IR 05000302/2008401

From kanterella
Jump to navigation Jump to search
IR 05000302-08-401, on 03/20/2008, Crystal River, Unit 3, Security Inspection, Cover Letter
ML080990486
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 04/08/2008
From: Joel Munday
NRC/RGN-II/DRS/PSB2
To: Young D
Florida Power & Light Co
References
IR-08-401
Download: ML080990486 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION pril 8, 2008

SUBJECT:

CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT - NRC SECURITY INSPECTION REPORT 05000302/2008401

Dear:

Mr. Young:

On March 20, 2008, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Crystal River Unit 3 Nuclear Generating Plant, Unit 3. The inspection covered one or more of the key attributes of the security cornerstone of the NRC=s Reactor Oversight Process. Portions of the inspection were conducted at the corporate office from January 7 through 10, 2008. The enclosed report documents the inspection results, which were discussed with Mrs. Dixon, NAS Manager, and other members of your staff on March 20, 2008. A re-exit was conducted with yourself and other members of your staff on April 3, 2008.

This inspection examined activities conducted under your license as they relate to security and compliance with the Commission=s rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

Based on the results of this inspection no findings of significance were identified. However, two licensee-identified violations which were determined to be of very low security significance are listed in this report. The NRC is treating these violations as non-cited violations (NCVs)

consistent with Section VI.A.1 of the NRC Enforcement Policy because of the very low security significance and because they are entered into your corrective action program,. If you contest these non-cited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator Region II; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Crystal River Unit 3 Nuclear Generating Plant.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system, ADAMS. B SECURITY RELATED INFORMTION FPC

ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter=s enclosure will not be available for public inspection.

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC=s document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.

Otherwise, mark your entire response ASecurity-Related InformationBWithhold Under 10 CFR 2.390@ and follow the instructions for withholding in 10 CFR 2.390(b)(1).

Sincerely,

/RA James Shehee for/

Joel T. Munday, Chief Plant Support Branch 2 Division of Reactor Safety Docket Nos. 50-302 License Nos. DPR-72 Enclosure: Inspection Report 05000302/2008401 w/Attachment: Supplemental Information cc: See Page 3 FPC 3 Craig Fugate cc w/encl: Director Jon A. Franke Division of Emergency Preparedness Director Site Operations Department of Community Affairs Crystal River Nuclear Plant (NA2C) 2740 Centerview Drive 15760 West Power Line Street Tallahassee, FL 32399-2100 Crystal River, FL 34428-6708 Chairman Michael J. Annacone Board of County Commissioners Plant General Manager Citrus County Crystal River Nuclear Plant (NA2C) 110 N. Apopka Avenue 15760 West Power Line Street Inverness, FL 36250 Crystal River, FL 34428-6708

Jim Mallay Phyllis Dixon Framatome ANP, Inc.

Manager 1911 North Ft. Myer Drive, Suite 705 Nuclear Assessment Rosslyn, VA 22209 Crystal River Nuclear Plant (NA2C)

15760 West Power Line Street Crystal River, FL 34428-6708 Stephen J. Cahill Crystal River Nuclear Plant (NA2C)

15760 West Power Line Street Crystal River, FL 34428-6708 R. Alexander Glenn Associate General Counsel (MAC - BT15A)

Florida Power Corporation P.O. Box 14042 St. Petersburg, FL 33733-4042 Steven R. Carr Associate General Counsel Legal Department Progress Energy Service Company, LLC P.O. Box 1551 Raleigh, NC 27602-1551 cc w/o encl:

William A. Passetti Bureau of Radiation Control Department of Health 2020 Capital Circle, SE, Bin #C21 Tallahassee, FL 32399-1741 3 ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter=s enclosure will not be available for public inspection.

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC=s document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response ASecurity Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390 (b)(1).

Sincerely,

/RA/

Joel T. Munday, Chief Plant Support Branch 2 Division of Reactor Safety Docket No.: 50-302 License No.: DPR-72 Enclosure: Inspection Report 05000302/2008 w/Attachment: Supplemental Information cc: See Page 3 Distribution w/encl:

F. Saba, NRR C. Evans, RII EICS (Part 72 Only)

L. Slack, RII EICS B. Westreich, NSIR (hard copy w/ encl)

E. McNiel, NSIR (hard copy w/ encl)

RIDSNRRDIRS OE Mail (email address if applicable)

PUBLIC (Enclosure Removed)

See Previous Concurrence X PUBLICLY AVAILABLE NON-PUBLICLY AVAILABLE SENSITIVE X NON-SENSITIVE ADAMS: G Yes ACCESSION NUMBER:_________________________

OFFICE RII:DRS RII:DRS RII:D RII:DRP RII:DRS SIGNATURE /RA/ /RA J. Shehee for/ /RA/

NAME RLPatterson JMunday MSykes DATE 4/4/2008 4/08/2008 4/4/2008 E-MAIL COPY? YESNO YESNO YESNO YESNO YESNO 3 OFFICIAL RECORD COPY DOCUMENT NAME: I:PSBII: Security OUO Reports: Crystal River IR 2008401.doc