IR 05000400/1978005

From kanterella
Jump to navigation Jump to search
Forwards IE Inspec Rept 50-400/78-05, 50-401/78-05, 50-402/78-05 & 50-403/78-05 on 780919-22 & Notice of Violation
ML20148Q888
Person / Time
Site: Harris  Duke Energy icon.png
Issue date: 10/26/1978
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Jackie Jones
CAROLINA POWER & LIGHT CO.
Shared Package
ML18003A292 List:
References
NUDOCS 7811300167
Download: ML20148Q888 (2)


Text

_ _ _ - - _ _ _ _ _ _ _ _ _ . . _____-_- __

,

,

'

O

' UNITED STATES I

~' [t,*mtCoq'o, 1 AIUCLEAR REGULATORY COMMISSION T ,-,

REGloN ll f

  • - '

t 101 M ARIETT A ST RE ET, '

  1. ATL ANT A, GEORGI A 30303 o, g

%,*****/ OCT 2 61978 l In Reply Refer To:

RII:RDB ,

50-400/78-5 l 50-401/78-5 l 50-402/78-5

.

50-403/78-5 l

!

l Carolina Power and Light Company ATTN: Mr. J. A. Jones Executive Vice President Engineering, Construction and Operation 336 Fayetteville Street Raleigh, North Carolina 27602 Centlemen:

This refers to the inspection conducted by Mr. R. D. Bradley of this office on on September 19-22, 1978, of activities authorized by NRC Construction Permit Nos. CPPR-158, CPPR-159, CPPR-160, and CPPR-161 f or the Shearon Harris Nuclear Power Plant Units 1, 2, 3 and 4 facilities, and to the discussion of our findings held with Mr. R. M. Parsons at the conclusion of the inspectio Areas examined during the inspection and our findings are discussed in the enclosed inspection report. Within these areas, the inspection consisted of selective examinations of procedures and representative records, interviews with personnel, and observations by the inspector Within the scope of this inspection, no itens of noncompliance were disclose We have examined actions you have taken with regard to previously identified enforcement matters. These are discussed in the enclosed inspection repor In accordance with Section 2.790 of the NRC's " Rules of Practice",

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room. If this report contains any information that you (or your contractor) believe to be proprietary, it is necessary that you make a written application within 20 days to this office to withhold AM bl

-- - _ _ - - _ - - - -

_ - - - _ - _ _ - _ - _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _

. .

.

OCT 2 6 ma Carolina Power and -2-Light Company such infomation from public disclosure. Any such application must include a full statement of the reasons on the basis of which it is i claimed that the information is proprietary, and should be prepared so that proprietary information identified in the application is contained in a separate part of the document. If we do not hear from you in this regard within the specified period, the report will be placed in the Public Document Roo Should you have any questions concerning this letter, we vill be glad to discuss them with yo

Sincerely, W

pc Charles E. Murphy, Chief v Reactor Construction and Engineering Support Branch Enclosure:

Inspection Report Nos. 50-400/78-05, 50-401/78-5, 50-402/78-5, 50-403/78-5 cc w/ enc 1:

Mr. Roland Tarsons, Site Manager Shearon llartis Nuclear Power Plant l

P. O. Box '01

New Hill, l' orth Carolina 27562

.

- ~ - - - - - - - m.-_ , _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ __ _ _ _ _