IR 05000400/2010405

From kanterella
Jump to navigation Jump to search
IR 05000400-10-405, on 08/12/10, Shearon Harris, NRC Office of Investigations Report 2-2010-023
ML102861827
Person / Time
Site: Harris 
Issue date: 10/05/2010
From: Ernstes M
NRC/RGN-II/DRS/PSB2
To: Burton C
Carolina Power & Light Co
References
IR-10-405
Download: ML102861827 (3)


Text

October 5, 2010

SUBJECT:

NRC OFFICE OF INVESTIGATIONS REPORT 2-2010-023, AND SHEARON HARRIS NUCLEAR PLANT INSPECTION REPORT 05000400/2010405

Dear Mr. Burton:

This refers to the investigation completed on August 12, 2010, regarding security activities at your Shearon Harris Nuclear Power Plant, Unit 1. The purpose of the investigation was to review the facts and circumstances associated with a security related issue. The results of the investigation were discussed on September 21, 2010, with Mr. B. Bernard and other members of your staff.

Based on the results of this investigation, no findings were identified. However, two licensee-identified violations which were determined to be of very low safety significance are listed in this report. The NRC is treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the NRC Enforcement Policy because of the very low safety significance of the violations and because they were entered into your corrective actions program. If you contest these non-cited violations, you should provide a response within 30 days of the date of this inspection report with the basis of your denial, to the Nuclear Regulatory Commission, Regional Administrator, Region II; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Shearon Harris Nuclear Station.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/readingrm/adams.html (the Public Electronic Reading Room). However, because of the security-related information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of the enclosures to this letter will not be available for public inspection. CP&L

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC=s document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response ASecurity Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390 (b)(1).

Should you have questions concerning this letter, please contact us.

Sincerely,

/RA/

Michael E. Ernstes, Chief

Plant Support Branch 2

Division of Reactor Safety Docket No. 50-400 License No. NPF-63

Enclosures:

1. Summary of Findings

2. Synopsis OI Investigation 2-2010-023

3. Licensee Identified Violations

4. Administrative Closure cc w/Encl: See Page 3 3

cc w/Encl:

cc w/Inspection Summary:

Brian C. McCabe Manager, Nuclear Regulatory Affairs Progress Energy Carolinas, Inc.

P.O. Box 1981 Raleigh, NC 27602-1981

Christopher Vice President Shearon Harris Nuclear Plant Carolina Power & Light Company P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165

Kelvin Henderson Plant General Manager Carolina Power and Light Company Shearon Harris Nuclear Power Plant P.O. Box 165, Mail Zone 3 New Hill, NC 27562-0165

Phyllis N. Mentel (Acting) Manager Support Services Shearon Harris Nuclear Power Plant P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165

R. J. Duncan, II Vice President Nuclear Operations Carolina Power & Light Company P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165

David H. Corlett Supervisor Licensing/Regulatory Programs Progress Energy P.O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165

David T. Conley Associate General Counsel Legal Dept.

Progress Energy Service Company, LLC P.O. Box 1551 Raleigh, NC 27602-1551

John C. Warner Manager Support Services Progress Energy Carolinas, Inc.

Shearon Harris Nuclear Power Plant P.O Box 165, Mail Zone 1 New Hill, NC 27562-0165

Christos Kamilaris Director Fleet Support Services Carolina Power & Light Company P.O. Box 1551 Raleigh, NC 27602-1551

Joseph W. Donahue Vice President Nuclear Oversight Carolina Power and Light Company P.O. Box 1551 Raleigh, NC 27602-1551