IR 05000324/1981021

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-324/81-21 & 50-325/81-21 on 810831-0904. No Noncompliance Noted.Major Areas Inspected:Prior Corrective Actions,Qa Program,Calibr Program,Nonroutine Reporting & Surveillance
ML20031E887
Person / Time
Site: Brunswick  
Issue date: 09/23/1981
From: Belisle G, Fredrickson P, Upright C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20031E879 List:
References
50-324-81-21, 50-325-81-21, NUDOCS 8110160520
Download: ML20031E887 (12)


Text

,-

. _.

=

. -.

_.

._

.-.

_ - _ _ _ _ _ _ - - -

_

.

[

'

UNITED STATES

!"

f, NUCLEAR REGULATORY COMMISSION

$

E REGION 11 e[

101 MARIETTA ST., N.W., SulTE 3100 o,

ATLANTA, GEORGIA 30303

.

Report Nos. 50-325/81-21, 50-324/81-21 i

Licensee: Carolina Power and Light Company 411 Fayetteville Street Raleigh, North Carolina 27602 Facility Name: Brunswick 1 and 2 Docket Nos. 50-325, 50-324 l

.

License Nos. DPR-71, DPR-62 Inspection at Brunswick site near Southport, North Carolina

/M/ [I A Inspectors:_G. A. BeTisle g

_ [/

/

Y Date' Signed b/

M L/

Y ff8f P. E. Fredricli fate Sfigned Approyed by: [Md1

/ur/'t

8[8r C. M. Upright,'Secfion p}fanch fates'igned fef Engineering and,pe'ctiond Engineering Ins Technical Inspection Division SUMMARY Inspection on August 31 - September 4,1981 Areas Inspected This routine, unannounced inspection involved 62 inspector-hours on site in the areas of licensee action on previous enforcement matters, design changes and modifie.ation:. organization and administration, QA Prograr innual review, onsite review commitwe, test and measurements equipment program, surveillance testing and calibration program, calibration, surveillance, non-routine reporting and

licensee actior, on previous inspection findings.

Results Of the 11 areas inspected, no violations or deviations were identified.

,

81101oOS2O 81

PDR ADOCK 05

0 PDR

.

.

REPORT DETAILS 1.

Persons Contacted Licensee Employees

  • D. Allen, Project QA/QC Specialist E. Bishop, Engineering Supervisor
  • T. Coburn, Director QA/QC
  • C. Dietz, General Manager J. Dimmette, Mechanical Maintenance Supervisor
  • K. Enzor, I&C/ Electrical Maintenance Supervisor

"M. Hill, Manager, Maintenance

  • M. Jones, On-Site Nuclear Safety G. Milligan, Principle Engineer, Onsite Nuclear Review
  • R. Morgan, Manager, Plant Operations
  • C. Mosley, Jr., Manager, Operations QA/QC
  • R. Poulk, Jr., Regulatory Specialist
  • W. Tucker, Manager, Technical Support NRC Resident Inspectors
  • L. Garner D. Johnson
  • Attended exit interview 2.

Exit Interview The inspection scope and findings were summarized on September 4, 1981 with those persons indicated in paragraph I above. The licensee acknowledged the inspection findings.

3.

Licensee Action on Previous Inspection Findings The following terms are defined and used throughout this report:

Accepted QA Program FSAR Chapter 13.4.3 AP Administrative Procedure CNSU Corporate Nuclear Safet.> Unit CNSS Corporate Nuclear Safety Staff ISI Inservice Inspection M&TE Measuring and Test Equipment QA Quality Assurance I

.-

-

, _ -

_

..

_

_

.

QC Quality Control T/S Technical Specifications Violations from insoection reports 50-325/80-42 and 50-324/80-39 were reviewed with respet.t to the licensee's response letters dated February 3, l

1981; March 20,1981; March 31,1981 and June 11, 1981.

I a.

(Llosed) Violation, Item A (325/80-42-01, 324/80-39-01):

Failure to include releases in semi-annual report. As stated in a letter from J. P. O'Reilly to J. A. Jones, dated April 10, 1981, this item was the subject of a separate investigation. The item was withdrawn from the inspection report.

b.

(Closed) Violation, Item D (36/80-42-04, 324/80-39-04).

Failure to audit actions taken to correct deficiencies. As stated in a letter from J. P. O'Reilly to J. A. Jones, dated April 10, 1981, this item was withdrawn from the inspection report due to the clarification provided in correspondence from B. J. Furr to J. P. O'Reilly dated February 3, 1981, Serial: No-81-192.

c.

(Closed) Violation, Item E (325/80-42-05, 324/80-39-05).

Failure to

'

provide adequate QA/QC personnel training. The inspector reviewed QAP 103, Personnel Indoctrination, Training, and Qual lfication, Revision 2 and identified that this procedure comprehensively outlines the qualifications of QA/QC personnel. Detailed discussions with cognizant personnel identified a change in management philosophy relative to personnel qualifications to the extent that personnel are not allowed to inspect activities un; ass they are fully trained and qualified ir the area they are inspecting. Although this procedure has just beer implemented, if rigidly adhered to, it will provide adequate controls for the training and qualification of QA/QC personnel.

d.

(Closed) Violation, Item F (325/80-42-06, 324/80-39-06):

Failure to review documents by QA prior to release.

The inspector reviewed Operating Manual Administrative Procedures, Volume 1, Revision 48, Section 5.5.3.D and identified that controls have been established for the review of procedures by QA.

The inspector reviewed a computer listing of all plant procedures and determined that this listing I

provides the necessary information for the initial QA review of any f

plant procedure and whether subsequent revision review is required.

'

The inspector reviewed a random sampling of procedures requiring QA review and determined that QA reviews were being performed as required.

e.

(Closed) Violation, Item I (325/80-42-09, 324/80-39-09):

Failure to follow procedures; ENP3, updating plant procedures; ENP3, identify drawings undergoing revision; ENP3, notification of training super-visor; RMI-3, stamping of drawings; and, AP limiting dates on special procedure.

(1) The inspector reviewed OP-3, Reactor Recirculation System, Revision 27 and verified that valves V1,2,7 and 8 had been removed from the valve lineup.

These valves were removed by Modifica-tion 79-272. The inspector also reviewed ENP-3, Plant Modifica-tion Procedure, Revision 12 and identified that the engineer includes " proposed" revisions to procedures effetted by the modification.

(2) The inspector reviewed ENP-3 as previously stated.

During the review of six plant modifications as discussed in paragraph 5, drawings were reviewed to verify that they were marked to delineate modifications in progress.

(3) The inspector reviewed ENP-3 and verified provisions clearly exist to ensure notification of training personnel when modifications are declared operational.

The inspector interviewed training personnel and verified that modifications are incorporated into training classes for plant personnel. Training Memo 902.1, Serial BSEP/81-0244 dated January 30, 1981 contains the controls for processing plant modifications into personnel tra.ining.

(4) The inspector reviewed RMI-3, Reproduction, Distribution and Accountability of Plant Documents, Revision 3 and also reviewed the drawing files and verified that posi ive controls have been t

established for updating plant drawings.

(5) The inspector reviewed the Operating Manual, Administrative Procedures, Section 5.1 and determined that controls had been established for the time interval for usage of Special Procedures.

The inspector randomly selected six Special Procedures and verified that these controls had been implemented.

f.

(Closed) Violation, Item J (325/80-42-10, 324/80-39-10):

Failure to establish measures for design analysis. The inspector reviewed ENP-3, Plant Modification Procedure, Revision 12.

This procedure has the necessary provisions for including the requirement that design analyses be provided for modifications.

The inspector selected six modifica-tions as discussed in paragraph 5 and verified that design ana.

"

were being provided for modifications.

g.

(Closed) Violation, Item (325/80-42-11):

Failure of CNSU to review safety evaluation. The inspector reviewed a letter from S. McManus to A. C. Tollison, Jr. dated November 19, 1980, File:

82-MH-116. This letter verified CNSU review of modification 79-057. The inspector also reviewed CNSP-4, Independent Review, Documentation, and Communication dated June 1,1981 (typograhical error in the licensee's response dated March 20, 1981 as CNSI-4) and identified that controls had been established for review of material by the CNS.-

.

_. -

-

..

-

-

4.

Unresolved Items Unresolved items were not identified during this inspection.

<

5.

Design, Design Changes and Modifications (37700)

References:

(a) QAP-14, Operating Plant Mcdification Control, Revision 2 (b) QAP-202, Plant Modification Review, Revision 2 (c) ENP-3, Plant Modification Procedure, Revision 12 The inspector reviewed references (a)-(c) to assure they met the require-ments of the accepted QA Program and Regulatory Guide 1.64 - October,1973 as endorsed by that Program. The inspector verified the following aspects of the plant modification program:

Modifications have been reviewed and approved in accordance with

-

10 CFR 50.59

-

Modifications were reviewed and approved in accordance with T/S and established QA/QC contro'.s

-

Modifications are cor. trolled by established procedures

-

Modifications were incorporated into existing procedures

-

Drawings were updated to reflect modifications.

,

The inspector selected six modifications (80-214,80-245, 81-173,80-237, 80-224 and 80-225) and verified the previously stated aspects of the modification program.

Based on this review, no violations or deviations were identified.

6.

Organization and Administration (36700)

Reference:

Technical Specifications The inspector reviewed various QA and administrative procedures to assure the existing plant organization is as required by the reference. There have been changes in the licensee's organizational structure. The licensee has submitted a revision to the T/S (Letter from E. E. Utley to T. A. Ippolito dated July 28, 1981, Serial No. - DQA-81-045) delineating these changes.

The qualifications of personnel due to this reorganization will be reviewed upon acceptance of the revision to the T/S by the NRC.

Based on this review, no violations or deviations were identified.

_ _

,

_

_.

7.

QA.'"ger

'.nnual Review (35701)

References (a) Letter from E. E. Utley to D. G. Eisenhut dated March 18, 1981, Serial No. 00A-81-026 (b) Memorandum from H. R. Banks to S. R. Zimmerman Cated July 31,1981 (Regulatory Guide 1.146 Revision 0)

(c) Memorandum from H. R. Banks to S. R. Zimmerman dated July 31,1981 (Regulatory Guide 1.58 Revision 1)

(d) Letter from E. E. Utley to D. G. Eisenhut dated June 8, 1981, Serial No. : No-81-984 (e) Corporate Quality Assurance Program, Revision 2 (f) Letter from F. R. Coburn to C. R. Deit,

R. J. Grover, Jr. and J. M. Waldort dated August 31, 1981, File 3820 (Implementation of New Corporate Quality Assurance Program)

(g) Operations Quality Assurance / Quality Control Manual of Procedures dated 9/81 (h) FSAR Chapter 13.4.3, Continuing Quality Assurance Program, Amendment 27 There have been substantive changes in the licensee's QA Program since the last inspection effort in this area (October 1980). References (a), (b) and (c) reiterate the licensee's commitments as orginally stated in reference (h).

The licensee has rewritten references (e) and (f) and is in the process of implementing these procedures. Since these procedures have been recently implemented on September 1,1981, the licensee is cognizant that there will probably be some problem areas to be refined.

The inspector discussed the new program with plant personnel and determined that they were aware of and showed renewed interest in changes in the program.

Based on this review, no violations or deviations were identified.

8.

Onsite Review Committee (40700)

References:

(a) Technical Specifications (b) AP, Paragraph 3.0, Plant Nuclear Safety Committee, Revision 39 (c) AI-9, Plant Nuclear Safety Committee Administration dated 9/80 Discussions with the resident inspector identified that they attend PNSC meetings consequently the inspector did not attend a PNSC meeting. The inspector reviewed PNSC meeting minutes from June 1,1981 through August 13, 1981 (Meeting minutes 162-219) and verified T/S requirements relative to membership, review I ocess, frequency of meetings and qualifications of personnel.

Based on this review, no violations or deviations were identifie _

-

__ _

. -.. ~

~__..__- - --_--_-

.

.- =_--

-. -

_.

..

_

.

.

!

!

l 9.

Measuring and Test Equipment Program (61724)

i References:

(a) Corporate Quality Assurance Program, Section 9, j

Calibration Control, Revision 1 i

(b) QCP-301, Tool and Instrument Calibration, Revision 2

'

(c) MP-01, Control of Measuring Devices and Test Equipment, Revision 13

,

I The lic 4:see's practices with respect to the test and measurement equipment progra 2 were reviewed to verify the following:

I Criteria and responsibility for assignment of calibration frequency

-

have been established

-

An equipment inventory list has been established which identified the i

calibration frequency, standards and procedures for all equipment to be used on safety related structures, systems or components Formal requirements exist for marking the latest inspection / calibration

-

on each piece of equipment or otherwise identifying the status of

.

!

calibration

!

-

A method has been provided for assuring that each piece of equipment is calibrated on or before the date required and that new equipment will be added to the list and calibrated prior to use

l Controls have been established to prohibit the use of equipment which

-

has not been calibrated within the prescribed frequen;y

-

Controls have been established to ensure that when a piece of equipment

is found out of calibration, the acceptability of items previously j

tested with that equipment will be evaluated and docume'.ted and the cause of that equipment being out of calibration will be evaluated.

<

Based on this review, no violations or deviations were identified.

J

'

10.

Surveillance Testing and calibration Control Program (61725)

References:

(a) Corporate Quality Assurance Program, Section 9, Calibration Control, Revision 1

'

l (b) ASME Boiler and Pressure Code,Section XI, 1977 Edition through Summer 1978 Addendum (c) MP-03, Calibration of Process Instruments, Revision 17 (d) MP-10, Preventative Maintenance Program, Revision 14 The referenced documents were reviewed with respect to the licensee's dCCepted Quality Assurance Program.

The review was concerned with T/S surveillance testing and calibration of is-lant safety-related instruments not specifically controlled by T/S.

,

I c-,

_-,

c.w

,-

,-m-,c-.c_m.r

-

v-_,,--.

.,,.._,,,,,,,,..-__-y.

.

..,_,_,.,,,,_-.,...,m,

.~.

,

.. - -

.... -

-

.

.

.

'

The licensee's practices were reviewed to verify the following:

-

A master schedule for surveillance testing / calibrations / inservice inspections was developed which included frequency, responsibility and status for each test / calibration / inspection

-

Responsibilities are assigned for maintaining the master surveillance schedule and for assuring that all scheduled tests / calibrations /

inspections are performed

-

Formal requirements, methods and responsibilities are established and defined for conduct, review and evaluation of tests / calibrations /

inspections

-

A master schedule for component calibrations had been established that included frequency, responsibility and status of safety-related components

-

Responsibilities are assigned to assure that the schedule is maintained and schedules are satisfied

-

Formal requirements have been established for performing calibrations in accordance with approved procedures.

Based on this review, one inspector followup item was identified.

!

Reference (a) requires that calibration of safety-related installed instru-

!

ments be performed on a periodic basis. Contrary to this requirement, as of September 4,1981, Instrumentation and Control calibration of safety-related instruments are not being performed on a periodic basis. Several instru-ments were beyond their calibration tolerance date and no action was being taken to resolve the late calibration problem. In addition, no effort was being made to identify those overdue instruments used to perform T/S surveillances and to notify the Operations Department of these instruments.

The inspector did not identify any T/S surveillances performed with calibra-i tion overdue on installed instruments. This problem of overdue calibrations

'

was addressed in a licensee evaluation of the preventive maintenance program based on a review of an Institute of Nuclear Power Operations checklist procedure. This evaluation identified the weaknesses in references (c) and (d) and comn.itted to revising both procedures by October 1,1981. As this

j deficiency in the calibration program was identified by 'he licensee, no

!

citation is issued. This area is identified as an inspector followup item

(325, 324/81-21-01) pending the NRC review of the calibration program for performance frequency and also for calibration status information being provided to the plant department using the installed instruments identified by the program.

l

!

t t

I.-..-,.

_..,_

..,_,...,_,..-,.,.._m..,

. _. _ _, _. _ - _ _ _,,_

,_,,

.

__

....

....

_

.

.-

.-

-_

._.-~_-

.

.

- _ -

-

.-

._

_ _ _.

..

.

.

I

i

<

11. Calibration (56700)

References:

(a) Corporate Quality Assurance Program, Section 9, Calibration Control, Revision 1

,

(b) MP-03, Calibration of Process Instrumentation,

'

Revision 17 I

Utilizing the licensee's calibration program as described in references (a)

and (b), the inspector verified that selected instruments and M&TE had

{

received the proper calibration according to the following criteria:

For completed calibrations, the documentation was complete, acceptance

-

criteria met, proper revision used and calibration conducted by i

qualified individuals

-

For calibration procedures, reviews are as required by T/S, controls

^

are established to meet limiting conditions for operation, equipment is returned to service, calibration equipment is traceable and acceptance values are within required limits

-

For M&TE, equipment is controlled by site procedures, calibration frequency is maintained, storage of equipment is proper and accuracy is traceable to the National Bureau of Standards or other independent testing organizations.

Based on this review, no violations or deviations were identified.

12.

Surveillance (61700)

References:

(a) Corporate Quality Assurance Program, Section 9, Calibration Control, Revision 1 (b) ASME Boiler and Pressure Code,Section XI, 1977 Edition through Summer 1978 Addendum

Utilizing the licensee's survei.llance program the inspector verified that selected plant surveillances met several required criteria:

-

T/S surveillance and ISI tests were covered by approved procedures

which contained applicable prerequisites and preparations, acceptance criteria and instructions to insure that systems or components are restored to operation following testing

-

Completed surveillances were reviewed in accordance with facility administrative requirements, were performed within the required time frequencies, were properly handled when tested items failed acceptance l

criteria and were performed by qualified individuals.

!

t

_ _ _ _.

...

-, _.. _,

.

..

.

._,_-_. _. - - - -. -. _.. -

,_.

.. _.

.

The revised ISI Program was initiated on July 1, 1981.

Although the present program appears sati sf actory, many periodic tests are being rewritten. The inspection of the fully revised program will be conducted during a subsequent inspection.

Based on this review, no violations or deviations were identified.

13. Nonroutine Report (90714)

References:

(a) AI-39, BSEP Program for Compliance to 10 CFR 21, Revision 5 (b) AI-43, NRC Reporting Requirements Summary, Revision 0 (c)

01-4, LCO Evaluation and Followup, Revision 8 (d) ENP-7, Licensee Event Reports (LER's), Revision 6 (e) RMI-1, Capture and Indexing of Correspondence and Plant Records, Revision 4 The inspector reviewed references (a)-(e) and verified that:

-

Administrative controls have been established for prompt review and evalution of off normal events

-

Administrative controls have been established for review: of planned and unplanned maintenance and surveillance testing activities

-

Administrative controls have been established for reporting safety-related events internally and to the NRC

-

Administrative controls contain provisions for recognition and reporting events that are covered by 10 CFR 21 Administrative controis have been established for review and evaluation

-

of vendor bulletins and circulars.

The licensee is in the process of developing similar administrative controls for NRC correspondence (bulletins, circulars and notices).

Based on this review, no violations or deviations were identified.

14.

Licensee Action on Previously Identified Inspection Findings (92701)

a.

(Closed) Open Item (325/80-42-14, 324/80-39-14):

Operations manual does not reflect Techincal Specification (T/S) organization. Since the date of the last inspection in this area (October 1980) there have been changes in the plant 1 corporate organizational structure.

The licensee submitted a T/S change to the NRC on July 28, 1981 (Letter from E. E. Utley to T. A. Ippolito, Serial No. 0QA-81-045) delineating these change _-

--..

---

_

_

_

_-

-.

..- ~.

. -

_

.

.

i

l i

i

.

b.

(Closed) Open Item (325/80-42-16, 324/80-39-16):

General employee training does not provide criteria for satisfactory completion of training.

The inspector reviewed TI-300, General Employee Training, Revision 5.

This procedure contains a description (Section 2.1.1) for the detailed training program and refers to the Training Manual for

,

'

Nuclear and Fessil Operations. The inspector reviewed the operating

)

guidelines of the General Employee Training (Badging) for Nuclear Operations Department and identified that criteria for satisfactory completion of training and subsequent badging has been included in the

guidelines.

c.

(Closed) Open Item (325/80-42-17, 324-80-39-17): Master drawing index does not include Engineering on distribution. The inspector reviewed selected drawing inventory cards (record cards) and ascertained that -

drawings are now being distributed to Engineering.

d.

(Closed) Open Item (325/81-42-18, 324/81-39-18):

Records generated

,

prior to new index system do not have a documented index. The inspec-

,

tor reviewed RMI-1, Capture and Indexing of Correspondence and Plant

'

]

Records, Revision 5 and RMI-2, Records Receipt and Storage Records

'

Management Instructions, Revision 3.

These two procedures differen-tiate the indexing system now being used for retention of records.

They also describe how older records are being stored apart from newer records.

I e.

(Closed) Open Item (325/80-42-19, 324/80-39-19): Construction records not controlled ny written procedures. The inspection reviewed RMI-1, Capture and Iviexing of Correspondence and Plant Records, Revision 5

-

and determines that controls have been established for the handling of

nicrofilm documentation.

'

f.

(Closed) Open Item (325/80-42-20, 324/80-39-20): Clarification between CNSU procedures and T/S. The inspector reviewed the procedures for operation of the CNSS. These procedures underwent a total rewrite on June 1, 1981.

The inspectors concern about the possibility of inadequate reviews by the CNSS have been addressed by CNSP-3, Subjects

>

Requiring Independent Review; CNSP-4, Independent Review, Documenta-

>

tion, and Communication and the Guidelines for Conduct of Corporate i

i Nuclear Safety Programs.

g.

(Closed) Open Item (325/80-42-21, 324/80-39-21):

Revise QAP-17 to include additional guidance for determining hold points. The inspector

reviewed QAP-204, Criteria for Hold Points, Revision 2 and identified i

that this procedure adequately describes the methods to be used for establishing hold points for electrical maintenance, electrical related plant modifications, mechanical maintenance, mechanical related plant modifications, structural concrete and structural steel and post installation and repair inspections.

h.

(Closed) Open Item (325/80-42-24, 324/80-39-24): Document cases where QA/QC technician's ' decision ' is overridden by QA supervisor.

The inspector reviewed QAP 204 as discussed in paragraph 14.g.

This

_ rocedure contains guidance for establishment of hold points during p

performance of QA/QC activities. The inspector also reviewed memos dated December 2,1980 and September 3,1981. The former memo from

-. - -. -

- - - - -. ~..

-

-. -

-

. -, - _ _ _

-

-,

..

.

D. A. Allen to plant QA technicians and specialist (File B10-13300, Serial:

BSEP/80-1971) provides a method for documentation if the QA supervisor overrides a QA technician's or specialist's decision.

The latter memo from C. H. Mosley, Jr. to F. R. Caburn and H. J. Young reiterates an open door policy at Brunswick and Robinson plants.

1.

(Closed) Inspector Followup Item (325/80-42-25, 324/80-39-25): Houta-keeping inspection. Discussion with the resident inspector identified that housekeeping is routinely monitored during their plant tours. If problem areas are identified, appropriate documentation is provided in their monthly inspection reports.

j.

(Closed) Inspector Followup Item (325/80-42-26, 325/80-39-26): Out-dated references in operating manual.

The inspector reviewed the Operating Manual, Volume 1, Administrative Prccedures, Paragraph 11, Plant Safety and identified that the outdated references had t'een removed and the correct references are now in place.

k.

(Closed) Inspector Followup Item (325/80-42-27/324/80-39-27): Include handling of defective rigging equipment in MP-6.

The inspector reviewed MP-6, Operation and Inspection of Cranes and Material Handling Equipment, Revi s t o'1 6 and identified that controls have been estab-lished for disposition of damaged or defective sling and hoisting equipment.

1.

(Closed) Inspector Followup Item (325/80-42-30, 324/80-39-30): Review Director Nuclear Safety and Quality Assurance self study program in quality assurance area. Due to organizational changes, this position has been deleted.

The onsite Quality Assurance Department has been realigned and now reports to a Director, QA/QC on site who in turn rgcets to the Manager, Operations QA/QC at the corporate office. This position reports to the Manager, Corporate Quality Assurance who in turn reports to the Executive Vice President, Power Supply and Engineering and Construction.