|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:UTILITY
MONTHYEARIR 05000245/19900231990-11-15015 November 1990 Insp Repts 50-245/90-23,50-336/90-25 & 50-423/90-23 on 901001-05.No Violations Noted.Major Areas Inspected: Radiological Controls Program IR 05000423/19900191990-11-14014 November 1990 Insp Rept 50-423/90-19 on 900905-1015.Violations Noted. Major Areas Inspected:Operations,Radiological & Chemistry Controls & Security & Maint & Surveillance IR 05000213/19900831990-11-0505 November 1990 Insp Repts 50-213/90-83,50-245/90-82,50-336/90-82 & 50-423/90-83 on 900924-28.No Violations Noted.Major Areas Inspected:Licensee Timeliness for Reporting/Operability Determinations IR 05000336/19900181990-11-0505 November 1990 Insp Rept 50-336/90-18 on 900822-1001.One Cited Violation, One Noncited Violation & One Deviation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint,Previously Identified Items,Engineering/Technical Support IR 05000245/19900191990-10-26026 October 1990 Safety Insp Repts 50-245/90-19,50-336/90-21 & 50-423/90-17 on 900904-07.No Violations or Deviations Identified.Major Areas Inspected:Qa Program Implementation IR 05000213/19900821990-10-23023 October 1990 Insp Repts 50-213/90-82,50-245/90-81,50-336/90-81 & 50-423/90-82,on 901001-12.No Violations Noted.Major Areas Inspected:Licensee Occupational Radiation Protection Program Activities During Unit 1 Refueling Outage IR 05000336/19900191990-10-15015 October 1990 Insp Rept 50-336/90-19 on 900910-14.No Violations Noted. Major Areas Inspected:Open Items & Allegations from Insp Rept 50-336/89-13 IR 05000245/19900161990-10-0303 October 1990 Partially Withheld Insp Repts 50-245/90-16,50-336/90-17 & 50-423/90-16 on 900827-31.Violations Noted IR 05000423/19900101990-08-17017 August 1990 Insp Rept 50-423/90-10 on 900612-0723.Violations Noted.Major Areas Inspected:Normal & Backshift Work Periods of Plant Operations,Maint & Surveillance,Security,Engineering & Technical Support,Radiological Controls & Safety Assessment IR 05000245/19900141990-08-16016 August 1990 Insp Repts 50-245/90-14,50-336/90-15 & 50-423/90-13 on 900723-27.One Noncited Violation Noted.Major Areas Inspected:Radiological Controls IR 05000423/19900061990-08-14014 August 1990 Insp Rept 50-423/90-06 on 900604-08.No Violations or Deviations Noted.Major Areas Inspected:Training Program, Including Licensed Operator Training Program for Initial Licensing & Requalification Program for Licensed Operators IR 05000245/19900111990-08-0909 August 1990 Insp Repts 50-245/90-11,50-336/90-12 & 50-423/90-09 on 900611-15 & 25-29.No Violations Noted.Major Areas Inspected: Review of Licensee Emergency Diesel Generator Fuel Oil Program IR 05000423/19900801990-08-0202 August 1990 Insp Rept 50-423/90-80 on 900416-25.No Violations Noted. Major Areas Inspected:Development of Sufficient Procedures in Appropriate Areas to Cover Broad Spectrum of Accidents & Equipment Failures IR 05000336/19900111990-07-31031 July 1990 Insp Rept 50-336/90-11 on 900530-0711.Noncited Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls/Emergency Preparedness,Maint/Surveillance, Engineering/Technical Support & Security IR 05000245/19900131990-07-24024 July 1990 Insp Repts 50-245/90-13,50-336/90-13 & 50-423/90-11 on 900609-13.No Violations or Deviations Noted.Major Areas Inspected:Radiological Environ Monitoring Program,Including Mgt Controls,Audits & Surveillance Procedures IR 05000245/19900091990-07-20020 July 1990 Insp Rept 50-245/90-09 on 900515-0625.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000245/19900071990-07-0606 July 1990 Insp Rept 50-245/90-07 on 900403-0514.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000423/19900081990-07-0303 July 1990 Partially Withheld Insp Rept 50-423/90-08 on 900503-0611 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected: Maint & Surveillance,Security,Engineering & Technical Support & Safety Assessment & Quality Verification IR 05000336/19900081990-07-0202 July 1990 Insp Rept 50-336/90-08 on 900425-27.No Violations Noted. Major Areas Inspected:Results of Eddy Current Exam of Steam Generators Performed During Oct 1989,w/emphasis on Acceptable Period of Operation for Steam Generators ML20055E7991990-06-29029 June 1990 Insp Rept 50-336/90-09 on 900417-0529.Violations Noted. Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Engineering/Technical Support, Committee Activities,Periodic Repts,Lers & Allegations ML20055D1431990-06-20020 June 1990 Enforcement Conference Rept 50-245/90-08 on 900615.Major Areas Discussed:Findings in Insp Rept 50-245/90-08 Re Shipment of Irradiated Hardware as Radwaste to Low Level Waste Disposal Facility in Barnwell,Sc on 900507 ML20055C3161990-02-21021 February 1990 Insp Rept 50-245/89-19 on 891023-27.Unresolved Items Noted. Major Areas Inspected:Review of Selected Deviations from Rev 4 to to GE Topical Rept NEDO-31331, Emergency Procedure Guidelines & Response to NRC Bulletin 88-007,Suppl 1 IR 05000423/19890191989-09-22022 September 1989 Insp Rept 50-423/89-19 on 890828-0901.No Violations Noted. Major Areas Inspected:Radiological & non-radiological Chemistry Program Including Confirmatory Measurements, Chemistry & Lab Qa/Qc IR 05000245/19890181989-09-13013 September 1989 Insp Repts 50-245/89-18,50-336/89-18 & 50-423/89-15 on 890807-11.No Violations Noted.Major Areas Inspected:Util Compliance W/Atws Rule (10CFR50.62) & QA Annual Review, Including Procurement Program & Matl Receipt & Storage IR 05000245/19890801989-08-31031 August 1989 Insp Repts 50-245/89-80,50-336/89-80 & 50-423/89-80 on 890530-0616 & 0710-14.No Violations Noted.Major Areas Inspected:Units 1,2 & 3 Maint Program & Implementation, Review of Maint Documents & Observation of Work in Progress IR 05000336/19890161989-08-21021 August 1989 Insp Rept 50-336/89-16 on 890616-0726.Violation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Committee Activities,Emergency Diesel Generator Operation & Fuel Oil Sys IR 05000423/19890131989-08-21021 August 1989 Insp Rept 50-423/89-13 on 890724-28.No Violations Noted. Major Areas Inspected:Fire Protection Prevention Program IR 05000245/19890161989-08-0202 August 1989 Insp Repts 50-245/89-16 & 50-336/89-15 on 890711-14.No Violations Noted.Major Areas Inspected:Implementation of Radiation Protection Program IR 05000423/19890111989-08-0202 August 1989 Insp Rept 50-423/89-11 on 890613-0717.No Violations Noted. Major Areas Inspected:Facility Tours of MP-3 Site,Esf Sys Walkdowns of Recirculation Spray Sys,Si Pump Cooling Sys, Turbine Driven Auxiliary Feed Pump Sys & Review of LERs IR 05000245/19890141989-07-28028 July 1989 Insp Rept 50-245/89-14 on 890616-0717.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Physical Security,Control Room Exercise Equipment & NRC Temporary Instruction 2513/93 IR 05000423/19890121989-07-21021 July 1989 Insp Rept 50-423/89-12 on 890626-30.No Violations or Deviations Noted.Major Areas Inspected:Inservice Insp Program,Steam Generator Eddy Current Insps & Water Chemistry Results IR 05000336/19890111989-07-21021 July 1989 Insp Rept 50-336/89-11 on 890505-0615.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Surveillance, Maint,Previously Identified Items,Allegations,Committee Activities,Licensee self-assessment & LERs IR 05000245/19890121989-07-19019 July 1989 Insp Rept 50-245/89-12 on 890509-0615.Major Areas Inspected: Previously Identified Items,Outage Activities,Plant Operations,Physical Security,Recirculation Pump Seal Failure Event,Reactor Scram on Low Main Condenser Vacuum & LERs IR 05000423/19890081989-07-11011 July 1989 Insp Rept 50-423/89-08 on 890515-0612.No Violations Noted. Major Areas Inspected:Plant Operations,Unresolved Item 50-423/87-12-01,previous Insp Findings,Plant Incident Repts, in-core Thimble Degradation & 10CFR50.59 Safety Evalautions IR 05000245/19890151989-07-0505 July 1989 Insp Repts 50-245/89-15,50-336/89-14 & 50-423/89-10 on 890619-23.No Violations or Deviations Noted.Major Areas Inspected:Effluent,Transportation & Solid Radwaste Programs, Including Mgt Controls,Audits,Qa & Program Implementation IR 05000245/19890131989-06-29029 June 1989 Enforcement Conference Rept 50-245/89-13 on 890621.Major Areas Discussed:Shipment of High Pressure Pump & Trailer W/ Removable External Radioactive Contamination from Licensee Reactor Site to Vendor Site in Moorestown,Nj IR 05000423/19890041989-06-28028 June 1989 Insp Rept 50-423/89-04 on 890405-0515.No Violations Noted. Major Areas Inspected:Plant Incident Repts,Reactor Scrams, Shutdown to Repair High Unidentified Leakage & Repair to Svc Water Piping & Physical Security IR 05000336/19890081989-06-20020 June 1989 Insp Rept 50-336/89-08 on 890324-0504.No Violations Noted. Major Areas Inspected:Plant Operations,Outage Activities, Surveillance,Maint,Plant Incident Repts & Allegations IR 05000245/19890081989-06-15015 June 1989 Insp Rept 50-245/89-08 on 880328-0508.No Unsafe Plant Conditions Noted.Major Areas Inspected:Plant Operations, Physical Security,Licensee Receipt Insp of New Fuel, Refueling,Plant Mods & LERs ML20245A8371989-06-0909 June 1989 Insp Rept 50-245/89-13 on 890517-18.Violations Noted Re Shipment of Package W/Removable External Radioactive Contamination in Excess of Limits & Failure to Supply Shipping Papers.Major Areas Inspected:Shipment of Pump IR 05000245/19890101989-06-0707 June 1989 Insp Repts 50-245/89-10 & 50-336/89-12 on 890515-19.No Violations Noted.Major Areas Inspected:Fire Protection & Prevention Program,Including Program Administration & Organization & Administrative Control of Combustibles ML20245A6781989-06-0707 June 1989 Insp Rept 50-245/89-11 on 890501-05.No Violations Noted. Major Areas Inspected:Observations,Review of Data,Licensee Response to Generic Ltr 88-01,NDE Procedures,Engineering Support & QA Involvement IR 05000245/19890091989-05-18018 May 1989 Insp Repts 50-245/89-09 & 50-336/89-10 on 890417-21.No Violations Noted.Major Areas Inspected:Review of Radiation Protection Activites at Unit 2 & Begining of Refueling Outage at Unit 1 IR 05000245/19890051989-05-17017 May 1989 Insp Repts 50-245/89-05 & 50-336/89-07 on 890417-21.No Violations Noted.Major Areas Inspected:Engineering Organization & Staffing,Qa,Plant Mods & Technical Training IR 05000423/19890031989-05-0303 May 1989 Insp Rept 50-423/89-03 on 890228-0404.No Violations Noted. Major Areas Inspected:Plant Operations,Status of Previous Insp Findings,Fuel Receipt & Insp,Generic Concerns About Steam Generator Tube Plugs,Esf Walkdown & LERs IR 05000245/19890041989-05-0303 May 1989 Insp Rept 50-245/89-04 on 8902214-0327.Major Areas Inspected:Previously Identified Items,Plant Operations, Physical Security,Ultrasonic Testing of Condensate Storage Tank,Maint Program Implementation & Committee Activities ML20246K0931989-04-26026 April 1989 Insp Rept 50-336/89-05 on 890211-0323.No Violations Noted. Major Areas Inspected:Outage Activities,Surveillance,Maint, Previously Identified Items,Plant Incident Repts & Allegations IR 05000245/19890061989-04-0707 April 1989 Insp Repts 50-245/89-06,50-336/89-09 & 50-423/89-06 on 890306-10.No Violations Noted.Major Areas Inspected:Review of Implementation of Radiation Protection Program at Unit 2 During Refueling Outage & Preparation of Outages for Units IR 05000245/19890071989-03-23023 March 1989 Insp Repts 50-245/89-07,50-336/89-06 & 50-423/89-07 on 890221-0303.No Violations or Deviations Noted.Major Areas Inspected:Site Observations & in-ofc Review of Data in Areas of Inservice Insp & Secondary Water Chemistry IR 05000245/19890031989-03-15015 March 1989 Insp Repts 50-245/89-03 & 50-336/89-04 on 890213-17.No Violations Noted.Major Areas Inspected:Unit 2 Refueling Outage Activities,Unit 1 Refueling Outage Preparation Activities & Station ALARA Practices 1990-08-09
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20207F1521999-05-25025 May 1999 Notice of Violation from Investigation Rept 1-94-021 on 940506-960329.Violation Noted:Between 740831-910407,licensee Made Changes to Facility Described in Safety Analysis Rept for Refueling Core Offloads Without Performing Evaluation ML20196K2621999-05-24024 May 1999 EN-99-020:on 980525,notice of Violation & Exercise of Enforcement Discretion Will Be Issued to Licensee.Action Based on Severity Level III Problem Consisting of Four Individual Violations Involving Refueling Outage PNO-I-99-022, on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions1999-05-11011 May 1999 PNO-I-99-022:on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours PNO-I-99-016, on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve1999-04-0707 April 1999 PNO-I-99-016:on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve ML20205M7201999-04-0606 April 1999 Notice of Violation from NRC OI Case 1-96-002 & Conclusions of Millstone Independent Review Team.Violation Noted. E Debarba,Deliberately Discriminated Against Supervisor in Performance Engineering Group at Millstone Station ML20205M7351999-04-0606 April 1999 Notice of Violation from Investigation in Case Numbers 1-96-002 & 1-97-007.Violation Noted:Licensee Discriminated Against Supervisor in Performance Engineering Group at Plant Due to Involvement in Protected Activities IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems ML20205J0941999-03-12012 March 1999 Rept of Review of Millstone Units 1,2 & 3:Allegations of Discrimination in NRC Ofc of Investigations Cases 1-96-002, 1-96-007,1-97-007 & Associated Lessons Learned ML20207M1131999-03-0909 March 1999 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:Employment of Two Contractor Employees Terminated in Aug 1997,in Part Because Individuals Raised Concerns Re MOV Program Manual ML20205G6161999-03-0909 March 1999 EN-99-010:on 990309,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based Upon Severity Level II Problem Involving Discrimination Against Two Contractor Employees at Millstone MOV Dept IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support PNO-I-99-006, on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys1999-01-29029 January 1999 PNO-I-99-006:on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ PNO-I-99-004, on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review1999-01-20020 January 1999 PNO-I-99-004:on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20199C6381999-01-0707 January 1999 Notice of Violation from Insp on 981006-1123.Violation Noted:On or Before 981120,conduit 9-15,in Fire Area A-24,not Sealed & Tested in Accordance with Astme E-119,fire Endurance Test PNO-I-99-001, on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power1999-01-0404 January 1999 PNO-I-99-001:on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power PNO-I-98-062, on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch1998-12-15015 December 1998 PNO-I-98-062:on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch ML20195H6901998-11-18018 November 1998 Notice of Violation from Insp on 980818-1005.Violation Noted:Engineering Evaluations Not Performed When RCS Heatup Rate Limit Exceeded on 951217 & When RCS Cooldown Rate Limit Exceeded on Three occasions,940424,0728 & 951215 IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan ML20155B1521998-10-23023 October 1998 Notice of Violation from Insp on 980810-0903.Violation Noted:Design Basis,As Described in FSAR Chapter 14,Accident Analyses Had Not Been Correctly Translated Into Plant Procedures & Acceptance Criteria IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities ML20154D1151998-09-11011 September 1998 Notice of Violation from Insp on 980413-24-0511-15,27-29, 0609-11 & 23-25.Violation Noted:Program Implemented TS 6.8.4.a,failed to Include Provisions to Reduce Leakage from RSS Heat Exchangers to SW Sys IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support PNO-I-98-039, 980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 9808111998-08-12012 August 1998 PNO-I-98-039:980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 980811 ML20237D3041998-08-12012 August 1998 Notice of Violation from Insp on 980413-0508.Violations Noted:Two Examples Identified Where Licensee Not Performing Leakage Testing of safety-related Valves in Sys That Could Contain Highly Radioactive Fluids During Accident IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20237B0741998-08-12012 August 1998 Notice of Violation from Insp on 980428-0629.Violation Noted:Licensee Failed to Direct Test Personnel to Close & Lock RHR Outboard Drain Valve IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc PNO-I-98-026, on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release1998-07-0101 July 1998 PNO-I-98-026:on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release PNO-I-98-025, on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting1998-06-30030 June 1998 PNO-I-98-025:on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support ML20249C6931998-06-19019 June 1998 Notice of Violations from Combined Insp on 980301-0427. Violations Noted:Prior to 980424,instrument Min Accuracy of Wind Speed Channels Were Not Measured as Required by Table 3.3-8 of Unit 2 TS 3/4.3.3.4 IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 ML20249B0421998-06-12012 June 1998 Notice of Violations from Insp on 980413-24.Violations Noted:Only 1 RCS Loop Operable W/Plant in Mode 4 on 980407 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes 1999-09-14
[Table view] |
Text
.
.
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
Report No. 50-423/86-07 l Docket N License No. NPF-49 Priority --
Category --
Licensee: Northeast Nuclear Energy C P. O. Box 270 Hartford, Connecticut 06141-0270 Facility Name: Millstone Nuclear Power Station - Unit 3 Inspection At: Waterford, Connecticut Inspection Conducted: January 19 - February 14, 1986 Inspectors: om ,
// I ales A. Prell, Reactor Engineer / dage
!M C. Ma~
Peter Wen, Reactor Engineer 3 /to /sb
' date Approved ~wW [ M Pster f4elgroth,4Wief, Test Program Section, M
date OB, DRS Inspection Summary: Routine unannounced inspection conducted on January 19 -
February 14, 1986 (Report No. 50-423/86-07)
Areas Inspected: Startup program review, post core hot functional test witnessing and test result review, initial criticality and low power physics testing, power ascension program review and test witnessing, and review of licensee actions on previous inspection findings. The inspection involved 225 hours0.0026 days <br />0.0625 hours <br />3.720238e-4 weeks <br />8.56125e-5 months <br /> on site by two region based inspector Results: No violations were identifie PDR ADOCK O y3
_
__ . __ _ __ ___
.
.
DETAILS 1.0 Persons Contacted
R. Bradley, Startup Engineer, NNECO
- K. Burton, Operations Supervisor, NNECO
-
- J. Crockett, MP-3 Unit Superintendent, NNECO E. Fries, Startup Engineer, NNEC0 N. Hulme, Startup Engineer, NNECO
'
- J. Jensen, QA Specialist, NNECO T. Kulterman, Senior Engineer, NUSCO J. Langon, Plant Engineer, NNEC0 T. Lyon, Startup Test Engineer, NNECO D. Miller, Startup Manager, NNECO D. Moure, Assistant Operations Supervisor, NNEC0 M. Pearson, Assistant Operations Supervisor, NNECO
- W. Richter, Assistant Startup Supervisor, NNECO A. Stengal, Startup Test Engineer, NNECO C. Wooten, Startup Test Engineer, NNEC0
!
- D. McDaniel, Reactor Engineer, NNECO
!
U.S. Nuclear Regulatory Commission
- F. Casella, Resident Inspector 1 *J. T. Shediosky, Senior Resident Inspector
!
- 2.0 Licensee Action on Previous Inspection Findings (Closed) IFI (50-423/85-71-16) The technical manual and precautions in j SP 3622.5, relating to the Turbine Driven Auxiliary Feedwater Pumps, (TDAFWP) caution the operator to exercise the manual speed adjusting knob following turbine operation to prevent system failure. A review of the procedure related to TDAFWP operation found that they did not adequately delineate this precaution nor did they require independent verification j that the governor was reset to its standby positio The inspector verified that Revision 7 to OP 3322 requires the operator to exercise the manual speed adjusting knob and provide independent verifica-tion of valve lineu This item is close (CLOSED) UNR (50-423/85-71-17) The following items were identified related to SP 3622 and Op 3322-
! 1) OP 3322, step 4.2 refers to -TS Figure Figure 3-7 is not included in the TS.
I
- - _ _
.,- - - - - . . _ , . - . - . . , - , , _ . . - _ . _ , . ,-- ,. - -. , , . , . - -
_ _ _ . . _ _ _
.
2) SP 3622.6 requires operation of the turbine driven AFW Pump at the minimum governor speed for 2 minutes. OP 3322 state that the AFW pump should not be operated below 1500 rpm to " ensure proper lubrication" 3) OP 3322 requires manual lubrication of the AFW pumps bearings if the pumps have not been operated within the previous 30 days. The pro-cedures did not however provide lubrication instruction The inspector verified that the licensee has deleted the reference in OP 3322 to TS Figure 3.7 and replaced it with reference to TS 3.7. The minimum governor speed setting for the turbine driven AFW pump is 1700 rpm, which is well above the 1500 rpm minimum speed stated in OP 3322. Also a standby D.C. Oil Lubrication pump would start on a low pressure signal to " ensure proper lubrication" if the rpms went below 1500 rp A letter from the manufacturer now indicates that manual lubrication is required for AFW pumps bearings if they have not been operated within the previous 40 days versus 30 days. Technical Specification surveillance requirement 4.7.1.2.1 requires each AFW pump to be demonstrated OPERABLE at least once per 31 days by developing a differential pressure of 1460 psid across each motor-driven pump and across the steam-turbine driven pump. Thus all pumps would have to be operated at least once every 39 days (31 days + 25%), which is one day short of 40 days maximum. Thus making the manual lubrication problem moo Based on the above this item is close (CLOSED) UNR (50-423/85-71-21) The precautions and restoration sections of SP 3646A.3, " Diesel Generator Interdependent Test", both listed "None",
which appeared inappropriate. Also the procedure did not include provi-sions for independent verification of equipment restoration following testin The reason there was no precautions or restoration section for SP 3646 is that the SP references OP 3346A for implementation. The inspector verified that OP 3346A has precautionary statements and restores the system. The SP data sheet now incorporates provisions for independent verification of system restoratio Based on the above this item is close (OPEN) UNR (50-423/85-71-22) Various problems were identified with the draft procedure SP 3646A.6, "Offsite Power Transfer Operability Test."
However, the problems identified by the inspector refer to testing of relays associated with the ESF system. Thus SP 3646A.4 " Engineered Safety Systems Integrated Test" appears to be the procedure of concer ___ _ _ ._ - _ _ _ _ _ ___ -______ _. ._
.
.
SP 3646A.4 is still in draft for This surveillance however is only to be done during refueling operations. The initial surveillance was satis-fied by preoperational test 3-INT-2004, "ESF Without loss of Power".
Based on the above this item remains unresolved pending review of the final approved surveillance procedure SP 3646 (CLOSED) CAT Finding - Violation (50-423/85-04-03): This item pertains to the welds identified as nonconforming to the procurement specifications related to some of the installed tanks, pressure vessels, and heat ex-changers. The licensee's field quality control representatives reinspect-ed all fillet welds identified as " Undersized" for equipment nozzles and supports for the subject QA Category I tanks, pressure vessels, and heat exchanger Subsequently, the nonconformance was evaluated for actual stress loading and reworked, as required, under SWEC's QA program, to meet the ASME Code for minimum weld siz To preclude similar incidents from happening in the future, the SWEC QA department instituted a compre-hensive weld inspection training program for QA/QC personnel, including project QA inspectors. In addition, the SWEC QA division, through a memo-randum to all district managers, stressed the company's commitment to pro-per fillet weld inspection. A review of the documentation and field veri-fication supported the adequacy of the licensee's corrective action against this deficienc Based on the above, the inspector determined that the licensee's action is complete. This item is close (CLOSED) UNR (50-423/85-34-04) This item pertains to effluent monitoring sensitivity dat The inspector reviewed the K4 man summary report and de-tector calibration data for the particulate and gas radiation monitoring systems. The detector is certified to have the characteristics noted in the referenced document Calibration is based on deposited activities on a copper disc using beta efficiencies of a proportional counting syste The beta and gamma scintillation detectors used were first calibrated using the standard factory procedure KNP 18-60 revision No violations were identifie ;
This item is close .- Post Core Hot Functional Test
!
'
3.1 Test Witnessing A various times during the inspection period, the inspectors witnessed testing in progress on a sampling basis and evaluated most portions of the Post Core Hot Functional Test. The tests witnessed included:
-- - . -
..--_4,.,._ . _ _ , , . . - , , - y,,, ,,,,%_. , , . , _ - , , . , . _ , , _ . - - - --...-n,.m.__,.w
.-
_ _
.
.
--
3-INT-5000, Appendix 5001, Shutdown Margin;
--
3-INT-5000, Appendix 5004, Rod Control Slaver Cycle and CRDM Timing;
--
3-INT-5000, Appendix 5006, RCS Leak Detection;
--
3-INT-5000, Appendix 5007, Pressurizer Heaters and Spray;
--
3-INT-5000, Appendix 5008, Rod Drop Testing;
--
3-INT-5000, Appendix 5011, Movable In-Core Detector Operation;
--
3-INT-5000, Appendix 5015, Digital Rod Position Indication Operational Test;
--
3-INT-5000, Appendix 5018, Rod Control Operational Test; Tests were observed for the following areas:
i
--
Tests were conducted in accordance with the approved test procedures; change to the procedures were made in accordance with the administrative procedur Prior to performing each test, briefing with the test crew and operation personnel were conducted and the briefing was adequat Test prerequisites and initial conditions were me Operator actions were correc Summary analysis was made upon completion of each tes All test results as verified by inspector direct observations indicated that overall test acceptance criteria have been met or proper test deficiencies were documented and followed up by the license The inspector also attended some of PORC/JTG (Plant Operation Review ,
Committee / Joint Test Group) meetings which approved test procedure change '
and final test result acceptance. The inspector noted that-in all instances the PORC/JTG approval process was formal, thorough, and deliberat .2 Test Results Review Those Post Core Hot Functional Test results identified in Appendix A were reviewed by the inspector to verify that:
--
test changes were approved and implemented in accordance with administrative procedures;
_
.
--
changes did not impact the basic objectives of the test;
--
test deficiencies and exceptions were properly identified, resolved, and resolution accepted;
--
the cognizant engineering group had evaluated the test results and signified that testing demonstrated design conditions were met; and,
--
test results compared with established acceptance criteria or were properly resolve Details relating to some of those test results reviewed are described belo . RCS Leak Detection (Appendix 5006)
The Millstone Unit 3 Technical Specifications (TS) require that surveillance be performed at least once per 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> using water inventory balance method to determine leakage from the reactor coolant system (RCS). The plant computer RCS leakage calculation program, SP 3J3 is designed to fulfill this requirement. Surveillance procedure SP 3601F.6, RCS Leak Test, delineates calculational steps and is used as a backup when the plant computer is not available. The purpose of this RCS Leak Detection test (Appendix 5006) was to verify that a known 1 gpm leak rate could be detected by the RCS Leakage Calculation Program SP 3J3 and surveillance procedure SP 3601 Baseline Leak Rate Test Prior to performing superimposed leak rate test, a baseline RCS leak rate was measured per program SP 3J3 and surveillance procedure SP 3601F.6 on January 22, 1986. The inspector performed independent calculations using an NRC-developed leak rate computer program NUREG-1107, "RCSLK9: Reactor Coolant System Leak Rate Determination for PWRs", to verify the licensee's calculation. These comparisons are:
Leak Rate (LR) Licensee Calculation Inspector Test Date (gpm) Pgrm 3J3 Hand Ca Ca Identified LR 0.723 0.74 0.73 (0630-1030) Unidentified LR 0.362 0.73 0.36 Based on the same set of initial and final data input, the inspector's calculation agreed closely with the licensee's program SP 3J3 calculation. The licensee's RCS leakage water inventory calculation methodology appeared to be adequat ._ _ _ _ _ .
!
I However, from test results review, the inspector identified the following items were either not included or not clearly spelled out in the licensee's procedur The large variation of unidentified leak rate observed betwen the computer program SP 3J3 and surveillance procedure hand calculation (0.362 gpm vs. 0.73 gpm) was primarily due to different values of initial pressurizer level used in the calculation. Instantaneous values at beginning and end of test were used in the licensee's calculation. Since the computer point data and the hand calculation input data were taken at slightly different times, system variation and/or instrument uncertainty might have contributed to this deviated inputs. The large uncertainty of RCS leakage calculation caused by this system variation could have an adverse impact on calculation results especially when the plant is experiencing some known leakag Level changes in Containment Drains Transfer Tank (CDTT),
Primary Drains Transfer Tank (PDTT), Pressurizer Relief !
Tank (PRT) and Accumulator Tank are counted as an identi-fied leakage. The unidentified leak rate is calculated by subtracting the identified leak rate from the total RCS leak rate. The TS limit (TS 3.4.6.2) for the unidentified leakrate is 1 gp Thus,. incorrect determination of iden-tified leak rate would affect the adequacy of the unidenti-fied leak rate calculation. The inspector noticed that the level change in these tanks, especially the PDTT, could come from various sources other than RCS. However, the surveillance procedure does not clearly indicate that leak-age from RCS can only be considered for identified leakag In addition, during the test, computer point GWS-F84 (VCT Divert flow to BRS) was observed having noise spikes which caused an erroneous computer entry of the VCT dump flo The computer program SP 3J3 requires manual adjustment of the calculated leak rate under these circumstance l These items are collectively an unresolved item pending ;
i further review by the inspector (50-423/86-07-01). I Superimposed Leak Rate Test
At the end of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> baseline leak rate test, a known leak !
rate of approximately 1 gpm was induced by opening valve l 3CHS-V800 (drain to auxiliary building sump). The Superim-posed Leak Rate Test was subsequently performed for 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> The licensee calculated. leak-rate results along with the inspector independently calculated results are compared below:
J
. - _ _ ._ ,- _ _ _ _ _ _ -
.
-
i 8 ,
I Leak Rate (LR) Licensee Calculation Inspector Test Date (gpm) Pgrm 3J3 Hand Ca Ca Identified LR 0.654 0.61 0.73 (1156-1401) Unidentified LR 1.625 1.76 1.54 ,
The change in the RCS leak test unidentified leakage is:
Licensee Calculation :
Program 3J3 Hand Calculation Inspector Calculation 1.263 1.03 1.18 This comparison indicated that the licensee's computer program performed adequately well. The superimposed leak rate as deter-mined by the licensee's computer program was 1.263 gpm (1.625 -
'
O.362) which did not meet test acceptance criteria of I gpm 9%. This discrepancy was discussed during JTG test result re-view. The relatively large uncertainty associated with this
'
test was attributed to the Controlatron flow instrument reading (3CHS-FI 391) which monitored the induced flow rate. During the test, this flow meter reading was shown to fluctuate from 0.98 gpm to 1.17 gpm. The test result was subsequently accepted by the JI . Pressurizer Heaters and Spray (Appendix 5007)
Pressurizer heaters and-spray effectiveness was checked on January 21, 1986. The inspector noted the following test results:
--
Pressurizer pressure response to opening of both normal spray valves (PCV 455B and PCV 455C) was within the test limits as recommended by the vendor (Westinghouse)
--
Pressurizer pressure response to energization of all
- pressurizer heaters was also within the test limits.
!
However, the total heater (Groups A through E)
j
'
capacity (1703.69KW) was found slightly off the test acceptance criteria of 1710-1890 KW TS require that Group A and Group B heaters, which are supplied by emergency power, each has a capacity of at least 175 KW. The measured heater capacities
,
for Group A and Group B heaters was 329.9 KW and 330 KW, respectively. Based on the satisfactory results for the pressurizer pressure response and TS requirements, the JTG accepted the test results.
l
!
--- -___- _, . ._, m-- . _ . , . . . ,, , , _ _ _ . . . .. _
- --
i .
>
.
2
--
Constant flow was established through each pressurizer spray line to minimize thermal shock when spray actua-tion was needed. However, due to leakage of both nor-mal spray valves, the bypass valves V15 and V59 were set at 1/16 turn which caused the proportion heater (Group C) to run at about 80% demand. This exceeded the vendor recommended value of 50%. The licensee and vendor are in the process of evaluating these test identified problem . Rod Drop Testing (Appendix 50081 The control rod drop time measurement was performed in accord-ance with test procedure 3-INT-5000, Appendix 5008, Component Rod Drop Testing. A computer timing system (Auto Rod Drop Test System) was set and calibrated prior to its use in measuring the rod drop time. All 61 control rods drop times were measured at cold no flow, cold full flow, and hot full flow condition Under cold test conditions an additional three rod drop time measurements were performed for those control rods whose rod drop times fell outside the two sigma (standard deviation) limit of the drop time for all control rods. While under the hot-full flow test conditions, the fastest and slowest rods were dropped ten additional times in addition to three additional rod drop tests for those rods that fell outside the two sigma limit.
'
All test results were consistent and acceptable and within the TS limit of 2.2 second .0 Low Power Physics Tests 4.1 Procedure Review Scope
'
'
The approved test procedures listed below were reviewed for technical and administrative adequacy and to verify that test planning satisfies
, regulatory guidance and licensee commitment INT-7000, Appendix 7004, Revision 1, " Isothermal Temperature Coefficient"
--
3-INT-7000, Appendix 7005, Revision 0, "RCCA or Bank Worth
- Measurement"
--
3-INT-7000, Appendix 7006, Revision 0, " Natural Circulation" l
I
.
- . . . - - - - - . . - . , , . - ,m. - - -. .
m , , ,, .- . --- . - - . - - - ..
.
'
10
)
Discussion f
The procedures were examined for: management review and approval; procedure format, clarity of stated test objectives; prerequisites; i
'
environmental conditions; acceptance criteria; source of acceptance criteria; references; initial conditions; attainment of test objec-tives; test performance documentation and verification; degree of
'
detail for test instructions; restoration of system to normal after independent verification of critical steps or parameters, and quality control and assurance involvemen .
Findings l
'
The review indicated that the procedures are consistent with regula-tory requirements, guidance, and with the licensee's commitment No discrepancies or unacceptable conditions were identified. The inspector had no further questions on these procedure .2 Test Witnessing and Data Review 4. Low Power Physics Testing At various times during the inspection period, the inspectors witnessed most portions of Low Power Physics Tests (LPPT). The tests witnessed include:
--
initia! criticality;
--
reactivity computer checkout;
- --
boron endpoint measurement;
--
isothermal temperature coefficient measurement;
,
--
rod worth measurement; and
--
flux mapping.
! Tests were observed for the following areas:
i
!
--
Low Power Physics Tests were conducted in accordance with the approved test procedure, 3-INT-7000, " Low Power Physics Tests," Revision ,
- --
Prior to performing each test, briefings with the test crew and operation personnel were conducted and the briefing was adequat Test prerequisites and initial conditions were met.
i i
_ . . -. . .
.
.
-
11
--
Summary analysis was made upon completion of each tes The major events during LPpT were as follows:
, January 23 2200 Reactor Critical January 24 0200 Completed Hot Zero Power Testing Range ,
,
Determination. The range of neutron
- flux (reactivity computer picoammeter)
<
was determined to be 1.6E-8 to 1.6E-7 amp ) 0420 Completed Reactivity Computer Checkout Comparisons of predicted and measured
'
i reactivities based on doubling time i measurement were acceptabl j 0715 Commenced ARO Boron Endpoint Measuremen j Measured Endpoint Boron Concentration was 1570.6 ppm. The predicted value was 1566 pp l 1004 Commenced ITC (ARO) measurement l
] 1030 Obtained first set of cooldown/heatup
- ITC values a
i
'
1400 Operations personnel found the RCS leakage source (Seal Filter Vent Valve) and isolated it. The inspector noted that at about 1330, a reactor operator was able to identify the RCS leakage based on control room panel indication Obtained additional set of ITC (AR0)
data. The averaged ITC's from heatup and cooldown agreed within il pcm/ The measured ITC (ARO) value of -1.03 pcm/ F agreed well with the predicted value of -1.69 pcm/ F. However, the corresponding MTC result of (+)0.92 pcm/ F exceeded the TS 3.1.1.3 a limi .l The licensee reactor engineer was fully l aware of the plant conditions and cor-responding TS 3.1.1.3 a LCO requirement l l
. . .. - - _ _ _ . . - - . _- _- ...
. ,
i l
-
l 12 l 2100 Commenced Control Bank (CB) D Rod Worth Measurement (Dilution Method)
2219 Completed CB D Rod Worth Measurement The measured CB D rod worth of 61 pcm was within the predicted range of 593 59 pc January 25 0020 Commenced Control Bank D Inserted j Measurement 0255 Measured Endpoint Boron Concentration (D IN) was 1516.7 ppm. The predicted i value was 1499 pp Commenced ITC (D IN) Measurement -
Cooldown- gp 0447 Commenced ITC (D IN) Measurement -
Heatup. The measured cooldown ITC was identical to the heatup ITC. The measured ITC value of -2.5.pcm/ F was-within the predicted range of -3.24 3 pcm/ Commenced CB C Rod Worth Measurement
(Dilution Method)
0807 Completed CB C Rod Worth Measurement
'
The measured CB C rod worth of 1223 pcm was within the predicted range of 1254 125 pcm.
0830 Commenced CB C&D Inserted Measurement Measured Endpoint Boron Concentration (C&D IN) was 1384 ppm. This value was i
'
within the predicted range of 1357 136 ppm.
'
0935 Commenced ITC (C&D IN) Measurement-The measured ITC VALUE OF -6.07 pcm/ F
- was within the predicted range of-6.52 3 pcm/ F. Also, the average ITC's from heatup and cooldown agreed within 1 pcm/* !
I'
!
.
_ -- __ - . - - . -
.
.
1 l 1100 Commenced Dilution for Rod Worth
Measurement of CB A & B 1704 The measured Endpoint Boron Concentration (A+B+C+D IN) was 1115 ppm. This value was within the
- predicted range of 1086 109 ppm.
, The measured CB B rod worth of 123 pcm was within the predicted range of 1208 121 pc The measured CB A rod worth of 121 pcm was also within the predicted range of 1239 124 pc Manually tripped the Reactor per
'
TS 4.10.1.2 requirement (In preparation for All-Rods-In Testing)
2000 Started up by pulling CB B 2016 Manually tripped the reactor per Test Procedure 7000, Step 7.12.3.4, also in preparation for All-Rods-In Testin Commenced Reactor Startup
'
2102 Reactor Critical with CB A at 40 steps l
'
2144 Commenced Shutdown Bank E (SE) rod worth measurement i
1 2206 Completed SE rod worth measurement
i The mesaured SE rod worth of 185.7 pcm
'
was within the predicted range of 188
19 pc Commenced Shutdown Bank D (SD) rod
, worth measurement j 2313 Completed SD rod worth measurement i
The measured SD rod worth of 547.8 pcm
! was within the predicted range of 526 53 pc Commenced Shutdown Bank C (SC) rod
- worth measurement i
.
.
January 26 0052 Completed SC rod worth measurement The measured SC rod worth of 679.6 pcm was within the predicted range of 655 66 pcm 0130 Measured Single Rod F-2 Rod Worth for information purpos Measured N-1 total rod worth with rod F-2 Stuck Out The measured value of 7925.7 pcm was within the predicted range of 7571 757 pc Commenced All-Rods-In With F-2 Stuck Out Boron Endpoint Measurement 0911 Completed All-Rods-In with F-2 Stuck Out Baron Endpoint Measurement The measured value of 765.2 ppm was within the predicted range of 725 73 pp Manually tripped the reactor per test procedure 7000 step 7.1 Reactor Critical 2238 Commenced control bank rod worth measurement in overlap January 27 0656 Completed control bank rod worth measurement in overlap (Boration Method)
The inspector noted that the measured total overlapping control bank rod worth of 4365.6 pcm was consistent with the previously measured sum (429 pcm) of January 28 LPPT temporarily being hold due to dif-ficulty in getting secondary side chemi-stry in specificatio l l
__ _ _ . _ _ _ . .. . _ _ . . ._ ._ . _ ___
.
,
I January 29 0313 Resumed LPPT. Started flux mapping with rod configuration at Rod Insertion Limi The measured incore tilt of 1.006 was less 2 than the design criterion of s 1.02 I
! 0600 Measured a single rod D-12 rod worth from Hot Zero Power Rod Insertion Limi ;
The measured value of 396.6 pcm was within
'
- the safety analysis assumed value of 780 pc ,
1046 Started flux mapping with rod configuration ct Rod Insertion Limit with D-12 fully out to simulate ejected ro '
The incore program picked up this asymmetric
- rod configuration with calculated maximum l Fg (Z) = 6.4757 which was less than FSAR as-
'
sumed value of 1 January 30 0630 Started flux mapping with rod configuration
, of Control Bank D.In i The measured incore tilt (1.023) was within i
FSAR/ Safety Review Criteria of 1.04, however, I
was slightly.in excess of the design limit of j
'
1.0 The licensee reactor engineer evaluat-ed this situation and attributed the cause to the Xenon left from the previous D-12 ejected rod worth / flux mapping tes I A six pass symmetric thimble map taken at i approximately 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> later showed almost
0 tilt. This confirmed the licensee reactor
- engineer's evaluation.
'
103*, Started flux mapping with All-Rods-Out rod
-
configuration.
j The measured incore tilt was the same as the Control Bank D In case.
!
,
'
The measured FAH in both Control Bank D In
, and ARO cases were acceptabl Completed flux mapping and LPPT.
l l
l l
I i
i t
. - , - - - . , - , , - , , , , , . _ _ , , - - . - . , .
.- -
. .,---....4, - -,,, m~,nv- ~ , ,r., m ,. , rn ,
-- . .= . . - . --
.
6
,
!
!
4. Low Power Physics Test Results Review
- The inspector independently verified that the predicted i values and acceptance criteria were obtained from "The
,
Nuclear Design and Core Physics Characteristics of the
- Mills., tone Generating Station Unit 3 Cycle 1," WCAP-10791, Revijion 1. The LPPT results are summarized below:
. Endpoint Boron Rod Worth ITC
, (ppm) (pcm) (pcm/ F)
- Test Con Mea Predicted Mea Predicted Mea Predicted t
ARO 157 .03 -1.69 l D IN 151 .5 593 -2.50 -3.24 D+C IN 1384 1357 1223 1254 -6.07 -6.52 D+C+B IN - -
123 D+C+B+A IN 1115 1086 121 '
D+C+B+A+ - -
18 S IN E
D+C+B+A+ - -
54 S *b E D IN
- D+C+B+A+
SE *b D+bC IN - - -
67 N-1 Rod 76 .7 7571 - -
,
i Worth with F-2 Stuck Out Control - -
436 Banks Over-lapping (Boration Method)
,
Rod D-12 - -
39 i Worth from RIL All measured values were close to and within the analytically predicted ranges with the exception of D-12 ejected rod worth
! measurements from RIL. In this case the measured rod worth of 39 pcm was within the safety analysis assumed value of 780 pc I Although the licensee did not measure the Shutdown Banks A and B rod i
I
,
-,,----r- - - - . - ,, , - - ,, , , , , , , , - , , - , - - n, ,-a- c- nw, ,r,,, , ---r,,e,,s -.-+,r v-- , - - g.,wn, -w---m- , - - . -
- ._ - - _ . _ - . - .--= -- .-.. - - . - . -
l .
.
- 17
i
worth in fuel vendor recommended rod configuration (Table A.4, WCAP-10791), instead an N-1 configuration with Rod F-2 stuck out was
, performed. This configuration provided a direct comparison of
<
measured rod worth (7925.7 pcm) against the value assumed in the FSAR analysis (6814 pcm). The measured rod worth confirmed the F5AR j analysis valu I
'
i
"
Following the discovery of the positive MTC value at ARO.HZP condi-tions, the licensee took correct actions including establishing ad-
- ministrative restrictions on Rod Withdrawal Limits and Boron Concen- ,
'
i tration Limits. The special report on this subject was submitted to
- NRC Region I (Letter from W. D. Romberg (NNECO) to T. E. Murley (NRC),
dated February 3,1986) in accordanc e with TS 3.1.1.3 requiremen f i The inspector verified that the operation personnel were aware of i
.I these restrictions and that the associated curve was located in the ;
control room curve log and was being use :
!
The inspector reviewed the low power flux maps and noted that the pre- !
dicted power distribution was generally agreed with the predicted !
values. No unacceptable power distributions were identifie I r
4. Conclusion -
1' I Low Power Physics Test was accomplished in accordanc( with !
approved procedures, data were acceptable, and test ot iectives '
, were me f
- Licensee performance during approach to criticality and
- ubse- f quent LPPT was deliberate, and carefully controlled. T5.,urveil- l lance requirements associated with the special test exceptions !
during LPPT were correctly addressed in the controlling pi ace- :
dure 3-INT-7000, " Lower Power Physics Tests," and adequately per- !
formed. Licensee management was responsive to inspector obser- !
.
'
vations. Problems ~ identified during the test such as positive !
MTC value at all-rods-out condition were disseminated to the :
appropriate groups and corrective actions were implemente !
l 5.0 Power Ascension Tests i t
j 5.1 Procedure Review l
!
- The approved test procedures listed in Attachment B were reviewed for technical and administrative adequacy and to verify that test
,
, '
j planning satisfies regulatory guidance and licensee commitment j d
!
-
a
'
i L
'
.
i
'
.
.
Discussion The procedures were examined for: management review and approval; procedure format, clarity of stated test objectives; prerequisities; environmental conditions; acceptance criteria; source of acceptance criteria; references; initial conditions; attainment of test objec-tives; test performance documentation and verification; degree of detail for test instructions; restoration of system to normal after testing; identification of test personnel; evaluation of test data, independent verification of critical steps or parameters, and quality control and assurance involvemen Findings The review indicated that the procedures are consistent with regula-tory requirements, guidance, and with the licensee's commitment No discrepancies or unacceptable conditions were identified. Ques-tions raised by the inspector to the licensee relating to the proce-dures were satisfactorily answere It was noted that the licensee is planning on seeking from the NRC full credit for two R.G.I.68 required tests: the ejected rod test at above 10% full power and the dropped rod test at 50% full power. This request will be based on the fact of these tests have been adequately demonstrated at prototype plants similar to MP-3. In a letter to NEU from Westinghouse dated January 20, 1985, Westinghouse concurred with NEU and stated that "The cost in time and the probability of subse-quent undesirable power distributions resulting from these tests lead to the conclusion that they should be dropped from the Millstone Nuclear Power Station Unit 3 test program." Westinghouse supported this statement with a table showing the number of operating plants similar in design to MP-3 which had successfully completed the tes lhe licensee committed in the FSAR Table 14.2-2 item number 30, to perform these two tests and will therefore be seeking a change to the FSAR from NRC allowing deletion of the This is an unresolved item (50-423/86-07-02).
5.2 Test Witnessing Portions of the following Power Ascension Test and the entirety of the Natural Circulation Test were witnessed by the inspectors. This included the initial test preparation and test restoration as well as witnessing the actual tes INT-7000, Appendix 7006, " Natural Circulation" Revision 0
_ _ - --_ -__ __-
. .__ _ _ . . _ __ _ _ - - _ . ~ .- --
.
.
i
--
3-INT-8000, Appendix 8018, " Automatic Steam Generator Level Control", Revision 0, Step 7.1 - Testing at Low Powe INT-8000, Appendix 8013, " Steam Dump control", Revision 0
,
These tests were witnessed for the following attributes: Appropriate procedure revision was available and in use by all '
crew member i Minimum crew requirements were me i All test prerequisites and initial conditions were met and/or !
! those which were waived were reviewed / approved in accordance ;
j with procedure / technical specification (TS) requirement <
I Test equipment required by the procedure was calibrated and in
,
service.
.1 I Test data equipment required by the procedure was calibrated to a common time bas . Test was performed as required by a technically adequate
procedur . Crew actions aopeared to be correct and timely during the performance of the tes Coordination was adequat . Quick summary analysis was made to assure proper plant response i to the tes . All data was collected for final analysis by the proper
, personne . Overall test acceptance criteria were me . The licensee's preliminary test evaluation was consistent with inspector's observatio i 12. Adherence to TS requirements was maintained for those tests which affect TS LCO The following discussion pertains to these test . Natural Circulation Test (Appendix 7006)
It took approximately ten minutes to establish natural circulation after the reactor coolant pumps had been trippe Natural circulation took place when AT reached approximately.
-e,.m , ,.,-- , ,cw.,
e,, . -p. - - e . g - - - - , , , - - - - - - .,..,_p .-,.,,,,,.yc,_ ..c. , , . . . , - . w- , , - , . . , ,r ..9--9
_ - _ _ _ _ _ _ _ _ _ _ _ _ _
.
.
37 F (TH0T ~ 594 F and TCOLD ~ 557 F). There appeared to be close correlation between the incore thermocouple readinos and T
H0 The majority of incore thermocouple readings ranged between 596 F and 602 After the RCS had stabilized on natural circulation, the letdown / charging system was initiated to see what affect it had on cooling down the primary coolant. It was discovered that the RCS began cooling down at a rate of approximately 1 F every four minutes. Questions raised by the inspector concerning the results of the test were satisfactorily answered by the license . Steam Generator Water Level Control Test (Appendix 8018)
This test was first performed on February 10, 1986. During the test, I&C personnel inadvertently shorted the steam generator level control system circuits which caused all feedwater regula-ting bypass valves to clos This resulted in a S/G low level reactor trip. The test was resumed on February 11, 1986. The inspector noted that a lesson learned from an earlier reactor trip which occurred on February 7,1986, was incorporated. Auc-tioneered high nuclear flux was fed to the bypass control cir-cuits to position the bypass valves during low power automatic S/G level control. Following the February 7, 1986 reactor trip, the bypass valve response was determined to be too fast. Cur-rently a gain adjustment factor of 2.44% valve opening /1% NI power was set in lieu of 8% valve opening /1% NI powe Preliminary test results indicated that the automatic S/G level control was stable. No unacceptable conditions were identifie . Steam Dump Test (Appendix 8013)
The steam dump test was performed in accordance with procedure Appendix 8013, " Steam Dump Control," Revision 0. This test was originally planned to be performed at 0% power. Test Change No. 3 modified the test procedure to be performed at 15% power level. There appeared, however, to be a lack of proper review for Test Change No. 3. As a result, during initial performance of Step 7.4, Plant Trip Controller Response Test, the procedure was found to difficult to follow. The test engineer quickly identified the problem and corrected the situation through Test Change No. 6. which was further reviewed by the PORC/JTG. Upon PORC/JTG approval, the test was resumed and completed without inciden . . -. . - . . - - ._ .- _ . - . ._. . - - . .
.
I
i
- 21 i
Preliminary test results indicated that the test objectives
} Were met and test data were acceptable.
!
l 6.0 Independent Calculation
!
j During the review of Post Core Hot Functional Test, Appendix 5009 - Pre-i critical RCS Flow Measurement, the inspector verified that the calcula-
! tions and math used to convert percentage of flow to inches of water (AP)
J and to calculated flow rates were correct.
i
! Also, as described in Section 3.2.1 detailed RCS leak rate calculation j was performed using NRC-developed leak rate comouter program NUREG-1107, j "RCSLK9: Reactor Coolant System Leak Rate Determination for PWRs", to
verify the licensee's calculatio .0 Quality Assurance / Quality Control i
The site QA/QC organization, manpower and planned activties to cover the startup test program was described in the NRC inspection report 35-5 During this inspection period, the inspectors noted that QC inspectors were actively following startup program tests. Appropriate surveillance reports were issued.
! . . -
i No unacceatable conditions were identified.
!
j 8.0 Plant Tours *
The inspe: tor made several tours of the facility during the course of the i inspectio1. This included tours of the turbine building, control building,
- and contral room. A review of the work in progress, security, cleanliress i and housekeeping was made.
<
9.0 Exit Meeting
!
- An exit meeting was held on February 14, 1986 to discuss the inspection j
scope and findings, as detailed in this report (see paragraph 1.0 for attendees).
- At no time was written material given to the license l The inspector determined that no proprietary information was utilized ,
during this inspection.
-
i
}
4 ,
e
$
f
.
.
APPENDIX A POST CORE HOT FUNCTIONAL TEST RESULTS REVIEWED
--
Appendix 5004, Rod Control Slave Cycler and CRDM Timing
--
Appendix 5006, RCS Leak Detection
--
Appendix 5007, Pressurizer Heaters and Spray
--
Appendix 5008, Rod Drop Testing
--
Appendix 5009, Precritical RCS Flow Measurement
--
Appendix 5011, Moveable In-Core Detector Operation
--
Appendix 5018, Rod Control Operational Test
-. . . . .-. - . _ - .- _ _ ._ . _ _ _ _
i 4 .
APPENDIX B POWER ASCENSION TEST PROCEDURES REVIEWED i
--
3-INT-8000, Power Ascension Test, Revision 0
--
3-INT-8000, Appendix 8001, Calorimetric, Revision 0
--
3-INT-8000, Appendix 8002, Nuclear Instrumentation Operational Alignment Verification, Revision 0
--
3-INT-8000, Appendix 8003, Calibration of Steam Flow and Feedwater Flow
,
Instrumentation at Power, Revision 0
--
3-INT-8000, Appendix 8004, Operational Alignment of Process Temperature Instrumentation, Revision 0
--
3-INT-8000, Appendix 8005, Reactor and Turbine Control, Revision 0 i
--
3-INT-8000, Appendix 8007, Radiation Monitoring System, Revision 0
--
3-INT-8000, Appendix 8008, Ventilation System Operability, Revision 0
--
3-INT-8000, Appendix 8009, Plant Chemistry, Revision 0
--
3-INT-8000, Appendix 8010, Neutron Shield Tank Cooling Test, Revision 0
--
3-INT-8000, Appendix 8011, Containment Penetration Temperature Monitoring, Revision 0
--
3-INT-8000, Appendix 8013, Steam Oump Control, Revision 0
- --
3-INT-8000, Appendix 8015, RCS Flow Measurement, Revision 0
- --
3-INT-8000, Appendix 8016, Turbine Overspeed, Revision 0~
,
--
3-INT-8000, Appendix 8017, Automatic Reactor Control, Revision 0
--
3-INT-8000, Appendix 8018, Automatic Steam Generator Level Control, Revision 0
--
3-INT-8000, Appendix 8019, Turbine Plant Component Cooling Water System I
- Balancing, Revision 0 j --
3-INT-8000, Appendix 8020, Power Coefficient, Revision 0
--
3-INT-8000, Appendix 8022, 10% Load Swing Tests, Revision 0 i
l
.
-
--
3-INT-8000, Appendix 8023, Reactor Trip / Shutdown Outside Control Room, Revision 0
--
3-INT-8000, Appendix 8026, Large Load Reduction, Revision 0
--
3-INT-8000, Appendix 8029, Pipe Fluid Transient Vibration Testing, Revision 0
--
3-INT-8000, Appendix 8030, Loss of Power (20% Power), Revision 0
--
3-INT-8000, Appendix 8031, Reactor Coolant System Boron Measurement, Revision 0
--
3-INT-8000, Appendix 8034, Thermal Expansion Restraint, Revision 0
--
3-INT-8000, Appendix 8035, Loose Parts Monitoring System, Revision 0
--
3-INT-8000, Appendix 8037, Main Steam Isolation Valve Closure Test, Revision 0
. - _ _ _ _ _ _ - - _ _ - _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ - _ _ _ - - _ _ _ _ _ - _ _ _ _ _ _ - . __ - - - _ _ _ _ _ _ _ _ _ _ _ _ - _ - - - _ _ - - _ _ - _ _ _ _ _ . _ _ - _ _