IR 05000387/2025010

From kanterella
Jump to navigation Jump to search
Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000387/2025010 and 05000388/2025010
ML25265A055
Person / Time
Site: Susquehanna  
Issue date: 09/22/2025
From: Erin Carfang
Division of Operating Reactors
To: Berryman B
Susquehanna
References
IR 2025010
Download: ML25265A055 (1)


Text

September 22, 2025

SUBJECT:

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 -

COMPREHENSIVE ENGINEERING TEAM INSPECTION (CETI) INSPECTION REPORT 05000387/2025010 AND 05000388/2025010

Dear Brad Berryman:

On September 11, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Susquehanna Steam Electric Station, Units 1 and 2, and discussed the results of this inspection with Mark Jones, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Erin E. Carfang, Chief Engineering Branch 1 Division of Operating Reactor Safety

Docket Nos. 05000387 and 05000388 License Nos. NPF-14 and NPF-22

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000387 and 05000388

License Numbers:

NPF-14 and NPF-22

Report Numbers:

05000387/2025010 and 05000388/2025010

Enterprise Identifier: I-2025-010-0024

Licensee:

Susquehanna Nuclear, LLC

Facility:

Susquehanna Steam Electric Station, Units 1 and 2

Location:

769 Salem Blvd., Berwick, PA

Inspection Dates:

August 25, 2025 to September 11, 2025

Inspectors:

A. Patel, Team Leader

P. Boguszewski, Senior Resident Inspector

J. Kulp, Senior Reactor Inspector

E. Miller, Senior Reactor Inspector

A. Turilin, Reactor Inspector

J. Cunningham, Reactor Inspector

Approved By:

Erin E. Carfang, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a comprehensive engineering team inspection at Susquehanna Steam Electric Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Comprehensive Engineering Team Inspection

The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Structures, Systems, and Components (SSCs) (IP section 03.01)===

For each component sample listed below, the team reviewed licensing and design basis documents and a sampling of applicable operator actions, periodic testing results, corrective action program documents, internal and external operating experience, preventive and corrective maintenance work orders, modifications, and aging management programs.

Additionally, the team performed walkdowns of accessible components and conducted interviews with licensee personnel.

The team used the attributes contained in IP 71111.21M, Appendix A, Component Review Attributes, such as those listed below as guidance. Specifically, the team evaluated these attributes in the course of applying IP 71111.21M, Appendix B, Component Design Review Considerations and IP 71111.21M, Appendix C, Component Walkdown Considerations.

(1) Emergency Diesel Generator A (0G501A)
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

(2) Reactor Core Isolation Cooling Pump (1P203)
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

(3) Reactor Core Isolation Cooling Injection Valve (HV2491F013)
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

(4)4.16 kV Engineered Safeguard System Auxiliary Bus 1B (1A202)

  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.

The team used Appendix B guidance for Instrumentation, Circuit Breakers and Fuses, Cables, Electrical Loads, and As-Built System.

(5) Engineered Safeguard System Channel A 125V DC Bus (1D612)
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.

The team used Appendix B guidance for Instrumentation, Circuit Breakers and Fuses, Cables, Electrical Loads, and As-Built System.

Modifications (IP section 03.02) (2 Samples)

(1) DCP 1863105, Replace Automatic Transfer Switches 1ATS219, Engineered Safeguard System 480V Motor Control Center
(2) EC-006-1081, Thermal Overloads for 89-10 MOVs that are Jogged/Throttled

10 CFR 50.59 Evaluations/Screening (IP section 03.03) (7 Samples)

(1) SD 02643, Revise OP-152-001, Functional Test of High Pressure Coolant Injection Lube Oil System
(2) SD 02684, Update Residual Heat Removal Pressure Safety Valve Capacities
(3) SD 02732, Unit 1 Cycle 24 Core Operating Limits Report Revision
(4) SE 00034, Commercial Load Center Unit 2 500kV Relay and Protection Upgrades and Tie-In
(5) SE 00035, Decrease in Turbine Valve Testing (Stride 2023-004)
(6) SE 00037, Turbine Valve Inspection Frequency Change
(7) SE 00038, Unit Startup with Auxiliary Boilers Unavailable

Operating Experience Samples (IP section 03.04) (1 Sample)

(1) Information Notice 19-02, Emergency Diesel Generator Excitation System Diode Failures

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified that no proprietary information was retained or documented in this report.

  • On September 11, 2025, the inspectors presented the comprehensive engineering team inspection (CETI) inspection results to Mark Jones, Plant Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Calculations

CALC EC-002-

0506

25 VDC System 1D610 Master Battery Calculation

Revision 47

EC-023-0508

A-D Diesel-Generator Fuel oil Storage Tank (FOST)

Capacity

Revision 1

EC-023-1012

Evaluate Impact of Use of Biodiesel (85) and Ultra-Low

Sulfur Diesel (ULSD) Fuel on the Diesel Generator Fuel Oil

Storage and Transfer System

Revision 3

EC-024-0503

Diesel Generator Load Calculation

Revision 39

EC-050-0549

Maximum RCIC Pump Discharge Pressure

Revision 1

EC-052-1055

CST Water Level for HPCI Suction Transfer

Revision 1

EC-VALV-0505

Scope of DC Powered Motor Operated Valves Requiring

Stroke Time Evaluations at Degraded Voltages

Revision 1

EC-VALV-1072

Actuator Sizing and Diagnostic Test Acceptance Criteria for

GL 89-10 / Appendix III Rising Stem MOVs (DC)

Revision 42

Corrective Action

Documents

CR-2022-10192

Corrective Action

Documents

Resulting from

Inspection

CR-2025-13452

CR-2025-13454

CR-2025-13456

CR-2025-13457

CR-2025-13525

CR-2025-13716

CR-2025-13788

CR-2025-13950

CR-2025-14019

CR-2025-14023

CR-2025-14035

CR-2025-14095

CR-2025-14097

CR-2025-14125

Drawings

M-155

Unit 1 P&ID, High Pressure Coolant Injection

Revision 60

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Changes

EC-004-1031

Plant AC Loadflow Analysis

Revision 8

EC-006-1081

Thermal Overloads for 89-10 MOVs that are

Jogged/Throttled

Revision 0

Miscellaneous

DBD006

Design Basis Document for Class 1E AC Electrical

Revision 5

DI-2019-07966

Evaluation for NRC Inspection Notice 2019-02

06/11/2019

E8385-01

Replacement DG A Voltage Regulator Bridge Rectifier

Diodes

08/07/2019

EDU-DIO-0008

Dedication Document for General Purpose Silicon Standard

Recovery Diodes

Revision 5

SD 02377

Replace Automatic Transfer Switches 1ATS219, 1ATS229,

2ATS219, & 2ATS229

Revision 0

SE 00034

Commercial Load Center Unit 2 Phase II 500 kV Tie-in

Revision 0

Procedures

SM-104-002

4KV Bus 1A202 2 year undervoltage channel calibration

Revision 18

SO-150-004

Quarterly RCIC Valve Exercising

04/30/2025

SO-150-006

RCIC Comprehensive Flow Verification

01/30/2025

Work Orders

WO 2333456

Month Chan A 1D610-125 VDC Battery Discharge Test

and Battery Charger Capability Test SM-102-A03

04/04/2024