IR 05000400/2008402
| ML082200525 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 08/07/2008 |
| From: | Joel Munday NRC/RGN-II/DRS/PSB2 |
| To: | Burton C Carolina Power & Light Co |
| References | |
| IR-08-402 | |
| Download: ML082200525 (4) | |
Text
August 7, 2008
SUBJECT:
RECEIPT OF REPLY TO NOTICE OF VIOLATION; EA-08-181 (NRC INSPECTION REPORT 05000400/2008402), DATED JULY 31, 2008
Dear Mr. Burton:
This letter documents the receipt of Carolina Power and Lights response to the Shearon Harris Nuclear Power Plant Notice of Violation discussed in letter, NRC Office of Investigation Report 2-2007-031, and Notice of Violation, dated July 3, 2008.
Based on the staffs review of Carolina Power and Lights response, no further enforcement action is necessary to ensure compliance with regulatory requirements discussed in the Notice of Violation. However, as part of upcoming routine baseline inspections the NRC will verify the implementation and adequacy of the corrective actions disclosed in your response.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system, ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Joel T. Munday, Chief Plant Support Branch 2 Division of Reactor Safety
Docket No. 50-400
License No. NPF-63
_________________________
G SUNSI REVIEW COMPLETE OFFICE RII:DRP
SIGNATURE RAM
NAME RMusser:rcm
DATE 08/07/2008 8/ /2008 8/ /2008 8/ /2008 8/ /2008 8/ /2008 8/ /2008 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO
cc w/encl:
Paul Fulford, Manager Performance Evaluation and Regulatory Affairs PEB5 Progress Energy Carolinas, Inc.
P.O. Box 1551 Raleigh, NC 27602-1551
Chris Director Site Operations Progress Energy Carolinas, Inc.
Shearon Harris Nuclear Power Plant P.O. Box 165, Zone 1 New Hill, NC 27562-0165
David H. Corlett, Supervisor Licensing/Regulatory Programs Progress Energy Carolinas, Inc.
Shearon Harris Nuclear Power Plant P.O. Box 165, Zone 1 New Hill, NC 27562-0165
David T. Conley Associate General Counsel-Legal Dept.
Progress Energy Service Company, LLC P.O. Box 1551 Raleigh, NC 27602-1551
Kelvin Henderson Plant General Manager-Harris Plant Progress Energy Carolinas, Inc.
Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Zone 3 New Hill, NC 27562-0165
Phyllis H. Mentel, (Acting) Manager Support Services Progress Energy Carolinas, Inc.
Shearon Harris Nuclear Power Plant P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165
Letter to Robert J. Duncan, II from Joel Munday dated: August 7, 2008
SUBJECT:
RECEIPT OF REPLY TO NOTICE OF VIOLATION; EA-08-181, NRC INSPECTION REPORT 05000400/2008402, Dated July 31, 2008
Distribution w/encl:
C. Evans, RII EICS S. Sparks, RII, EICS L. Slack, RII EICS R. Musser, RII, DRP B. Westreich, NSIR (hard copy w/ encl)
E. McNiel, NSIR (hard copy w/ encl)
G. West, NSIR D. Riffle, NSIR RIDSNRRDIRS OE Mail (email address if applicable)