IR 05000382-07-401, on 07/09/2007 - 07/12/2007, Waterford Steam Electric Station, Unit 3, Security Baseline Inspection
ML072130556
Person / Time
Site: Waterford Entergy icon.png
Issue date: 08/01/2007
From: Shannon M
Plant Support Branch Region IV
To: Walsh K
Entergy Operations
References
IR-07-401
Download: ML072130556 (4)


Text

ust 1, 2007

SUBJECT:

WATERFORD STEAM ELECTRIC STATION, UNIT 3 - NRC SECURITY INSPECTION REPORT 05000382/2007401

Dear Mr. Walsh:

On July 12, 2007, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Waterford Steam Electric Station facility. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results which were discussed on July 12, 2007, with Mr. J. Kowalewski, General Manager and other members of your staff.

This inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings of significance were identified.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Document Room or from the Publicly Available Records (PARS) component of NRC's document system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection. SAFETY-RELATED INFORMATION Entergy Operations, Inc. -2-In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security Related Information - Withhold under 10 CFR 2.390 and follow the instructions for withholding in 10 CFR 2.390(b)(1).

Sincerely,

/RA/

Michael P. Shannon, Chief Plant Support Branch Division of Reactor Safety Docket No.: 50-382 License No.: NPF-38 Enclosure: Inspection Report 05000382/2007401 w/attachment: Supplemental Information cc w/o enclosure:

Mr. Jeff Forbes Senior Vice President and Chief Operating Officer Entergy Operations, Inc.

P.O. Box 31995 Jackson, MS 39286-1995 Vice President, Operations Support Entergy Operations, Inc.

P.O. Box 31995 Jackson, MS 39286-1995 Ms. Kimberly S. Cook, Director Nuclear Safety Assurance Entergy Operations, Inc.

17265 River Road Killona, LA 70057-0751 SAFETY-RELATED INFORMATION Entergy Operations, Inc. -3-Mr. Joe Kowalewski General Manager, Plant Operations Waterford 3 SES Entergy Operations, Inc.

17265 River Road Killona, LA 70057-0751 Manager, Licensing Entergy Operations, Inc.

17265 River Road Killona, LA 70057-3093 Mr. John McCann Director, Nuclear Safety & Licensing Entergy, Operations, Inc.