IR 05000424/2021002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000424/2021002 and 05000425/2021002
ML21211A289
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 07/30/2021
From: Alan Blamey
Division Reactor Projects II
To: Gayheart C
Southern Nuclear Operating Co
References
IR 2021002
Download: ML21211A289 (18)


Text

July 30, 2021

SUBJECT:

VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 & 2 - INTEGRATED INSPECTION REPORT 05000424/2021002 AND 05000425/2021002

Dear Ms. Gayheart:

On June 30, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Vogtle Electric Generating Plant, Units 1 & 2. On July 21, 2021, the NRC inspectors discussed the results of this inspection with Mr. Drayton Pitts and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Alan J. Blamey, Chief Reactor Projects Branch 2 Division of Reactor Projects

Docket Nos. 05000424 and 05000425 License Nos. NPF-68 and NPF-81

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000424 and 05000425

License Numbers:

NPF-68 and NPF-81

Report Numbers:

05000424/2021002 and 05000425/2021002

Enterprise Identifier: I-2021-002-0016

Licensee:

Southern Nuclear Operating Company, Inc.

Facility:

Vogtle Electric Generating Plant, Units 1 & 2

Location:

Waynesboro, GA

Inspection Dates:

April 01, 2021 to June 30, 2021

Inspectors:

M. Endress, Senior Resident Inspector

K. Kirchbaum, Operations Engineer

D. Mas-Penaranda, Resident Inspector

C. Safouri, Senior Resident Inspector

J. Viera, Senior Operations Engineer

Approved By:

Alan J. Blamey, Chief

Reactor Projects Branch 2

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Vogtle Electric Generating Plant, Units 1

& 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at 100 percent rated thermal power (RTP). On April 12, 2021, the unit was down powered to 80 percent to resolve 1C condenser vacuum issues. The unit was returned to RTP on April 16, 2021.

Unit 2 operated at or near 100 percent RTP for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week, increasing the amount of time on site as local COVID-19 conditions permitted.

As part of their onsite activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities; and completed on site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather related to a tornado watch for Burke County on May 3, 2021.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1 train A component cooling water (CCW) partial equipment alignment walkdown due Unit 1 train B CCW out of service for maintenance, on May 26, 2021.
(2) Unit 1 train A nuclear service cooling water (NSCW) partial equipment alignment walkdown due to auxiliary component cooling system outside of normal configuration (1-HV-2058 valve failure), on June 2, 2021.
(3) Unit 1 train A motor driven auxiliary feedwater (MDAFW) with Unit 1 train C turbine driven auxiliary feedwater (TDAFW) out of service for maintenance on steam admission valve 1-HV-5106, on June 3, 2021.
(4) Unit 1 train B emergency diesel generator (EDG) partial equipment alignment walkdown due to Unit 1 train A EDG out of service for maintenance, on June 7, 2021.
(5) Unit 2 train A and B spent fuel cooling and purification system pumps partial equipment alignment walkdown, on June 19, 2021.

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) Unit 1 train B EDG and supporting systems following a major system outage, on May 17, 2021.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zones 59/68/69/75, Unit 1 rod control switchgear areas, on June 13, 2021.
(2) Fire Zones 59/68/69/75, Unit 2 rod control switchgear areas, on June 13, 2021.
(3) Fire Zones 94/95/173/174/107/108/120/121, Unit 2 train A and B, cable spreading rooms, on June 19, 2021.
(4) Fire Zones 76/77A/77B/78A/78B/71, Unit 2 train A and B, battery and switchgear rooms, on June 19, 2021.
(5) Fire Zones 56A/56B/79A/79B/83/152, Unit 2 train C and D, battery and switchgear rooms, on June 19, 2021.

71111.06 - Flood Protection Measures

Cable Degradation (IP Section 03.02) (1 Sample)

The inspectors evaluated cable submergence protection in:

(1)1NE7ADKEM39 1NE7ADKEM40 1NE9GHKEPB01

71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)

(1) Biennial Requalification Written Examinations The inspectors evaluated the quality of licensed operator biennial requalification written examinations administered between October through November 2020.

Annual Requalification Operating Tests

The inspectors evaluated the adequacy of the facility licensees annual requalification operating test.

Administration of an Annual Requalification Operating Test

The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.

Requalification Examination Security

The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.

Remedial Training and Re-examinations

The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.

Operator License Conditions

The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.

Control Room Simulator

The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.

Problem Identification and Resolution

The inspectors evaluated the licensees ability to identify and resolve problems associated with licensed operator performance.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during the Unit 1 downpower to 80 percent for 1C condenser cleaning, on April 12, 2021.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated "Just in Time" training for the Unit 1 downpower to 80 percent, on April 2, 2021.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Periodic Evaluation (a)(3) Review from January 2020 to May 2021, on June 25, 2021.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 1 elevated risk due to train B EDG system outage, on April 26, 2021.
(2) Implementation of planned Risk Informed Completion Time (RICT) risk management actions for the Unit 1 train B EDG major outage, on April 26, 2021.
(3) Unit 1 train B CCW system outage with planned RICT, on May 25, 2021.
(4) Unit 1 train A EDG outage with planned RICT, on June 8, 2021.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 1 TDAFW steam inlet valve exceeding stroke time, on April 16, 2021.
(2) Unit 2 rod control system following unexpected automatic 3-step rod insertion, on May 4, 2021.
(3) Unit 1 train A NSCW transfer pump trip, on May 25, 2021.
(4) Unit 1 train B NSCW fan #1 hold down stud broken, on May 28, 2021.

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) SNC1060859, Unit 1 Train B sequencer PC node box replacement, on April 27, 2021.

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) Unit 2 train B centrifugal charging pump system outage, on March 31, 2021.
(2) Unit 1 train B NSCW fan #1 gearbox replacement, on April 7, 2021.
(3) Unit 1 train B EDG major outage, on April 29, 2021.
(4) Unit 1 train B EDG jacket water leak and subsequent weld repair, on May 3, 2021.
(5) Unit 2 train B NSCW fan #3 AX5 relay replacement, on May 7, 2021.
(6) Unit 1 TDAFW steam inlet motor operated valve 1-HV-5106 relay and contactor replacement, on June 3, 2021.
(7) Unit 1 train A EDG major outage, on June 10, 2021.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1)

===14807B-1, Unit 1 Train B Motor Driven Auxiliary Feedwater Pump Annual Time-Delay Relay Test and Monthly Operability run, on April 7, 2021.

(2)24753-1, Steam Generator #4 Level (Narrow Range) Protection Channel II 1L-549 Channel Operational Test and Channel Calibration, on June 3, 2021.

(3)14980A-1, EDG 1A Operability Test - Fast Start, following a major outage, on June 14, 2021.

Inservice Testing (IP Section 03.01)===

(1)

===14810-1, Unit 1 TDAFW Pump & Check Valve Inservice Test, on May 10, 2021.

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated an emergency preparedness drill in the simulator and technical support center on May 18, 2021. The drill involved a fire in a MDAFW pump room, an anticipated transient without trip condition, red heat sink conditions, and then subsequent transition into recovery.

Drill/Training Evolution Observation (IP Section 03.02)===

The inspectors evaluated:

(1) A licensed operator continuing training simulator scenario that included a drill and exercise performance indicator opportunity involving an earthquake, on May 12, 2021.
(2) A licensed operator continuing training simulator scenario that included a drill and exercise performance indicator opportunity involving a loss of 120 VAC instrument power followed by a steam generator tube rupture and faulted steam generator, on June 21,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10)===

(1) Unit 1 (April 1, 2020 - March 31, 2021)
(2) Unit 2 (April 1, 2020 - March 31, 2021)

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1) Unit 1 (April 1, 2020 - March 31, 2021)
(2) Unit 2 (April 1, 2020 - March 31, 2021)

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in Setpoint Control Drift Monitoring Program that might be indicative of a more significant safety issue.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 21, 2021, the inspectors presented the integrated inspection results to Mr.

Drayton Pitts and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Corrective Action

Documents

Resulting from

Inspection

10795150

Procedures

18036-C

Seismic or Severe Weather Event

NMP-OS-017

Severe Weather

3.0

71111.04

Corrective Action

Documents

Resulting from

Inspection

10798526, 10798531, 10803760

Drawings

1X4DB135-1

P& I Diagram Nuclear Service Cooling Water System, No.

202,

1x4DB135-2

P&I Diagram Nuclear Cooling Service Water System, NO.

202

1X4DB136

P&I Diagram Component Cooling Water System, System

Number 1203

1X4DB137

P&I Diagram Component Cooling Water System, System

Number 1203

1X4DB161-2

P&I Diagram Auxiliary Feed Water System, N

O. 1302,

1X4DB170-2

P&I Diagram Diesel Generator System Train B, No. 2403

2X4DB130

P&I Diagram Spent Fuel Cooling and Purification System

No. 1213

2.0

Miscellaneous

Tagout: 1-DT-2403-

00336(3)

Hang temporary lift to support diesel generator 1B meggar

test

05/05/2021

Procedures

11145-1

Diesel Generator Alignment

11150-1

Nuclear Service Cooling Water System Alignment

11610-1

Auxiliary Feedwater System Alignment

11715-1

Component Cooling Water System Alignment

13145B-1

Diesel Generator Train B

2.1

71111.05

Corrective Action

Documents

Resulting from

10808406

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Inspection

Fire Plans

2756A-2

Zone 56A - Control Building - Level B Fire Fighting Preplan

2.1

2756B-2

Zone 56B - Control Building - Level B Fire Fighting Preplan

0.2

2759-1

Zone 59 - Control Building - Level B Fire Fighting Preplan

1.2

2759-2

Zone 59 - Control Building - Level B Fire Fighting Preplan

0.2

2768-1

Zone 68 - Control Building - Level B Fire Fighting Preplan

1.2

2768-2

Zone 68 - Control Building - Level B Fire Fighting Preplan

0.2

2769-1

Zone 69 - Control Building Level B Fire Fighting Preplan

1.2

2769-2

Zone 69 - Control Building - Level B Fire Fighting Preplan

0.2

2771-2

Zone 71 - Control Building - Level B Fire Fighting Preplan

2.0

2775-1

Zone 75-Control Building - Level B Fire Fighting Preplan

4.1

2775-2

Zone 75 - Control Building - Level B Fire Fighting Preplan

0.2

2776-2

Zone 76 - Control Building - Level B, Non-Train 1-E MCC

Room Fire Fighting Preplan

1.1

2777A-2

Zone 77A - Control Building - Level B Fire Fighting Preplan

2.0

2777B-2

Zone 77B - Control Building - Level B Fire Fighting Preplan

1.4

2778B-2

Zone 78B - Control Building - Level B, Train "A" Battery

Room Fire Fighting Preplan

1.2

2779A-2

Zone 79A - Control Building Level B Fire Fighting Preplan

1.0

2779B-2

Zone 79B - Control Building - Level B Fire Fighting Preplan

1.2

2783-2

Zone 83 - Control Building - Level B, Electrical Chase Fire

Fighting Preplan

0.2

2794-2

Zone 94 - Control Building - Level A Fire Fighting Preplan

4.0

2795-2

Zone 95 - Control Building - Level A, Train "A" Spreading

Room Fire Fighting Preplan

5.0

2807-2

Zone 107 - Control Building - Levels 1 and 2 Fire Fighting

Preplan

3.1

2808-2

Zone 108 - Control Building - Levels 1 and 2 Fire Fighting

Preplan

3.1

2820-2

Zone 120 - Control Building - Level 2 Fire Fighting Preplan

2821-2

Zone 121 - Control Building Level 2 Fire Fighting Preplan

2843-1

Zone 143 - Diesel Generator Building Electrical Tunnel A -

Level C Fire Fighting Preplan

3.0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2852-2

Zone 152 - Control Building - Level B Fire Fighting Preplan

1.0

2861-1

Zone 161 - Diesel Generator Building Fire Fighting Preplan

4.0

2863-1

Zone 163 - Diesel Generator Building - Train A DFO Day

Tank Fire Fighting Preplan

3.2

2873-2

Zone 173 - Control Building - Level A Fire Fighting Preplan

1.2

2874-2

Zone 174 - Control Building - Level A Fire Fighting Preplan

1.2

71111.06

Corrective Action

Documents

10797717, 10548947, 10435389, 10361960, 10314218,

10312667, 10296364, 10027344

Corrective Action

Documents

Resulting from

Inspection

10797717, 10797724

Procedures

NMP-ES-051-004

Pull Box Inspection

6.0

Work Orders

SNC1105998

71111.11B

Corrective Action

Documents

CAR 277476

Unanticipated 1BA03 de-energization during B ESFAS

testing (LOSP)

03/21/2020

CAR 278695

Unexpected Boration (reactivity error)

2/15/2020

CAR 279115 (TE

1085446, TE

1085454)

Single SRO Exam 2 question overlap with SRO Exam 1

(2020 Biennial Written Examination)

03/21/2021

CR 10805933

Simulator malfunction inadvertently removed during

administration of 2021 Annual Operating Test

06/15/2021

Miscellaneous

20 Biennial RO

Exam 4

20 Biennial RO Exam 4

10/28/2020

20 Biennial SRO

Exam 4

20 Biennial SRO Exam 4

10/28/2020

20

Requalification

Training

Attendance

Records

October-December 2020 Training Attendance Records

4th Quarter

20

DS-01

Operating Test Dynamic Simulator Scenario, Week 4,

Scenario A

Revision

10.5

DS-07

Operating Test Dynamic Simulator Scenario, Week 2,

Revision

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Scenario A

23.4

DS-09

Operating Test Dynamic Simulator Scenario, Week 2,

Scenario B

Revision

24.3

DS-10

Operating Test Dynamic Simulator Scenario, Week 1,

Scenario A

Revision

18.3

DS-37

Operating Test Dynamic Simulator Scenario, Week 4,

Scenario B

Revision 6.5

DS-40

Operating Test Dynamic Simulator Scenario, Week 1,

Scenario B

Revision 2.1

Medical Records

Operator Medical Records (11)

June 2021

Reactivation

Records

Operator Reactivation Records (6)

June 2021

Scenario Based

Testing (SBT)

DS-07, DS-09, DS-10, DS-37 Scenario Based Testing

V-LO-TA-40002

Classify an Emergency Event (SRO Only)

06/21/2021

V-RQ-JP-10008-

001

Implement Tech Spec LCO Requirements for a Failed NR

Temperature Instrument (SRO Only)

05/20/2021

V-RQ-JP-14405-

001

Perform Boron Injection Flow Path Verification in

Response to Equipment Failure

05/23/2021

V-RQ-JP-17213-

2

Respond to a Radiation Alarm During a Liquid Radwaste

Release (Alternate Path)

06/22/2020

V-RQ-JP-18009-

004

Maintain RCS Temperature Following SG Tube Leak

(Alternate Path)

05/20/2021

V-RQ-JP-18030-

2

Respond to a Loss of Spent Fuel Pool Level

05/21/2021

V-RQ-JP-18038-

006A-1

Locally Energize Train A Switchgear Following Local

Diesel Start

05/18/2018

V-RQ-JP-18038-

006A-2

Locally Energize Train A Switchgear Following Local

Diesel Start

05/20/2021

V-RQ-JP-19030-

004

Depressurize RCS to Reduce Break Flow to Ruptured

Steam Generator-Normal Pressurizer Spray Not Available

- Alternate Path

05/29/2021

V-RQ-JP-19100-

001

Isolate the RCS and Limit Cooldown Following a Loss of

All AC (Alternate Path)

05/13/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

V-RQ-JP-19200-

005

Evaluate Critical Safety Function Status Trees (CSFSTs)

with an Inoperable Integrated Plant Computer (IPC)

05/23/2021

V-RQ-JP-19211-

007

Locally Trip the Reactor (Alternate Path)

05/29/2021

V-RQ-JP-19263-

001

Respond to Voids in the Reactor Vessel

05/11/2021

V-RQ-JP-NMP-EP-

141-007

Classify an Emergency Event (SRO Only)

05/29/2021

71111.11Q Corrective Action

Documents

10782494, 10785112

Miscellaneous

V-RQ-SG-

2104WBCleaning

Water Box Cleaning Power Maneuver JITT

1.0

Procedures

2004-1

Power Operation (Mode 1)

6.0

13724-1

Circulating Water System

41.1

13800-1

Main Turbine Operation

79.2

71111.12

Calculations

V-RIE-MR-U00

Document the Vogtle 1 & 2 Maintenance Rule Risk

Ranking and Performance Criteria Assessment

71111.13

Corrective Action

Documents

Resulting from

Inspection

10793227, 10794367

Miscellaneous

Daily Status Report

05/24/2021

Plan of the Day

05/24/2021

Phoenix A4 Risk

06/07/2021

Phoenix RICT

06/07/2021

Plan of the Day

06/07/2021

Daily Status Report

06/07/2021

Phoenix PRA 4/25/21 - 5/4/21

Phoenix A4 Risk

05/24/2021

Phoenix Unit 1 RICT

05/24/2021

eSOMS Logs 4/25/21 - 5/4/21

Procedures

13419-C

Diesel Generator RICT Support

10.3

NMP-GM-031

On-Line Configuration Risk Management Program

9.0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NMP-GM-031-001

Online Maintenance Rule (a)(4) Risk Calculations

6.0

NMP-GM-031-002

Calculation of RMAT and RICT for the RICT Program

5.0

NMP-GM-031-003

Risk Management Actions for 10 CFR 50.65(a)(4) and the

Risk Informed Completion Time Program

8.0

NMP-GM-031-004-

GL01

Vogtle 1 & 2 RICT System Guidelines

1.0

71111.15

Corrective Action

Documents

10788092, 1086044, 10787264, 10786197, 10788655,

10790958, 1087827, 10768536, 10795427, 10800003

Corrective Action

Documents

Resulting from

Inspection

1088742, 10802559, 10788672

Drawings

2X6AU01-00492

Process Control System Cabinet 08 Interconnection Wiring

Diagram

9.0

2X6AU01-00493

Interconnecting Wiring Diagram Cabinet 08

2X6AU01-00494

Process Control System Cabinet 8 Interconnecting Wiring

Diagram

9.0

Engineering

Changes

1019003501DCP

TDAFW Turbine Speed Control Replacement

6.0

Engineering

Evaluations

CR 10790958 - Operability Determination Support Basis

04/17/2021

Miscellaneous

Unit 2 Unexpected Rod Insertion: Fault Tree, Investigation

Summary, IPC Information, U2 Inadvertent Rod Insertion

IRT Writeup

Unit 1 NSCW Transfer Pump #8 Fault Tree and Refute

Matrix

05/27/2021

Engineering Evaluation - 1A NSCW Transfer Pump

05/27/2021

14581A-1

Train A NSCW Transfer Pump Operability Test following

packing replacement

05/26/2021

GP-15618

Vogtle Electric Generating Plant Units 1 and 2 Upper

Plenum Anomaly Information Exchange Meeting

05/14/1992

Procedures

14581A-1

Train A NSCW Transfer Pump Operability Test

1.1

AX6AA04-00030

Precautions, Limitations & Setpoints for Nuclear Steam

Supply Systems

67.0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

SNC1150438, SNC1085187, SNC1100676, SNC1151209

71111.18

Engineering

Changes

SNC1060859

Unit 1 PC Node Box Replacement

Work Orders

SNC1083057

71111.19

Corrective Action

Documents

10788092, 1086044, 10787264, 10786197, 10788655,

10793199, 10793227, 10796069

Corrective Action

Documents

Resulting from

Inspection

10808100

Drawings

1X2D05A024

NSCW Cooling Tower 1B-Unit 1 Forming Plan at Fan Deck

EL. 250'-11

10.0

Procedures

14808B-2

Train B Centrifugal Charging Pump and Check Valve IST

and Response Time Test

7.0

Work Orders

SNC1048447, SNC11565884, SNC1149827,

SNC1149971, SNC1132092, SNC1060425, SNC960486,

SNC961243, SNC963233, SNC1151084, SNC1150438,

SNC1151209, SNC1153969, SNC1155594, SNC1156584,

SNC1133603

71111.22

Corrective Action

Documents

10686257

Procedures

14545B-1

Motor Driven Auxiliary Feedwater Pump B Monthly

Operability Test

2.1

14807B-1

Train B Motor Driven Auxiliary Feedwater Pump / Check

Valve Inservice and Response Time Test

5.2

14980A-1

Diesel Generator 1A Operability Test

31.3

24753-1

Steam Generator Level (Narrow Range) Protection

Channel II 1L-549 Channel Operational Test and Channel

Calibration

27.2

Work Orders

SNC1124465

71114.06

Miscellaneous

V-RQ-SE-21301

21 Segment #3 DEP Scenario

1.0

V-RQ-SE-21301

21 Segment #3 DEP Scenario

1.0

71151

Corrective Action

Documents

10807536, 10807538, 10808315

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Resulting from

Inspection

Miscellaneous

Monthly Data Export Unit 1 RCS Activity - April 2020 to

March 2021

Monthly Data Export Unit 2 RCS Activity - April 2020 to

March 2021

Monthly Data Export Unit 1 RCS Identified Leak Rate -

April 2020 to March 2021

Monthly Data Export Unit 2 RCS Identified Leak Rate -

April 2020 to March 2021

Unit 1 eSOMS Rounds - April 2020 to March 2021

Unit 2 eSOMS Rounds - April 2020 to March 2021

VEGP 1&2 RCS Data - April 2020 to March 2021

NEI 99-02

Regulatory Assessment Performance Indicator Guideline

71152

Corrective Action

Documents

10759811, 10491708, 10368251, 10725143, 10759811,

10804138, 10793015, 10787581, 10796682, 10806678

Corrective Action

Documents

Resulting from

Inspection

1089845, 1089846

Procedures

NMP-ES-033

Setpoint Control Program

8.0

NMP-ES-033-003

Setpoint Control Program Drift Monitoring

5.0