

^

procedures. They were found to have been developed and processed in

accordance with these procedures.

The NRC. inspected the inside and outside storage areas as well as the

l

weld road room and oven area.

These areas were found to be in

compliance with the storage procedures and suitable for the type of

material stored.

Inspection of recent surveillance reports for these

,

areas found that surveillance were being performed to the specified

l

frequency and that the area surveillance forms were completed

j

including notation of deficiencies,

i

-

The approved vendors list was reviewed to determine if a current

audit or evaluation had been performed for each vendor. This review

four.d all vendors listed to be in compliance or to have been rernoved

from the approved vendors list.

The qualifications and certification files of all receipt inspectors

were reviewed.

These were found to be in accordance with the

requirements of ANS0-N45.2 and the BSC procedure for inspector

qualification.

No violations or deviations were identified during this area of

inspection.

'

S.

CPRT Central and Working Files

The purpose of this inspection was to verify that the CPRT central and

working files have been established, maintained, and controlled in

.

accordance with the requirements of. Policy and Guideline (PAG) PAG-02,

l

Revisions 0 and 1. " Policy on Assembly of CPRT Program Central and Working

Files,: and PAG-11, Revision 0, " Policy for Controlling Access to the CPRT

'

File and Closed Working Files."

\\

. _.

. _ _

_ - - _

t

.....

.

..

...

.

..

..

..

..

......

...

....

.

.

.

l

..

.,

.

44-

-

PAG-02 describes:

(a) documents to be included in the CPRT central files;

(b) accountability mechanisms; (c) specific requirements for content

organization, and format of ISAP working files; and (d) the criteria used

by the results report and working file review committee (RRRC) in their

]

review of completed working files and results reports for compliance to

l

'

ISAP requirements.

PAG-11 describes the measures used to control access

to CPRT files.

PAG-02 and PAG-11 are implementing documents for CPRT

Program Plan,.Section III.J. "CPRT. Program Records," and Appendix G,

a

Attachment 4, " Verification of Issue-Specific Action Plan Working' Files."

]

It should be noted that FAG-02, Revision 0, and PAG-11. Revision 0, were

!

!

not issued until May 12, 1986, and July 30, 1986, respectively.

Work

accomplished prior to issuance of PAG-02 and PAG-11 was inspected for

.I

-

compliance using the requirements in the CPRT Program Plan,Section III.J.

and Appendix G, Attachment 4.

a.

Organization of Central Files

The description of the central file contents and file index.is

provided in ' PAG-02, paragraph 2 and Attachment 6.6.

To verify

implementation of the PAG-02 requirements, the file index and file

contents log of each file was examined for compliance with

requirements.

In cases where files were too large for 100%

inspection, sampling was used to verify file content.

For example,

j

of the ten closed ISAP working files, seven were 100% inspected and

a

three were sampled.

l

l

i

Tne results of this inspection verified that file indexes, content

logs, and file contents were consistent with requirements. The only

l

exception was the CPRT Program Director's personnel file which did

not contain the required objectivity questionnaire / evaluation

documentation. This matter has been identified as a deviation in

paragraph 2.a of this appendix.

l

b.

Control of Documentation / Files

Accountability of a file is accomplished by matching documentation

r

listed on the content file log against those documents in the file.

Procedurally, documents or document packages contained in the file

are required to be identified with the file number and the content

log sequential number. PAG-02, Revision 1, requires working file

documents or the contents of documentation packages to be

sequentially page-numbered. This allows for accountability and/or

recompiling should pages be mixed after or during reproduction, file

transmittal, or other use. The central file is in the process of

,

numbering pages of working files processed prior to PAG-02,

'

Revision 1.

With the exception of working files, the pages of

documents, such as action plans, results reports, CPRT program plan,

etc., were always numbered.

s

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _. _ _ _

_

__

_ - _-_-___-__- _

_

. _ _

-

.

.

.

45-

-

PAG-11 requires controlled access to the file cabinets containing the

files.

Files are locked when not in use.

With the exception of the

working files, files may be removed from the central file mom by

using check out cards to account for the documents.

The NRC inspected checkout cards, access methods to file cabinsts,

the practice used to review working files in the central file room,

and documentation accountability..The practices used were found to

conform to PAG-02 and PAG-11 requirements.

c.

Verification of ISAP Working Files

l

Appendix G, Attachment 4 of the CPRT Program Plan describes the

'

requirements, responsibility, and criteria for the review and

verification of working file by the RRRC. This review occurs after

the ISAP has been completed and prior to the results report (RR)

being submitted to the SRT for review and approval. The purpose of

this review / verification is to determine:

(1) the contents of the

working file is complete and organized to be consistent with the-

requirements of the CPRT Program Plan, and-(2) the work reported and

"

conclusions reached in the RR are supported by information contained

l

in the working files.

Prior to May 22, 1986, che RRRC performed review activities using

checklists individually developed from Appendix G, Attachment 4.

The

l

checklists listed criteria to be used in verifying consistency

)

between the ISAP, working files, and.RR.

Results of the

review / verification were documented on the checklist with actions

required. After actions required were completed by the responsible

issue coordinator, the RRRC conclusions resulting' form the review and

i

verification were documented in a working file verification report.

'

The verification report was.then submitted with the RR to the SRT for

their review. Of the seven working files reviewed using Appendix G

l

checklist,sixwerefoundinthebackupffle,buttherewasno

commitment to retain the checklist.

In each case, the working file

verification report was in the file to document the performance of

the RRRC review and the conclusions reached.

Retention of the

working file verification report is a requirement.

The three. working files processed by the RRRC using PAG-02,

Revision 0, were found to~ comply to stated requirements of PAG-02 and

Appendix G.

Found in the backup files were detailed checklists

listing criteria to perform reviews, actions required, identification

closure of actions required, and the completed RRRC report submitted

j

I

tu the SRT.

t

l

The NRC inspector witnessed a portion of in-process review of I.d.3

',

by the RRRC and found it to comply with PAG-02, Revision 1,

requirements. A checklist was used to document review results and

actions required.

.

_

_ _ _ _ _ _ _.. _ _ _ _ _. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

e

'

-46-

.

In summary, the NRC inspector determined that the CPRT hao established

measures to develop and maintain the CPRT central files.

Procedures

governing the central file activities have been suitab'ly implemented with

one observed exception concerning the objectivity questionnaire missing

from the CPRT Program Director's personnel file noted above. Other files

appear to contain the required documentation. Accountability and access

to files were controlled per procedural requirement.

With respect to the results report and working files review performed by

j

the RRRC, their reviews were found to conform to the applicable

j

requirements and guidelines.

The inspected documentation confirmed the

{

performance of reviews and that conclusions reached were reported to the

i

/

SRT as required.

_

Based upon a review of central files and supporting documentation, for

RRRC activities, it appears that PAG-02, Revision 0 and 1, and PAG-11,

Revision 0, have been adequately implemented.

.

9.

ERC Overview Inspection Program

i

The purpose of this inspection was to verify that the ERC overview

}

inspection program, as delineated in ERC-QA-28, Revision 3, " Performance

of Overview Inspections," was being implemented in accordance with

requirements. According to ERC personnel, the objectives of the overview

inspection program are:

(a) to measure the effectiveness of ERC

{

activities, and (b) g third party reinspection / documentation review

inspectors performin

to determine the adequacy of QIs in directing

inspection activities. To achieve these reinspection / documentation review

activities, and (b) to determine the adequacy of QIs in directing

,

inspection activities.

To achieve these objectives, the Ols duplicate the

j

initial reinspection or documentation review, then by comparing these

j

results with the initial reinspection / documentation review identify any

inconsistencies.

Inconsistencies are then evaluated for validity and

q

resolution including required actions to prevent recurrence.

'

The NRC inspector developed a checklist detailing requirements identified

in ERC-QA-28, Revision 3,

nd compared a sample of overview inspection

verification packages (VPs) against the checklist to determine if the VPs

'

were developed and processed in accordance with ERC-QA-28 requirements.

Of the ten certified Ols, seven had performed the majority of the overview

inspections,

The sample of overview VPs was selected to contain at least

one or more packages from each of the seven most active Ols.

It was noted

that, in some cases, more than one OI participated in a single overview

inspection.

This inspection was structured to evaluate the following

topics:

sample selection, determination of accessibility, preparation of

overview VPs, completion of overview checklists, comparison of results

with the initial reinspection, completion of overview inspection report

and verification and followup of actions required.

i

. - ~.. - _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ - _ _. _ _ _ _ _

r

.

I

e

~

-47-

j

i

a.

Sample Selection

VPs documenting the results of initial reinspection / documentation

reviews were randomly selected for overview inspection.

Based on the

type of reinspection activity, the sampling technique is described in

ERC 0A-28 for the selection of VPs for overview inspection. The NRC

sample selected for inspection was 16 out of a total of 51 ERC

j

inspectors.

The number of inspectors sampled were by discipline:

q

six-piping; five-mechanical, three-electrical, and two-civil. The

i

NRC review of this sample included:

the overview inspection program

selection methods and use of random tables, calculations, and

selection results. Based on documentation reviewed, the sample

,

selection used in the overview inspection program conformed to

procedural requirements,

b.

Determination of Accessibility

The OI required to confirm that any necessary equipment / services to

perform overview inspections are in place and that the sample is

accessible. This practice was found to be documented.

If the

equipment / services was not available or the sample inaccessible, such

j

was documented in the sample selection log and another accessible

'

sample chosen in accordance with procedures.

c.

Preparation of Overview VPs

)

The overview VP is prepared by ERC and duplicates the initial VP used

by the ERC inspector.

Upon receipt, the 01 supervisor is responsible

to verify that the overview VP is complete and accurate prior to

assignment to an 01.

Based on the NRC inspector's review of 17

overview VPs, it was determined that the 01 supervisor had verified

the completeness and accuracy of VPs. The contents of this packages

were found to agree with the contents from which lists all the

documents that comprise the overview VP; e.g., inspection drawings,

supplemental inspection instructions, and inspection checklist.

d.

Completion of Checklists and VP Contents Form

In the review of overview inspection checklists, it was found thi.t

some checklists were not processed in accordance with ERC-QA-28

requirements. Noted errors were:

corrections not initialed and

dated; absence of required entries; no justification or explant. tion

for "N/A" (not applicable) entries; supplemental checklist not signed

by OI; and added documents to the VP were not entered on the VP

contents form. These type errors were also identified by ERC during

audit ERC-86-03, June 16-20, 1986.

Corrective action responding to

these findings was the conduct of an independent review of historical

VPs.

A detailed checklist was developed to identify errors in

checklists and content forms.

ERC was in the process of conducting

this historical review of VPs during the NRC inspection.

The NRC

inspector examined 12 historical review results.

VP checklist and

_ - _ _ _ _ _ _ _ _.

_

- _ _ - _

. _ _.

o

-

.

'

-48-

content form errors that were identified were being corrected.

VPs

processed after completion of this corrective action would be subject

to independent reviews to assure completion errors are being

,

identified and corrected.

Comparison cf Overview Inspection Results vs Initial Reinspection

j

e.

Results

Procedurally, a comparison is required to be made between the

overview inspection packages and the initial reinspection / document

review package to identify inconsistencies. Those inconsistencies

t

confirmed as being valid are reported in the overview inspection

.

J

report for required action.

During the NRC's comparison of the

packages, it was found that not all inconsistencies were identified

i

'

by the 01.

Examples of inconsistencies were:

inspection checklists

reflect disagreement between ERC inspectors and Ols, but the overview

,

inspection report did not identify the disagreement; the ERC

'

inspector or 01 accepted an attribute and the other inspector would

enter N/A; and items not inspected by overview were inspected by the

initial ERC inspectors. These types of inconsistencies were also

identified in audit ERC-86-03.

Corrective action taken was to also

address these type errors in the historical review of overview VPs.

During 'the NRC's inspection of the 12 historical reviews, it was

found that the inconsistency errors were being addressed and when

indicated, inspector retraining was conducted.

f.

Overview Inspection Reports

Seventeen overview inspection reports were examined. The results

from overview inspections were found to t,e documented on the reports

j

per procedural requirements.

Information in overview inspection

reports included:

accept / reject criteria; the observed deviating

condition; and action required with a completion schedule. Typical

corrective action included:

inspector retraining, reinspection of

identified inconsistency, revising'Ols or the combination thereof.

The overview inspeciton reports were reviewed and approved by the 01

supervisor and transmitted by memo to the responsible ERC personnel

for action.

g.

Followup and Verification of Actions Required

ERC-QA-28 delineates steps for the verification of actions required.

Of the 17 Vs reviewed, 11 contdined overview inspection reports

requiring actions to correct identified inconsistencies.

One

overview inspection report contained on error in that the required

corrective action had not been ven fied. This type error was to be

addressed in the historical review being performed by overview

personnel as a result of a finding in audit ERC-86-03. To assure the

historic 61 review was effective und would identify this type of

_

--

-_--___-___A

_

..

.

'-

error, the NRC witnessed the historical review of the overview

inspection report. The error was identified during the historical'

d

review.

To date, 104 overview inspection reports required corrective action.

Seventy-nine related to findings against reinspection inspectors

(inspector effectiveness), and 25 related to ERC engineering

(inadequacy of QQIs).

Inspector deficiencies identified in overview

inspection reports.are trended for corrective action tc prevent.

I

recurrence. When engineering deficiencies are identified, the

appropriate QI-is revised as necessary, and previously completed' work

per the affected QI is essessed for impact.

~

As of July 28, 1986, 46 open overview inspection reports requiring-

l

corrective action were from 8 to.175 days past the scheduled closure

i

date.. Audit ERC-86-03 identified the overdue reports as untimely

corrective action.

In response to this audit finding, ERC

established a tracking system to monitor the status of overview

,

l

inspection reports and their progress.

10.

Exit Interview

Exit interviews were conducted on August 7, 1986, and September 5, 1986,

!

with the applicant's representatives identified in paragraph 1-of this

6ppendix.

During these interviews, the NRC inspectors summarized the

scope and findings of the inspection. The applicant acknowledged the

findings.

f

!

-

I

o

!

,

.

L _ _- - -_.

0