IR 05000334/2016005
| ML16235A293 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 08/31/2016 |
| From: | Silas Kennedy Division Reactor Projects I |
| To: | Richey M FirstEnergy Nuclear Operating Co |
| Kennedy S | |
| References | |
| IR 2016005 | |
| Download: ML16235A293 (7) | |
Text
August 31, 2016
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR BEAVER VALLEY POWER STATION UNIT NOS. 1 AND 2 (REPORT 05000334/2016005 AND 05000412/2016005)
Dear Mr. Richey:
On August 9, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Beaver Valley Power Station, Unit Nos. 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2015, through June 30, 2016. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Beaver Valley Power Station, Unit Nos. 1 and 2, operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Beaver Valley Power Station, Unit Nos. 1 and 2, during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through June 30, 2018. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last half of the inspection period in the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, and Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. The NRC conducted audits of licensee efforts towards compliance with these Orders, and the information gathered will aid staff in development of the ultimate Final Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing Temporary Instruction 2515-191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.
In Staff Requirements Memorandum - SECY 16-0009, Recommendations Resulting from the Integrated Prioritization and Re-Baselining of Agency Activities, (ADAMS Accession #
ML16104A158) the Commission approved the NRC staff recommendation to discontinue the formal mid-cycle assessment process beginning in calendar year 2017. This will be the final mid-cycle assessment letter. The staff will continue to conduct assessment reviews and communicate changes in the assessment of licensee performance quarterly, and will also issue end-of-cycle assessment letters.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRCs Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (610) 337-5046 with any questions you have regarding this letter.
Sincerely,
/RA/
Silas R. Kennedy, Chief Projects Branch 6 Division of Reactor Projects
Docket Nos. 50-334 and 50-412 License Nos. DPR-66 and NPF-73
Enclosure:
Inspection Plan
ML16235A293 SUNSI Review
Non-Sensitive
Sensitive
Publicly Available
Non-Publicly Available
OFFICE RI/DRP RI/DRP RI/DRP
NAME JKrafty/JK SShaffer/SS SRKennedy/SRK
DATE 08/29/16 08/17/16 08/29/16 Letter to Mr. Marty Richey from Silas R. Kennedy dated August 31, 2016
SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR BEAVER VALLEY POWER STATION UNIT NOS. 1 AND 2 (REPORT 05000334/2016005 AND 05000412/2016005)
DISTRIBUTION w/encl:
DDorman, RA DLew, DRA MScott, DRP DPelton, DRP RLorson, DRS SKennedy, DRP SShaffer, DRP SElkhiamy, DRP MHenrion, DRP JKrafty, DRP, SRI BReyes, DRP, RI CBozlinski, DRP, ROAA JBowen, RI, OEDO RidsNrrPMBeaverValley Resource RidsNrrDorlLpl1-2 Resource ROPreports Resource RMcKinley, DRS JNoggle, DRS MGray, DRS PKrohn, DRS CCahill, DRS DJackson, DRS NMcNamara, RI, SLO DTifft, RI, SLO DScrenci, RI, PAO NSheehan, RI, PAO RidsNrrDirslpabResource ROPassessment Resource
Page 1 of 3 07/25/2016 13:28:24 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Beaver Valley Inspection / Activity Plan 07/01/2016 - 06/30/2018 EXM10/3
- BEAVER VALLEY 1 INITIAL EXAM
1 FY17-BV1 INITIAL OPERATOR LICENSING EXAM U01922 09/12/2016 09/16/2016
FY17-BV1 INITIAL OPERATOR LICENSING EXAM U01922 10/31/2016 11/11/2016 71124
- RAD SAFETY INSPECTION
1, 2 IP Radiation Monitoring Instrumentation 71124.05 07/11/2016 07/15/2016 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 07/11/2016 07/15/2016 1, 2 IP Radiological Environmental Monitoring Program 71124.07 07/11/2016 07/15/2016 1, 2 IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 07/11/2016 07/15/2016 71152
- PI & R SAMPLE - EFFLUENT MONITORS
1, 2 IP Problem Identification and Resolution 71152 08/01/2016 08/04/2016 71124
- RAD SAFETY INSPECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 10/03/2016 10/07/2016 1, 2 IP Occupational ALARA Planning and Controls 71124.02 10/03/2016 10/07/2016 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 10/03/2016 10/07/2016 1, 2 IP Occupational Dose Assessment 71124.04 10/03/2016 10/07/2016 7111108P
- BV U1 INSERVICE INSPECTION
1 IP Inservice Inspection Activities - PWR 7111108P 10/03/2016 10/14/2016 71124
- RAD SAFETY INSPECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 11/07/2016 11/11/2016 1, 2 IP Occupational ALARA Planning and Controls 71124.02 11/07/2016 11/11/2016 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 11/07/2016 11/11/2016 1, 2 IP Occupational Dose Assessment 71124.04 11/07/2016 11/11/2016 1, 2 IP Occupational Exposure Control Effectiveness 71151-OR01 11/07/2016 11/11/2016 71124.08
- RADWASTE
1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 12/05/2016 12/09/2016 7111108P
- U2 INSERVICE INSPECTION
2 IP Inservice Inspection Activities - PWR 7111108P 04/10/2017 04/21/2017 7111111B
- BV2 REQUAL INSP WITH P/F RESULTS
2 IP Licensed Operator Requalification Program 7111111B 06/19/2017 06/23/2017 71124
- HP INSPECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 05/01/2017 05/05/2017 1, 2 IP Occupational ALARA Planning and Controls 71124.02 05/01/2017 05/05/2017 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 05/01/2017 05/05/2017 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 3 07/25/2016 13:28:24 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Beaver Valley Inspection / Activity Plan 07/01/2016 - 06/30/2018 71124
- HP INSPECTION
1, 2 IP Occupational Dose Assessment 71124.04 05/01/2017 05/05/2017 EP
- EP PROGRAM INSPECTION
1, 2 IP Alert and Notification System Testing 7111402 06/19/2017 06/23/2017 1, 2 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 06/19/2017 06/23/2017 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 06/19/2017 06/23/2017 1, 2 IP Performance Indicator Verification 71151 06/19/2017 06/23/2017 10/8EXAM
- BEAVER VALLEY 2 INITIAL EXAM
2 FY18-BV2 INITIAL OPERATOR LICENSING EXAM U01938 10/09/2017 10/13/2017
FY18-BV2 INITIAL OPERATOR LICENSING EXAM U01938 11/06/2017 11/17/2017 71152B
- PI&R BIENNIAL
1, 2 IP Problem Identification and Resolution 71152B 06/05/2017 06/09/2017 1, 2 IP Problem Identification and Resolution 71152B 06/19/2017 06/23/2017 71124
- HP INSPECTION
1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 08/07/2017 08/11/2017 1, 2 IP Occupational Dose Assessment 71124.04 08/07/2017 08/11/2017 1, 2 IP Radiation Monitoring Instrumentation 71124.05 08/07/2017 08/11/2017 ISFSI
- ISFSI LOADING CAMPAIGN INSPECTION
1, 2 IP Operation Of An ISFSI 60855 09/25/2017 09/29/2017 1, 2 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 09/25/2017 09/29/2017 71124
- HP INSPECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 10/16/2017 10/20/2017 1, 2 IP Occupational ALARA Planning and Controls 71124.02 10/16/2017 10/20/2017 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 10/16/2017 10/20/2017
IP Occupational Exposure Control Effectiveness 71151-OR01 10/16/2017 10/20/2017
IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 10/16/2017 10/20/2017 7111121
- CDBI
1, 2 IP Component Design Bases Inspection 7111121 10/16/2017 10/20/2017 1, 2 IP Component Design Bases Inspection 7111121 10/30/2017 11/03/2017 1, 2 IP Component Design Bases Inspection 7111121 11/13/2017 11/17/2017 71124
- RAD SAFETY INSP
1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 01/22/2018 01/26/2018 1, 2 IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 01/22/2018 01/26/2018 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 3 of 3 07/25/2016 13:28:24 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Beaver Valley Inspection / Activity Plan 07/01/2016 - 06/30/2018 7111111B
- UNIT 1 REQUAL INSP W/ P/S RESULTS
1 IP Licensed Operator Requalification Program 7111111B 04/09/2018 04/13/2018 TI-191
- FUKUSHIMA LESSONS-LEARNED
1, 2 IP Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 2515/191 02/19/2018 02/23/2018 71124
- RAD SAFETY INSP
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 04/23/2018 04/27/2018 1, 2 IP Occupational ALARA Planning and Controls 71124.02 04/23/2018 04/27/2018 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 04/23/2018 04/27/2018 1, 2 IP Occupational Dose Assessment 71124.04 04/23/2018 04/27/2018 U1 ISI
- UNIT 1 INSERVICE INSPECTION
1 IP Inservice Inspection Activities - PWR 7111108P 04/23/2018 05/04/2018 EP
- EP EXERCISE INSPECTION
1, 2 IP Exercise Evaluation 7111401 06/11/2018 06/15/2018 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.