November 18, 2015
SUBJECT:
SHERON HARRIS NUCLEAR PLANT - U.S. NUCLEAR REGULATORY
COMMISSION SECURITY INSPECTION REPORT 05000400/2015403
Dear Mr. Faulk:
On October 28, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Shearon Harris Nuclear Plant. The inspection covered one or more of the key attributes of the Security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report (IR) documents the inspection results that were discussed on October 28, 2015, with Ms. Tanya Hamilton and members of the Shearon Harris and Duke Corporate staff.
No findings were identified during this inspection.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public inspections, exemptions, requests for withholding, of the NRC's "Agency Rules of Practice and Procedure," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room, or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS); accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
However, the material enclosed herein contains Security-Related Information in accordance with 10 CFR 2.390(d)(1), and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the Enclosure will not be made available electronically for public inspection in the NRC Public Document Room, or from the PARS component of NRCs ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information - Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1), and follow the instructions for withholding in 10 CFR 2.390(b)(1).
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Sincerely,
/RA/
Binoy B. Desai, Chief Plant Support Branch 2 Division of Reactor Safety
Docket No. 50-400 License No. NPF-63
Enclosure:
NRC IR 05000400/2015403 w/Attachment: Supplementary Information (OUO)
cc: Distribution via Listserv
ML15322A286 SUNSI REVIEW FORM 665 ATTACHED OFFICE RII:DRS/PSB2 RII:DRS/PSB2 RI:DRS/PSB2 RII:DRP/BR4 RII:DRS/PSB2
SIGNATURE JHW2 via e-mail JDG1 via e-mail BBD for JOB2 GTH1 BBD
NAME J. Wallo J. Graham J. Brown G. Hopper B. Desai
DATE 11/ 18 /2015 11/ 17 /2015 11/ 18 /2015 11/ 18 /2015 11/ 18 /2015
E-MAIL COPY YES NO YES NO YES NO YES NO YES NO cc:
Edward T. ONeil, Director Nuclear Protection Services Shearon Harris Nuclear Power Plant 5413 Shearon Harris Road New Hill, NC 27562