IR 05000362/1982004

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-362/82-04 on 820308-12.No Noncompliance Noted.Major Areas Inspected:Const Activities Re Electrical Cables,Electrical Components & safety-related Structures
ML20050L155
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 03/26/1982
From: Eckhardt J, Hernandez G, Wagner W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML20050L133 List:
References
50-362-82-04, 50-362-82-4, NUDOCS 8204140248
Download: ML20050L155 (5)


Text

.

o U. S. NUCLEAR REGULATORY C0fEISSION a

REGION Y Report No.

50-362/82-04 (C0N)

Docket f!o.

50-362 (CON)

License No.

Cppp-98 Safeguards Group Licensee:

Southern California Edison Comoanv 2244 Walnut Grove Avenue Rosemead. California 91770 Facility Name:

San Onofre Unit 3 Inspection at:

Construction site. San Diegn County. califnrnia Inspection conducted: March 8-12.1982 Inspectors: k

// c&daflu S'

6 8 2.

W.

agner,

.aEtor Inspector

/ Date61gned a. duus a /u,/ez-pHernandez, ReacUr Inspector Date Signed

'

-

[

S/ff,/f3g.

' '

Appr6ved by:

J 'H. Eckhardt, Acting Chief

/Dat( Signed eactor Projects Section 1 Sumary:

Inspection on March 8-12, 1982 (Report No. 50-362/82-04)

Areas Inspected: Routine, unannounced inspection by regional based inspectors of construction activities involving electrical cables, electrical components, and safety related components and structures.

The inspection involved 62 onsite inspection hours by two NRC inspectors.

Results:

No deviations or items of noncompliance were identified.

8204140240 82033o DR ADOCK 05000362 RV Fom 219 (2)

PDR

.__.

..

'

DETAILS 1.

Individuals Contacted a.

Southern California Edison Company (SCE)

  • D. B. Schone, Project QA Supervisor
  • D. C. Stonecipher, Construction QA Supervisor
  • G. P. Vaslos, QA Engineer
  • N. M. Ferris, QA Engineer V. A. Gow, QA Engineer b.

Bechtel Power Corporation (Bechtel)

  • J. H. McCarty, Project QC Manager
  • L. W. Hurst, Project QA Manager
  • J. W. Sheppard, Project QA Supervisor
  • D. T. Lobree, Project Field Engineer J. L. McGath, Mechanical QC Engineer R. R. Garrett, lead Field Engineer R. E. Brown, Senior QC Engineer - Instrumentation / Equipment G. Lees, Construction Field Engineer J. Duke, Construction Field Engineer
  • Denotes those present at the NRC management meeting on March 12, 1982.

2.

Site _To_ur_

Upon arrival at the site, the inspectors toured the containment building to ascertain general compliance with regulatory requirements, codes, standards and site procedures.

The emphasis of tour was to determine if Class IE cables were being provided with adequate protection from potential hazards such as missiles or pipe failures. The Class IE and associated circuit cables inspected appeared to be satisfactorily protected. During the tour the inspectors also examined a number of permanent attachment welds made to heavy sectioned structural columns

!

for compliance with AWS D1.1 preheat requirements. Review of weld l

records indicated that the welds were made utilizing welding procedure specifications qualified for welding without preheat in compliance with the rules of AWS D1.1.

No items of noncompliance or deviations were identified.

3.

Electrical (Components and Systems)

The inspector observed various facets of work activities in progress and completed relative to the installation of electrical equipmen.

<

<

-2-

This activity was performed to verify conformance with applicable specifications and QC procedure requirements. This included reviewing receipt inspection documentation, equipment identification and location, and reviewing construction QC inspection reports.

The following electrical components were inspected:

a.

125 VOC Batteries The inspector observed the storage conditions of the 125 VDC batteries associated with Battery Rack Nos. 3B007 (Train A) and 38008 (Train B). The electrolyte levels and temperatures were as required for rated performance.

Each battery installation included instrumentation and alarms, such as, a voltmeter, high and low battery voltage alarms, and ground detectors, b.

125 VDC Bus to Breaker No. 3BY03 - This breaker feeds battery charger 38001.

c.

Load Center (Distribution Panel) No. 3BZ d.

HPSI Pump No. 3P018 I

e.

Containment Emergency. Sump Pump No. 3HV9302 f.

Containment Fan'No. A072 g.

Class 1E Inverter No. S31807EY002 (Channel B)

h.

Boric Acid Makeup Pump No. T071 to Panel No. P174

'

No items of noncompliance or deviations were identified.

4.

Electrical Cables and Terminations The inspector examined work in progress and completed work on the

-

.

cable schemes indicated below for compliance with licensee procedures,

'

PSAR commitments and IEEE-384 Specific areas inspected included cable size, cable termination points, routing, separation and protection.

]rl Type of Circuit Cable Scheme No.

From j

3AA0403 Containment Spray Panel 3A0403 Power - 4160V Switchgear Pump P012

-..

.

_ _..

__

- _ _., _ _

__

.-

.--

..

-

-

.

'

!

-3-Cable Scheme No.

From Tjl Type of Circuit 3BBZ37P8 Motor Control AFW Pump P504 Power - 480V Load Center Center BZ37 3ABE36P1 Motor Control Isolation Valve Power - 480V Load Center Center BE36 HV 4371 38W47060C MOV 4706 Relay Panel Control Cable to 3MS-4706 Electric Valve Operator

'3BY24100C Panel L071-3R Terminal Box Control Cable 3CY0315P1 NSSS Auxiliary Panel 3L71-3R Power - 250V Switchgear Relay Cabinet LO71 3AY0124P1 Circuit Breaker Panel 3L71-3F Power - 250V Switchgear Y001 The inspector observed that the pull card for cable scheme number 3AY0124P1 indicated the cable was to terminate in panel 3L71-SF instead

,

of panel 3L71-3F as actually installed.

However, the cable in question I

was properly installed and inspected by QA/QC as dictated by the appropriate wiring diagram, and the computer generated pull card was determined to be in error. The wiring diagram provides the acceptance criteria for inspection.

No items of noncompliance or deviations were identified.

5.

Safety Related Components - Review of Quality Records

a.

The quality records for four safety related components were reviewed to ascertain whether these records reflect work accomplishment consistent with NRC requirements and PSAR commitments. The following four components were selected:

Component Serial Number

(1) HPSI Pump S/N 1075155 (2) Containment Spray Pump S/N 1075145 (3) Reactor Coolant Pump S/N 701-N-0561 (4) MSIV S/N 484769

,

l

,

,

p

-

-

y-7,--

---,. - - -

--.,-.,-%

,

g,%_g-__

__..____-__-..y

-

ye, _. -, _--

---e.-

~

...i

-

-

-

,

.

..

-4-

.

The vendor and ' licensee records examined included the following:

Records required list

.

Material receiving list

.

Material received reports

-

.

.

Document deficiency notices

.

Mill test certifications 'and analysis

.

,

Weld material certification,'and analysis

.

~

NDE. reports

'-

-

.

Hydrostatic test reports

.

. _,

Nonconformance reports

..

"

.

Supplier Deviation Disposition' Requests

.

Post weld heat treat records.

.

No items of' noncompliance or deviations 'were' identified.

b.

The field welds and welding documentation for the below listed welds were examined for compliance to the applicable licensee procedures and the applicable codes and standards.

Component Spool Weld Number (1) HPSI No. 015 A

No. 005 G,J(C),K(C)

(2) MSIV Valve inlet / outlet BC, BD c.

The radiographs for the following welds were examined for compliance to the applicable procedures, codes and standards.

Component Weld Number (1) HPSI A

(2) MSIV BC and BD No items of noncompliance or deviations were identified in any of the above examinations.

6.

Exit Meeting The inspectors met with licensee representatives (denoted in paragraph 1)

on March 12, 1982. The scope of the inspection and findings as detailed in this report were discussed.