IR 05000341/1993003
| ML20044F828 | |
| Person / Time | |
|---|---|
| Site: | Fermi |
| Issue date: | 05/25/1993 |
| From: | Wright G NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Gipson D DETROIT EDISON CO. |
| References | |
| GL-89-10, NUDOCS 9306010095 | |
| Download: ML20044F828 (2) | |
Text
paja c(q UNIT E D STATES o
y, g
NUCLEAR REGUL.ATORY COMMisslON
[
) v. /
REGION til r
CL E N E LLYN. ILLINO15 60137
%'.... * *o MAY 2 51933 Docket No. 50-341 The Detroit Edison Ccmpany ATTN:
Mr. D. Senior Vice President Nuclear Generation 6400 North Dixie Highway Newport, MI 48166
Dear Mr. Gipson:
SUBJECT:
NON-CITED VIOLATION (NRC INSPECTION REPORT NO. 50-341/93003(DRS))
This will acknowledge receipt of your letter dated May 14, 1993, in response to our letter dated March 30, 1993, transmitting a Non-Cited Violation associated with Inspection Report No. 50-341/93003(DRS).
This report summarized the results of the Generic Letter 89-10 inspection at your Fermi 2 Nuclear Power Station. We have reviewed your corrective actions and have no further questions at this time.
These corrective actions will be examined during future inspections.
Sincerely,
'
f Cs'
' G. C. Wright, Chief Engineering Branch See Attached Distribution 9306010095 930525 PDR ADOCK 05000341 O
\\
neuc zw
,-
-
.
... _.
-
.
l
.
.
Doualas R.Gipson l
Vere Pres:sent i
Nw0 teat Operatons
.l h5 f
Ferm12
. Edison iREiEF" ca..
-
May 14, 1993 NRC-93-0052 l
!
l
.
U. S. Nuclear Regulatory Commission
.
Attention: Document Control Desk Washington, D. C.
20555
-!
i
!
References:
1)
Fermi 2
.
NRC Docket No. 50-341
NRC License No. NDF-43 l
2)
NRC Inspection Report No. 50-341/93003
dated March 30, 1993 i
l Subject:
Reply to Non-Cited Violation dated March 30, 1993 l
i
!
Enclosed is Detroit Edison's response to a non-cited violation-j contained in Reference 2.
This violation was for failure to promptly
evaluate results from MOV dynamic testing performed as part of
'
Ferni 2's commitment to' Generic Letter 89-10.
i This was a self-identified violation by Detroit Edison. Therefore, the violation was not subject to enforcement action because of Detroit
Edison's effort in identifying and developing a plan to correct the
{
violation.
'
.
If you have any questions regarding this response, please contact
!
Elizabeth A. Hare, Senior Compliance Engineer at (313) 586-1427.
j I
Sincerely,
' r'
.f t
!
f I
Enclosure
Attachment:
Procedure 47 306.02 j
MOV Program Guideline Attachment 11
i
REGION lit f
$
GL EN E LLVN. ILLlNOIS 60137
%...../
MAY 2 51993 Docket No. 50-341 The Detroit Edison Company ATTN:
Mr. D. Senior Vice President Nuclear Generation 6400 North Dixie Highway Newport, MI 48166
Dear Mr. Gipson:
SUBJECT:
NON-CITED VIOLATION (NRC INSPECTION REPORT NO. 50-341/93003(DRS))
This will acknowledge receipt of your letter dated May 14, 1993, in response to our letter dated March 30, 1993, transmitting I m ited Violation associated with Inspection Report No. 50-341/93003(bRS).
This report summarized the results of the Generic Letter 89-10 inspection at your Fermi 2 Nuclear Power Station. We have reviewed your corrective actions and have no further questions at this time.
These corrective actions will be examined during future inspections.
Sincerely,
/
j'I Ow
-
Ma,y,e,
.
' G. C. Wright, Chief Engineering Branch See Attached Distribution 9306010095 930525 PDR ADOCK 05000341 G
-
.
/' U6D C -ZE C)
--
a v
,
'
The Detroit Edison Company
MAY r 51993 Distribution cc: John A. Tibai, Supervisor of Compliance P. A. Marquardt, Corporate Legal Department cc w/1tr did 05/14/93:
OC/LFDCB Resident Inspector, RIII James R. Padgett, Michigan Public Service Commission Michigan Department of Public Health Monroe County Office of Civil Preparedness Fermi LPM, NRR T. Scarbrough, NRR M. Holbrook, INEL P. Eapen, RI F. Jape, RIl M. Hunt, RII T. Westerman, RIV P. Narbut, RV
.
--
-
-,
!
,
l
-
..
.
j
" Douglas R.' Gipson
vite Prescent Nutiear opera 1 sons
}
Q Fermi 2 '
~
f Edison Edi3BF" 2:ss
-
,
May 14, 1993
,
A
i U. S. Nuclear Regulatory Commission
Attention: Document Control Desk
!
Washington, D. C.
20555
,
!
References:
1)
Fermi 2 NRC Docket No. 50-341
NRC License No. NPF-43
>
f 2)
NRC Inspection Report No. 50-341/93003 i
dated March 30, 1993
!
!
Subject:
Reply to Non-Cited Violation dated March 30, 1993 i
!
!
Enclosed is Detroit Edison's response to a non-cited violation
-;
contained in Reference 2.
This violation was for failure to promptly l
evaluate results from MOV dynamic testing performed as part of
.
Fermi 2's commitment to Generic Letter 89-10.
!
!
This was a self-identified violation by Detroit Edison. Therefore,
_;
the-violation was not subject to enforcement action because of Detroit
!
Edison's effort in identifying and developing a plan to correct the i
'
violation.
If you have any questions regarding this response, please contact Elizabeth A. Hare, Senior Compliance Engineer at (313) 586-1427
Sincerely, f
.V
'
.p i
)
Enclosure
'
Attachment: Procedure 47 306.02
,
MOV Program Guideline Attachment 11 l
i cc:
T. G. Colburn i
A. B. Davis l
,.
'
W. J. Kropp
,
N. P. Phillips
!
Region III l
f
Q]Ih.D.hh
- a i
,
.
-
-
-
.
.
.
.'
.,
i Enclosure to-
{
NRC-93-0052 Page.1
'
,
s Reply to Non-Cited Violation 50-341/93003 dated March 30, 1993
Statement of Non-Cited Violation:
i 10 CFR Part 50, Appendix B, Criterion II, " Test Control," requires
!
licensees to evaluate the results of tests to assure that test
'
requirements have been satisfied. Failure to promptly evaluate j
results from NOV dynamic testing performed as part of its commitment
,to Gsneric Letter 89-10 is considered a violation of Criterion.II.
]
However, the NRC wants to encourage and support licensee's initiatives
- '
for self-identification and ' correction of the problems.- Berefore,
'
this violation is not being cited because the criteria specified in Section VII.B.2 of the " General Statement of Policy and Procedures for i
NRC Enforcement Action," (Enforcement Policy, 10 CFR Part 2, Appendix C) were satisfied. Specifically, the licensee identified
.
that thorough test result evaluations were not completed at the time
~
of the dp tests and subsequently developed a "HOV Post-testing Review" evaluation form to review the results. ~The licensee committed to complete an evaluation form for the 21 previously performed dp tests
}
by May 14, 1993, and to include consideration of motor capability.
In i
addition, plant, procedures were revised to require prompt evaluation
following future dp tests.
i Include in your response:
(1) the revised acceptance criteria for MOV
- !
tests, including consideration of actuator motor capability, and (2)
[
the results of the reevaluation of the MOV tests evaluated using the-
,
previous unacceptable criteria.
]
Detroit Edison Response:
!
i (1) Revised Acceptance Criteria for MOV Tests l
.
's As committed during the Phase II Inspection, Detroit Edison will use thrust reduction margin for the rate of loading, stem lube degradation
and torque switch repeatability effects along with the diagnostic i
equipment accuracy. 'Ihe revised thrust acceptance criteria being used-(
o during the static as well as dynamic test evaluation process is j
already included as Attachment 4 to procedure 47 306.02 "v0TES System Operating Procedure" (see attachments). A copy of the revised procedure 47 306.02 was sent to NRC Region III the last week of-.
i February 1993 MOV Program Guideline Attachment 11 (see attachments)
I was revised to account for reduction in the thrust margin due to above i
mentioned effects per the industry adopted' methodology. Bis revised
'
thrust acceptance criteria was used for evaluation of dynamic test results. Procedure'47 306.02 Attachment 4 will be-further revised
.l prior to the next MOV test to better coordinate with the revisions to
,
'
the MOV Program Guideline Attachment 11.
Procedure 47 306.02 requires completion of the evaluation of dynamic and static test results prior
.
i
!
.!
<-
i i
I f
Enclosure to NRC-93-0052 Page 2
'!
to processing the work package through the Nuclear Shift Supervisor for returning the MOV to service.
Detroit Edison is considering the use of a statistical scandard deviations approach in combining the thrust reduction effects due to rate of loading and sten lube degradation. Until plant specific parameters for rate of loading and stem lube degradation can be established by additional dp testing, industry provided data will be utilized. Therefore, Attachment 4 to Procedure 47 306.02 may be
'
revised if the statistical approach is acceptable based on further dynamic testing performed at Fermi 2.
Detroit Edison presently evaluates the actuator motor capability during the diagnostic testing based on 60% locked rotor seating current (LRA) for safety related HOVs except a for few HOVs where the seating current criteria is lower than 60% LRA. This criteria is included in the procedure 47 306.02, " VOTES System Operating Procedure".
In response to the NRC Inspector's concern for unseating motor current during the opening stroke for gate valves, procedure 47 306.02 was revised to include the 60% LRA for maximum unseating motor current. During the design basis review, the actuator motor
,
capability at degraded voltage is evaluated per the Limitorque SEL
methodology which verifies the motor torque output meets the design required torque and provides the maximum allowable torque switch setting based on the spring pack curve. However, due to variation in the spring pack stiffness and stem factor, the motor capability during the diagnostic testing could not accurately be predicted by torque switch setting and measured thrust. Therefore, Detroit Edison feels confident that the motor capability evaluation based on its operating parameter (i.e., motor current) during the diagnostic testing is a more accurate performance indicator.
(2) Results of Re-evaluation of the MOV Tests
.
Based on the revised acceptance criteria for HOV tests describe'd
!
above, as committed during the Phase II Inspection, Detroit Edison evaluated the dynamic test results of 21 MOVs. The evaluation included the review of the differential pressure acting on the HOV and the calculation of rate of loading and valve factor for those cases during which acceptable differential pressure (dp) compared to the design basis dp was available during testing. The summary of evaluation is as follows:
The differential pressure (dp) achieved during the dynamic testing for 9 HOVs was between 77 and 100% of the design dp.
The valve factors and rate of loading results obtained from the evaluation were considered along with the stem lube degradation, torque switch repeatability and equipment accuracy for predicting thrust margin as well as HOV capability at the design basis differential pressure. The rate of loading effects varied from 15 to 32%. The valve factors at flow cut off for globe valves were lower than those used in the design
!
<
.
Enclosure to NRC-93-0052
Page 3
,
basis review and for gate valves were higher than those used in the design basis review. However, these HOVs are considered operable based on the available and required thrust at the revised valve factors based on the dynamic testing. As part of the MOV evaluation process, Deviation Event Reports (DER) were issued due to marginally meeting the acceptance test criteria or exceeding the presently available maximum structural strength limits for valves and actuators. Based on HOV operating history and the range of over thrust, these valves are considered acceptable. Issuance of the DERs will ensure further evaluation and follow-up corrective action are performed in a timely manner.
Five HOVs did not cxperience adequate differential pressure during the dynamic testing due to inadequate system lineup configuration. The inadequate differential pressure was due to the pressure effects from interconnected piping not properly isolated from the test loop. Four of these HOVs are minimum flow HOVs for pulps and need to be retested such that there is no pressure effect on the downstream side due to flow in other connected piping system. These HOVs will be scheduled for re-testing during or prior to the fourth refueling outage scheduled to start in March 1994. The dynamic test results (VOTES thrust signature) for one more MOV could not be evaluated due to a high calibration error for extrapolation. The design basis
differential pressure for this HOV is only 15 psid and therefore the HOV will not be retested under dynamic conditions. These HOVs have
<
'
been tested in the static condition and do have adequate thrust margin for performing their safety functions. This. conclusion is based on the static test results of an additional 59 HOVs tested at Fermi 2.
Six HOVs in Residual Heat Removal (RHR) service water system were
tested undar normal service water system operating configuration.
These HOVs are located at the discharge end of the system. Due to
substantial pressure drop throughout the system, differential pressure experienced by these HOVs was around 6 psig and therefore, the flow
'
cut off points on the thrust signature could not be clearly differentiated. These HOVs were only dynamically tested and as-left thrust values were equal to or above the target thrust at design basis dp of 135 psig. The design basis differential pressure (dp) and target thrust are based on the mispositioning scenario which considered the pumps deadheading and no system pressure drop is occurring. Supplement 4 to G.L. 89-10 exempts BWR plants from consideration of the mispositioning scenario. Detroit Edison elected to consider the mispositioning scenario during the design basis for conservative Maximum Expected Differential Pressure (MEDP) and corresponding thrust requirements but did not dynamically test these HOVs under the mispositioning scenario. The HOVs stroked (open/close)
during the dynamic testing with as-left thrust higher than the minimum design required thrust corresponding to MEDP. These valves are considered operable and capable of performing the safety function.
Therefore, no further testing will be performed for these six HOVs.
,
..
.
....
.
-
f s
'fJu'cicar Production - Fermi 2 47,306.02
Performance Evaluation Procedure Revision 5 Page
- ;
g. -
VOTES SYSTEPA OPERATirJG PROCEDURE i
I Revision Summary
'
1) Added Enclosure D to list exceptions to seating current acceptance enteria.
2) fAade minor changes to clarify acceptance criteria in Attachment 2.
Implementation Plan
i
[X) Revision effective immediately - ongoing work impacted l
!
[ ] Ongoing work may proceed using previous revision
!
I Attachments
042393 Test Data Sheet
042393 Degradation Data Sneet
,
012993 Stem Diameter Reduction Due to Axial Slot
022593 fAOV Post-Testing Static or Dynamic Test Review
,
.
Enclosures NTR2GD \\II.E~
y )gg3 [
A 090192 VOTES Cable Connection Guide B
012993 Stem Transition Region
- y C
100891 Test Site Trace FAarking DATE EXFinc.D D
042393 Seating Current Capacity Exceptions E
042393 Planning and Preparation
,
ARfAS - ifJFORfAATIOfJ SERVICES (& M,Tw,3u.'.sm
Date approved: 050193 Reiease autnorized ov:
Change numbers incorporated: 93-0744 Date_$OM3 DSfJ 4730602 Rev
DTC TPfJPP File 1703 02 Recipient 3d k
a d$t> 51LO11E
_
.
_
_
i 47.306 02
,
,
.
Revision 5 t
Page 2
,
.
1.0 PURPOSE This procedure provides instructions for the Static or Dynamic testing of motor-operated valves (fADVs) using Liberty Technology's Valve Operation Test and Evaluation System (VOTES). This procedure is to be followed in order to comply with the requirements of NRC Geneeric tetter 89-10 to verify, trend and track MOV performance and/or ability to perform its intended safety function.
NOTE:
As a matter of practice, the first *as left" test on a valve is considered the baseline test. Each subsequent test is compared to the baseline test for trending and evaluation. A new baseline test should be performed as soon as possible after any major work which may be done on the valve or operator which may change the valve's baseline characteristics. This may include but is not limited to: valve disassembly, reseating, repacking, stem replacement, MOV gear, bearing, bearing housing gaskets, torque switch or stem nut replacements.
2.0 PRECAUTIONS AND 1.lMITATIONS 2.1 Review applicab!e Radiation Work Permit (RWP) for requirements in the work area.
2.2 Do not allow the entry of foreign materials into working parts of the valve operator.
2.3 Only individuals that have completed VOTES Training / Certification or individuals under the direct supervision of qualified personnel may operate the VOTES equipment.
2.4 Only individuals that have completed VOTES Signature Analysis or MOVATS Signature Analysis training may perform Signature Analysis for purposes of completing the Degradation Data Sheet, Attachment 2.
.
2.5 Ensure all power connections to VOTES System are 120Vac,60 Hz.
-
2.6 Ensure the VOTES System is deenergized while installing test equipment, associated sensors and wirmg connectors to prevent voltage / current spikes from damaging the computer / test equipment.
.
2.7 Do not operate computer in area where ambient temperature is less than 50 F or
greater than 104 F.
i 2.8 When a problem or nonconformance is noted, work shall stop if the testing is detrimental to the valve or system. Notify the NSS to ensure that required
,
deficiencies are resolved before a valve is returned to service. All deficiencies noted shall be listed on the Work Request as appropriate.
2.9 If there must be jumpers installed or wires lifted to stroke valve, the use of an Interim Alteration Checklist is required.
2.10 As-Found signatures should be acquired before altering setting >f torque switch or
limit switches.
2.11 Electrical circuits associated with MOVs cannot be isolated during certain plant i
conditions. These must be identified prior to work.
)
I
&
'
.
.
47.306.02 Revision 5
,
Page 3-
-
2.12 The following improper actions may damage FAOV actuators:
2.12.1 Ufting the actuator by the handwheel.
'
i f
2.12.2 Use of excessive force on the declutch lever when engaging into manual drive mode.
2.12.3 Use of excessive force on the declutch lever in attempt to return the actuator to the electrical operation position. Internal damage is possible.
2.12.4 Use of unauthorized mechanical lever on the handwheel to seat or unseat the valve could cause damage to actuator and valve.
'
2.13 The sequence and method of testing may be repeated or altered at the discretion of the Test Leader to ensure complete data acquisition for subsequent signature analysis. Re-tests may be performed under this procedure provided the tests are sequentially numbered and each is documented on a separate consecutively numbered Test Data Sheet, Attachment 1.
.
2.14 If during performance of this procedure, it is discovered that actuator rework is required, it should be done in accordance with Procedure 35.306.006, Enclosure C.
j 2.15 11 during performance of this procedure,it is discovered that the' VOTES Force Sensor
}
is not properly attached to the valve yoke (e 9. not preloaded), it shall be removed l
and a new sensor installed per 35.LitA 009.
2.16 Any discrepancies noted during the conduct of this procedure must be reported to
'
the appropriate Supervisor for disposition.
j 2.17 Verify duty cycle for each valve is followed.
>
2.18 As steps are performed / completed, the boxes at the end of the step may be checked
{
011 (optional).
j
-+
2.19 Ensure calibration device will fit the valve stem (e g. mini C Clamp - 1 1/8 inches max, C Clamp - 17/8 inches max [or 21/4 inches for newer stylel D Clamp *31/2 inches max, U Clamp 51/2 inches max. maxi U Clamp - 8 inches max).
i
!
2.20 Use of the computer / printer in an * Airborne Radioactivity" or * Loose Surface Contamination * area may result in internal contamination of the computer / printer due
,
,
to the required cooling air flow through the computer / printer.
]
l 2.21 A short adapter cable is provided to connect cable from the Breakout Box to Signal Conditioning Box. Every attempt should be made to locate the short cable at the Signal Conditioner Box to avoid its contamination. Up to 500 ft. of signal cable can
be used between Breakout Box and Signal Conditioning Box.
l 2.22 A Torque Switch Transducer (TST) or a Thrust fAeasuring Device (TtAD) may be utilized if needed to determine spring pack displacement. This will normally be utihred in a spare channel in the breakout box.
2.23 The VOTES Technical tAanual can be utilized as a reference for guidelines on this testing.
i
~
\\
i n
'
-
.
47.306.02 Revision 5 Page 4
.
2.24 ff the maximum values as contained in the test data sheet are exceeded, the valve shall be declared inoperable either until the valve is adjusted within the limits or Nuclear Engineering analyzes and accepts the out of specification condition'.
'
2.25 An *as found* LLRT should be performed prior to any adjustments, repair, or enhancements to the valve, packing gland, stem or operator. This includes but is not limited to stem lubrication or nut tightening.
2.26 in some cases, to perform a sensor calibration,it may be necessary to loosen and remove the packing gland nuts or follower to prevent calibrator clamp interference.
The performance of this on an LLRT valve will inop the valve and invalidate the valve's LLRT results. Ensure the Test Supervisor is notified PRIOR TO loosening the gland nuts to assure that the *as found* LLRT results are not jeopardized and that a
- post * LLRT can be performed immediately after the thrust test.
2.27 Peak motor seating current should not exceed 60% of locked rotor amps (LRA) on safety related MOVs. This value is the * Rule of Thumb * and if exceeded, must be evaluated in the Degradation Data Sheet, Attachment 2. Exceptions to this * Rule of Thumb * are listed in Seating Current Capacity Exceptions, Enclosure D.
3.0 REQUIRED EQUIPMErJT 3.1 Portable Computer 3.2 Printer (optional)
-
3.3 Breakout Box 3.4 Signal Conditioning Box 3.5 Calibration Device (C-clamp. U-clamp as appropriate, etc )
3.6 VOTES System Cables per Enclosure A 3.7 Ruler or Micrometer
.
3.8 Flashlight 3.9 Screwdrivers 3.10 Approved Degreasing Solution
3.11 Adjustable Wrenches 3.12 Gaskets / spare parts as appropriate r
i I
.
.
47.306.02
Revision 5 Page 5 l
.
-
3.13 For DC valves
,
3.13.1 DC Switch Probes / Fluke Current Probe i
3.13 2 DC Switch Probe Interface Box 3.13.3 P-3500 Portable Strain FAeter r
i 3.13.4 DC Voltmeter
3.14 For AC valves 3.14.1 AC Current and Switch Probes 3.15
"ITl/tADVATS' Torque Switch Transducer (TST) (OPTIONAL)
f
,
3.16
'ITl/tAOVATS' Thrust fAeasuring device (TtAD) (OPTIONAL)
i 3.17 Torque Wrench
.
4.0 PREREQUISITES
4.1 Obtain working copy of ALL applicable drawings and associated changes.
i1 TJOTE:
FAore conservative torque switch settings and stem thrust values may be provided on the Test Data Sheet after the review of valve history by the FAaintenance Planner.
4.2 Obtain recommended torque switch settings and stem thrust requirements for.
l opening and closing strokes from CECO PAVL Screens and fill out the Test Data Sheet l
as appropriate.
I1 s
4.3 VOTES Forces Sensor mounted on valve yoke with preload in normal range (-1500 to
'
+1000 uVN).
i1
.
4.4 Verify test equipment calibration is current.
,
I1
'
4.5 Obtain permission from Shift Supervisor to perform test and to operate the valve l
either locally or from the Control Room.
I1
i
/
INITIAL /DATE
,
e l
!
i
!
.
' !
47.306.02
-'
,
Revision 5 Page 6
.
!
'
5.0 PROCEDURE
'
.
5.1 Setup NOTE:
The necessary valve /act'sator information should be obtained from Engineering and FAaintenance history. Poisson's Ratio and the IAodulus of Elasticity (Young's fAodulus) can be obtained for a given stem material from material property tables. It is suggested that as much data entry into the
{
computer take place prior to entry into a high radiation or high temperature
'
areas.
5.1.1 if possible locate Signal Conditioning box and Portable Computer outside of
-
contaminated areas.
Il
!
5.1.2 Locate Breakout Box at the valve. Ensure it cannot fall and be damaged.
.
f
[]
t CAUTION Exercise care when removing limit switch cover from actuator, some circuits may be energized from a separate power source.
51.3 Record the open and closed "As Found' torque switch settings on the Test
Data Sheet.
i ()
,
u CAUTION
!
Verify that the System 120 VAC power is dicconnected prior to connecting or disconnecting the computer A/D signal cable (CB4-100).
5.1A Attach VOTES cables per Enclosure A, 'v0TES Cable Connection Guide," for cable and equipment connections.
.
I}
.
)
_
_
i
e
47306.02 Revision 5 Page 7
-!
!
'
'
>
5.2 FAotor Current Probes NOTE:
The Simpson FAotor Current Probe is for AC valves only. The Belf or Fluke
,
FAotor Current Probes are for AC and DC valves.
I
5.2.1 IF the Bell or Fluke Factor Current Probe is to be used, THEN GO TO Step 5.2.3.
!
I1
<
5.2.2 Simpson fAotor Current Probe Setup 1.
Place probe around motor lead T2.
' [1
'
2.
Ensure AC fAotor Current Probe cable is connected to J6 on the Breakout Box,.
'
I1
,
fJOTE:
When using the Simpson FAotor Current Probe, the current range selected (orange scale) should be approximately 6 times the motor running current -
to encompass the expected inrush.
3.
Set correct current range on probe. Communicate the probe setup
!
information to the computer operator.
I1
.
t 4.
GO TO Section 53.
'
Il b
.
'
!
.
,
W
,e
,
.
.
.
.
.
'
47.306 02
'
Revision 5
Page 8 NOTE:
To maintain consistency from test to' test for probe connections, maintain the same probe orientation on motor lead.
.
5.2.3 Bell or Fluke FAotor Current Probe Setup 1.
Depress and hold the push-to-read switch to verify that battery is in satisfactory condition.
[]
2.
Place probe around motor lead Al or A2 for DC valve or around motor a
[]
NOTE:
There can be a few millivolts of thermal drift during the first 60 to 120 seconds of warmup of the current probe. For maximum DC accuracy, a warmup of 2 minutes before zeroing will eliminate 95% of the drift.
3.
Zero FAotor Current Probe
,
a.
Using a multimeter set on DC volts, connect to probe and adjust zeroing potentiometer on the motor current probe to obtain a zero voltage output on the multimeter. After zeroing, leave the current probe on.
[]
!
,
,
b.
Using a P-3500 Portable Strain meter zero FAotor Current Probe as follows:
1) Connect BNC male connector end of supplied zeroing cable to BNC female connector on the probe. Connect the banana plug end of the zeroing cable to S- (white) and S+ (green)
inputs on P-3500.
[]
.
2) Setup P-3500 as follows:
a) Gage Factor range of 4.3 - 9.9
[]
l
-
b) Balance selector set to 0
[]
c) Balance potentiometer adjusted to 5
[]
d) fAultiple set to X10
[]
e) Full Bridge selected
[]
f)
Depress Amp Zero button then zero the amplification adjustment
[]
,
I
_ _.
,
47.306.02
'
'
'
Revision 5 -
Page 9
-
.
NOTE:
When using the FAotor Current Probe, the current range selected should be
at least six times (6X) the motor running current. For DC valves, the current
!
!
selected should be approximately 100 times the motor current, up to the maximum range available on the probe. The probe must be re-zeroed each
time the scale is changed.
!
3) Select range on current probe using Range Switch.
l
[]
4) Depress Run button on P-3500.
I1
,
5) Turn current probe on with pusti-to-read switch, lock on with
slide lock and wait approximately 2 minutes.
I1 6) Zero output of Factor Current Probe using zero adjustn.ent
thumbwheel on probe.
I1
-
7) Leave current probe turned on.
[]
8) Disconnect zeroing cable and secure P-3500
'
I1 4.
Connect factor Current Probe cable to J6 on the Breakout Box.
-
[]
5.
Communicate the probe setup information to the computer operator.
[]
,
'
,
s
-
'
!
[
i s
!
I f
t I
-
-.
-
-.
u
.
t
'
.
.
.
47.CS02 Revision 5 i
Page 10 i
,
'
5.3 Switch Current Probes Setup NOTE:
The VOTES System can handle up to four switch leads simultaneously. The l
close torque switch shall be one lead that is monitored. It shall be at the l
discretion of the Test Leader which other leads are to be monitored.
'
i 5.3.1 IF OC Switch Current Probes are to be used. THEN GO TO Step 5.3.3.
[}
5.3.2 AC Switch Current Probes Setup.
1.
Place current probes A through D around the appropriate leads.
j l1 2.
Indicate on the Test Data Sheet / Computer Oata File which lead each switch probe is monitoring.
I1
f 3.
Turn Signal Conditioning Box Oft
..
l
[g])
'
s
.
4.
GO TO Section 5.4.
'
'
I}
%
f
i
,
h
,
e h
!
/
l
!
,
,
h t
- 47.306 02
.
.
Revision 5
Page 11
-
t 5.3.3 DC Switch Current Probes Setup
-
l 1.
Connect DC Switch Probe interface Box Signal Out cable to either
,
'
Connector J4 or JS on the Breakout Box.
I1 2.
Connect DC Switch Probe interface Box Power cable to either J2 or J3 connection on Breakout Box.
I1
3.
Connect DC Switch Probes to four connectors on DC Switch Probe
,
interface Box.
.
I1 l
4.
Turn Signal Conditioning Box ON.
I1
NOTE:
The zero offset for each switch probe channel should be confirmed each time the probes are connected to the DC Switch Probe Interface box.
5.
Place switch probes around the appropriate leaos on the outgoing side of switch. Place current probe around switch wire with current flow in direction as shown on the diagram affixed to the probe.
l]
NOTE:
Due to initial thermal drift of the probes, allow at least ten minutes for their output to stacitize before zeroing.
,
!
6.
Adjust zero offset knobs on top of DC Switchf Probe intedace Box for each prcbe channel until LED indicators extinguish, Probes are now l
$
2eroed Lock zero offset knobs.
l1 7.
Indicate on the Test Data Sheet / Computer Data File which lead each switch probe is monitoring.
'
I1
'
.
,
s
!
.
r l
O
i
.
O
-
-
-
'
.
,
47.306 02 l'
Revision 5 Page 12
.
'
5.4 Calibrating the VOTES Force Sensor r
,
..
.
I NOTE (1):
The calibration procedure must be performed at least twice for every l
sensor mounted on a valve yoke. The calibration procedure should be l'
repeated if the close torque switch setting has been changed by '
greater than one (e.g. from 2-1/2 to 1-1/2), if the actuator body or valve has been physically altered, a new VOTES sensor installed, or a new stem has been installed.
I
!
NOTE (2):
in some cases, to perform a sensor cahbration it may be necessary to loosen and remove the packing gland nuts or follower to prevent calibrator clamp interference. The performance of this on an LLRT valve will inop the valve and invahdate the valve's LLRT results.
-
Ensure the Test Supervisor is notified PRIOR TO loosening the gland
nuts to assure that the *as found" LLRT results are not leopardized anct that a * post * LLRT can be performed immediately after the thrust
'
test.
5 4.1 From the main menu, press key to select VOTES Sensor Calibration" menu.
.I1 i
5 4.2 Follow the menu on the VOTES system software prompts.
I1
!
5 4.3 Select appropriate calibratiori device per Table 1.
i TABLE 1 l
Calibration Device Stem Diameter (in)
l
tAini C-clamp
through 1 1/8
!
C-clamp
through 1 7/8 i
C-clamp (new style)
O through 2 1/4
,
D-clamp 1 1/8 through
'3 1/2
'
U-clamp
through 5 1/2 FAaxi U-clampf
through
'
,
'
I1 e
~
'
!
54.4 Select appropriate cahbrationkevice gains and follow the instruction on the
,
screens. Enter calibrator and voltmeter numbers in preceedmg spaces provided.
%
l o
1.
When using C-clamp or mini C-clamp, the gain saould be set at 20.
l I1
!
t 2.
When using the D-clamp. U-clamp, or FAax.i U-clamp, the gain should y
be set at 2 or higher.
i I1
[
'
3.
VOTES Force Sensor gain should normally be set at 5.
I1
t IfJITIALS f
~ !
-
e O
?
-
p 47.306.02
,
,_
Revision 5 Page 13 5.4.5 Record calibration device number arid calibration due date.
.
M&TE No.
l Cal Due Date I
i l
i Initial /Date 5.4.6 If the stem has an axial slot (for anti-rotation), then Attachment 3 needs to be completed to calculate the reduce effective stem diameter. When the corrected Deff has been calculated enter a 'U' at the computer prompt, then change the displayed stem diameter to the calculated Deff-OTHERWISE check N/A.
Effective Diameter N/A INITIALS NOTE:
If during calibration, saturation of a channel occurs, Abort Cal, Lower Gain Setting and reperform calibration.
5.4.7 IF the D-clamp, U-clamp or maxi U-clamp is to be used THEN GO TO Step 5.4.9.
I1 NOTE:
Ensure valve has been closed electrically prior to calibration.
5.4.8 Calibration of VOTES Force Sensor using mini C-clamp or C-clamp.
-
CAUTION
Do not mount C-clamp on the unthreaded portion of stem within 1 stem diameter of the trar}sition point from threaded to unthreaded, or
+
1/2 stem diameter into the thread. See Enclosure B for illustration.
1.
Clean that ponion of the valve stem where the C-clamp is to be attached using an approved degressing solution.
I1
.
_- _
i 47.306 02
-
Revision 5
!
Page 14
!
-
i
!
'
CAUTION Loosening and removing packing gland nuts will invalidate the valves LLRT.
!
!
!
CAUTION i
C-clamp must not strike any portion of valve during calibration or it will be j
damaged. It should be attached to valve stem in a position free of
'
interference with other valve components so that there is sufficient clearance
!
during seating, taking into account slight stem rotation during operation.
I NOTE:
Whenever possible position the clamp bridging the anti-rotation slots, f
i 2.
For gate valves, place the valve in an open-stressed condition. The perfect condition is just before disc pullout. This will mean that the
valve never gets fully unseated.
j l1
!
3.
For globe valves, fully unseat the valve, ensure cal stroke is done after handwheeling in open direction.
.
I1 4.
Carefully seat C-clamp anvil against valve stem and support with one
}
hand while running in C-clamp assembly with other hand. (Use the
!
thumb of the hand supporting the C clamp to prevent rotation of the
[
t V-block).
I1 l
'
S.
Press Ley to select " Tighten C-clamp"
[]
NOTE:
IF when tightening the C-clamp the reading exceeds -3000 the C-clamp
}
shall be completely loosened and then re-tightened to achieve the se, quired
reading i
}
6.
Prior to mountmg clamp on stem. verity displayed value on computer
~
screen is at approximately -2000 to -3000. Slowly tighten C-clamp and as C-clamp is tightened, value will approach zero, then begin to
,
go negative again. Tighten C-clamp to achieve readmg of -2700 to j-3000. Follow instructions on screen.
Il
i 7.
Press key to select * Calibrate VOTES Force Sensor". At this point the l
VOTES software will display messages concerning the Zeroing of the j
Current Probe, VOTES Force Sensor and ti e Cahbration Device. Follow i
instructions on screen.
l I1
$
.i
.l
-
. -_.
,
.
.
,
.
47.306.02 i
Revision 5 (
Page 15 i
8.
Close actuator electrically. The computer will now gather data from j
the C-clamp and VOTES sensor and produce two curves for operator to select calibration points.
~
i (l
!
9.
GO TO Step 5.4.10.
'[]
t FJOTE:
Ensure valve has been closed electrically prior to calibration.
'
5.4.9 Calibration of VOTES Force Sensor using D-clamp. U-clamp, or maxi
,
U-cla mp.
1.
Connect DC Voltmeter to test points on Proximetor Box and verify initial gap voltage is -5.5 volts DC */- 0.25 volts for U or maxi
U-clamp or -12.0 +/.20 volts for the D-clamp. If the gap voltage
does not fall into this range, reset the Proximity Probe.
I1
'
TJOTE:
As used in this section, U-clamp refers to either the D-clamp. U-clamp or maxl U-clamp.
CAUTIOtJ
!
Do not mount U-clamp on the unthreaded portion of stem wit'hin 1 stem diameter of the transition point from threaded to unthreaded, or 1/2 stem diamets into the thread. See Enclosure B for illustration.
2.
Clean that portion of the valve stem where the U-clamp is to be attached using an approved degreasing solution.
[}
t CAUTIOrd i
Loosening and removing packing gland nuts will invalidate the valves LLRT.
'
.'
.
CAUTIOtJ U-clamp must not strike any portion of valve during calibration or it will be d a m a g e d. U-clamp should be attached to valve stem in position free of interference with other valve components so that there is sufficient axsal
,
i clearance during seating, taking into account slight stem rotation during operation.
i 3.
For gate valves, place the valve in an open-stressed condition. The j
perfect condition is just before disc pullout. This will mean that the valve never gets fully unseated.
{
I]
-
-
-
-
l 47.306 02 l
Retrision S
!
"
Page 16
,
!
i 4.
For globe valves, fully unseat the valve, ensure cal stroke is done after f
handwheeling in the open direction.
!
!
-
I]
5.
Carefully set U-clamp anvil against valve stem and support with one hand while running-in the U-clamp stem assembly with other hand (use the thumb of the hand supporting the U-clamp to prevent
rotation of the V-block).
!]
l 6.
Slowly tighten U-clamp until DC Voltmeter reads between -10.6 and -10.9 VDC.
!]
l 7.
Disconnect DC Voltmeter.
[]
.
it may be necessary to immediately, electrically or manually open the motor -
FJOTE:
,
,
l operator off of its seat after closing during calibration. This will be i
necessary to determine a * Torque Correction * factor.
{
8.
Press key to select " Calibration VOTES Force Sensor". Follow instructions on screen.
[]
.
9.
Close actuator electrically. The computer will now gather data from
the U-clamp and VOTES Force Sensor and produce two curves for operator to select calibration points.
!]
,
.
-
>
INITIALS i
t
'
5410 Trace point selection for sensor calibration.
F 1.
Ensure the two traces follow each otner. If one plot lesels off before the other plot, the device whose plot leveled should have its gain l
reduced and the test re-performed
'
I1
'
2.
Votes uses automatic spike suppression / removal for the calibration j
.
!
traces, but it is still a necessity to redo test which display a
-
significant amount of noise.
[]
I
-
i 3.
The two traces should show an initia! sharp change from a stem tension condition to a transition area then another sharp change as the valve seats. The first priority is to find and mark the *zero" force spot (this is essentially the same point as the C3 mark placed on full l
stroke traces).
[]
4.
Next, with the cursor on the initial flat line area to the left (Defore the
first sharp change) press F3-IAart to place the left boundary mark for calculation. FAove the cursor to the far right flat area (lust after the sharp seatir g slope) and press F3-Mark to establish the right side bound ary. Now, press F10-Continue to allow the computer to calculate the correlation slope.
I]
<
.
-
-
-
-
-
.-
.
.
.
_
_ _.
.
.
i
,
-
-.
.
!
,
47.306.02 Revision 5
!
Page 17
~
i 5.
The computer will display the correlation slope trace as well as values
for:
'
.
a.
RSO - (root mean square) correlation factor f
b.
BFSL sens - best fit straight line sensitivity, or the slope of the new curve.
'
c, fAeter gf gage factor
!
d.
100% - fAaximum thrust rating for that operator
'
i e.
CFA - Curve Fit accuracy
[]_
(
6.
For the calibration to be acceptable the CFA must be between.970 and 1.00. if _ CFA is within that acceptance criteria then the value of i
RSQ is meaningless. If true zero value had not been identified (or
,
marked) then an fuA will appear after CFA. which makes an RSO value (
the determining factor for meeting the.970 - 100 acceptance criteria.
in that case it is also highly desirable to make every effort to obtain
an RSO of at least >.997, so that system accuracy is not degraded.
.i
[]
I 7.
If the values are acceptable save the calibration to the hard disk then repeat the calibration to verify that the two slope values (BFSL sens)
'
are within 5% of each other. Record the applicable values on the test
,
'
data sheet. If the second calibration had a better CFA (or RSO) then save it to the herd disk. which overwrites the first cal. If the first cal i
had better values then simply do not save the second test.
I IJ
!
N 8.
Press key (s) to return to the " Acquire Test Data" menu.
I
[]
,
f INITIALS
'
.
-
-
.
i
.
.
j i
f
!
.
47.306.02
.
,
Revision 5 Page 18 5.5 Data Acquisition
,
,
t
'
NOTE (1):
Stem should be in an *AS FOUND* condition for the 1st stroke. (do not add lubrication after cleaning stem for calibration). Only add stem lubrication for the final *AS LEFT* trace.
!
t i
!
NOTE (2):
Compute.' will ask if operator wishes to zero sensors. Sensors should not be zeroed at this point unless valve is in an unstressed state, or a
!
previous calibration is being utilized. Should the Votes sensor trace
!
!
flatten at a high thrust, this would require a rezero and retest.
!
NOTE (3):
If acquisition time is available, it is desired to get open ano c.i%.
on j
the same trace.
~
!
5.5.1 Press key to initiate *Aquire Test Data" I1 l
!
5.5.2 Press key to select * Input Test Info *. Enter valve tag number and follow screen instructions.
i I1 l
.
5 5.3 Press key to select " Select Sensors *. (Normally VOTES sensor, current and
!
switches)
i
'
I]
5.5.4 Enter sensors utilized for test including the TST or TfAD as requested by
.
Engineering or supervisor. Referer'ce Attachment 1.
.
I1 5.5.5 Press key to select * Comment Upcoming Test" and input information into I
'
computer. Follow the menu through the necessary menu fields to select gains (Reference Section 5 4) through to data collection sequence.
l
[]
l
!
5.5 6 Stroke actuator in direction desired computer well collect data and store it i
I onto memory.
I1
,
5 5.7 After aquiring the test data, press ~Y" for a quick fock at the data.
)
-
()
5.5 8 Press Key (F4) to save data to hard disk if the data is acceptable.
!
..
I1 j
5.5.9 Go to " View Test Data * field to evaluate trace (s)
II i
!
!
I
,
l i
!
i t
?
..
'
.
47.30602 Revision 5 i-age 19 5.5.10 Review the stroke traces as necessa'ry to allow identification and marking of the key points listed in Table 2 below.
.
[]
TABLE 2-Suggested fainimum marks performed in field
-
fAotor start
-
Stem Compression fully relieved
FAaximum force at disc pullout
-
012 -
Open torque bypass switch opens 017 -
FAotor current cutoH CD
-
Factor start C3
-
Tension to compression transition C14 -
Close torque switch opens (CST)
C15 -
FAotor current cuton
.
C16 -
fAaximum thrust value i
NOTE:
Prior to marking traces, determine the appropriate location on tne trace for establishing the zero pcint on the VOTES FORCE SEfJSOR TRACE (F8).
fJormally this will be near the beginning of the closed stroke at the tension i
to compression transition (C3); in some cases it will be clearer at the
!
beginning of the stroke at the point where stem compression is fully
.
relieved (04). Point C3 is preferable.
'
5.5.11 Completion of Test Data Sheet:
i 1.
Determine numerical values for the stroke trace marked points and fill in the Test Data Sheet.
I1 2.
Ensure proper configuration of Limit Switch settings.
I]
i
.
!
5.5.12 If it is determined at this time that adjustments neea to be made to
valve / actuator outside the ranges specified in the Test Data Sheet, obtain
!
approval from Engineering or supervisor prior to performing adjustments. If
adjustments are required that are within the ranges specified in the Test
{
Data Sheet they are performed in accordance with Procedure 35 306.006 i
guidelines. After adjustments are made the valve / actuator shall be retestec
{
under this procedure.
l I1
5 5.13 If after adjustments and/or lubrication re perform applicable steps in 5.5 for
"As Left" data as directed by fJuclear Engineering or Test Supervision.
5.5.14 Record Test Equ5 ment used and the equipment calibration information on the Test Data St < ;.
I}
i IfJITIALS
I J
_
-
4/.306 02
.
.
Revision 5 Page 20 5.6 Restoration
'
.
,
.
CAUTION
Verify that the System 120 VAC power is disconnected prior to connecting or disconnecting the computer A/D signal cable.
5.6.1 Remove motor current probe and switch current probes; and disconnect VOTES sensor cable from sensor and replace cap on sensor connector body.
I1 5.6.2 Reinstallation of lifted leads and/or removal of jumpers.
1.
Inform NASS/NSO of intent to return equipment control circuit to normal condition.
[]
2.
Reinstall all lifted leads and/or remove all jumpers as appropriate.
I1 5.6.3 Record the *As Left torque switch settings on the Test Data Sheet.
I1 5.6 4 Verify limit housing cover gasket is reuseable or replace with new; and reinstalt actuator limit switch cover.
I1
!
5.6.5 Remove test equipment from test area following applicable RWP requirements and return to storage location as directed by the Test Leader.
I1 INITIALS
,
'
5.6.6 Record test personnel:
'
Printed Name initials Signature l
,
I i
j
I
-
<
.
47.306.02
.
.
Revision 5 Page 21 5.7 Data Analysis
-
NOTE (1):
Section 5.7 of this procedure is not required to be performed while valve testing is underway in the field. 11 shall depend on the requirements of the individual Work Package and shall be at the discretion of the Foreman / Analyst when this step is to be performed.
For a complete report it is advisable to have traces marked and comments made on the test.
NOTE (2):
The remainder of this procedure requires only the computer and printer and may be completed in an office environment.
5.7.1 From the FAain FAenu, press key to select " Analysis;" and follow instructions on screen and pick traces to view, mark and plot on screen as required.
I1 5.7.2 Once all applicable points have been marked return to ' Reports' menu and follow instructions on screen to print applicable repons.
I1 5.7.3 Perform Evaluation of " Test Results Summary ~ sheet from Page 1 of the Long Report.
'
I]
5.7.4 Complete Attachment 2 * Degradation Data Sheet '
I1 5.7.5 Complete Attachment 4, " VOTES Post Testing Static or Dynamic Test Review" as required.
I1 INITIALS
.
.
-
.
.
'
47.303 02
.
Revision 5 Page 22 i
!
6.0 INDEPENDENT VERIFICATION - None
'
.
7.0 ACCEPTANCE CRITERIA 7.1 In Attachment 1, verify *As Left Conditions" torque switch settings (TSO, TSC) and thrust at TSC Trip, are within the * Required Values" limits.
i Maintenance Evaluator Signature Date OR
Test signatures have been analyzed and found acceptable by Nuclear Engineering.
FAaintenance Evaluator Signature Date r
7.2 Static Test - In Attachment 4, verify As Found static test evaluation has been performed and the results of the evaluation are satisf actory.
.
Engineering Evaluator Signature Date
'
OR i
initiate a DER documenting the unsatisf actory static test results.
!
'
>
Engineering Evaluator
,
Signature Date 7.3 Static Test - in Attachment 4, verify As left static test evaluation has been performed
.
and the results of the evaluation are satisfactory.
Engineering Evaluator
-
Signature Date
.
.
OR initiate a DER documenting the unsatisfactory static test results.
!
i Engineering Evaluator
,
Signature Date l
!
,
<-
l I
I
.
'
-
47.306 02
..
Revision 5 Page 23
-
,
7.4 Dynamic Test - In Attachment 4 verify As left Dynamic test evaluation has been performed and the results of the evaluation are satisfactory.
'
i Engineering Evaluator Signature Date
'
!
!
initiate a DER documenting the unsatisfactory static test results.
!
!
Engineering Evaluator Signature Date
!
END OF TEXT
,
t
i
}
!
t
$
f T
,
i I
f
.
,
,
@
-
,
I I
I
!
!
!
,
t b
_y
\\
.
.
.
TEST DATA SHEET VALVE PIS No.
LLRT VALVE - Y / N REQUIRED VALUES:
-
FAIN TSO SETTING-REO'D CST THRUST-
lb s.
l IAIN TSC SETTING-lAAX ALLOWED THRUST-Ib s.*
LIMITER PLATE-
- LifAITING COfAPONENT-PACKING GLAND TORQUE-ftIbs FAOTOR LRA -
(X60% =
}
SENSOR CALIBRATION: (Data for last 2 Cal Testa only)
Packing Gland Nut Adjustments [ ] N/A Interference? Y/N Nuts Removed? Y/N Retorqued? Y/N TEST # -
TEST # -
Accepted and stored RSO -
/CFA-RSO -
/CFA-Test No.
i Sens.-
Sens.-
Stem Anti Rotation Slot FAcasurements Width (in.)
Depth (in )
'
V-Block Location [ ] 90 from slot
[ ] over slot
[ ] on threads
[ ] in transition (in. from threads)
[ ] on solid i
Calibrator used:
/
Voltmeter used:
/
Serial No.
/ CalDue F4&TE No.
/ CalDue AS FOUND THRUST TESTING RESULTS:
TSO SETTING-THRUST AT TSC TRIP (C14)-
Ibs.
TSC SETTING-FAAXIfAUfA THRUST (C16)-
ibs.
[
LifAITER PLATE-TEST CONDITIONS: Static
/
Dynamic Packing Gland Torque Checked? Y/N Torque Wrench Used CalDue
Stem relubed [ ]
AS LEFT THRUST TESTING RESULTS:
f TSO SETTING-THRUST AT TSC TRIP (C14)-
Ibs.
TSC SETTING-fAAXIfAUTA THRUST (C16)-
Ib s.
.
LifAITER PLATE-TEST CONDITIONS: Static
/
Dynamic j
TRACE ANALYSIS RESUiTS:
.
!
[
Stroke T:mes:
OPEN-sec CLOSE-sec
'
LS Actu. or r Rotor No.-
2
4
% Full open-
%
%
%
%
!
Peak Seating Current amps Peak Unseating Current amps r
PERSONNEL PERFORfAING TESTS TEST DATE t
i'
TEST COfAfAENTS t
f
!
'Use test comments section to describe any unique or abnormal conditions discovered during test L
performance. Also discuss any special tools or devices that were necessary, and any rework or adjustments that were made in support of this test.
l l
'
Form 47.306.02 Att 1 P1/1042393
,
- - _ - _ _ _ - _ _ _ _ - - _ _ - _ _ _ _
- _ _ - _. _
.. -.
,
.
.
,
DEGRADATION DATA SHEET
, Valve PlS Test Date
-
NOTE: The following information should be obtained from "as-left VOTES signatures.
l 1.
TS Bypass Out of Spec.?
[ ] YES~
[]NO 2.
Any backseating? (if *YES~, quantify)
Lbs.
[ ] YES
[]NO
{
3.
Loose stem nut?
'. J YES
[]NO l
4.
Evidence of localized or Lbs.
[ ] YES
[]NO cyclic loading?
5.
High motor average current?
%
[ ] YES
[]NO
,
I (greater than 120% FLA)
'
6.
Motor current peak during stroke.
[ ] YES
[]fJO 7.
Torque switch problem?
[ ] YES
[]NO 8.
Limit switch problem?
[ ] YES
[]NO 9.
Gear or stem / stem nut wear evident?
[ ] YES
[]NO 10.
Excessive inertia.
[ ] YES
[]NO (% inertia > 50% thrust a TSC)
11.
Acceptance Critena thrust at CST or
[ ] YES
[ ] fJO total thrust outside of desired range.
12.
Motor current increases as valve strokes
[ ] YES
[]NO with no unusual loading?
,
13.
Contact Drop Out Time Problems
[ ] YES *[]NO (> 20 miliseconcs)
i.
Peak Seating or Unseating Current
[ ] YES
[]NO i
greater than 60% of Motor nameplate locked rotor current *
15.
Is Kalsi upgrade report applicable?
[ ] YES
[]NO Initial Signature Analysis Final Acceptance Complete and Acceptable Evaluation I
/
I Maintenance Nuc Eng or Tech Eng
- Check Er. closure D for exceptions
!
I DTS 47.306.02 Att 2 P1/2 042393
,,..... -.
.
.
.
.
..
...
.. -
-
._
._.
.
-
_-
!
.
,
f DEGRADATION DATA SHEET
,
t
,
.
15.
Documentation of Degradation Observed.
,
,
.
W
-
l
i r
i
!
,
!
I
!
!
~
!
W
.
.
l
-
'
o i
.
,
s
,,
!
I I
DTS 47306.02 Att 2 P2/2 042393
,
-
.
,
,y 47.306.02
[' [ h,h
[
Attachment 3, Page 1 of 2 012993 STEM DIAMETER REDUCTION DUE TO AXtAL SLOT 1. For THREADED stem calibrations c. Calcu!sted D,due to threads:(Results will be D.n.)
D,, =
x D, = D.,
- ( O.68/ TPI )
Dn=
o D.,n -
- ( O.681
)
c. Calculate new D,,, for threaded catbrations Mrlde the 0,,, =
transition area.
b. Calculate D,,, due to slot: (Result will be D.,,,)
1. Distance, = 0.167 x D,,,,,, = 0.167 x 1. Calcutate effective depth of slot:
Distance, =
,
Depth,,, = Depth - [ ( D,,,,, - D, I / 2 Distance,= 0.500 x D,,,,,, = 0.500 x Depth, =
-[(
)/2
-
Distance, =
Depth,, =
2. Measure approximate distance between center!ine 2. Calcutate Area,,of Keyway of V-block to the stems transition point = >
Area Key,,, = Slot width x Depth.,
inches.
Area Key,,, =
x Determine multiplier as follows:
Area Key,,, =
[ ]-if measured distance (rtep 1.c.21 is < =
Distance 1 then Multiplier = 1.10 3. Calcu'. ate Area,,, of Stem
'
Area Stem, = ( 3.142 x D,.n' ) / 4
[ 1-if measured distance (step 7.2) is >
Distance 1 but < Distance 2 then Multiplier -
Area Stem.,, = ( 3.142 x
- I/4 1.03
.
Area Stem,,, =
3. Calcutate new D, as follows:
s 4.
Calcutate the Area Ratio,,,
tal For stem with no axial slet (D )
-3 Area Ratio,,, = Area Key,,, / Area Stem,,
D.,
D, x appi; cable multiplier (1.03 or Area Ratio,,,
/
1.10)
Area Ratio,,, =
D--
x
-
.
5. Calculate D,,,,
D=
D, = D,,n x ( 1. Atea Ratio,,, )
'
(b) For stem wrth axial slot (D,,,,1
'
D,,, =
x ( 1-I D,,,,
D,., x appUcable rnuftiplier (1.03 or D,,
1.10)
6. D.,,is the value to enter for calibration if the D.,,,
=
x calibrator v-block can be mounted 90 degrees from the slot D,,,,
=
'
7. If the calibrator v-block must be placed a the
'
slot, a D.,, murt te calcuisted. Determine the muttiplier to use as follows:
Performed by (Name.Date)
'
Multiplier 1 is 1.03 = = > for Area Ratio,,, < =.05 Muttiplier 2 is 1.07 = = > for Area Ratio,,, > 05
!
Verified by (Namestate)
4-D,, = D,, x applicabie muttiptier
,
i
-
-..
._
.
47.306.02
>
,.
,
Att:chment 3, Page 2 of 2 012993
,
STEM DIAMETER REDUCTION DUE TO AXIAL St.OT
-
r
!
2. Fct 50tfD stem calibrations Csiculate new D,,for solid stem calibrations inside the -
c.
c. With NO ax!al slot = >.
transition area.
j D,., = D,,,,, (no corrections)
t
' b. Fct stems with an axlal slot = >
1. Distance,= 0.20 x D,.,, = 0.20 x
,
t 1. Calculate Area., of Keyway
[
'
Ares Key,, = Slot width x Slot depth Distance,=
2. Measure approximate distance between contartine
Area Key,, =
x
of V-block to the stems transition point = >
inches.
.
Ares Key, =
Determine multiplier as follows:
2. Calculate Ares,,, of Stem Area Stem = ( 3.142 x D,,,,8 ) / 4 Area Stem, = ( 3.142 x 8)/4 ( )-if measured distance (step 2.c.21is < =
'
Distance 1 then Multiptier = 0.88
Area Stem,, =
,
[ ]-if measured distance (step 2.c.21is >
,
Distance 1 then Multiplier = 0.98 3. Calcu! ate the Area P.atio,,
..
i Area Ratio,, = Area Key,,, / Area Stem,,,
'
Area Ratio,, =
/
3. Calcutate new D., as follows-tal For stem with no axial slot (D,.41 l
D.,.. = 0,,,, x applicable multiplier (0.88 or
.
Area Ratio,, =
,
0.9 81 5. Calcutate Effective Diameter D.,,
i D,,,
=
D.,,,, x ( 1-Atsa Ratio,,1 D,
=
x
-
D,,, =
x(1 I
D=
.
!
. D.,, =
(b) For stem with axial slot (D )
6. D,,,is the value to enter for calibration if the D,
- D, x applicable multiplier 10.88 or cal;brator v-block can be mounted 90 degrees from 0.9 81-
,
,
the slot
.
D,,,, =
x-t 7. If the cal;brator v-block must be placed pyrithe I
slot, a D.,, must be calculated. Determine the D,,,,
=
.l multiplier to use as follows:
Muttiplier i ls 1.03 for Area Ratio,, < =.05 Muttiptier 2 is 1.07 for Area Ratio,,, >.05 i
.
D.,,, = D.,., x applicable multiplier
,
Performed by (Name/Date)
!
!
D=
.x
~
'L D,,,, =
'
Verified by. (Name/Datel i
.!
r*
I I
h thkh
,
.
!
i I
~ ~ * *
....-n,
- ~.
-.
-
~~
~
_
,__.....
e s.-
-
-
-
.
P 47.306.02 EST AIAIL@l3 COM
- far""'""
VOTES POST TESTING STATIC OR DYNAMIC TEST RESUI.TS REVIEW t
VA1.VE NO:
.
DESCSFTION Dr&lGN STATIC TEST DYN AMIC TEST
,
TEST DATE TEST No.
~
'
WRNO.
+
-
,
.,.a,,
.Q:..
,
'
f, THRJST CALC
.
.
3ggn ;493
'
uEDP Cx.C i
sTru uAirRx
Ur (X 1C*)
ILBEPTY QATAl
STEM EFFECTIVE DIA.
tuBERTY DATA)
STEM NOM DIA.
- T.P.t.
- T.P.R.
CST THRUST MAX:VUM THRUST e
AVE. PUNN!NG FCRCE
,
FLOW CUTOFF THRUST CAUERATION i
EXTRAPOLATION ORIFICE ARE A j
[
MEDP (CLOSING)
'
-
PRES $URE AT CLOSING L MEDP T.S.C.
M;N:
MAX:
- (F O R p = _._)
.
T.S.C.
MIN:
MAX:
'
- (FOR p =_.J PACKtNG LOAD
,
'
MIN REQ *D THRUST AT FV =_. _
em 4.m en-a aer :
>
MAX ALLOWABLE THRUST an:w=e era acu
,
i
UMTING COMPCNENT VALVE ELEV.
,
CST TORCUE
.
ACTUATOR TCDQUE RATING
.
.
- - Data which should be documented during package preparation
.
i (
-.
.
47.306.02
,
Attachment 4, Page 2 of 7 022593 VOTES POST TESTING STATIC OR DYNAMIC TEST RESULTS REVIEW t-
.
A.
STATIC TEST REVIEW D N/A VALVE NO:
1.
IF CAUBRATED ON THREADS VMICH ARE IN A TOROUED CONDmON, THDJ TOROUE CORRECTION FACTOR (TCF)
WILL APPLY. OTHERWISE, TCF =1.0.
TCF =
BASIS:
2.
MATERIAL CORRECTION FACTOR (MCF):
MCF= UBERTY E4 =
=
.
TEST EN 3.
STEM EFFECTIVE DIA (SED) CORRECTION FACTOR (SEDCF):
SEDCF = UBERTY SEO =
=
TEST SEO 4.
RATE OF LOADING FACTOR FROM PREVIOUS TEST (S), ROL=
(IF ROL FACTOR HAS NOT BEEN PREVIOUSLY C
DETERMANED FOR THIS VALVE, USE ROL ASSUMPTION AS STATED IN MOV GU:DEUNE OF DBD A3100).
BASIS:
5. TOROUE SWITCH REPEATABluYY(TSRJ=0.
(IN DECIMAL FORM)
FOR TSS = 1 AND SPRWGP ACK < 50 FT48.. TSR. e 0.20 FOR TSS = 1 AND SPR;NCPACK > 50 FT-LB.. TSR= e 0.10 FOR 755>1 AND $PNNCPACK <50 FT48.. TSR so.10 FOR TSS> 1 AND SFNNGPACK > 50 FT LE., TSR= AC.05 6.
STEM LUBE DEGRADATION (SLD)=0.
(IN DECIMAL FORM)
BASIS:
7.
VOTES ACCURACY (ACC)= 0. _ (IN DECIMAL FORM) -INCLUDE EXTRAPOLATION ERROR IF APPLICABLE (USING CURVE FIT). INCLUDE ADDITIONAL ERROP. DUE TO SLOT IF APPUCABLE. REFERENCE VOTES MANUAL
,
BASIS:
,
8.
STATIC TEST CALCULATION OF ACCEPTBLE VALUES:
.
.
8.1 STATIC TEST CST THRUST'TCF'MCF'SEDCF'(1-ROL)*(1.SLD)*(1-(ACC8 +TSRrgur) 3
,
MIN REQUIRED THRUST-DESIGN PACKING LOAD + AVE RUNNING FORCE:
- (1-l'(1-l'11- (
8+
- )"*) =
+
-
- ,
=
8.2 STATIC TEST MAX THRUST'TCF'MCF'SEDCF'(1 +(ACC8+TSR')"') s MAX ALLOWABLE THRUST:
- 11 + (
8+
$"') s
8.3 CST TOROUE*(1 +TSR) s TOROUE RATING D N/A
- (1 +
1s 8.4 IF CRlTERIA IN 8.1, 8.2 OR 8.3 IS NOT MET, JUSTIFICATION AND ACTIONS REQUIRED OR TAKEN :
S
<
\\
-
--
- -... -,
.. -..
. _ _ _.
..
-
- _.
-
. -... -
.
,
...
.
.
47.306.02 i
Attachment 4, PaDe 3 of 7
-
022593
-
- VOTES POST TESTING STATIC OR DYNAMIC TEST RESULTS REVIEW f
B. DYNAMIC TEST REVIEW D N/A VALVE NO:
.
(
1. IF CAUBRATED ON THREADS WHICH ARE IN A TOROUED CONDITION, THEN TOROUE CORRECTION FACTOR (TCF)
WILL APPLY. OTHERWISE, TCF=1.0.
.
TCF=
BASIS:
-i
?
2. MATERIAL CORRECTION FACTOR (MCF):
!
MCF= (18EMTYTh =
=
TEST EN
\\
i
'
3. STEM EFFECTIVE DIA (SED) CORRECTION FACTOR!SEDCF):
SEDCf = UBERTY Se'O =
=
TEST SED 4. TOROUE SWITCH REPEATABIUTY(TSR)= 0._ (IN DECIMAL FORM)
l I
FOR TSS = 1 AND SPRNGPACK < 50 FT LS., TSR= t o.20 i
FOR TSS = 1 AND SPRWGPACK > 50 FT-LS.. TSR = 20.10 FOR TSS > 1 AND $PRINGPACK < 50 FT.LS., TSR = 20.10 f
FOR TS$>1 AND SPRINGPACK > 50 FT.LS. TER= a0hl
,
5. STEM LUBE DEGRADATION (SLD)=0.
(IN DECIMAL FORM)
BASIS:
'
!
e 6. VOTES ACCURACY (ACCl=0.
(IN DECIMAL FORM)-INCLUDE EXTRAPOLATION ERROR IF APPUCABLE(USING CURVE FIT). INCLUDE ADDITIONAL ERROR DUE TO SLOT IF APPUCABLE. REFERENCE VOTES MANUAL
!
BASIS:
.
s
,
i
h 7.
CORRECT PRESSURES FOR TAP ELEVATION:
._
___
_,
...
..
_.,
VALvt a
j
.
.
.
_
i
.{
D:wcsTREA&E
.
.
t
-
- - Data which should be documented during package preparation dp= (UPSTREAM PRESSURE - DOWNSTREAM PRESSURE) ecomerman crvatue =
l
!
,
8. CALCULATE VALVE FACTOR, F,
!
l F, = H F, - F,1/[A. * dp)] * TCF * MCF * SEDCF
!
l/l 11 *
F, = ti
-
-)
F, =
)
WHERE:
Fe= AVERAGt. "UNNING FORCE
-.{
F,= FLOW EUTOFF THRUST Ao= ORIFICE Ahi.A j.
dp= TEST DtFFERENTIAL PRESSURE
.
t
. _ _ _ _. _
_ _
.
' 8
'
,
,
,,,
.
. -
- - - -. - - - - - - - - - - - - - - - - - - - - - - -
o
.
.
'
47.306.02 j]
Attachment 4, Page 4 of 7
{Ih[ew]
022593 VOTES POST TESTING STATIC OR DYNAMIC TEST RESULTS REVIEW 9. CALCULATE RATE OF LOADING, ROL: (NOTE: TSS & SPRINGPACK MUST NOT HAVE CHANGED BETWEEN STATC &
DYNAMIC TESTS FOR THE FOLLOWING ROL CALCULATION [S) TO BE VALID.)
ROL = 1 -(ICST THRUST * TCF * MCF ' SEDCF),, /[ CST THRUST * TCF * MCF ' SEDCF),,=1 I
)
1/(
ROL = 1 - (
ROL = 1 - (
1/f I=1-ROL =
IF TEST D1D NOT YlELD AN ABSOLUTE CST THRUST VALUE leg.a bad *zero"), THE FOLLOWING MAY BE USED PROVIDED NO CHANGES WERE MADE TO THE VALVE OR ACTUATOR WHICH COULD HAVE AFFECTED RUNNING FORCE BETWEEN THE DYNAMIC TEST & STATIC TEST:
ROL = 1 -(ICST THRUST - AVE RUNNING FORCE)dtCST THRUST - AVE RUNNING FORCE)
)
1/t ROL = 1 - (
-
-
ROL = 1 - (
1/f I=1-ROL =
10. EXTRAPOLATION OF MAXIMUM FORCE (NOTE: THE FOLLOW 1NG LINEAR EXTRAPOLATION MAY NOT BE VAUD AT <
-
'
80%MEDP. IF <B0% JUSTIFY USE OF THIS ECUATION. A MULTI PRESSURE TEST PLAN MAY BE NEEDED.)
TEST dp 2: 80% MEDP O
YES O
NO
,
Fe = (TCF * MCF 'SEDCF ' FINAL THRUST * MEDP / TEST dp) + ((DIA m)' * n /4 * (P, - P.,,ll II
'
/
) + ((
l' * a /4 * (
-
F
={
Fe - (
/
)+(
- a /4 *
I=
+
,
,
Fe =
i WHERE:
Fe = EQUIVALENT MAXIMUM FORCE REQUIRED AT MEDP CONDITIONS
TEST dp = DIFFEREF % PRESSURE DURING TEST
~
P,= PRESSURE AT F
.iLATED CLOSING MEDP
,
Pan = TEST UPST-
. PRES $URE AT VALVE 11. DYNAMC TEST CALCULATION OF ACCEPTABLE VALUES:
11.1 DYNAMIC TEST CST THRUST'TCF'MCF'SEDCF'(1 SLD) * (1-[ACC'+TSRT3 m MIN REOUIRED THRUST-DESIGN PACKING LOAD,(AVE RUNNING FORCE - STEM DLA' * n 14 * Pun ).m * (1 + ACC)
NOTE:
IF * ACTUAL * TEPM IN ABOVE EOUATION IS s 0 THEN USE O.
- (1
) ' 11 - (
8+
Yr8) =
-
'
'
' * a /4 *
) * (1 +
+(
-
=
19.2 DYNAMIC TEST MAX THRUST'TCF'MCF'SEDCF'(1 +(ACC'+TSR')")s MAX ALLOWABLE THRUST i
- (1 + (
2+
211 /2) s
.
!
l s
.I
'
'
i
---.
.---...
---
.
. -. -.
...
... -
.
__
_
..
.
_
i i
r
-'[
47.306.02
"
l Attachment 4, Page 5 of 7 -
' j 022593 VOTES POST TESTING STATIC OR DYNAMIC TEST RESULTS REVIEW '
-
.
11.3 F cy< DYNAMIC TEST CST THRUST *TCF'MCF*SEDCF'(1-SLD) * (1 TSR)
i
,
<
- (1-
) * (1 -
,
_
t 4'
,
,
j 11.4 F,< DESIGN F,
<
-
.
11.6 CST TOROUE*11 +TSR) s TOROUE RATING
,
- (1+
1s
.
-
"
O
- 11.6. IF CRITERlA IN 11.1,112,11.3,11.4 or 11.5 t$ NOT MET, JUSTIFICATION AND ACTIONS REQUIRED OR
+
TAKEN *
,
v i
P
-
i f
?
'h i
I
-
.
,
'
,j
~
[
.F
-
.
Ia
-)
k
..
!
.
i
'
l
.
j
'
's
.
. :
r
^
i
'!
!
i
..
+
-
t-4 e
.
..... _ -
-. - _
_ _ _ _ _ _.
_...
-- -
__
_._i
-
_
_
.,
..
-
-
-
-
-
- -.
.
.
i
.
.
47.306.02 j
Attachment 4, Page 6 of 7
022593 VOTES POST TESTING STATIC OR DYNAMIC TEST RESULTS REVIEW f
.
,
COMPLETION OF STATIC OR DYNAMIC EVALUATION - 0 STATC aDYNAMc nBOTH
-
I
VALVE NO:
,
Performed by (Name/Date)
i
)
Verified by (Name/Date)
i i
i REMARKS:
.
.
.
.
?
!
t
.
.
e
,
E
'
,
i
?
W I
+
I
!
I
'
f
- '
.
"
L
_
.
.
_ _ -.
.
.
,,..
.. - -.
- -... :--. --- -
__
. -....
.
._
t
.
.
.
47.306.02
,
Attachment 4, Page 7 of 7
'
,
022593
,
"
VOTES POST TESTING STATIC OR DYNAMIC TEST RESULTS REVIEW
'
!
!
REMARKS:
,
,
t
5
?
?
.
k
>
i.
,
e i
a
,
s
'
t
!
..
47.306.02-t
'
.
Enclosure A; Page 1 of 3
'
090192
t VOTES CABLE CONNECTIOfJ GUIDE
i Breakout Box Connections
-
l t
Connector #
Cable / Component J1 Cable CB1-100, Votes Force Sensor -or-
!
Cable CB1-100, Auxiliary Sensor
,
J2 Cable CB17-100. DC Switch Probe Interface Box Power Line -or-
[
Cable CBS-100, Load Rod -or-
,
,
Cable CB13-100, Accelerometer -or-
Spare Channel j
J3 Cable CBS-100, C Clamp or mini C Clamp -or-
,
Cable CB7-100, U Clamp to Proxiineter Clamp -or-l
Cable CB17-100, DC Switch Probe interface Box Power Line -or-
Cable CB12-100, Auxiliary Sensor -or-
Spare Channel
i J4 AC Switch Probes (2) -or-
[
Cable CB16-100. DC Switch Probe / interface Box
J5 AC Switch Probes (2) -or-
Cable CB16-100, DC Switch Probe / interface Box
s l
J6 Cable CB15-100 AC Motor Current Probe -or-
Cable CB15-100. DC Motor Current Probe r
i J7 Cable CB14-100, Sound Powered Headphones i
JB Cable CB3-100, to Signal Conditioner -or-
Cable CB9-100 to Signal Conditioner
-
L
Signal Conditioner Connections j
J2
-
Cable CB11-100, Computer Power Supply l
J3 Cable CB9-100 to Breakout Box
,
Cable CB3-100 to Breakout Box
,
J4 Cable CB4-100, Main Signal Cable to Computer Headphone Jack Cable CB14-100, Sound Powered Headphone J1 Cable CB10-100, Power Connection (120V,60 Cycle) (LAST)
e
!
Only one cable may be hooked up at any one time. Any Cable / Component listed may be
connected to the Breakout BodSignal Conditioner at any one time depending on the testing configuration / task.
!
,
t
.
.
.
...-
...
.
.
.
.
._
!
,.
.
t 47.306.02 Enclosure A. Page 2 of 3
~!
VOTES CABLE CONNECTION GUIDE
.
090192
-
.
-
'
.
I
.
Ac s.=
.
,
.
.
_
I.l i
,
_
_
l
-
,
i
.
-
-
-
.
J
-
<
,
I s
!
-
--
-
.
<
.
~
i
O
.
l 1 1 1 1 a
o
.
.i
.
,
_
,
_
,
.
__
,
,
,
.
8 l
!
.
- _
=
-
}i
.
- - -
i
,
,
.
.
__
_.
Al
-
.
.
I i
.
.
.
I
-
%
g
_
.
,.
,
.
.
.
,
_1
=
,
,
,
.
.
.
c
. -,.
.
,
P e-y f
.
.
_
._
.
-
-
4.
i i
a 4,
.
L J
3
..
I i
i I
l i
i i
j
-
.
.
O O
O O
O O
O
<,
I j
j i
!
]
}
If I
I I
I i
g
1
=]
l. -
1
,
,
_
__
_
__
__
__
--
--
__
-
_
_ _
---
-
.
.'
-
i
.... _.
-
-
.
__
.. _ _
.
,
.
i
'
.
'
I 47.305.02 e
'
Enclosure A. Page 3 of 3 090192
.
VOTES CABLE CONNECTION GUIDE
!
'
oc sex
-
ij
-
-
,
I I
e
1 l
g
'
-
-
e
-
,
,,
._
__
-
iO
'
j j l i ao
-
-
mas M
, IEEN
,
,
,
.
3
l 1 _!
}
.
- - -
=
,
.
.
,
,
.
.
!
.
,
-
,
_____
i i
i
.
.
4
+
,
.. _.
.
_
g
,
,
-.
-
i.
-
-
-
-
I, ;
e e,
i,
>
.
a i,
I, j
i.
d-i i
i.
j h
,
-
I
'
jII
..
~
!!
i i
i i
i
'1
.
,
,
,
.
i i
i i
-
-
,
,,
-
.
o a
o oa o
o (
__
l i. i. i. i
!
t i
i
!
1 i
,
s s
.
>
>
u
.
.
_L
.
__
_
. _. _.
. _.
- --
_,,,,, _,, _,, _.
.
.
.
..
.
.
.
~ 47.306.02
-
,
Enclosure B, Page 1 of 1 i
.
012993
'
STEM TRANSmON REGION
-
,
.
!
&
Q1 G.
i
-
-
.
m
!
--
.
Q.2. %*
R
!p.
O'
I
.
., -
I
. L m.e
Yu r,
y~ '
y g
,
_
-
e
,,e i
-
-
i
-
u
-
i g__,
.y b
.- ;
x;
-
,
.
Gy{$. ?~
4 x! - :
%
,a.+.-
G N
. - -
y
~-..a.-
-
!
la
.
-
.
y q
W i m, j= <"
r;
.
ct'&,i
. -.
,
-
,
Twtan Y Os Oneise
.*
- 3r E
.
y" !
Aspe
!
i
.r ffh 7,- m %
N i
-
-
c.,,,;,
pm w%%O
-
%
w w
.ug,
,
,
-
.w u
<
wIf *[
',
- 1 by : Ap-,.m p glig.:
,<
.n
,
w alw ai um n -.-
.
-t
[#g-c@%g m
-
r im
'-
.,
s ilN. s
-
5.T
- ' ' " -
pg_@e t
N.
.
p,i,d s
e. a
-
<
-
.
....
b
"hi Y.uwoman umb:
'
?-
Lit yy<
,
s
.,,w,-
..
.
i
.
..
.[4t!T'.fl!
glEE.fE!!!
-
'
-
.
g
%.
-
.
,
.
HT AVAIBI5 00Ff
-
-
,
l (.
.
.
!-
'
_.. -
_ _. _.
_
_
. _,.
,_._
.
A k
4 s
5F
[=
,
EI
-
.
-
-
.
l j
-
e RE Rh
. g.1
.
l s
i
,"
'
nJ.
-
t
.
f g
-
l I
I
,
'
~g
'
J I
E R e, K t
I w
EEV Of f
'
4*-
i 2$3 h
-
g
'N:
t
~
.
a
~
s us i
.
-
x E
I I
E, k,.
i
"3 i
y
_.
>
,
$
i
-
I
g!!sN-Ir a
-
a y
lisi ll l
-
<
1 p!
'
-
x
>
!;
x
'
l4
!I
{5 r
g h
~
E
!
f gI t
~
,
gj ag
h.
.
g
,
$2 i
Ej I
8
ili E
i
'
.
i
,
k I
,
h
<f
I I
sf*I I
i
.
-
E E5
.
I
- i!
$
i m
g
'
551
'
,
~
,
I
'
E
~
I, w[
!
I j
,
'
,g Ey
,
,
r t in I
12 h,
-
'~
I
i i
=
ga (
E
s1
.
l
.
,
e
.
_
..
-
- _ _ _ _ _ _. _ _.
l 47.306.02
{
Enclosure D. Page 1 of 1 042393 SEATING CURRENT CAPA" CITY EXCEPTIONS
,
BASIS:
Item 14 of Attachment 2, * Degradation Data Sheet.* looks at the peak seating / unseating current to verify that it does not exceed 60% of the nameplate locked rotor current. This criteria is acceptable for DC and AC motor operated valve motors with the exception of those listed below:
1.
Seating Current Limits (ref. NEPJ-93-0062)
Valve PIS No.
Acceptance Criteria (Amps)
E4150F003 100 l
E4150F006 160 E4150F059 3.4 E5150F008
E5150F095
83105F031A 47.2 I
J 2.
Unseating Current limits (ref. NEPJ-93-GiO6)
Valve PIS No.
Acceptance Criteria (Amps)
E4150F003 100
'
E4150F006 160 E4150F007 212.9 E4150F059 3.4 E5150F008
E5150F095
B3105F031A 47.2 E1150F008 214.7 i
.
e l
-
h I
-
-
- - _ - _ _ _
.............
-
-
I
.
_
f 47.306 02
.
-
Enclosure E. Page 1 of 2
042393 PLANNING AND PREPARATION
.
QUALIFICATION REQUIREMENTS
Individuals performing testing shall have completed VOTES training / certification or shall be j
'
under the direct supervision of individuals who have received the training / certification.
individuals performing evaluation of the test results shall have completed VOTES
- training / certification and shall have received training in MOV signature analysis (VOTES MOVATS or equivalent).
SUPPORT RECOMMENDATIONS Operatio'ns personnel, as needed, to operate isolation valves.
PLANT / SYSTEM REQUIREMENTS
As determined by the NSS or his designee who signs on the Work Package / Procedure.
ENVIRONMENTAL REQUIREMENTS
Use of computer / printer should be limited to areas which are not contaminated.
MATERIAL AND EQUIPMENT REQUIREMENTS i
M&TE:
1.
Cahbration Devices (C-clamp. U-clamp as appropriate.
',
etc )
.
Other Equipment:
1.
Portable Computer l
2.
Printer (optional)
3.
Breakout Box
4.
Signal Conditioning Box 5.
Sound Powered Headphones
'
6.
VOTES System Cables per Enclosure A
- '
7.
Approved Stem Lubricant 8.
Ruler or Micrometer
9.
Flashlight 10.
Screwdrivers
,
-
11.
Approved Degreasing Solution
!
'
12.
Adjustable Wrenches 13.
Gaskets / spare parts as appropriate
_;
14.
For DC valves:
DC Switch Probes / Fluke Current Probe
DC Switch Probe Interface Box
!
P-3500 Portable Strain Meter i
D. C. Voltmeter l'
D. C. Ammeter 15.
For AC valves:
j AC Current and Switch Probes
AC Ammeter (Optional)
16.
Multimeter (ohms and AC-DC volts)
!
IT!/MOVATS (TST) " Torque Switch Transducer"
ITl/MOVATS (TMD) " Thrust Measuring Device'
,
i i
__
'
o o
47.306.02 Enclosure E. Page 2 of 2 042393 i
PLANNING AND PREPARATION f
r
!
'
SOURCE REFERENCE:
[
Use References:
o 35.306.006 l
o 3511M.009 o
35.306.003
F Other References:
o HENZE - MOVATS Advanced Signature Analysis Student
!'
Handbook o
VMC2-24.7 - VOTES Valve Operation Test and Evaluation
!
System Users Manual o
B & W Valve Operation Test and Evaluation System
!
Training Manual
END v
,
[
.
!
.
!
.
,
f L
t i
f
,
!
!
i
!
l
.
,
I
,
._
_ _.
.._
.
_ _
Attachment #11 c3o507 DTC: VCMOV FILE #: 1804.03 Page 1 of i
a MOV POST-TESTING REVIEW--CLOSING DIRECTION TEST PIS/
,
,
V#
,
VLV/ACT. SIZE, TYPE & DRIENT:
t
-
.
I DESCRIPTION DESIGN STATIC TEST DYNAMIC TEST t
+
-
'
>
~~.
TEST DATE fBh 4 V M 4di.
.
.s O; s
,
-
$ l w $ d h e " 3fi
.
TEST NO.
,
~;b::B W :ds 45
,
,
,n
'" t *.e%s:s ;;c
'
WR NO.
- +'-s,
-
^
.s Y.a JXydf j WT
>h Mn.:
- 5
.
M W jg' g' + m($}6..- u g.
kyg g g f3j Q'M':ssjlcen;"$4 CQ,.*3'fji%-h >.oM. %
..
!
THRUST CALC
amemu em4% ~
nemn.mg:wap:n.s
~
eer - -
,
r ~nmm.ww v,
~
& W:w L^
AN.Gwaqc..:!e;
@gh%j
!
%RQPT&,gM<M;%yrdw-:%:t*-y?99
! sq.ifgliki /
.
Q Q:m:wwc @, w e %a c.a$
MEDP CALC
ws;u.a.;::M%,nng v,:pu 5 d
naen v,n:
<,w
,
.,;re.;
m m
,
.
,
STEM MATEPIAL
,
- E/r (X 10 )
r I
(UEERTY DATA)
,
>
STEM NOM DIA.
.
a
'
T.P.I.
,
l
T.P.R.
i
l STEM EFFECTIVE
(UEERTY DATA)
,
l
l DIA
.
-
i
-
e
,.
gia
' * :#
b :2 CST THRUST
,
e.s
., _.
-
!
"
,
MAXIMUM THRUST e""
+
I
..,.
~,
!
'
45 NM[$EE j
AVE. RUNNING
>
i AI*D5$
E :.;?
i
'
I FORCE
.$
OfDO l
'
FLOW CUTOFF e
e u"p w; '~
4,
,
-
< se
' -
>
- -
-
ftn,
nd'
THRUST F
(k:'$
^
'[ Mk
,
,
,
,
- V
.
l l
l CALIBRATION
,
j
_
,
i
- EXTRAPOLATION
-
i 1:$%;Q-:+
"
-W..
ORIFICE AREA
93 J* - Th:
.i s.
.
,
'
- Qy8 y
..%.---
""
x
?
- -,...,.
,,,,
t f
.,...,
- $'fg1
- P *
' '
~
m-
.
MEDP (CLOSING)
(
Q, ' * ff;
~ &.
W
..%
.,.
a Qjn M.:m,MA ;,M;g;m
>
-
a., P
s
'
PRESSURE AT
- M..
-;n
> y-c.
,-
,.9 ;.
- 73._, m
,
ey _ %
s'
ie I
(CLOSING MEDP
,
.
T.S.O.
MIN:
MAX:
j
- (FOR p=
)
.
t t
T.S.C.
MIN:
MAX:
- (FOR p=
)
l
.
-
-
.
to -
,e 2.s.
%
l PACKING LOAD sym " ' an s@
1WE *n,
%#r: ;J i
.
!
- s m
a,
..
y,
_m.g
'.'
>
d.w
,'
N:~ M-C, i. N,
a
'
s
- MIN REQ'D
-.; :
THRUST AT
- W Wr 'sM. s w
.
" %-
a.-
_a m : m> e-
' ~x9
,
m
,
- m,;.
rw-r
',
'm
>" w m
m
>
,
s,.
i TV=
naa m.co m ec2
.
'
,
n.
...
,m
-
' M,
<,1
!
i
' ~.
,
T^.7
, m.
..
,
,..,., l
-
"
FAX ALLOWABLE
.
a-m.
a"
! t*
w n2 s
!
THRUST axamas =m eca ar - "
,
i
<
. ::n W L
- ; :
~
4:-
'
'
-
+
-
LIMITING
~
wp
~
-.
u.
,
- , ;.91.
u
<
,
>
COMPONENT
,
,
l a
,
. _ _,
,
_. -
,
.
.
,
-_
_
Attachment #11 saoso7 Pcga 2 of
...
MOV POST-TESTING REVIEW--CLOSING DIRECTION TEST PIS/
'
I DESCRIPTION DESIGN STATIC TEST DYNAMIC TEST
"
s ~ xu ;;+3 su c
- w, m o
VALVE ELEV.
MCE2nd: AC/
ad1t Onahx?r
-
n.~
'
i m
.
'
~i
'
-
@
jhi/lh h l h k N N O M [s :
!
ACTUATOR
TORQUE RATING stagersssi!6 c,W %
WesM - ", -is
,
!
,
A.
STATIC TESl_}tEVIEw O
N/A 1.
IF CALIBRATED ON THREADS WHICH ARE IN A TORQUED CONDITION, THEN TORQUE CORRECTION FACTOR (TCF) WILL APPLY.
OTHERWISE, TCF=1.0.
>
TCF=
BASIS:
2.
MATERIAL CORRECTION FACTOR (MCF) :
ggy, LIBERTY Elv,
,
TEST E/v i
3.
STEM EFFECTIVE DIA (SED) CORRECTION FACTOR (SEDCF):
SEDCF, M ERN SD,
,
TEST SED 4.
RATE OF LOADING FACTOR, ROL=
(IN DECIMAL FORM)
.
BASIS:
5.
TSR= TORQUE SWITCH REPEATABILITY =0._
(IN DECIMAL FORM)
i FOR TSS=1 AND SPRINGPACK <50 FT-LB.
TSR=10.20
,
FOR TSS=1 AND SPRINGPACK >50 FT-LB.
TSR=10.10
,
FOR TSS>l AND SPRINGPACK <50 FT-LB.
TSR=10.10
,
FOR TSS>l AND SPRINGPACK >SO FT-LB.
TSR=10.05
,
.
6.
STEM LUBE DEGRADATION: SLD=
,(IN DECIMAL FORM)
!
BASIS:
7.
ACC= VOTES ACCURACY =0.
(IN DECIMAL FORM)
INCLUDE EXTRAPOLATION ERROR IF APPLICABLE (USING CURVE FIT).
INCLUDE ADDITIONAL ERROR DUE TO SLOT IF APPLICABLE.
REFERENCE VOTES MAliUAL.
BASIS-
!
.
.
Attachment #11 s20so7 Paga 3 of
,
MOV POST-TESTING REVIEW--CLOSING DIRECTION TEST PIS/
., _
8.
STATIC TEST ACCEPTANCE CRITERIA:
,
8.1 STATIC TEST CST THRUST *TCF*MCF*S5DCF* (1-ROL-SLD-(TSR +ACC ) any
2 h MIN REQUIRED THRUST-DESIGN PACKING LOAD + AVE RUNNING FORCE:
h
O YES O
NO O
N/A 8.2 STATIC TEST MAX THRUST *TCF*MCF*SEDCF* (1+(TSR +ACC ) r2)5 MAX
2 ALLOWABLE THRUST:
S O
YES O
NO 8.3 CST TORQUE * (1+(TSR + TORQUE ACCURACY 2)tr2 5 TORQUE RATING
$
$
O YES O
NO O
N/A 8.4.
IF NO, JUSTIFICATION AND ACTIONS REQUIRED OR TAKEN :
!
s
!
a
-
P I
!
I
?
'
,.
\\
.
Attcchment fIl sacso7 Paga 4 of
&
.
MOV POST-TES7ING REVIEW--CLOSING DIRECTION TEST PIS#
B.
DYNAMIC TEST REVIrw O
N/A
<
1.
IF CALIBRATED ON THREADS WHICH ARE IN A TORQUED CONDITION, THEN TORQUE CORRECTION FACTOR (TCF) WILL APPLY.
OTHERWISE,
-
TCF=1.0.
TCF=
BASIS:
2.
MATERIAL CORRECTION FACTOR (MCF):
I' =
MCF= U
'
=
TEST E/v 3.
STEM EFFECTIVE DIA (SED) CORRECTION FACTOR (SEDCF):
SEDCF=bIBEM SfQ,
,
TEST SED
4.TSR= TORQUE SWITCH REPEATABILITY =0.
(IN DECIMAL FORM)
FOR TSS=1 AND SPRINGPACK <50 FT-LB., TSR=10.20 FOR TSS=1 AND SPRINGPACK >50 FT-LB., TSR=10.10 FOR TSS>l AND SPRINGPACK <50 FT-LB., TSR=io.10 FOR TSS>l AND SPRINGPACK >50 FT-LB., TSR=do.05 5.
STEM LUBE DEGRADATION: SLD=
(IN DECIMAL FORM)
BASIS:
6.
ACC= VOTES ACCURACY =0.
(IN DECIMAL FORM)
,
INCLUDE EXTRAPOU. TION ERROR IF APPLICABLE (USING CURVE FIT).
INCLUDE ADDITIONAL ERROR DUE TO SLOT IF APPLICABLE.
REFERENCE
,
VOTES MANUAL.
BASIS:
i
.
,
7.
CORRECT PRESSURES FOR TAP ELEVATION:
DESCRIPTION MEASUREMENT CAGE #
TAP #
TAP EL.
PRESEURE AT VALVE
! UPSTREAM
! DOWNSTREAM
+
+
+
,
__
dp=(UPSTREAM PRESSURE -DOWNSTREAM PRESSURE)coRREcTro com11rVAT10N" i
-.
-
-
..
-
htfachm:nt #11 saoso7 Pago 5 of
'
,
NOV POST-TESTING REVIEW--CLOSING DIRECTION TEST.
PIS#
.j
.i 8.
CALCULATE VALVE FACTOR, Fy
.j
.
Fy= (F -F ) / (A *dp) * TCF*HCFoSEDCF
1 o
'
,
WHERE F = FLOW CUTOFF THRUST i
,
F = AVERAGE RUNNING FORCE
Ao= ORIFICE AREA dp= TEST DIFFERENTIAL PRESSURE L
9.
CALCULATE RATE OF LOADING, ROL:
NOTE:
TSS & SPRINGPACK MUST NOT HAVE CHANGED BETWEEN STATIC & DYNAMIC TESTS FOR THE FOLLOWING ROL CALCULATION (S) TO BE VALID.
ROE =1- ((CST THRUST *TCF*MCF*SEDCF) srAncCST TH
=
i
\\
IF TEST DID NOT YIELD AN ABSOLUTE CST THRUST VALUE (eg.a bad 'zero'),
,
THE FOLLOWING MAY BE USED PROVIDED NO CHANGES WERE MADE TO THE VALVE OR ACTUATOR WHICH COULD HAVE AFFECTED RUNNING FORCE BETWEEN THE DYNAMIC TEST & STATIC TEST:
i ROL-1- ((CST THRUST-AVE RUNNING FORCE) srAncCST I
,
'
10.
EXTRAPOLATION OF MAXIMUM FORCE NOTE: THE FOLLOWING LINEAR EXTRAPOL). TION MAY NOT BE VALID AT <
'
80%MEDP.
17 <80%, JUSTIFY USE OF THIS. EQUATION.
A MULTI-PRESSURE TEST PLAN XAY BE NEEDED.
TEST dp h 80% MEDP O
YES O
NO r
Fa= (TCF*MCF*SEDCF*F *MEDP/ TEST dp) + (DIAG 7m ::/4 * (P -Pnst) ) *
e
1
=
!
o
';
=
'
FLOW CUTOFF THRUST WHERE F
=
i F e = EQUIVALENT MAXIMUM FORCE REQUIRED AT MEDP
,
CONDITIONS TEST dp = dp DURING TEST
'
P = PRESSURE AT CALCULATED CLOSING MEDP i
Pnn= TEST UPSTREAM PRESSURE AT VALVE
&
.d i
e I
t-
,. -
Attachment #11 saoso7
.Page 6 of
.
...
MOV POST-TESTING REVIEW--CLOEING DIRECTION TEST PIS#
- 11. - DYNAMIC TEST ACCEPTANCE CRITERIA:
11.1 DYNAMIC TEST CST THRUST *TCF*MCF*SEDCF* (1-SLD-(TSR +ACC )sa) - 2-MIN-
2 REQUIRED THRUST-DESIGN PACKING LOAD +(AVE RUNNING FORCE-STEM
lDIA 3774 p7m) Amg* (1+ACC)
NOTE: IF " ACTUAL" TERM IN ABOVE EQUATION IS S O, USE O.
m D
YES O
NO 11.2 DYNAMIC TEST MAX THRUST *TCF*MCF*SEDCF*
(1+(ACC +TSR )sa)$ MAX ALLOWABLE THRUST
2 s
s O
YES O
NO 11.3 F m p< DYNAMIC TEST CST THRUST *TCF*MCF*SEDCF*(1-SLD-TSR)
<
^
<
O YES O
NO 11.4 Fv< DESIGN Fy O YES O
NO 11.5 CST TORQUE * (1+(TSR + TORQUE ACCURACY )1a g.10RQUE. RATING
2 S
- O YES-O NO O
N/A-11.6.
IF NO, JUSTIFICATION & ACTIONS REQUIRED OR TAKEN : -
-
%
Attachment #11 s30507 Page of MOV POST-TESTING REVIEW--CLOSING DIRECTION TEST PIS#
REMARKS:
-
,
i
!
-
l
-
l l
J
Attachmant #11 sacso7 Psgm of n
.s s
MOV POST-TESTING REVIEW--CLOSING DIRECTION TEST PIS#
APPROVAL OF EVALUATION
.
EVALUATION PERFORMED BY:
PRINT / SIGNATURE DATE EVALUATION REVIEWED BY:
PRINT / SIGNATURE DATE EVALUATION APPROVED BY:
PRINT / SIGNATURE DATE
.
-