IR 05000293/1982028

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-293/82-28 on 821012-14.No Noncompliance Noted.Major Areas Inspected:Scram Discharge Vol & Associated Piping Design,Per IE Bulletins 80-17 & 79-14 & NUREG-0803
ML20028B747
Person / Time
Site: Pilgrim
Issue date: 11/17/1982
From: Bettenhausen L, Eapen P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20028B741 List:
References
RTR-NUREG-0803, RTR-NUREG-803 50-293-82-28, IEB-79-14, IEB-80-17, NUDOCS 8212030200
Download: ML20028B747 (3)


Text

o

.

U. S. NUCLEAR REGULATORY COMMISSION

REGION I

Report No. 50-293/82-28 Docket No. 50-293 License No. DPR-35 Priority

-

Category C

Licensee: Boston Edison Company 800 Boylston Street Boston, Massachusetts 02199

~

Facility Name:

Pilgrim Nuclear Power Station Inspection At:

Pilgrim Nuclear Station and Corporate Office Inspection Conducted:

October 12 - 14, 1982 Inspector:

K. h II!/4!E2 P. K. Eapen, Ph.D., Reactor Inspector datd signed Approved by:

IA M 8 /84 M

//// 7/b_

L. H. Bet'tenhausen, Ph.D., Chief, Plant date signed Systems Section, EPB, DETP Inspection Summary:

Inspection on October 12 - 14, 1982 (Report No. 50-293/82-28)

AreasInspected: Routine, announced inspection of the Scram Discharge Volume and associated piping design. The inspection involved 12 inspection hours at the site and 12 inspection hours at the corporate office by one region-based inspector.

Results: No violations were identified in the inspected area.

!

,

l

.

8212030200 821119

~

PDR ADOCK 05000293 G

PDR

- - - -

-,

. -.

-

_

_

_

.

.

Details 1.

Persons Contacted

  • J. Ashkar, Deputy Manager, Nuclear Engineering
  • J. Ballentine, Vice President, Operations
  • R. Butler, Manager, Nuclear Engineering Department
  • R. Fairbank, Group Leader, Fluid Systems and Mechanical Components
  • T. Ferris, Licensing Engineer

'

  • J. Keyes, Senior Licensing Engineer
  • H. O'Connor, Engineer
  • W. Ringen, Senior System Safety Engineer
  • R. Weiler, Consultant, Teledyne NRC
  • J. Johnson, Senior Resident Inspector H. Eichenholtz, Resident Inspector The inspector also held discussions with other members of the Power Station and corporate personnel.
  • Denotes those present at the exit interview conducted on October 14, 1982.

2.

Follow-up on Licensee Event Report (LER)82-005 and IE Bulletin 80-17 In light of IE Bulletin 80-17, the licensee undertook a review of the Scram Discharge Volume Piping. The licensee's contractor performed a system walkdown of the Scram Discharge Volume Piping in January 1982.

The contractor identified several discrepancies between as-built and as-designed configuration. After a detailed analysis of the identified differences, the licensee issued LER 82-05 on February 26, 1982. The LER reported the findings of the contractor's walkdown in accordance with the facility's Technical Specifications.

In the above LER, the licensee stated that eight pipes were stressed above the code allowables and interim station operability limits set forth in IE Bulletin 79-14.

These lines were modified during the last refueling outage to bring the stresses within the operability limit.

At present, the licensee's contractors are performing the necessary analysis for upgrading the piping system associated with the Scram Discharge Volume. A preliminary and conservative analysis of the SDV piping system identified that the thermal stress exceeded the code allowable at the point the line from the Hydraulic Control Unit meets the Scram Discharge Volume. As stated in licensee's letter dated June 4,'1982, to Mr. D. B

,

Vassallo of NRC, the licensee' intends to upgrade the Scram Discharge

Volume piping to meet the requirements of NUREG 0803 by December 198 r

..

.

The inspector reviewed the licensee's bases for continued operation prior to the completion of the upgrade. The licensee stated to the inspector that a break at the identified high thermal stress location would not prevent the control rod drive system from performing the Safe Shutdown (Scram) function. As stated in BECo Letter No.82-160, dated June 4, 1982, the consequences of the pipe break, if it occurred prior to the piping system modification, will be well within the bounds of the reasoning presented in NUREG 0803.

The licensee's representatives stated that the engineering documents, such as drawings, calculations, and computer programs will be obtained from the contractors and made available for NRC review. The inspectors stated that detailed review of the above design documents would be conducted in future NRC inspections.

This item will be followed under open item 50-293/82-10-04).

Based on the above, the inspector concluded that the licensee's actions in this matter were responsive and the scheduled actions for the future were consistent with NUREG 0803 and prudent piping system analysis methods.

In addition, it was confirmed that operation prior to the completion of detailed analysis and modification did not constitute an unreviewed safety question, since the consequences of this operation are bounded by the reasonings presented in NUREG 0803.

3.

Exit Interview At the conclusion of the inspection, the inspector met with the licensee's representatives denoted in paragraph 1 to summarize the inspection findings as detailed in this report. The licensee acknowledged the inspector's statements.

--

-