IR 05000324/1990022
| ML20055H431 | |
| Person / Time | |
|---|---|
| Site: | Brunswick |
| Issue date: | 07/10/1990 |
| From: | Blake J, Economos N NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML20055H430 | List: |
| References | |
| 50-324-90-22, 50-325-90-22, GL-84-07, GL-84-7, NUDOCS 9007260198 | |
| Download: ML20055H431 (9) | |
Text
_
-r-e
'
'
^
.
,
+.
>
nn magt, DNITED STATES '
i
- ~
- 4
'o NUCLEAR REGULATORY COMMISSION r
,
,
f'
~ REGION 11 3'
J
- _
'101 MARIETTA STREET,N.W.
'
ATI.ANTA, GEORGI A 30323
-
g,.....;/
,
,
.
Report Nos.:
50-325/90-22 Land 50-324/90-22 Licensee:
Carolina-Power and Light Company!
P. 0; Box 1551
,i
.
Raleigh, NC 27602-Docket Nos.: 50-325 and 50-324 License Nos.-
' Facility Name:
Brunswick 1 and 2-
Inspectio o u te -
un 11-15, 1950 j
Inspector._
7/ o o-N c
my
.,/
'Date Signed
_-j.
Approved by.
/.
<
'
9v J.
Take, Chief
'Date Signed
.
M te ials and Processes Section i
ng 'eering Branch
.i Division of Reactor Safety i
l SUMMARY
._i Scope:
This routine, unannounced inspection was performed to provide the inspector the
' opportunity to meet with the ~icensee and discuss planning and technical issues y
associated with the recirculation system' inlet safe-ends, cort-spray - system safe-ends and associated piping. replacement. The modificationiisLscheduled for the upcoming September refueling outage.
Results:
!
By document review, and through; discussions"with management.and key. technical
'
personnel,- the inspector. ascertained that the : licensee is movi_ng' forward.in-
- 3 this project following the guidelinei ofj Generic -Letter' 84-07. : Accordingly,
the licensee has generated controlling documents which address organization
'i structure / responsibilities; design, radiation. protection,.'and 7 engineering
}
specifications for procurement, pipe installation and: testing activities, ~ In'
i the areas' inspected, violations or deviations were not' identified.
i
"
'
9007260198 900713 PDR ADOCK 05000324
Q PDC i
,
,;
n.
mg y
a
-^b
_.
.
,
.. -
e
>
.
(
-.
i
)
. REPORT DETAILS-
'i
5:
1.
Persons Contacted j
h Licensee Employees
.
-!
- W.- J. Dorman, QA/QC Manager
'
J.:L. Harness, General Ms BNP
- R. E. Helme, Manager, Teci Support.
,
- J. R. Holder, Hansger, Outages..ad Modifications
- R. -Johnsen, Project. Manager, Recirculation Piping
-
- T. Jones, Regulatory Compliance Specialist
- D E. Moore, 'ricnager, Engineering NED'
t T. Pitchford, Lead Engineer, Recirculation Projects L
- R..M. Poulk, Supervisor Regulatory Programs-
- R. L. Warden, Manager, Maintenance
'
Other licensee employees contacted during -this inspection i ncluded engineers, technicians, operators, mechanics, and office personnel.
Other Organizations ~
'
General Electric Nuclear Plant Services-R. Markley, Shift Supervisor NRC Resident Inspectors
- W. Le'vis, Resident Inspector
,
- D. Naison,. Resident Inspector I
- Attended exit interview l
l 2.
Replac c ent of BWR Recirculation Piping-(2512/13)
L a.
Design Changes and Modification Program-Unit-1-(37702)
Replacement of thel Brunswick' Plant Unit-l' Recirculation Systemiinlet
'
safe-ends,12-.icch riser piping J and core spray safe-ends : and ' iping p
is :the result of c CP&L 'conmitment to the Commission (NRC) - Letter,
No. NLS-89-192, dated June.28, 1989, from.'R. A. Watson to: the
'
Commissiom NUREG 0313,~Rev.~ 2,
" Technical Report : on ~ Material-
-
Selection and Processing Guidelines for BWR Coolant Pressure' Boundary Piping" has been evoked for the selection of. replacement materials.
Installation, weiding and nochining requirements are those=
reccmmended by the Electric JPower Research Institute.(EPRI),. and will be adhered to, 'as much ; as possible.
Followint completion of. the~
L recirculation pi.pe replacement modifit.3 tion.of Unit-2, in-February'of i1990, the licensee began preparations for the same modification in Unit-1.
As in Unit-2, _ the primary purpoce for the recirculation
,
f
=
e
,-
e
-
e w
,, e
-
--y-e t-
--
--t y
L y
,
.
-$
.
.
system and core spray system safe-end/ riser pipe replacement plant modification (PM), is to replace existing intergranular stress corrosion cracking (IGSCC) susceptible material,.within the reactor coolant rtcirculation piping system, with ~1ow carbon, corrosion resistant austenitic stainless steel type 316 NG material-and thereby mitigate the main cause for IGSCC-on this system.. The project is
-
essentially a direct replacement effort of, existing; components withL the exception of using scamless, ~ induction bent risers and. an improved -design safe-end ' which eliminates the. thermal sleeve attachment weld.
.The controlling documents for_ the subject.
modifications are PM_ #89-092, Core Spray- (CS),;-Safe-End Replacement; and PM #89-095, Reactor Coolant Recirculation -(RCR), System Inlet
Safe-Ends / Riser Replacement.
More specifically, the scopegof_these-j modifications will require the following activities:,(A) removal, by j
machining, of weld overlays on seven safe-end to recirculation-inlet j
nozzle (RPV Nozzle N2)- welds and two safe-endLto core spray inlet
'
nozzle (RPV nozzle NS) welds (nine - nozzle.. overlays : total);
~(B) removal and replacement of recirculation system-N2 nozzle safe-ends and twelve inch inlet piping; (C) removal' and replacement of core spray system NS nozzle safe-ends and _ a portion of the piping.
(piping will be replaced with a forged. carbon: steel transition piece).
tnis 'will standardize. the-design with-Unit-2;. (D) removal,. by
-
machining, of the original Inconel ' 182 RPV nozzle cladding and butter, including removal of: the flaws and. repair, :if required. of
!
the low alloy steel:(LAS),. nozzle base material, with replacement of
!
the cladding and butter with stainless steel (309L) weld material.
. A'pplicable ASME/ ANSI codes and standards including = code [ case (s)
invoked for these modifications are as follows:
ASME B&PV Cede,Section II, 1986 Edition with 1988 Addenda --
I ASME B&PV Code, Section. IX, Latest. Edition _ and. Addenda, at time of. procedure and performance qualification.-
ASME B&PV Code,Section XI,1980- through W81 Addend. Code Case N-432 ASME B&PV Code,Section V, 1986 Edition I
a AWS D1.1 - 1988 Edition.
,
ANSI N45.2.1-1980 Cleaning of Fluid Systems and L Associated -
. ;
Components for Nuclear Power Plants Licensee issued specifications; applicable to this modif,1 cations -are
.as follows:
a 248-153 CP&L-Specification for Precurement of ASME III, CL'1'
Stainless Steel. Pipe & _ Fittings
'
,
ze8-156
" Design Spbcification for LReactor _ Coolant
,{
Recirculation System N2 Nozzles, Safe Ends and --
'
Thermal Sleeves."
i
,
q-l i i p
c
,
Y 4
d
,G-de
_
a.
g
. s-.
'
,
.j
,
.
>
.
-..
.
<. 4 L
1
,
l
..
.
248-157 Design Specification for ' Core : Spray : System N5 -
j
Nozzles, Safe-Ends Thermal ~ Sleeves and Transition
Pieces..
.
248-158 CP&L-Specification for - Field Replacement of j
Reactor' Coolant-Recirculation' System Inlet
?
Safe-Ends and Piping i
i L
CPL-XXX-W-01~
. elding Filter Metals for NuclearL Power
'
W
......
l.
. Plants.
'
Following is a tabulation _ and a. summary of exis' ting. materials. and replacements for the subject. modification (s)r Comy w t Existing Material-Replacement Material Saft~u ' (core Typec316L-
' Type 316L NG.SS i
spiar'
N5 Nozzle Cladding Inconel 82'and 182 Type 309L SS
,
Transition Piece (Pipe) SA-333 Gr. 6-SA-350 Grade LF2'
'
Discharge Riser Type 304 Stainless
~ Type 316 NG SS-Steel-(SS)-
Safe-ends Inconel.600 Type 316 NG:SS (recirculation)
,
a Thermal' Sleeve Inconel 600
. Type.316 NG SS'
Extensions N2 Nozzle Cladding - Inconel 82 and 182-Type 309L SS-Weld Metal Inconel.Inconel 82:ano 182,--
. Type 308L SS Type:308L SS,,308'LSS
' and Incone1~82 (Th'ermal-Sleeve'
-
only)-
t ER705-2'or'E7019-ER705-2, ER705-3.or E7018 CS-b.
Pipi_ng Configuration
..
.(1) Reactor Coolant Recirculation System Piping'
Ic The - RCR system pl. ping configuration wi.11 ' remain essentia11y'
.
unchanged as.a tesult of PM #89-095; However,la few minor i
details will change and are discussed below.
L l
,
,
T jb-
,,.
,,u
=N-:
'*
a
):
'
.,
.
,
'
.
.
>
I
'
,
4-
\\Y
.
..
,
L The replacement-safe-ends will include an integrally forged
'
thermal sleeve extension : which _ will improve the stress profile in the:" tuning fork" region.
The new design will.
.
,
also eliminate the existing creviced condition. which has contributed to cracking 'at the thermal sleeve 1 attachment
weld.-
~
L
The ten (10)' existing risers will be replaced with
-
induction, bent seamless piping, thus. eliminating l ten (10)-
welded elbows' and, ; correspondingly,-
twenty.. (20)
L circumferential welds. - The: replacement risers will 'also. be -
,
l slightly longer in the-horizontal plane. than the existing.
>
risers and will eliminateL the " safe-end"' extension"i spool pieces in the' existing system.
Since the replacement l
risers are seamless, the number of longitudinal weld seams l
in the RCS system will also be reduced.
- A summary of welds that will-be eliminated by this project is as follows (excluding differentia 1' pressure tap welds):
'
l l DESCRIPTION OF WELDS TO BE ELIMINATED INUMBERll
I l-l-
! Circumferential:
Riser to Elbow l
20. l l
l l
l Circumferential:
Safe-End to, Safe-End Extens-l = 10 l
L I
I I:
l Circumferential:
Thermal Sleeve to Safe-End:
l
.10- -l:
,
-l l-l-
"
>
l Lcngitudinal:
Pipe
20 l
-[
l l
I a
l Longitudinal:
Elbows l
l-i
,
I
_
TOTAL-1.-80 -l
I
'
L l.
L I
I l
l l
A decrease in' total '. number -" welds.is: a design improvement
since weld joints (including heat-afft :ts zones) L are more.
,
E susceptible toIGSCC -than other aren n no sensitized-
'
austenitic ~ stainless-steel; and Inconel piping systems.
Therefore,.this change improvesElong ter
' liability of the CS
,
system.
The existing RCR system discharge risers have differentia 1'
L pressure -instrument taps which were-cut, capped and-abandoned. in place by a previous plant. modification.
The replacement ~ risers ; do : net' include instrument -taps. - Thi s -
change does-not-degrade RCR system design or function since L
the existing taps are --abandoned ' ands are not described in L
the-FSAR. Additionally, removal. of the taps will' eliminate '
i 1-p
ll
!
,
r.
m
__
1-
.
-
'. '
-
,
,
the possibility of a ' small-bore =line break caused by failure of the abandoned pipe stubs or-caps.
-*
-N2 nozzles will be slightly shortened to elitdnate existing.-
i flaws'and some may require localized repair. :In all cases,
'
the modified configuration will be analyzed to establish the original design criteria have been met.
(2) Core Spray, System Piping
.
The primary change instituted by Plant Mod. No.89-092 is a-J material upgrade to mitigate tintergranular-stress - corrosion
.j
- '
cracking (IGSCC) of ' replaced components.. The original 304 stainless steel safe ends ;were replaced in 1979 'with 316L'
j!
stainless steel safe-ends._ The purpose of ~this project is to
!
replace the 316L-stainless steel-safe ends vith 316NG stainless-
!
steel safe-ends and to replace. the existing Inconel weld butter and cladding on the nozzles with: Type : 309L stainless steel.
Portions-of. the original piping were also replaced ~ in 1979.
These portions will be replaced with carbon = steel transition.
pieces. The " transition piece" is a' carbon' steel forging.and forms the interface between the safe-end and the first CS elbow.
-
The transition-piece configuration is ' essentially identical to Unit-2 and will, therefore, eliminate one circumferential weld per loop or a total of two joints.
<
3.
Welding (55050)
By : specification review and discussions-with cognizant personnel, tne j
inspector ascertained the following regarding welding activities. ; Welding
- 3 heat treatment and cutting processes and equipment.will be demonstrated as being suitable for the application on mock-ups and, for welding and post.
weld heat treatment, per applicable ASME Sections.II, IX andLXI require-
'
ments.
Welding will.be performed-using Diametric ;or Arc Machines-Inc.
automatic orbital Gas Tungsten Arc - Welding' (GTAW).. equipment with remote -
!
control aided by video equipment.
Weld joints will be made usingL "K" type consumable; inserts',1/8" x 5/32"..
[
This includes the thermal sleeve weld.
Welding procedures will' be qualified using a 50/50:(t 5%) Argon-Helium-sh%idihg gas mixture. The backing gas shall be 99.9's high purity' argon.
i The shielding gas mixture willLbe. welding grade.or better.
~
Heat'. input for the mixed gas: welding 'of butt weided joints shall: have La
}
maximum energy density of.1.7 megajoules, per cubic ; inch with a. primary.
{
voltage of_9.S maximum except.for root passes and cap passes.
Increasing s
heati. input beyond 1.7 megajoules l is permitted only. by variations - of
. primary: voltage ; input. No other changes are permitted which could result in a higher megajoule output.
i l
_
.
._J
- - _ -
+.
o
,
...
>
j n ja
,
..
-6 j
,
L
,
,
Shielding and b6cking gasses willL be filtered and. dried as necessary to L
provide a maximum dewpoint at the weld of -45'.
Welding operators will be qualifie at the site using 316 NG or 316L, 0.02% maximum rarbon: material.
Completed welds will be nondestructively
.
examined in accordance with ASME Sections III, V, and XI requirements as-applicable.
l-
' Post-medification -hydrostatic testing will be -performed per the L
requirementsaof'ASME Section XI.
~
-
l
.
Preservice-and Inservice examinations will be conducted in accordance with L
ASME; Section' XI requirements.
This area will be-addressed in ~ subsequent.
inspections. Other areas 1 reviewed during thi; inspection included quality-
, assurance requirements, piping analysis, design reports, and justification.
.for continued operation. Because these areas were reviewed and discussed in detail in Report 89-35, they wi.ll not be addressed in this report'since
.
they apply to this modification also;
~
(
,
Piping Procedure and-Specifications (49051)
4.
o
. Work procedures reviewed for technical content and for compliance _with
'
l applicable codes, standardsLand regulatory requirements were as follows:
-
L CPL-1.0 Rev. 1
. General Rigging.
L CPL-2.0 Rev. 1
' Material and Processes L
CPL-3.0 Rev. 1 Arc Strike Removal
-
= CPL-4.0 Rev.'1 Etching Procedure CPL-5.0 Rev. 1 Cleanliness Control Proc.
?
CPL-8.0 Rev. 1-Material Handling and Storage
!
CPL-9.0 Rev. 1 Control of' Measuring and Testing Equipment
'
CPL-10.0-Rev. 2:
Thermal Cutting l
CPL-29.0 Rev. 2 Purging of Piping Joints and-Controllof Gasses CPL-30 Rev~. 2
' Cal /on of. Meas;/g and Testing Equipment 5.
Procurement, Receiving'and Storage - 35065 a.
Filler Metal Material'
>
Welding materials 1needed for this PM were procured by;the' licensee l'
from a-previously approved vendor. ' The procuring document,-was CP&Ls '
,
L Specification, CPL-XXXX-W-01 Rev 4 Welding Filler-Metals ~ and(
L Materials Procurement for Nuclear Power Plants.
Additional ~
procurement requirements for chromium-nickel steel welding materials,-
i specific to this EPM,, were added as Supplementary ;. Requirements,-
,
L Part 1, We?d Procurement -- ASME Section III Class 1.
Purchase y
Vendor Order Size Type-Heat Sandvik 685724 1/8" (
ER308-L S19068
,
O b di
-
.
_.
.
.
-
.
_
_
.~
l
.
,
.-
.
e
'4 g
.
7^
.f
,
' (cont'd)
_
Purchase-Vendor Order Sizei
~ Type Heat Sandvik 685724 3/32" 4.
ER308-L-S12613 Sandvik 685724 0.035" 4.' ER309-L S22366 i
The inspectnr-noted the material had been receipt inspected by the licensee-and in process _of being - stored.
Quality record were reviewed' to ascertain whether ^ chemical analysis and mechan _ical-properties were. in accordance with applicable code and subject-specification requirements'.
Within the areas inspected,.no -violation or deviation -were identified.
b.
Core Spray Transition-Pieces The control _ ling document for the core spray transition-pieces is the licensee's specification No. -248-123 Rev. 4.
By reference _ this specification invokes ASME' Section 'III' 1986 Edition.
Material for the subject componentsTwas produced per_ ASME: Specification SA-350, _
Grade LF2, which: applies to carbon and low-alloy steel forging i
intended primarily-for low temperature service and requires noted toughness testing. The subject transition = pieces.were purchased from WFI Nuclear Products-Inc. of Houston. Texas ' under. CP&L's purchase
)
order #565674. They were manufactured to meet requirements on CP&L's
sketch #M-P753-04 Rev. C, from material produced from heat number-
-
667SNB. At the time of this inspection, the subject components had q
been received and receipt inspected in1:accordance with site -QA
procedures. The inspector found that the,three ordered transition
pieces identified by serial. number N5361A-1 thru 3, had been properly identified inspected and stored, while-the: quality re' cords. indicated'
-that all specification requirements had beenfmet.
-
e
- 6.
Action on Previous Inspection Findings (92701).
i
_
_
_
-
i (Closed) NOV 325,324/09-35-01, Failure to Review Changes to Procurement-Documents / Specifications-The licenseefs letters' of. response.' dated i
January 5 and - April 5,1990, were reviewed and determined acceptable' by-
.
the Region II staff.
The inspector.had ' discussions with the _ cognizant.
Project Engineer and, examined the corrective actions: as' stated in the letters of response.
The inspector concluded _ that the licensee hadi j'
determined the full extent of the subject noncompliance, performed the
'
necessary follow-up actions-to correct the present.-conditions and
';
developed the necessary corrective actions to preclude conditions of this:
problem. The corrective actions :1dentified in the letter'of-. response.have been implemented.
(Closed)- IFI, - 325,325/88-25-02, Implementation of Permanent Program for
i Repetitive Failure Identification,
!
l J
.
--
-
,
..
.
..
.
.
.
.,
...
,
.,
r-
..
,
I
.
.
.
.
I This : item was' identified for the' purpose' of tracking the licensee's l
development tf a trending program, to detect repetit_ive failures of key
'
plant equipment. Plant program procedure, PLP-05, April '1,,1989 has been.
f implemented and is currently used for.this purpose. The subject procedure-
- defines the criteria 'for determining repetitive component failures, root'
!
I cause. analysis. and problem resolution.
However, = this-procedure:;is:
presently undergoing revis ten so as to change the method of component'
. identification from the use of tag number (s) to that of-component model
. number.
By this change, the licensee hopes to ascertain whether -
!
repetitive problems-can be. related to specific manut.acterers rather than the ~ severity of application and/or service life. limitations. -The
,
inspector reviewed
'a' print out Lof approximately. one - hundred. (100)
'
equipment. failures designated as _ repetitive failures to determine 4the
>
identification and: disposition of those' types-failures and found that the program now in place, address the inspectors concerns ecd,.therefore, any-
,
further inspection effort in. this area. should be.licited to program-monitoring.
7.-
Exit Interview l
The inspection scope and results were summarized on-June -15,.1990, with i
those persons indicated in paragraph 1.
The-' inspectors described the
'
areas inspected and discussed. in-detail the inspection-results-. listed.
below.
I The licensee was commended for doing an outstanding. job in. thab vendor 4 surveillance efforts as evidenced by visits to contractor / vendor plants in'
!
Osaka, Japan; Houston;. Texas and Wayne,cPennsylvania.
These inspections-
~
were performed by highly competent personnel whose1 efforts identified and j
corrected problems with materials and processes which if leftl undetected j
would have disrupted the work effort..The licensee'was!also/ commended:for a.significant improvement in' planning for this project las evidenced by'a chango in project management, increased site facil.ities, -improved vendor surveillance and process-controls; The licensee did :not' identify as proprietary'any of.-the material provided to or reviewed by-the inspectors-during this inspection.
Dissenting comments were: not received from. the.
l
!
licensee.
r
',
r
-- j
,
.i
.i
.
-
-
-
,
--
.
--.-