IR 05000387/2025002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000387/2025002 and 05000388/2025002
ML25217A109
Person / Time
Site: Susquehanna  
Issue date: 08/05/2025
From: Sherlyn Haney
Division of Operating Reactors
To: Berryman B
Susquehanna
References
IR 2025002
Download: ML25217A109 (1)


Text

August 5, 2025

SUBJECT:

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 -

INTEGRATED INSPECTION REPORT 05000387/2025002 AND 05000388/2025002

Dear Brad Berryman:

On June 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Susquehanna Steam Electric Station, Units 1 and 2. On July 28, 2025, the NRC inspectors discussed the results of this inspection with Edward Casulli, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Sherlyn Haney, Acting Chief Projects Branch 1 Division of Operating Reactor Safety

Docket Nos. 05000387 and 05000388 License Nos. NPF-14 and NPF-22

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000387 and 05000388

License Numbers:

NPF-14 and NPF-22

Report Numbers:

05000387/2025002 and 05000388/2025002

Enterprise Identifier: I-2025-002-0042

Licensee:

Susquehanna Nuclear, LLC

Facility:

Susquehanna Steam Electric Station, Units 1 and 2

Location:

769 Salem Blvd., Berwick, PA

Inspection Dates:

April 1, 2025 to June 30, 2025

Inspectors:

D. Antonangeli, Senior Resident Inspector

J. England, Senior Resident Inspector

E. Brady, Resident Inspector

D. Beacon, Senior Project Engineer

N. Mentzer, Senior Project Engineer

E. Miller, Senior Reactor Inspector

R. Rolph, Senior Health Physicist

J. Tifft, Senior Reactor Inspector

Approved By:

Sherlyn Haney, Acting Chief

Projects Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Susquehanna Steam Electric Station,

Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On June 6, 2025, the unit down powered to 75 percent for a control rod sequence exchange and returned to rated thermal power on June 7, 2025. The unit remained at or near rated thermal power for the remainder of the inspection period.

Unit 2 began the inspection period shut down for the refueling outage U222RIO. On June 2, 2025, the unit was started up and achieved rated thermal power on June 3, 2025. On June 16, 2025, the unit down powered to 63 percent for a control rod pattern adjustment and returned to rated thermal power on June 18, 2025. The unit remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in Inspection Manual Chapter 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2, major components in the drywell for standby liquid control, containment instrument gas, core spray, and residual heat removal on April 16, 2025
(2) Unit Common, standby gas treatment on May 13, 2025
(3) Unit 2, reactor building chiller following maintenance on May 22, 2025

Complete Walkdown (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the 'A' emergency diesel generator support systems on June 12, 2025.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection (IP Section 03.01) (7 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 2, turbine building, 656' and 729' elevations, fire areas 0-31H, 2-31B, 2-31L, and 2-35B, on April 2, 2025
(2) Unit Common, refueling floor, 818' elevation, fire area 0-8A, on April 7, 2025
(3) Unit 2, drywell, 704' to 779' elevations, fire area 2-4F, on April 14, 2025
(4) Unit 2, reactor building, 719' and 683' elevations, fires areas 2-3A, 2-3B-N, 2-3B-S, 2-4A-N, and 2-4A-S, on April 17, 2025
(5) Unit Common, control structure, 676', 754', and 771' elevations, fire areas 0-27A, 0-27B, 0-27C, 0-27E, 0-28A-I, 0-28A-II, 0-28B-I, 0-28B-II, 0-28C, 0-28D, 0-28E, 0-28-F, 0-28G, 0-28H, 0-28-I, 0-28J, 0-28K, 0-28L, 0-28M, 0-28N, and 0-28T, on May 29, 2025
(6) Unit Common, control structure, 698' elevation, fire areas 0-24A, 0-24B, 0-24C, 0-24D, 0-24E, and 0-24G, on June 10, 2025
(7) Unit 2, reactor building, 719' elevation, fire areas 2-4C and 2-4D, on June 23, 2025

Fire Brigade Drill Performance (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the on-site fire brigade performance during their response to a fire in the 'B' condenser on April 21, 2025.

71111.08G - Inservice Inspection Activities Boiling-Water Reactor (BWR)

BWR Inservice Inspection Activities - Nondestructive Examination (NDE) and Welding Activities

(IP Section 03.01)

The inspectors evaluated BWR NDE testing by reviewing the following examinations from March 31 to April 3, 2025:

(1)

  • Liquid penetrant surface examination of reactor recirculation piping welded attachments RWS200-HW-10AA through -10AD (NDE Report PT-25-001 through PT-25-004)
  • American Society of Mechanical Engineers (ASME),Section XI, Article IWE, general visual examination of drywell liner on 704', 719' and 738' elevations (CISI-VT-25-007)
  • ASME,Section XI, Article IWL, general visual examination of containment concrete on 670', 683', 704' and 719' elevations (CISI-VT-25-093, -094, -067, and -071)
  • Ultrasonic testing volumetric examinations of a sample of core shroud welds in quadrant 'A' and 'D' (work order 26787633-0)

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during Unit 2 start up on June 2, 2025.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated just-in-time training for an ASME Class 1 boundary leakage test on April 14, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:

(1) Unit 2, residual heat removal pump 2B breaker replacement on May 28, 2025
(2) Unit Common, 'A' emergency diesel generator lube oil pressure switches replacements on June 30, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 2, elevated risk during common residual heat removal work window during the week of April 14, 2025
(2) Unit Common, during 'B' control structure chiller work the week of May 12, 2025
(3) Unit Common, elevated risk during emergency service water division 1 maintenance on June 26, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 2, emergency safety system transfer bus supply breaker, 2A20301, did not close during restoration after annual loss-of-coolant accident/loss of off-site power test on March 28, 2025
(2) Unit 2, 'B' and 'D' main steam isolation valves failed local leak rate testing on April 4, 2025
(3) Unit 2, control rod blade 46-07 identified as coupled during blade exchange activities on April 9, 2025
(4) Unit 2, seismic monitor functional test failure on April 9, 2025
(5) Unit 2, division 2 'A' and 'B' 250-volt battery charger not sharing charging loads on June 18, 2025

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit 2, engineering change 2803696 for residual heat removal shutdown cooling isolation valve, HV251F009, permanent actuator motor replacement following failure on April 13, 2025

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated Unit 2 refueling outage 22RIO activities from April 1 to June 3, 2025.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (5 Samples)

(1) Unit 2, SM-283-004, Main Steam Isolation Valve Fail Safe Testing, following main steam isolation valve spring replacement on April 8, 2025
(2) Unit 2, SO-200-023, ASME Class I Boundary Leak Test, following reactor vessel disassembly and reassembly on April 20, 2025
(3) Unit 1, SO-170-011, Secondary Containment Drawdown and In-Leakage Surveillance Test Zones I and III, on April 22, 2025
(4) Unit Common, SI-024-301, 5-Year Calibration of 'A' Diesel Generator Lube Oil Low Pressure Switches, PSL-03481A1, A2, A3, and A4 following replacement of PSL-03481A1 and A2 on April 29, 2025
(5) Unit 2, SO-252-005, 48-Month High-Pressure Coolant Injection Flow Verification, high-pressure coolant injection system post-maintenance testing during startup on June 3, 2025

Surveillance Testing (IP Section 03.01) (4 Samples)

(1) Unit 2, SM-288-104, 48-Month Division I-2D650-250 Volts Direct Current Battery Discharge Modified Performance Test and Battery Charger Capability Test, on April 3, 2025
(2) Unit 2, SO-259-200, 24-Month Logic System Functional Test of the Primary and Secondary Containment Isolation System, on April 4, 2025
(3) Unit 2, SO-283-001, 24-Month Division 1 Automatic Depressurization System Logic System Functional Test, on April 9, 2025
(4) Unit Common, SO-054-001, B Logic System Functional Test of the Emergency Service Water System Pump 'B' Start and Reset Logic, on May 20, 2025

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) Unit 2, SO-253-00A, 24-Month Standby Liquid Control Operability (Loop A), on April 5, 2025

Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)

(1) Unit Common, DC-B5B-100, Attachment B, Operations of the B.5.b Portable Generators, on May 29,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1) The inspectors observed workers exiting the radiologically controlled area at Unit 2 during the refueling outage in Unit 2.
(2) The inspectors observed workers exiting the radiologically controlled area at Unit 1 during the refueling outage in Unit 2.

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:

(1) Personnel de-staging high contamination robotic equipment on the refueling floor
(2) Electricians working under the vessel during the Unit 2 refueling outage
(3) Carpenters removing scaffold in the drywell during the Unit 2 refueling outage
(4) Operators loading fuel in the reactor vessel during the Unit 2 refueling outage High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)

The inspectors evaluated licensee controls of the following high radiation areas and very high radiation areas:

(1) Heat exchanger cell in the Unit 2 reactor building on the 749' elevation
(2) Fuel pool pump room in the Unit 2 reactor building on the 749' elevation
(3) Clean-up holding pump room in the Unit 2 reactor building on the 779' elevation

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

OTHER ACTIVITIES - BASELINE

71152A - Annual Follow-up of Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Review of corrective actions for condition report (CR)-2024-13422, Startup from Unit 1 Cycle 24 Maintenance Outage Not in Compliance with Control Rod Drop Analysis
(2) Review of corrective actions associated with 4 kilovolt breaker failure (CR-2024-13462)

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified that no proprietary information was retained or documented in this report.

  • On April 3, 2025, the inspectors presented the inservice inspection results to Doug LaMarca, Director - Strategic Planning, and other members of the licensee staff.
  • On April 10, 2025, the inspectors presented the radiological hazard assessment and exposure control inspection results to Doug Lamarca, Director - Strategic Planning, and other members of the licensee staff.
  • On July 28, 2025, the inspectors presented the integrated inspection results to Edward Casulli, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Corrective Action

Documents

Resulting from

Inspection

CR-2025-06799

CR-2025-06802

CR-2025-06803

CR-2025-08540

CR-2025-08549

Miscellaneous

CL-024-0012

Diesel Generator A

Revision 13

CL-259-0719

Unit 2 719' Containment Close-Out

Revision 12

CL-259-0738

Unit 2 738' Containment Close-Out

Revision 2

CL-259-0752

Unit 2 752' Containment Close-Out

Revision 3

CL-259-0767

Unit 2 767' Containment Close-Out

Revision 2

71111.05

Calculations

EC-013-1913

PGCC Halon Systems for the Units 1 and 2 Upper & Lower

Relay Rooms

Revision 0

NEDO-10466-A

Licensing Topical Report Power Generation Control

Complex Design Criteria and Safety Evaluation

February

1979

Corrective Action

Documents

CR-2025-07150

Corrective Action

Documents

Resulting from

Inspection

AR-2025-06036

AR-2025-06329

AR-2025-06894

AR-2025-06897

AR-2025-06902

AR-2025-06904

AR-2025-08195

AR-2025-09289

CR-2025-06030

CR-2025-06039

CR-2025-09248

CR-2025-09251

Fire Plans

FP-013-CS

Control Structure Digital Prefire Plan

Revision 2

FP-1-CS-754

Susquehanna S.

E.S. Prefire Plan Units 1 & 2, El. 754

Revision 0

FP-1-CS-771

Susquehanna S.

E.S. Prefire Plan Units 1 & 2, El. 771

Revision 0

FP-2-RB-683

Susquehanna S.

E.S. Prefire Plan Unit 2, El. 683

Revision 0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.05

Fire Plans

FP-2-RB-719

Susquehanna S.

E.S. Prefire Plan Unit 2, El. 719

Revision 0

FP-2-TB-656

Susquehanna S.

E.S. Prefire Plan Unit 2, El. 656

Revision 0

FP-2-TB-729

Susquehanna S.

E.S. Prefire Plan Unit 2, El. 729

Revision 0

FP-213-100

Drywell (II 400, II 516, II 607) Fire Zone 2 4F, Elev. 704'

through 807'

Revision 4

FP-213-RB2

Unit 2 Reactor Building Prefire Plan

Revision 2

Miscellaneous

Halon Concentration Test Report 1U706

05/27/1982

2A5931

PGCC Fire Protection System

Revision 0

Procedures

SM-113-015

3-Year Inspection, Level/Weight Measurement, and

Pressure/Flow Verification of Halon Cylinders

Revision 8

71111.08G Corrective Action

Documents

Resulting from

Inspection

CR-2025-05353

CR-2025-05456

CR-2025-05574

71111.11Q Procedures

SO-100-023

ASME Class I Boundary Leakage Test (Infrequently

Performed Test or Evolution)

Revision 15

71111.12

Corrective Action

Documents

CR-2025-07497

CR-2025-09186

71111.13

Miscellaneous30-001

CREOASS 'A' Train - 9/9/24

Revision 0

54-009-ESW DIV 1 Emergency Service Water Division 1

Revision 0

71111.15

Corrective Action

Documents

CR-2024-11300

CR-2025-04411

CR-2025-04793

CR-2025-04802

CR-2025-05033

CR-2025-05430

CR-2025-10230

Procedures

NDAP-QA-0004

Procedure Change Process

Revision 40

71111.15

Work Orders

RACT 2655184

RTPM 2655446

RTSV 2418113

RTSV 2425512

RTSV 2633020

RTSV 2701544

RTSV 2749527

71111.18

Corrective Action

Documents

CR-2025-06503

Engineering

Changes

EC 2803696

Replace HV251F009 Actuator Motor

Revision 0

Procedures

IP-ENG-001

Nuclear Standard Process

Revision 3

71111.20

Corrective Action

Documents

Resulting from

Inspection

CR-2025-07296

CR-2025-07298

CR-2025-07301

CR-2025-07378

Procedures

OP-2RF-001

RX Vessel/Cavity Flood-Up and Let Down During Refueling

Outages

Revision 41

Work Orders

RACT 2655156

71111.24

Corrective Action

Documents

CR-2025-03171

CR-2025-03911

Corrective Action

Documents

Resulting from

Inspection

CR-2025-04019

CR-2025-06004

Miscellaneous

2-001-U2 HPCI

SOW Week of

3/17/25

Protected for Unit 2 HPCI SOW

Revision 0

Procedures

DC-B5B-100

B

Operations of the B.5.b Portable Generators

Revision 14

SI-024-301

5-Year Calibration of 'A' Diesel Generator Lube Oil Low

Pressure Switches PSL-03481A1, A2, A3, A4

Revision 11

SM-288-104

48-Month Division 1 2D650 - 250VDC Battery Discharge

Modified Performance Test and Battery Charger Capability

Test

Revision 24

71111.24

Procedures

SO-054-001B

Logic System Functional Test of the ESW System Pump B

Start and Reset Logic

Revision 5

SO-170-011

Unit 1 Secondary Containment Drawdown and In-Leakage

Surveillance Test Zones I and III

Revision 9

SO-200-023

ASME Class I Boundary Leak Test

Revision 11

SO-252-005

48-Month HPCI Flow Verification

Revision 29

SO-253-003A

24-Month SBLC Operability (Loop A)

Revision 10

SO-259-200

24-Month Logic System Functional Test of the Primary and

Secondary Containment Isolation System

Revision 6

SO-283-001

24-Month Division 1 ADS Logic System Functional Test

Revision 2

Work Orders

PCWO 2345661-0

PCWO 2807421-0

RTPM 2655412

RTPM 2655414

RTPM 2655415

RTSV 2633037

RTSV 2635026

RTSV 2635027

RTSV 2639600

RTSV 2639601

RTSV 2639612

RTSV 2639613

RTSV 2639631

RTSV 2807650

WO 2685630-0

71124.01

Corrective Action

Documents

Resulting from

Inspection

CR-2025-05991

Potential for Individuals to Enter a LHRA from Platforms

Next to the Reactor Feed Pump Turbines

04/07/2025

CR-2025-06077

Identified Metal Filings on the Valve Body of 251F060A

Residual Heat Removal (RHR) Injection to Recirculating

Loop A

04/08/2025

CR-2025-06160

Follow-up Actions for Contamination Incidents That Are

<100 ccpm

04/09/2025

71152A

Corrective Action

Documents

CR-2024-13462

Procedures

LS-120

Issue Identification and Screening Process

Revision 16

LS-125

Corrective Action Program

Revision 17

MT-GE-048

Cutler-Hammer Type DHP-VR 4.16 kV Circuit Breaker and

Switchgear Inspection and Maintenance

Revision 35