IR 05000369/2025003
| ML25328A131 | |
| Person / Time | |
|---|---|
| Site: | Mcguire, McGuire |
| Issue date: | 11/26/2025 |
| From: | Robert Williams NRC/RGN-II/DORS |
| To: | Pigott E Duke Energy Carolinas |
| References | |
| IR 2025003 | |
| Download: ML25328A131 (0) | |
Text
SUBJECT:
MCGUIRE NUCLEAR STATION - INTEGRATED INSPECTION REPORT 05000369/2025003 AND 05000370/2025003
Dear Edward Pigott:
On September 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at McGuire Nuclear Station. On November 19, 2025, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
Due to the temporary cessation of government operations, which commenced on October 1, 2025, the NRC began operating under its Office of Management and Budget-approved plan for operations during a lapse in appropriations. Consistent with that plan, the NRC operated at reduced staffing levels throughout the duration of the shutdown. However, the NRC continued to perform critical health and safety functions and make progress on other high-priority activities associated with the ADVANCE Act and Executive Order 14300. On November 13, 2025, following the passage of a continuing resolution, the NRC resumed normal operations. However, due to the 43-day lapse in normal operations, the Office of Nuclear Reactor Regulation granted the Regional Offices an extension on the issuance of the calendar year 2025, 3rd quarter integrated inspection reports normally issued by November 15, 2025, to December 31, 2025. The NRC will resume the routine cycle of issuing inspection reports on a quarterly basis beginning with the calendar year 2025, 4th quarter integrated inspection reports, which will be issued 45 days after the 4th quarter ends on December 31, 2025.
No findings or violations of more than minor significance were identified during this inspection.
November 26, 2025 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Robert E. Williams, Jr., Chief Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000369 and 05000370 License Nos. NPF-9 and NPF-17
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000369 and 05000370
License Numbers:
Report Numbers:
05000369/2025003 and 05000370/2025003
Enterprise Identifier:
I-2025-003-0023
Licensee:
Duke Energy Carolinas, LLC
Facility:
McGuire Nuclear Station
Location:
Huntersville, North Carolina
Inspection Dates:
July 1, 2025, to September 30, 2025
Inspectors:
C. Safouri, Senior Resident Inspector
F. Young, Resident Inspector
S. Battenfield, Operations Engineer
K. Lei, Emergency Preparedness Inspector
M. Rich, Emergency Preparedness Inspector
J. Tornow, Physical Security Inspector
J. Walker, Senior Emergency Preparedness Inspector
Approved By:
Robert E. Williams, Jr., Chief
Projects Branch 1
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at McGuire Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Unit 1 operated at or near 100 percent rated thermal power (RTP) for the entire inspection period.
Unit 2 operated at or near 100 percent RTP for the entire inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (2 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Unit 1 and Unit 2 auxiliary feedwater (CA) pumps assured suction sources from nuclear service water system, on July 23, 2025
- (2) Unit 1 and Unit 2 interior doghouses, including portions of the main steam system, main steam vent to atmosphere system, and main steam supply to auxiliary equipment for steam generators 1B, 1C, 2B, and 2C, on September 6, 2025
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (2 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Unit 2 train A and train B 4160V switchgear and electrical penetration rooms, on July 25, 2025
- (2) Unit 1 and Unit 2 shared equipment areas of auxiliary building elevation 716 and mechanical penetration rooms, on August 22, 2025
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the control room during Unit 1 rod cluster control assembly bank repositioning, on August 11, 2025, and Unit 1 train B main feedwater pump high pressure governor steam leak in the turbine building, on August 12, 2025.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (4 Samples)
- (1) The inspectors observed and evaluated annual requalification operating testing, on July 22, 2025
- (2) The inspectors observed and evaluated annual requalification operating testing, on July 24, 2025
- (3) The inspectors observed and evaluated annual requalification operating testing, on July 29, 2025
- (4) The inspectors observed and evaluated annual requalification operating testing, on August 5 and 8, 2025
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (2 Samples)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:
- (1) Nuclear condition report (NCR) 02526647, Unit 1 train A diesel generator (D/G)battery charger failure, on July 15, 2025
- (2) NCRs 02540897 and 02541049, Unit 2 train A CA suction swap over pressure switches, 2CAPS5002 and 2CAPS5350, found out of tolerance during calibration, on September 10, 2025
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (1 Sample)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) NCR 02566232, Unit 1 turbine driven CA pump implementation of risk-informed completion time in response to an emergent gearbox seal issue, on August 28, 2025
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
- (1) NCR 02560176, Unit 1 train B D/G control air to shutdown cylinders solenoid failure, 1VGSV5171, on July 2, 2025
- (2) NCR 02535481, station lubrication manual discrepancies for Unit 1 and Unit 2 diesel ventilation fan motors, on July 2, 2025
- (3) NCR 02540358, Unit 1 turbine driven CA pump bearing vibrations in alert range, on July 17, 2025
- (4) NCR 02566122, diesel building ventilation calculation indicating classification as a harsh environment per 10 CFR 50.49, on August 18, 2025
- (5) Room temperature gradient and annunciator response during Unit 1 train A D/G 24-hour surveillance run, on August 18, 2025
71111.24 - Testing and Maintenance of Equipment Important to Risk
The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:
Post-Maintenance Testing (PMT) (IP Section 03.01) (4 Samples)
- (1) PT/0/A/4200/002, "Standby Shutdown Facility Operability Test," following standby shutdown facility planned maintenance window, on July 8, 2025
- (2) PT/0/A/4350/028B, "125 Volt Vital Battery Quarterly Inspection," for Unit 1 and Unit 2 shared vital battery, EVCD, following equalizing charge, on July 30, 2025
- (3) PT/1/A/4350/002A, "Diesel Generator 1A Operability Test," following Unit 1 train A D/G 24-hour run and subsequent maintenance, on August 21, 2025
- (4) PT/1/A/4252/001, "Unit 1 Turbine Driven Auxiliary Feedwater Pump Performance Test," and PT/1/A/4252/007, "Auxiliary Feedwater System Turbine Driven Train Performance Test," following replacement of turbine governor gearbox shaft seal, on August 29, 2025
Surveillance Testing (IP Section 03.01) (3 Samples)
- (1) Unit 1 upper personnel airlock overall leak rate test, on July 31, 2025
- (2) Unit 2 channel IV power range ex-core nuclear instrument channel, 2N-44, channel operational test, on July 31, 2025
- (3) Unit 2 loop A, B, C, and D reactor coolant pump undervoltage and underfrequency 18-month calibration and functional test, on August 4, 2025
71114.01 - Exercise Evaluation
Inspection Review (IP Section 02.01-02.11) (1 Sample)
- (1) The inspectors evaluated the biennial emergency plan exercise during the week of August 26, 2025. The simulated scenario began with a small leak on the reactor cold leg exceeding the threshold value for declaration of an Unusual Event. A short time later, an auxiliary feed pump failed to start due to a breaker issue, while concurrently the reactor failed to trip thus meeting the conditions for declaration of an Alert. As the scenario progressed, the turbine driven CA pump tripped due to a governor link issue.
The loss of heat sink resulted in a red critical safety functional area, thus meeting the conditions for declaration of a Site Area Emergency. The Offsite Response Organizations were able to demonstrate their ability to implement emergency actions.
71114.04 - Emergency Action Level and Emergency Plan Changes
Inspection Review (IP Section 02.01-02.03) (1 Sample)
- (1) The inspectors evaluated submitted Emergency Action Level, Emergency Plan, and Emergency Plan Implementing Procedure changes during the week of August 25, 2025. This evaluation does not constitute NRC approval.
71114.06 - Drill Evaluation
Additional Drill and/or Training Evolution (1 Sample)
- (1) The inspectors evaluated an emergency preparedness drill that consisted of a faulted steam generator tube rupture, on September 24, 2025.
71114.08 - Exercise Evaluation - Scenario Review
Inspection Review (IP Section 02.01 - 02.04) (1 Sample)
- (1) The inspectors reviewed and evaluated in-office, the proposed scenario for the biennial emergency plan exercise at least 30 days prior to the day of the exercise.
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
MS08: Heat Removal Systems (IP Section 02.07)===
- (1) Unit 1 (July 1, 2024, through June 30, 2025)
- (2) Unit 2 (July 1, 2024, through June 30, 2025)
MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)
- (1) Unit 1 (July 1, 2024, through June 30, 2025)
- (2) Unit 2 (July 1, 2024, through June 30, 2025)
MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)
- (1) Unit 1 (July 1, 2024, through June 30, 2025)
- (2) Unit 2 (July 1, 2024, through June 30, 2025)
BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)
- (1) Unit 1 (July 1, 2024, through June 30, 2025)
- (2) Unit 2 (July 1, 2024, through June 30, 2025)
BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)
- (1) Unit 1 (July 1, 2024, through June 30, 2025)
- (2) Unit 2 (July 1, 2024, through June 30, 2025)
EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)
- (1) July 1, 2024, through June 30, 2025 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
- (1) July 1, 2024, through June 30, 2025 EP04: Emergency Response Facility and Equipment Readiness (ERFER) (IP Section 02.14) (1 Sample)
- (1) January 1, 2025, through June 30, 2025
71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
- (1) NCR 02550766, Unit 1 safety injection system containment penetration check valve, 1NI-436, failed as found penetration test, on September 8, 2025
71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)
- (1) The inspectors reviewed the licensees corrective action program to identify potential trends in out-of-tolerance evaluations associated with measurement and test equipment that might be indicative of a more significant safety issue.
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On August 28, 2025, the inspectors presented the emergency preparedness exercise inspection results to T. Scott and other members of the licensee staff.
- On November 19, 2025, the inspectors presented the integrated inspection results to Edward Pigott and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
MCFD-1574-01.00
Flow Diagram of Nuclear Service Water System - RN
MCFD-1574-01.01
Flow Diagram of Nuclear Service Water System - RN
MCFD-1574-02.00
Flow Diagram of Nuclear Service Water System - RN
MCFD-1574-03.00
Flow Diagram of Nuclear Service Water System - RN
MCFD-1592-01.00
Flow Diagram of Auxiliary Feedwater System (CA)
MCFD-1592-01.01
Flow Diagram of Auxiliary Feedwater System (CA)
MCFD-1593-01.01
Flow Diagram of Main Steam System (SM), Main Steam
Vent to Atmosphere (SV)
MCFD-1593-01.02
Flow Diagram of Main Steam Supply to Auxiliary Equipment
System (SA), Turbine Exhaust System (TE)
Drawings
MCFD-1593-01.03
Flow Diagram of Main Steam System (SM), Main Steam
Vent to Atmosphere (SV)
CSD-MNS-PFP-
AB-0716-001
Auxiliary Building Elevation 716 Pre-Fire Plan
CSD-MNS-PFP-
AB-0733-001
Auxiliary Building Elevation 733 Pre-Fire Plan
Fire Plans
CSD-MNS-PFP-
AB-0750-001
Auxiliary Building Elevation 750 Pre-Fire Plan
Drawings
MCFD-1593-02.00
Flow Diag of Steam Supply to FDWP Turb Sys (SP) Turb
Exhaust Sys (TE) Moisture Sep REHT Bleed Stm System
(HM)
ASE-16
Annual Requalification Operating Exam - Scenario 16
08/05/2025
ASE-17
Annual Requalification Operating Exam - Scenario 17
08/05/2025
ASE-18
Annual Requalification Operating Exam - Scenario 18
07/24/2025
ASE-19
Annual Requalification Operating Exam - Scenario 19
07/22/2025
ASE-32
Annual Requalification Operating Exam - Scenario 32
07/29/2025
ASE-33
Annual Requalification Operating Exam - Scenario 33
07/22/2025
ASE-35
Annual Requalification Operating Exam - Scenario 35
07/29/2025
Miscellaneous
ASE-44
Annual Requalification Operating Exam - Scenario 44
07/29/2025
AP/1/A/5500/01
Steam Leak
Procedures
PT/0/A/4150/041
RCCA Bank Repositioning
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
MCC-1210.04-00-
0043
Instrument Loop Uncertainty for CA-RN Swapover Suction
Pressure Switch Loops CAPS5002, 5012, 5042, 5350,
5360, 5370, 5380, 5381, 5390, 5391
Calculations
MCC-1223.42-00-
0054
Documentation of the Adequacy of the Assured Suction
Sources to the Unit 2 CA Pumps
MC-24-0055
Plant Health Committee Action Commitment - 1A EDG
Battery Charger Failure
2/19/2024
Miscellaneous
MCM 1356.08-
0015.001
Instruction Manual for 125 VDC 50 Amp Diesel Generator
Battery Chargers
AD-OP-ALL-0212
Risk Informed Completion Time Program Calculations,
3, RICT Projection Overview for Unit 1 turbine
driven auxiliary feedwater pump emergent issue
Miscellaneous
RICT-2025-03
Risk Informed Completion Time Datasheet for Unit 1 turbine
driven auxiliary feedwater
08/26/2025
Calculations
MCC-1211.00-00-
0004
Diesel Generator Ventilation Calculation
Nuclear Condition
Report
2551623
Corrective Action
Documents
Problem
Investigation
Program (PIP)
M-91-00088
Corrective Action
Documents
Resulting from
Inspection
Nuclear Condition
Report
2566122
MCEE-0120-09.07
Elementary Diagram Diesel Gen 1B Start Circuit
MCFD-1591-01.01
Flow Diagram of Feedwater System (CF)
MCFD-1609-04.00
Flow Diagram of Diesel Generator Starting Air System (VG)
MCID-1499-VG.03
Instrument Detail D.G. Pneumatic/Hydraulic Control
Schematic
Drawings
MCM 1205.08-
0083.001
Valve, Solenoid, Position Indication, Nuclear Service Model:
V573-5231-9
1.0
Miscellaneous
MCS-1206.00-00-
0001
McGuire Pipe Rupture Analysis Criteria Specification
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
MCS-1206.00-02-
0002
Specification for the Design of Power Piping Systems
Materials and Components
217
MCS-1591.CF-00-
0001
Design Basis Specification for the CF System
MCS-1593.SM-00-
0001
Design Basis Specification for the SM, SV and SB Systems
MCS-1609.VG-00-
0001
Design Basis Specification for the VG System
MCS-1609.VN-00-
0001
Design Basis Specification for the VN System
MCTC-1609-
VG.V009-01
Valve Design Criteria/Operability Requirements and
Compensatory Measures: Solenoid Valves 1/2VG-5160,
1/2VG-5161, 1/2VG-5170, 1/2VG-5171
Procedures
OP/1/A/6101/010A
Annunciator Response for Panel 1AD-19 (Diesel Generator
Panel 1A)
20735067, 20700520
Work Orders
Work Request(s)
281681
Corrective Action
Documents
Nuclear Condition
Report
2562044, 02566232, 02566519, 02553074
Corrective Action
Documents
Resulting from
Inspection
Nuclear Condition
Report
2567693
25926
M, CGI, PQL, 9230058046, Mechanical Seal, SKF, HGB/TS
Engineering
Changes
25927
Turbine Driven CA Pump Governor Gearbox shaft seal
equivalency
Miscellaneous
LCOTR# A-1-25-
01160
LCO Tracking: Unit 1 Upper Containment Airlock Overall
Leak Rate Test
07/31/2025
IP/0/A/3061/012
Charging Site Lead-Acid Batteries
PT/0/A/4200/041
Standby Shutdown Facility Diesel Load Rejection Test
PT/1/A/4200/001
E
Upper PAL Overall LRT
Procedures
PT/2/A/4600/014
G
NIS Power Range N-44 Channel Operational Test
033
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
PT/2/A/4971/021
Reactor Coolant Pump (RCP)
Undervoltage/Underfrequency Functional Test
PT/2/A/4971/022
Reactor Coolant Pump (RCP) Undervoltage Relay (ABB
27N) Calibration)
PT/2/A/4971/023
Reactor Coolant Pump (RCP) Underfrequency Relay (ABB
81) Calibration
20633048, 20653991, 20660639, 20661904, 20700339,
20700340, 20709106, 20711351, 20724996, 20724997,
20724998, 20725000, 20717637, 20700520, 20746078,
20746193, 20725192, 20724671
Work Orders
Work Request(s)
291020, 20291094, 20291095, 20291107, 20292010
Procedures
CSD-EP-MNS-
0101-01
MNS EAL TECHNICAL BASIS DOCUMENT
Duke Energy Common Emergency Plan
Procedures
EP-MNS-EPLAN-
ANNEX
Duke Energy McGuire Emergency Plan Annex
Corrective Action
Documents
Nuclear Condition
Report
2569804, 02569805
Miscellaneous
MNS Drill 25-04
09/16/2025
MSPI Derivation Report - McGuire Unit 1 - MSPI Cooling
Water System - Unavailability Index (UAI)
08/11/2025
MSPI Derivation Report - McGuire Unit 1 - MSPI Cooling
Water System - Unreliability Index (URI)
08/11/2025
MSPI Derivation Report - McGuire Unit 2 - MSPI Cooling
Water System - Performance Limit Exceeded (PLE)
08/11/2025
MSPI Derivation Report - McGuire Unit 2 - MSPI Cooling
Water System - Unavailability Index (UAI)
08/11/2025
MSPI Derivation Report - McGuire Unit 2 - MSPI Cooling
Water System - Unreliability Index (URI)
08/11/2025
MSPI Derivation Report - McGuire Unit 1 - MSPI Heat
Removal System - Performance Limit Exceeded (PLE)
08/11/2025
MSPI Derivation Report - McGuire Unit 1 - MSPI Heat
Removal System - Unavailability Index (UAI)
08/11/2025
71151
Miscellaneous
MSPI Derivation Report - McGuire Unit 1 - MSPI Heat
08/11/2025
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Removal System - Unreliability Index (URI)
MSPI Derivation Report - McGuire Unit 2 - MSPI Heat
Removal System - Performance Limit Exceeded (PLE)
08/11/2025
MSPI Derivation Report - McGuire Unit 2 - MSPI Heat
Removal System - Unavailability Index (UAI)
08/11/2025
MSPI Derivation Report - McGuire Unit 2 - MSPI Heat
Removal System - Unreliability Index (URI)
08/11/2025
MSPI Derivation Report - McGuire Unit 1 - MSPI Residual
Heat Removal System - Performance Limit Exceeded (PLE)
08/11/2025
MSPI Derivation Report - McGuire Unit 1 - MSPI Residual
Heat Removal System - Unavailability Index (UAI)
08/11/2025
MSPI Derivation Report - McGuire Unit 1 - MSPI Residual
Heat Removal System - Unreliability Index (URI)
08/11/2025
MSPI Derivation Report - McGuire Unit 2 - MSPI Residual
Heat Removal System - Performance Limit Exceeded (PLE)
08/11/2025
MSPI Derivation Report - McGuire Unit 2 - MSPI Residual
Heat Removal System - Unavailability Index (UAI)
08/11/2025
MSPI Derivation Report - McGuire Unit 2 - MSPI Residual
Heat Removal System - Unreliability Index (URI)
08/11/2025
MSPI Derivation Report - McGuire Unit 1 - MSPI Cooling
Water System - Performance Limit Exceeded (PLE)
08/11/2025
Corrective Action
Documents
Nuclear Condition
Report
2554562, 02542835, 02488726, 02488727
Work Orders
20721023, 20444744, 20437522
Corrective Action
Documents
Resulting from
Inspection
Nuclear Condition
Report
2570856
AD-EG-ALL-1107
Quality Classifications
Procedures
AD-NS-NGO-0005
Conduct of Standards Lab
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
AD-SS-ALL-0001
Control of Portable Measuring and Test Equipment and
Plant Tools and Portable Media/Mobile Devices (PMMD)
Nuclear Condition
Report
2541641, 02543290, 02543405, 02545032, 02546856,
2555319, 02560887
PD-NS-ALL-0001
Measuring and Test Equipment Program
3