July 30, 2021
SUBJECT:
VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 & 2 - INTEGRATED INSPECTION REPORT 05000424/2021002 AND 05000425/2021002
Dear Ms. Gayheart:
On June 30, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Vogtle Electric Generating Plant, Units 1 & 2. On July 21, 2021, the NRC inspectors discussed the results of this inspection with Mr. Drayton Pitts and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Alan J. Blamey, Chief Reactor Projects Branch 2 Division of Reactor Projects
Docket Nos. 05000424 and 05000425 License Nos. NPF-68 and NPF-81
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000424 and 05000425
License Numbers:
Report Numbers:
05000424/2021002 and 05000425/2021002
Enterprise Identifier: I-2021-002-0016
Licensee:
Southern Nuclear Operating Company, Inc.
Facility:
Vogtle Electric Generating Plant, Units 1 & 2
Location:
Waynesboro, GA
Inspection Dates:
April 01, 2021 to June 30, 2021
Inspectors:
M. Endress, Senior Resident Inspector
K. Kirchbaum, Operations Engineer
D. Mas-Penaranda, Resident Inspector
C. Safouri, Senior Resident Inspector
J. Viera, Senior Operations Engineer
Approved By:
Alan J. Blamey, Chief
Reactor Projects Branch 2
Division of Reactor Projects
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Vogtle Electric Generating Plant, Units 1
& 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Unit 1 began the inspection period at 100 percent rated thermal power (RTP). On April 12, 2021, the unit was down powered to 80 percent to resolve 1C condenser vacuum issues. The unit was returned to RTP on April 16, 2021.
Unit 2 operated at or near 100 percent RTP for the entire inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week, increasing the amount of time on site as local COVID-19 conditions permitted.
As part of their onsite activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities; and completed on site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
Impending Severe Weather Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather related to a tornado watch for Burke County on May 3, 2021.
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Unit 1 train A component cooling water (CCW) partial equipment alignment walkdown due Unit 1 train B CCW out of service for maintenance, on May 26, 2021.
- (2) Unit 1 train A nuclear service cooling water (NSCW) partial equipment alignment walkdown due to auxiliary component cooling system outside of normal configuration (1-HV-2058 valve failure), on June 2, 2021.
- (3) Unit 1 train A motor driven auxiliary feedwater (MDAFW) with Unit 1 train C turbine driven auxiliary feedwater (TDAFW) out of service for maintenance on steam admission valve 1-HV-5106, on June 3, 2021.
- (4) Unit 1 train B emergency diesel generator (EDG) partial equipment alignment walkdown due to Unit 1 train A EDG out of service for maintenance, on June 7, 2021.
- (5) Unit 2 train A and B spent fuel cooling and purification system pumps partial equipment alignment walkdown, on June 19, 2021.
Complete Walkdown Sample (IP Section 03.02) (1 Sample)
- (1) Unit 1 train B EDG and supporting systems following a major system outage, on May 17, 2021.
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Fire Zones 59/68/69/75, Unit 1 rod control switchgear areas, on June 13, 2021.
- (2) Fire Zones 59/68/69/75, Unit 2 rod control switchgear areas, on June 13, 2021.
- (3) Fire Zones 94/95/173/174/107/108/120/121, Unit 2 train A and B, cable spreading rooms, on June 19, 2021.
- (4) Fire Zones 76/77A/77B/78A/78B/71, Unit 2 train A and B, battery and switchgear rooms, on June 19, 2021.
- (5) Fire Zones 56A/56B/79A/79B/83/152, Unit 2 train C and D, battery and switchgear rooms, on June 19, 2021.
71111.06 - Flood Protection Measures
Cable Degradation (IP Section 03.02) (1 Sample)
The inspectors evaluated cable submergence protection in:
(1)1NE7ADKEM39 1NE7ADKEM40 1NE9GHKEPB01
71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)
- (1) Biennial Requalification Written Examinations The inspectors evaluated the quality of licensed operator biennial requalification written examinations administered between October through November 2020.
Annual Requalification Operating Tests
The inspectors evaluated the adequacy of the facility licensees annual requalification operating test.
Administration of an Annual Requalification Operating Test
The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.
Requalification Examination Security
The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.
Remedial Training and Re-examinations
The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.
Operator License Conditions
The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.
Control Room Simulator
The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.
Problem Identification and Resolution
The inspectors evaluated the licensees ability to identify and resolve problems associated with licensed operator performance.
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the control room during the Unit 1 downpower to 80 percent for 1C condenser cleaning, on April 12, 2021.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated "Just in Time" training for the Unit 1 downpower to 80 percent, on April 2, 2021.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (1 Sample)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:
- (1) Periodic Evaluation (a)(3) Review from January 2020 to May 2021, on June 25, 2021.
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Unit 1 elevated risk due to train B EDG system outage, on April 26, 2021.
- (2) Implementation of planned Risk Informed Completion Time (RICT) risk management actions for the Unit 1 train B EDG major outage, on April 26, 2021.
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
- (1) Unit 1 TDAFW steam inlet valve exceeding stroke time, on April 16, 2021.
- (2) Unit 2 rod control system following unexpected automatic 3-step rod insertion, on May 4, 2021.
- (3) Unit 1 train A NSCW transfer pump trip, on May 25, 2021.
- (4) Unit 1 train B NSCW fan #1 hold down stud broken, on May 28, 2021.
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)
The inspectors evaluated the following temporary or permanent modifications:
- (1) SNC1060859, Unit 1 Train B sequencer PC node box replacement, on April 27, 2021.
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (7 Samples)
The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:
- (1) Unit 2 train B centrifugal charging pump system outage, on March 31, 2021.
- (2) Unit 1 train B NSCW fan #1 gearbox replacement, on April 7, 2021.
- (3) Unit 1 train B EDG major outage, on April 29, 2021.
- (5) Unit 2 train B NSCW fan #3 AX5 relay replacement, on May 7, 2021.
- (6) Unit 1 TDAFW steam inlet motor operated valve 1-HV-5106 relay and contactor replacement, on June 3, 2021.
- (7) Unit 1 train A EDG major outage, on June 10, 2021.
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance tests:
Surveillance Tests (other) (IP Section 03.01)
(1)
===14807B-1, Unit 1 Train B Motor Driven Auxiliary Feedwater Pump Annual Time-Delay Relay Test and Monthly Operability run, on April 7, 2021.
(2)24753-1, Steam Generator #4 Level (Narrow Range) Protection Channel II 1L-549 Channel Operational Test and Channel Calibration, on June 3, 2021.
(3)14980A-1, EDG 1A Operability Test - Fast Start, following a major outage, on June 14, 2021.
Inservice Testing (IP Section 03.01)===
(1)
===14810-1, Unit 1 TDAFW Pump & Check Valve Inservice Test, on May 10, 2021.
71114.06 - Drill Evaluation
Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated an emergency preparedness drill in the simulator and technical support center on May 18, 2021. The drill involved a fire in a MDAFW pump room, an anticipated transient without trip condition, red heat sink conditions, and then subsequent transition into recovery.
Drill/Training Evolution Observation (IP Section 03.02)===
The inspectors evaluated:
- (1) A licensed operator continuing training simulator scenario that included a drill and exercise performance indicator opportunity involving an earthquake, on May 12, 2021.
- (2) A licensed operator continuing training simulator scenario that included a drill and exercise performance indicator opportunity involving a loss of 120 VAC instrument power followed by a steam generator tube rupture and faulted steam generator, on June 21,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification
The inspectors verified licensee performance indicators submittals listed below:
BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10)===
- (1) Unit 1 (April 1, 2020 - March 31, 2021)
- (2) Unit 2 (April 1, 2020 - March 31, 2021)
BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)
- (1) Unit 1 (April 1, 2020 - March 31, 2021)
- (2) Unit 2 (April 1, 2020 - March 31, 2021)
71152 - Problem Identification and Resolution
Semiannual Trend Review (IP Section 02.02) (1 Sample)
- (1) The inspectors reviewed the licensees corrective action program for potential adverse trends in Setpoint Control Drift Monitoring Program that might be indicative of a more significant safety issue.
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On July 21, 2021, the inspectors presented the integrated inspection results to Mr.
Drayton Pitts and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
Resulting from
Inspection
10795150
Procedures
18036-C
Seismic or Severe Weather Event
NMP-OS-017
Severe Weather
3.0
Corrective Action
Documents
Resulting from
Inspection
10798526, 10798531, 10803760
Drawings
1X4DB135-1
P& I Diagram Nuclear Service Cooling Water System, No.
202,
1x4DB135-2
P&I Diagram Nuclear Cooling Service Water System, NO.
202
1X4DB136
P&I Diagram Component Cooling Water System, System
Number 1203
1X4DB137
P&I Diagram Component Cooling Water System, System
Number 1203
1X4DB161-2
P&I Diagram Auxiliary Feed Water System, N
1X4DB170-2
P&I Diagram Diesel Generator System Train B, No. 2403
2X4DB130
P&I Diagram Spent Fuel Cooling and Purification System
No. 1213
2.0
Miscellaneous
Tagout: 1-DT-2403-
00336(3)
Hang temporary lift to support diesel generator 1B meggar
test
05/05/2021
Procedures
11145-1
Diesel Generator Alignment
11150-1
Nuclear Service Cooling Water System Alignment
11610-1
Auxiliary Feedwater System Alignment
11715-1
Component Cooling Water System Alignment
13145B-1
Diesel Generator Train B
2.1
Corrective Action
Documents
Resulting from
10808406
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Inspection
Fire Plans
2756A-2
Zone 56A - Control Building - Level B Fire Fighting Preplan
2.1
2756B-2
Zone 56B - Control Building - Level B Fire Fighting Preplan
0.2
2759-1
Zone 59 - Control Building - Level B Fire Fighting Preplan
1.2
2759-2
Zone 59 - Control Building - Level B Fire Fighting Preplan
0.2
2768-1
Zone 68 - Control Building - Level B Fire Fighting Preplan
1.2
2768-2
Zone 68 - Control Building - Level B Fire Fighting Preplan
0.2
2769-1
Zone 69 - Control Building Level B Fire Fighting Preplan
1.2
2769-2
Zone 69 - Control Building - Level B Fire Fighting Preplan
0.2
2771-2
Zone 71 - Control Building - Level B Fire Fighting Preplan
2.0
2775-1
Zone 75-Control Building - Level B Fire Fighting Preplan
4.1
2775-2
Zone 75 - Control Building - Level B Fire Fighting Preplan
0.2
2776-2
Zone 76 - Control Building - Level B, Non-Train 1-E MCC
Room Fire Fighting Preplan
1.1
2777A-2
Zone 77A - Control Building - Level B Fire Fighting Preplan
2.0
2777B-2
Zone 77B - Control Building - Level B Fire Fighting Preplan
1.4
2778B-2
Zone 78B - Control Building - Level B, Train "A" Battery
Room Fire Fighting Preplan
1.2
2779A-2
Zone 79A - Control Building Level B Fire Fighting Preplan
1.0
2779B-2
Zone 79B - Control Building - Level B Fire Fighting Preplan
1.2
2783-2
Zone 83 - Control Building - Level B, Electrical Chase Fire
Fighting Preplan
0.2
2794-2
Zone 94 - Control Building - Level A Fire Fighting Preplan
4.0
2795-2
Zone 95 - Control Building - Level A, Train "A" Spreading
Room Fire Fighting Preplan
5.0
2807-2
Zone 107 - Control Building - Levels 1 and 2 Fire Fighting
Preplan
3.1
2808-2
Zone 108 - Control Building - Levels 1 and 2 Fire Fighting
Preplan
3.1
2820-2
Zone 120 - Control Building - Level 2 Fire Fighting Preplan
2821-2
Zone 121 - Control Building Level 2 Fire Fighting Preplan
2843-1
Zone 143 - Diesel Generator Building Electrical Tunnel A -
Level C Fire Fighting Preplan
3.0
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2852-2
Zone 152 - Control Building - Level B Fire Fighting Preplan
1.0
2861-1
Zone 161 - Diesel Generator Building Fire Fighting Preplan
4.0
2863-1
Zone 163 - Diesel Generator Building - Train A DFO Day
Tank Fire Fighting Preplan
3.2
2873-2
Zone 173 - Control Building - Level A Fire Fighting Preplan
1.2
2874-2
Zone 174 - Control Building - Level A Fire Fighting Preplan
1.2
Corrective Action
Documents
10797717, 10548947, 10435389, 10361960, 10314218,
10312667, 10296364, 10027344
Corrective Action
Documents
Resulting from
Inspection
10797717, 10797724
Procedures
NMP-ES-051-004
Pull Box Inspection
6.0
Work Orders
SNC1105998
Corrective Action
Documents
Unanticipated 1BA03 de-energization during B ESFAS
testing (LOSP)
03/21/2020
Unexpected Boration (reactivity error)
2/15/2020
1085446, TE
1085454)
Single SRO Exam 2 question overlap with SRO Exam 1
(2020 Biennial Written Examination)
03/21/2021
CR 10805933
Simulator malfunction inadvertently removed during
administration of 2021 Annual Operating Test
06/15/2021
Miscellaneous
20 Biennial RO
Exam 4
20 Biennial RO Exam 4
10/28/2020
20 Biennial SRO
Exam 4
20 Biennial SRO Exam 4
10/28/2020
20
Requalification
Training
Attendance
Records
October-December 2020 Training Attendance Records
4th Quarter
20
DS-01
Operating Test Dynamic Simulator Scenario, Week 4,
Scenario A
Revision
10.5
DS-07
Operating Test Dynamic Simulator Scenario, Week 2,
Revision
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Scenario A
23.4
DS-09
Operating Test Dynamic Simulator Scenario, Week 2,
Scenario B
Revision
24.3
DS-10
Operating Test Dynamic Simulator Scenario, Week 1,
Scenario A
Revision
18.3
DS-37
Operating Test Dynamic Simulator Scenario, Week 4,
Scenario B
Revision 6.5
DS-40
Operating Test Dynamic Simulator Scenario, Week 1,
Scenario B
Revision 2.1
Medical Records
Operator Medical Records (11)
June 2021
Reactivation
Records
Operator Reactivation Records (6)
June 2021
Scenario Based
Testing (SBT)
DS-07, DS-09, DS-10, DS-37 Scenario Based Testing
V-LO-TA-40002
Classify an Emergency Event (SRO Only)
06/21/2021
V-RQ-JP-10008-
001
Implement Tech Spec LCO Requirements for a Failed NR
Temperature Instrument (SRO Only)
05/20/2021
V-RQ-JP-14405-
001
Perform Boron Injection Flow Path Verification in
Response to Equipment Failure
05/23/2021
V-RQ-JP-17213-
2
Respond to a Radiation Alarm During a Liquid Radwaste
Release (Alternate Path)
06/22/2020
V-RQ-JP-18009-
004
Maintain RCS Temperature Following SG Tube Leak
(Alternate Path)
05/20/2021
V-RQ-JP-18030-
2
Respond to a Loss of Spent Fuel Pool Level
05/21/2021
V-RQ-JP-18038-
Locally Energize Train A Switchgear Following Local
Diesel Start
05/18/2018
V-RQ-JP-18038-
Locally Energize Train A Switchgear Following Local
Diesel Start
05/20/2021
V-RQ-JP-19030-
004
Depressurize RCS to Reduce Break Flow to Ruptured
Steam Generator-Normal Pressurizer Spray Not Available
- Alternate Path
05/29/2021
V-RQ-JP-19100-
001
Isolate the RCS and Limit Cooldown Following a Loss of
All AC (Alternate Path)
05/13/2021
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
V-RQ-JP-19200-
005
Evaluate Critical Safety Function Status Trees (CSFSTs)
with an Inoperable Integrated Plant Computer (IPC)
05/23/2021
V-RQ-JP-19211-
007
Locally Trip the Reactor (Alternate Path)
05/29/2021
V-RQ-JP-19263-
001
Respond to Voids in the Reactor Vessel
05/11/2021
V-RQ-JP-NMP-EP-
141-007
Classify an Emergency Event (SRO Only)
05/29/2021
71111.11Q Corrective Action
Documents
10782494, 10785112
Miscellaneous
V-RQ-SG-
2104WBCleaning
Water Box Cleaning Power Maneuver JITT
1.0
Procedures
2004-1
Power Operation (Mode 1)
6.0
13724-1
41.1
13800-1
Main Turbine Operation
79.2
Calculations
V-RIE-MR-U00
Document the Vogtle 1 & 2 Maintenance Rule Risk
Ranking and Performance Criteria Assessment
Corrective Action
Documents
Resulting from
Inspection
10793227, 10794367
Miscellaneous
Daily Status Report
05/24/2021
Plan of the Day
05/24/2021
Phoenix A4 Risk
06/07/2021
Phoenix RICT
06/07/2021
Plan of the Day
06/07/2021
Daily Status Report
06/07/2021
Phoenix PRA 4/25/21 - 5/4/21
Phoenix A4 Risk
05/24/2021
Phoenix Unit 1 RICT
05/24/2021
eSOMS Logs 4/25/21 - 5/4/21
Procedures
13419-C
Diesel Generator RICT Support
10.3
NMP-GM-031
On-Line Configuration Risk Management Program
9.0
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
NMP-GM-031-001
Online Maintenance Rule (a)(4) Risk Calculations
6.0
NMP-GM-031-002
Calculation of RMAT and RICT for the RICT Program
5.0
NMP-GM-031-003
Risk Management Actions for 10 CFR 50.65(a)(4) and the
Risk Informed Completion Time Program
8.0
NMP-GM-031-004-
GL01
Vogtle 1 & 2 RICT System Guidelines
1.0
Corrective Action
Documents
10788092, 1086044, 10787264, 10786197, 10788655,
10790958, 1087827, 10768536, 10795427, 10800003
Corrective Action
Documents
Resulting from
Inspection
1088742, 10802559, 10788672
Drawings
2X6AU01-00492
Process Control System Cabinet 08 Interconnection Wiring
Diagram
9.0
2X6AU01-00493
Interconnecting Wiring Diagram Cabinet 08
2X6AU01-00494
Process Control System Cabinet 8 Interconnecting Wiring
Diagram
9.0
Engineering
Changes
1019003501DCP
TDAFW Turbine Speed Control Replacement
6.0
Engineering
Evaluations
CR 10790958 - Operability Determination Support Basis
04/17/2021
Miscellaneous
Unit 2 Unexpected Rod Insertion: Fault Tree, Investigation
Summary, IPC Information, U2 Inadvertent Rod Insertion
IRT Writeup
Unit 1 NSCW Transfer Pump #8 Fault Tree and Refute
Matrix
05/27/2021
Engineering Evaluation - 1A NSCW Transfer Pump
05/27/2021
14581A-1
Train A NSCW Transfer Pump Operability Test following
packing replacement
05/26/2021
GP-15618
Vogtle Electric Generating Plant Units 1 and 2 Upper
Plenum Anomaly Information Exchange Meeting
05/14/1992
Procedures
14581A-1
Train A NSCW Transfer Pump Operability Test
1.1
AX6AA04-00030
Precautions, Limitations & Setpoints for Nuclear Steam
Supply Systems
67.0
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Work Orders
SNC1150438, SNC1085187, SNC1100676, SNC1151209
Engineering
Changes
SNC1060859
Unit 1 PC Node Box Replacement
Work Orders
SNC1083057
Corrective Action
Documents
10788092, 1086044, 10787264, 10786197, 10788655,
10793199, 10793227, 10796069
Corrective Action
Documents
Resulting from
Inspection
10808100
Drawings
1X2D05A024
NSCW Cooling Tower 1B-Unit 1 Forming Plan at Fan Deck
EL. 250'-11
10.0
Procedures
14808B-2
Train B Centrifugal Charging Pump and Check Valve IST
and Response Time Test
7.0
Work Orders
SNC1048447, SNC11565884, SNC1149827,
SNC1149971, SNC1132092, SNC1060425, SNC960486,
SNC961243, SNC963233, SNC1151084, SNC1150438,
SNC1151209, SNC1153969, SNC1155594, SNC1156584,
SNC1133603
Corrective Action
Documents
10686257
Procedures
14545B-1
Motor Driven Auxiliary Feedwater Pump B Monthly
Operability Test
2.1
14807B-1
Train B Motor Driven Auxiliary Feedwater Pump / Check
Valve Inservice and Response Time Test
5.2
14980A-1
Diesel Generator 1A Operability Test
31.3
24753-1
Steam Generator Level (Narrow Range) Protection
Channel II 1L-549 Channel Operational Test and Channel
Calibration
27.2
Work Orders
SNC1124465
Miscellaneous
V-RQ-SE-21301
21 Segment #3 DEP Scenario
1.0
V-RQ-SE-21301
21 Segment #3 DEP Scenario
1.0
71151
Corrective Action
Documents
10807536, 10807538, 10808315
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Resulting from
Inspection
Miscellaneous
Monthly Data Export Unit 1 RCS Activity - April 2020 to
March 2021
Monthly Data Export Unit 2 RCS Activity - April 2020 to
March 2021
Monthly Data Export Unit 1 RCS Identified Leak Rate -
April 2020 to March 2021
Monthly Data Export Unit 2 RCS Identified Leak Rate -
April 2020 to March 2021
Unit 1 eSOMS Rounds - April 2020 to March 2021
Unit 2 eSOMS Rounds - April 2020 to March 2021
VEGP 1&2 RCS Data - April 2020 to March 2021
Regulatory Assessment Performance Indicator Guideline
Corrective Action
Documents
10759811, 10491708, 10368251, 10725143, 10759811,
10804138, 10793015, 10787581, 10796682, 10806678
Corrective Action
Documents
Resulting from
Inspection
1089845, 1089846
Procedures
NMP-ES-033
Setpoint Control Program
8.0
NMP-ES-033-003
Setpoint Control Program Drift Monitoring
5.0