IR 05000275/1989032
| ML16342B671 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 05/07/1990 |
| From: | Martin J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | Shiffer J PACIFIC GAS & ELECTRIC CO. |
| References | |
| NUDOCS 9005210133 | |
| Download: ML16342B671 (8) | |
Text
Docket Nos. 50-275 and 50-323 Pacific Gas and Electric Company 77 Beale Street Room 1451 San Francisco, California 94106 Attention:
Mr. J.
D. Shiffer, Senior Yice President and General Manager Nuclear Power Generation Business Unit Gentlemen:
SUBJECT:
FINAL REPORT ON SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE, REPORT NUMBERS 50-275/89-32 AND 50-323/89-32 This letter refers to the NRC Systematic Assessment of Licensee Performance (SALP) Board evaluation of Pacific Gas and Electric Company's (PGIIE's)
performance at the Diablo Canyon Nuclear Power Plant for the period August 1, 1988 through December 31, 1989. 'n our management meeting on March 22, 1990 as documented in Inspection Report Nos. 50-275/90-12 and 50-323/90-12 dated April 16, 1990, we discussed your plans for addressing a number "of the SALP issues and you indicated at that time that you did not expect to comment further on the SALP report.
This was confirmed with you after issuance of the SALP management meeting report by Hr.'. M. Mendonca of my staff.
Further, we noted that you made no comment in our SALP meeting which would require revision of the SALP report; therefore, the SALP report as issued on March 13, 1990 is considered final.
In accordance with 10 CFR 2.790(a),
a copy of this letter will be placed in the NRC Public Document Room.
No reply to this letter is required; however, should you have any questions, we will be pleased to discuss them with you.
Sincerely, John B. Martin Regional Administrator Enclosure:
Appendix I (NRC Conclusions)
9005210133 900507 PDR ADOCK 05000275
-2-MAY,
(ops cc w/enclosure:
J.
A. Sexton,'GSE J.
D. Townsend, PGRE R.
F. Locke, PGSE, D. A. Taggart, PG8E News Services, PG&E T. L. Grebel, PGSE State of CA
bcc w/enclosure:
Project Inspector Resident Inspector docket file G.
Cook B. Faulkenberry J. Martin R.
Zimmerman A. Chaffee P. Koltay, NRR bcc w/o enclosure:
N. Western M. Smith
.
J. Zollicoffer REGION V
BOlson >q~g MMMendonca 5/ g /90 5/ "//90 SRi,chards 5/ y/90 Chairman Carr Commissioner Roberts Commissioner Rogers Commissioner Curtis Commissioner Remick J. Taylor, EDO J. Sniezek, DEDOR T. Hurley, NRR J. Lieberman, OE J. Larkin, NRR R. Bevan, NRR RSca 5/g /90 PP+
RZimmerman 5/7/90 EQUEST COPY UEST COPY Y
NO YES NO tin
/90 RE EST COPY YES /
NO EQ EST COPY R
YES /
NO E
ST COPY NO RE UEST COPY
/
NO
APPENDIX I NRC CONCLUSIONS A.
Comments Received From Licensee No written response was provided.
B.
NRC Conclusions Re ardin Acce tabilit of Licensee's Planned Corrective Actions Me concluded that your proposed actions to address areas needing improvement were responsive.
We will review your progress as part of our future inspection program, as appropriate.
C.
Re ional Acministrator's Conclusions Based on Consideration of Licensee's
~Res onse I have concluded that the overall ratings in the affected areas have not changed.