IR 05000269/2019004
| ML20044D438 | |
| Person / Time | |
|---|---|
| Site: | Oconee |
| Issue date: | 02/13/2020 |
| From: | Frank Ehrhardt NRC/RGN-II/DRP/RPB1 |
| To: | Burchfield J Duke Energy Carolinas |
| References | |
| IR 2019004 | |
| Download: ML20044D438 (35) | |
Text
February 12, 2020
SUBJECT:
OCONEE NUCLEAR STATION - INTEGRATED INSPECTION REPORT 05000269/2019004 AND 05000270/2019004 AND 05000287/2019004
Dear Mr. Burchfield:
On December 31, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Oconee Nuclear Station. On January 27, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Oconee Nuclear Station.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; and the NRC Resident Inspector at Oconee Nuclear Station. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Frank J. Ehrhardt, Chief Reactor Projects Branch 1 Division of Reactor Projects
Docket Nos. 05000269 and 05000270 and 05000287 License Nos. DPR-38 and DPR-47 and DPR-55
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000269, 05000270 and 05000287
License Numbers:
Report Numbers:
05000269/2019004, 05000270/2019004 and 05000287/2019004
Enterprise Identifier: I-2019-004-0022
Licensee:
Duke Energy Carolinas, LLC
Facility:
Oconee Nuclear Station
Location:
Seneca, SC
Inspection Dates:
October 01, 2019 to December 31, 2019
Inspectors:
J. Nadel, Senior Resident Inspector
J. Parent, Resident Inspector
A. Ruh, Resident Inspector
A. Butcavage, Reactor Inspector
P. Cooper, Reactor Inspector
C. Dykes, Health Physicist
M. Meeks, Senior Operations Engineer
A. Nielsen, Senior Health Physicist
M. Riley, Reactor Inspector
J. Rivera, Health Physicist
Approved By:
Frank J. Ehrhardt, Chief
Reactor Projects Branch 1
Division of Reactor Projects
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Oconee Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
Failure to Verify Adequacy of Reactor Building Cooling Units Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000269,05000270,05000287/2019004-01 Open/Closed
[H.6] - Design Margins 71111.18 Inspectors identified a Green, non-cited violation of 10 CFR Part 50, Appendix B, Criterion III,
Design Control, when the licensee failed to verify the adequacy of design of the reactor building cooling units (RBCUs). Specifically, safety analysis engineers failed to verify the minimum test acceptance criteria for RBCU capacity remained adequate after modifying the safety analysis.
Additional Tracking Items
Type Issue Number Title Report Section Status LER 05000269/2019-002-00 LER 2019-002-00 for Oconee Nuclear Station,
Unit 1, Core Flooding System Loss of Safety Function 71153 Closed
PLANT STATUS
Unit 1 operated at or near 100 percent rated thermal power (RTP) for the entire inspection period.
Unit 2 began the inspection period at 100 percent RTP. On November 9, 2019 the unit was shut down for a planned refueling outage. The unit was returned to 100 percent RTP on December 11, 2019 and remained at this power level for the remainder of the inspection period.
Unit 3 operated at or near 100 percent RTP for the entire inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.04Q - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (1 Sample)
The inspectors evaluated system configurations during partial walkdowns of the following system:
- (1) Alternate chilled water system during turbine building heavy lifts over main feeder buses on November 5-7, 2019
71111.05Q - Fire Protection
Quarterly Inspection (IP Section 03.01) (4 Samples)
The inspectors evaluated fire protection program implementation in the following selected areas:
- (1) Unit 1 Turbine Building Elevation 796', Fire Zones 34, 34A, 35, 36, and 44 on October 21, 2019
- (2) Unit 2 Turbine Building Elevation 822', Fire Zones 40 and 41 on October 24, 2019
- (3) Unit 3 Turbine Building Elevation 822', Fire Zones 38, 39, and 39A on October 24, 2019
- (4) U2 Reactor Building All Elevations, Fire Zone 123 on December 8, 2019
71111.08P - Inservice Inspection Activities (PWR) PWR Inservice Inspection Activities Sample (IP Section 03.01)
- (1) The inspectors evaluated pressurized water reactor non-destructive testing by reviewing the following examinations from October 7 - 11, 2019:
1. Ultrasonic Examination (UT)
a. UT Examination of Component ID: 2-GRID-001, Containment Liner Plate, (Observed)
2. Penetrant Testing (PT)
a. Review of Pre-Fab Final PT, Weld ID 171162, Engineering Change No. 402444, Unit-2 Alloy 600 Phase III RCS Hot Leg Pressure Tap Safe End, Final PT Documentation, ASME Class 1, Fillet Weld, Work Order 20083860-03
3. Visual Examination (VT-2)
a. VT-2 Leakage Examination, 2-RPV-HEAD-PEN, Reactor Vessel Closure Head, Outer Surface, ASME Class 1 (Reviewed)
4. Eddy Current Testing (ET)
a. SG 2A-ET for tubes R12C23, R26C3, ASME Class 1 (Observed)b. SG 2B-ET for tubes R131C53, R138C33 & R151C1, ASME Class 1 (Observed)
The inspectors evaluated the licensees boric acid corrosion control program performance, through field walk-down inside containment and review of the boric acid program corrective actions and evaluations of reported leakage.
71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance
Requalification Examination Results (IP Section 03.03) (1 Sample)
- (1) Annual Review of Licensee Requalification Examination Results: On July 1, 2019, the licensee completed the comprehensive biennial requalification written examinations and the annual requalification operating examinations required to be administered to all licensed operators in accordance with Title 10 of the Code of Federal Regulations 55.59(a)(2), Requalification Requirements, of the NRCs Operators Licenses. During the week of December 16, 2019, the inspectors performed an in-office review of the overall pass/fail results of the individual operating examinations and the crew simulator operating examinations in accordance with Inspection Procedure (IP) 71111.11, Licensed Operator Requalification Program. These results were compared to the thresholds established in Section 3.02, Requalification Examination Results, of IP 71111.11.
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the Unit 2 Control Room during reactor coolant system draining to 145" on November 10, 2019.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated licensed operators perform table top training on new emergency preparedness procedure AD-EP-ALL-0111, "Control Room Activation of the ERO," Revision 0, on November 20, 2019.
71111.12 - Maintenance Effectiveness
Routine Maintenance Effectiveness Inspection (IP Section 02.01) (4 Samples)
The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:
- (1) Nuclear Condition Report (NCR) 2249515, Standby shutdown facility (SSF) diesel generator (DG) tripped on overcurrent
- (2) NCR 2294220, Repetitive processor failures in Unit 3 automatic feedwater isolation system digital channel 1B trip confirm module
- (3) NCR 02303769, Blown fuse caused a partial loss of control power to ACB-6, which provides normal auxiliary power to the 2X switchgear for KHU-2
- (4) NCR 02295613, B main control room chiller compressor tripped after seizing
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)
The inspectors evaluated the risk assessments for the following planned and emergent work activities:
- (1) Risk assessment and work controls for SSF auxiliary service water (ASW) pump oil drain/sample and analysis on October 24, 2019
- (2) Risk assessment and work controls for the Unit 2 reactor coolant system (RCS) drain down to 145 inches on November 10, 2019
- (3) Risk assessment and work controls for low pressure service water (LPSW) system breach during 2LPSW-1116 replacement on November 16, 2019
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 02.02) (6 Samples)
The inspectors evaluated the following operability determinations and functionality assessments:
- (1) Immediate determination of operability (IDO) for NCR 2294192, acceptance criteria for reactor building cooling unit capacities may be non-conservative
- (3) IDO for NCR 2300141, main control room envelope door found blocked open
- (4) IDO for NCR 02301011, evaluation of a Part 21 for Rotork Valves - failure of the beryllium copper clutch ring in their NA1 actuators manufactured between January 1, 1979 and December 31, 1982
- (5) Wall thickness acceptance evaluation for NCR 2302194, ultrasonic readings below recommended minimum thickness on Unit 2 main feed piping in east penetration room
- (6) NRC operability review of NCR 02304315, U1/U2 LPSW A & B pumps auto start due to low U1/U2 LPSW header pressure during Unit 2 engineered safeguards (ES) Ch 3 testing
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)
The inspectors evaluated the following temporary or permanent modifications:
- (1) Change to calculation OSC-8064, Appendix K to credit increased reactor building cooling unit capacities in accident containment analyses for 24 month operating cycles
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the following post maintenance tests:
- (1) Post-modification test of motor operated valve 2RC-219 per PT/2/A/0152/017, "Reactor Coolant System Valve Stroke Test," following implementation of engineering change (EC) 403752 to replace the SSF letdown line on December 2, 2019
- (2) Post-modification test of solenoid valve 2RC-223 per PT/2/A/0152/017, "Reactor Coolant System Valve Stroke Test," following implementation of EC 403752 to replace the SSF letdown line on December 2, 2019
- (3) Post-modification test of motor operated valve 2RC-218 per PT/2/A/0152/017, "Reactor Coolant System Valve Stroke Test," following implementation of EC 403752 to replace the SSF letdown line on December 6, 2019
- (4) Post-modification test PT/2/A/0400/020, "SSF RC Letdown Line Discharge Test,"
following implementation of EC 403752 to replace the SSF letdown line on December 6, 2019
- (5) PT/3/A/0203/006 A, "Low Pressure Injection Pump Test - Recirculation," following the removal and reinstallation of the 3A Low Pressure Injection Pump Motor on December 12, 2019
71111.20 - Refueling and Other Outage Activities
Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated U2R29 activities from November 9, 2019 to December 12, 2019.
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance tests:
Surveillance Tests (other) (IP Section 03.01)
- (1) PT/2/A/0203/008, "Component Test of ES Channels 3 & 4," on November 23, 2019
- (2) PT/2/A/0610/001 J, "Emergency Power Switching Logic Functional Test," on November 25, 2019
Inservice Testing (IP Section 03.01) (1 Sample)
- (1) PT/1/A/0152/013, "Low Pressure Service Water System Valve Stroke Test," on October 23, 2019
Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)
- (1) PT/2/A/0151/019, "Penetration 19 Leak Rate Test," on December 1,
RADIATION SAFETY
71124.01 - Radiological Hazard Assessment and Exposure Controls
Radiological Hazard Assessment (IP Section 02.01) (1 Sample)
The inspectors evaluated radiological hazards assessments and controls.
- (1) The inspectors reviewed the following:
Radiological Surveys
- ONS-M-20190808-8, Independent Spent Fuel Storage Installation, August 8, 2019
- ONS-M-20190913-12, Independent Spent Fuel Storage Installation, September 13, 2019
- ONS-M-20191112-63, Unit 2 Reactor Building 3rd floor, November 12, 2019
- ONS-M-20019116-14, Unit 2 Reactor Building Basement, November 16, 2019
- ONS-M-20191118-4, Unit 2 1st Floor Containment, November 18, 2019
- ONS-M-20191118-3, Unit 2 2nd Floor Containment, November 18, 2019
- ONS-M-20191119-44, Unit 2 Reactor Building Basement, November 19, 2019
- ONS-M-20191119-11, Unit 2 Reactor Building 3rd floor, November 19, 2019
Air Sample Survey Records
- ON19111200063 U2RX HDMOVE #7393...RWP 2158, November 12, 2019
- ON19111900003 U2RX Reactor Head "O" Ring Cut and Removal, November 19, 2019
Instructions to Workers (IP Section 02.02) (1 Sample)
The inspectors evaluated instructions to workers including, labels, radiation work permits and electronic dosimeter alarm setpoints used to access high radiation areas.
- (1) The inspectors reviewed the following:
Radiation Work Permits, including RWPs for airborne areas if available
- 2216, U2 RXB A/B ROTSG-Set up/Remove/Replace Primary Manway/Handhole Covers, Revision 29
- 2221, U2 RXB-A/B ROTSG Tube Plugging/ Stabilization/ Plug Removal, Revision 24
- 2069, SSF Let Down Line Replacement, Revision 0
Electronic Alarming Dosimeter Alarms
- RWP #3999, Dose rate setpoint/Dose rate alarm: 25 mrem/hr/57 mrem/hr, April 23, 2018
- RWP #1270, 50 mrem/hr /51 mrem/hr, November 2, 2018
Labeling of Containers
- Auxiliary Building 304
- Refueling Floor by equipment hatch
Contamination and Radioactive Material Control (IP Section 02.03) (1 Sample)
The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material. The inspectors verified transactions of nationally tracked sources had been reported.
- (1) The inspectors verified the following sealed sources are accounted for and are intact:
- ONS 732, March 1988, 4.0 E+5
- ONS 733, March 1988, 1.3 E+2
- ONS 65, February 1971, 5.00 E+5
- ONS 534, October 1985, 1.00 e+3
Radiological Hazards Control and Work Coverage (IP Section 02.04) (1 Sample)
The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities.
- (1) The inspectors also reviewed and observed the following risk significant radiological work activities:
- Steam Generator A & B tube plugging/manway removal
- SSF let down line replacement activities
- U2RB 2LP-176 & 177 valve inspection work
- U2 2B1 "J" leg decontamination High Radiation Area and Very High Radiation Area Controls (IP Section 02.05) (1 Sample)
- (1) The inspectors evaluated risk-significant high radiation area and very high radiation area controls, including postings and physical controls.
Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 02.06) (1 Sample)
- (1) The inspectors evaluated radiation worker awareness and performance and radiation protection technician proficiency.
71124.02 - Occupational ALARA Planning and Controls
Radiological Work Planning (IP Section 02.01) (1 Sample)
The inspectors evaluated the licensees radiological work planning.
- (1) The inspectors reviewed the following activities:
- ALARA Plan 2019-ONS-2-O-006, Safe Shutdown Facility Letdown Line Replacement, Revision 0, Revision 1, Revision 2
- ALARA Plan 2018-ONS-1-O-017, Incore Instrumentation, Revision 0
- ALARA Plan 2019-ONS-2-O-001, Incore Instrumentation, Revision 0
Verification of Dose Estimates and Exposure Tracking Systems (IP Section 02.02) (1 Sample)
The inspectors evaluated dose estimates, exposure tracking and source term reduction effectiveness
- (1) The inspectors reviewed the following as low as reasonably achievable planning documents:
- ALARA Critique (Equivalent), 2018-ONS-1-O-017, November 13, 2018
- In-Progress Review (Equivalent), 2019-ONS-2-O-006, 50%, November 15, 2019
- In-Progress Review (Equivalent), 2019-ONS-2-O-006, 75%, November 24, 2019
Implementation of ALARA and Radiological Work Controls (IP Section 02.03) (1 Sample)
The inspectors reviewed as low as reasonably achievable practices and radiological work controls.
- (1) The inspectors reviewed the following activities:
- RWP 2069, SSF Letdown Line Replacement Unit 2
- RWP 2221, Steam Generator Tube Plugging
Radiation Worker Performance (IP Section 02.04) (1 Sample)
The inspectors evaluated radiation worker and radiation protection technician performance and implementation of ALARA techniques and controls for work activities during job tasks associated with Unit 2 Refueling Outage 29.
- (1) The inspectors reviewed the following:
- Steam generator manway removal/ replacement & tube plugging
- U2RB 2LP-176 & 177 valve work
- SSF letdown line replacement
- 2B "J" leg decontamination
71124.03 - In-Plant Airborne Radioactivity Control and Mitigation
Engineering Controls (IP Section 02.01) (1 Sample)
The inspectors evaluated equipment used to mitigate and monitor airborne radioactivity and verified licensee has established trigger points for evaluating airborne alpha and beta emitting radionuclides.
- (1) The inspectors reviewed the following:
Installed Ventilation Systems
- Unit 1 and Unit 2 Main Control Room Emergency Filtration System
Temporary Ventilation System Setups
- Unit 2 Refueling Outage 29 S/G A HEPA Vacuum
Portable or Installed Monitoring Systems
- AMS-4 Continuous Air Monitor, Unit 1 and Unit 2 Spent Fuel Pool
Use of Respiratory Protection Devices (IP Section 02.02) (1 Sample)
The inspectors evaluated the licensees use and maintenance of respiratory protection equipment. This included review of respirator qualification records and grade D quality supplied air.
- (1) The inspectors reviewed the following:
TEDE-ALARA evaluations for the use of respiratory protection equipment
- Unit 2, B Cavity, "J leg decontamination
- Reactor vessel O-ring cut and removal
Respiratory protection used during work activities
- Unit 2, B Cavity, "J leg decontamination
Periodic Inspection records for staged respirators (ready-for-use)
- October 2019
- November 2019
Self-Contained Breathing Apparatus for Emergency Use (IP Section 02.03) (1 Sample)
The inspectors evaluated the licensees storage and maintenance of SCBA for emergency use. This included a review of SCBA qualification records.
- (1) The inspectors reviewed the following:
Periodic Inspection records for staged SCBAs (ready-for-use)
- August 2019
- September 2019
SCBA maintenance records (past 2 years)
- SCBA Enrad # 4214
- SCBA Enrad # 4145
71124.04 - Occupational Dose Assessment
Inspectors evaluated licensee performance with respect to the methods for instrumentation use, monitoring, assessment and assignment for occupational dose.
Source Term Categorization (IP Section 02.01) (1 Sample)
- (1) The inspectors evaluated the licensees characterization of the source term and use of scaling factors for the use of hard-to-detect radionuclide activity.
External Dosimetry (IP Section 02.02) (1 Sample)
- (1) The inspectors evaluated the external dosimetry program implementation.
Internal Dosimetry (IP Section 02.03) (1 Sample)
The inspectors evaluated the internal dosimetry program implementation.
- (1) The inspectors reviewed the following:
Whole Body Counts
- Facial Particle, U2 Reactor Building Deep End Canal Work, November 27, 2019
In-vitro internal monitoring
- Sample No. 4, Diving Activities, April 30, 2019
Dose assessments performed using air sampling and DAC-hr monitoring
- Sample ON19111900004, U2 Reactor Building Cutting of O-Ring, November 18, 2019
Special Dosimetric Situations (IP Section 02.04) (1 Sample)
The inspectors evaluated licensee methods for assessment of special dosimetric situations such as declared pregnant worker, exposure in nonuniform fields, shallow dose equivalent and neutron exposure.
- (1) In addition to DPW records inspectors also reviewed the following:
EDEX exposures
- None were available during this inspection period.
Shallow Dose Equivalent
- None were available during this inspection period.
Neutron Dose Assessment
- Temporary Neutron Exposure Log, DSC159 ISFSI Campaign, July 7, 2019
71124.05 - Radiation Monitoring Instrumentation
Walk Downs and Observations (IP Section 02.01) (1 Sample)
During plant walkdowns the inspectors evaluated and observed material condition, calibration stickers, and source check status of many portable survey instruments and personnel contamination monitors. Inspectors also observed source check demonstrations on portable instrumentation. Inspectors also evaluated the use of area radiation monitors and continuous air monitors.
- (1) Some instruments and records inspectors reviewed included but were not limited to the following:
Personnel contamination monitors, portal monitors and small article monitors
- ARGOS personnel contamination monitors at Turbine Building satellite RCA exit point
- CHRONOS small article monitors at Turbine Building satellite RCA exit point
- GEM-5 portal monitors at Protected Area exit
Portable Survey Instruments, ARMS, and Air Samplers/CAMS
- Portable ion chambers
- Portable telescoping GM detectors
- Area Radiation Monitors in Auxiliary Building
- AMS-4 continuous air monitor in U1/U2 spent fuel pool
Calibration and Testing Program (IP Section 02.02) (1 Sample)
The inspectors reviewed the calibration/testing frequency, methods and records for various types of monitoring, survey and analysis instrumentation. Inspectors reviewed results of the Inter-laboratory comparison program.
- (1) The inspectors reviewed the following calibration records:
Laboratory Instruments
- Liquid Scintillation Detector # 106756 TR-4, July 1, 2019
- High Purity Germanium Detector # 5, August 26, 2019
Whole Body Counter
- Whole Body Counter # ONSFS1, October 18, 2019
Post-Accident Monitoring Instrumentation
- 1-RIA 57, Containment High Range Radiation Monitor, March 26, 2019
- 1-RIA 58, Containment High Range Radiation Monitor, March 26, 2019
Portal Monitors, Personnel contamination Monitors, and Small Article Monitors
- ARGOS-5ABZ, Enrad ID # 07808, September 16, 2019
- GEM-5, Enrad ID # 03351, September 26, 2019
- Chronos-4, Enrad ID # 12395, September 17, 2019
Portable Survey Instruments, Area Radiation Monitors, and Continuous Airborne Monitors
- Ludlum Model 12-4 (remball), Enrad ID # 02844, January 15, 2019
- Telepole Enrad ID # 02707, March 21, 2019
- 1-RIA 1, Unit 1 and Unit 2 Main Control Room Area Radiation Monitor, September 1, 2019
- Ion chamber, Enrad ID # 11433, September 6, 2019
- AMS-4 Continuous Airborne Monitor Enrad # 10728, October 15, 2019
Electronic Dosimeters
- Dosimeter # A11CAA, August 21,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification
The inspectors verified licensee performance indicators submittals listed below:
MS06: Emergency AC Power Systems (IP Section 02.05)===
- (1) Unit 1 (October 1, 2018 - September 30, 2019)
- (2) Unit 2 (October 1, 2018 - September 30, 2019)
- (3) Unit 3 (October 1, 2018 - September 30, 2019)
MS09: Residual Heat Removal Systems (IP Section 02.08) (3 Samples)
- (1) Unit 1 (October 1, 2018 - September 30, 2019)
- (2) Unit 2 (October 1, 2018 - September 30, 2019)
- (3) Unit 3 (October 1, 2018 - September 30, 2019)
OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)
- (1) November 2018 - October 2019
PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
- (1) April 2018 - October 2019
71152 - Problem Identification and Resolution
Semiannual Trend Review (IP Section 02.02) (1 Sample)
- (1) The inspectors reviewed the licensees corrective action program for potential adverse trends that might be indicative of a more significant safety issue from July 1, 2019 through December 31, 2019.
Annual Follow-up of Selected Issues (IP Section 02.03) (3 Samples)
The inspectors reviewed the licensees implementation of its corrective action program related to the plant modifications in Trench 3 and the protected service water ductbank, the rotork motor operated valve actuators, and the Keowee CX transformer:
- (1) NCRs 2203327 and 2282671, corrective actions for NRC violations from report 2018-013 associated with separation of buried cables
- (2) NCR 2235278, resolution of NRC identified violation regarding incorrect use of combined qualification for Rotork motor operated valve actuators
- (3) NCR 2257729, deferral of planned CX PM and Doble Test following 2018 deferral of CX Doble test. Resulted in a corrective action to replace the CX Transformer ahead of the 2024 planned replacement schedule.
71153 - Followup of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)
The inspectors evaluated the following licensee event reports (LERs):
- (1) LER 05000269/2019-002-00, Unit 1 Core Flooding System Loss of Safety Function (ML19262H511). The circumstances surrounding this LER are documented in Inspection Report 05000269/2019003 Section
INSPECTION RESULTS
Failure to Verify Adequacy of Reactor Building Cooling Units Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems
Green NCV 05000269,05000270,05000287/2019004-01 Open/Closed
[H.6] - Design Margins 71111.18 Inspectors identified a Green, non-cited violation of 10 CFR Part 50, Appendix B, Criterion III, Design Control, when the licensee failed to verify the adequacy of design of the reactor building cooling units (RBCUs). Specifically, safety analysis engineers failed to verify the minimum test acceptance criteria for RBCU capacity remained adequate after modifying the safety analysis.
Description:
On December 15, 2015, safety analysis engineers revised the large break loss of coolant accident long-term containment response calculation, OSC-8064. The purpose of the revision was to show with new, improved reactor building cooling unit (RBCU)performance data, that the existing post-LOCA containment temperature and pressure profiles would remain bounding even after considering the increased decay heat produced by operating the reactor on a 24-month vs. an 18-month cycle. Maintaining the existing profiles was important because the acceptable environmental qualification of post-accident monitoring instrumentation and other electrical components in the reactor building were based on those profiles. In Appendix K of the calculation, safety analysis engineers began using a new, vendor-supplied, performance capability curve for modeling the cooling capacity of the RBCUs.
Although the improved capacity was being used in the safety analysis, the acceptance criteria for routine RBCU performance tests continued to be based on the old curve. Monitoring performance against the old curve was considered appropriate because engineers assumed that a cooling unit performing at the old curve would, under the new external conditions, also perform at the new, improved curve. Engineers made this assumption because they considered the two curves to be representative of the capacity of the same physical cooling unit with just the external conditions being changed. Inspectors identified that this assumption was incorrect because the two curves made different assumptions about the cooling units internal fouling.
On September 26, 2019, inspectors identified that when engineers began using the new, improved capacity curve, they failed to recognize that most of the improvement was due to a difference in the assumed fouling factor between the new and old curves. The old curve was based on a 0.0005 (hr-ft2-°F/BTU) fouling factor, but the new curve was based on zero fouling. Removing the fouling factor accounted for approximately 75 percent of the improvement gain in the new capacity curve. The remaining 25 percent improvement was due to the curve being generated from reactor building environmental conditions that more closely resembled the safety analysis initial conditions. As a result, a cooling unit operating at the old curve would only be operating at approximately 83 percent of what was assumed in the safety analysis.
Once the performance test acceptance criteria were recognized to be non-conservative, operators reviewed the most recent actual performance data for the three RBCUs on each unit to verify that the safety analysis could still be satisfied. For Unit 1 the available operating margin was reduced from 77 percent to 47 percent. For Unit 2 the available operating margin was reduced from 19 percent to -0.8 percent. For Unit 3 the available operating margin was reduced from 39 percent to 16 percent. The available margin is routinely monitored during plant operation because it declines over time due to tube-side fouling from the low pressure service water system. To support continued operability on Unit 2 until the planned refueling outage in November 2019, engineers demonstrated in an immediate determination of operability that the existing post-loss-of-coolant accident (LOCA) containment temperature and pressure profiles would be maintained if the assumed low pressure service water temperature was reduced from 90 degrees Fahrenheit to 85 degrees. This was reasonable because the lake temperature had already peaked for the season at 83 degrees. About two weeks later, a prompt determination of operability demonstrated an alternate approach by re-performing the safety analyses with a 20 percent reduction in assumed RBCU capacity, and showing that the post-LOCA containment temperature profile would generally be elevated by 10°F, but the limiting reactor building electrical equipment would remain environmentally qualified and operable.
Corrective Actions: The licensee revised the safety analysis to reflect the expected minimum RBCU capacity, issued a human performance crew learning communication to the safety analysis group, and initiated action to procure additional RBCU data from the vendor to validate assumptions.
Corrective Action References: NCR 2294192
Performance Assessment:
Performance Deficiency: The failure to verify the adequacy of design of the RBCUs per 10 CFR Part 50, Appendix B, Criterion III, was a performance deficiency. Specifically, safety analysis engineers failed to verify the minimum test acceptance criteria for RBCU capacity remained adequate after modifying the safety analysis.
Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. Specifically, the non-conservative acceptance criteria could have reasonably resulted in unintended operation outside of the safety analyses because expected higher fouling over time could have reduced margin to the point where the safety analyses were no longer bounding.
Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 2, Mitigating Systems Screening Questions, inspectors determined the finding was of very low safety significance (Green) because it was a deficiency affecting the design of the RBCUs, and qualification of reactor building electrical equipment, but they maintained their operability.
Cross-Cutting Aspect: H.6 - Design Margins: The organization operates and maintains equipment within design margins. Margins are carefully guarded and changed only through a systematic and rigorous process. Special attention is placed on maintaining fission product barriers, defense-in-depth, and safety related equipment. In this case, a change was made to a design calculation that involved items outside the expertise of the originator (i.e.
fouling). Applying special attention and rigor such as obtaining additional reviews from subject matter experts or the vendor may have prevented the error. Although the original deficiency was introduced more than the nominal three-year period typically associated with present performance, the cross-cutting aspect was assigned because, in April 2019, safety analysis engineers re-validated the existing methodology after it was questioned by site engineering.
Enforcement:
Violation: 10 CFR Part 50, Appendix B, Criterion III required, in part, that design control measures shall provide for checking the adequacy of design, such as by the performance of design reviews. Contrary to the above, since December 15, 2015, the design review performed for large break loss of coolant accident long-term containment response did not verify the adequacy of design of the RBCUs. Specifically, safety analysis engineers failed to verify the minimum test acceptance criteria for RBCU capacity remained adequate after modifying the safety analysis.
Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On December 12, 2019, the inspectors presented the Radiation Protection Baseline Inspection inspection results to Ed Burchfield, Site Vice President and other members of the licensee staff.
- On January 27, 2020, the inspectors presented the integrated inspection results to J. Ed Burchfield and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.04Q Calculations
OSC-10963
Electrical Design Input Calculation for Engineering Change 110408
OSC-10969
Mechanical Design input Calculation for the Alternate
Chilled Water (AWC) System
OSC-7934
Auxiliary Building GOTHIC Heat Up Analysis - PSW Event
Cases
OSC-9659-ICC-
0004
NFPA 805 Impacts due to AWC Manual Valve Position
Changes
Corrective Action
Documents
286301, 20153797, 2276864, 1854557, 1857675,
277519, 2278566, 2296376, 2298512, 2167815
Drawings
O-6708
One Line Diagram Alternate Chill Water (AWC) 4160/600V
System
O-6708-A
One Line Diagram Alternate Chill Water (AWC) 600/208V
System
O-6708-B
One Line Diagram Alternate Chill Water (AWC) 600/208V
System
OFD-116Q-1.1
Flow Diagram of AWC System Yard Chillers and Auxiliary
OFD-116Q-1.2
Flow Diagram of AWC System Auxiliary Building Chiller
No.1 Main Headers
OFD-116Q-1.3
Flow Diagram of AWC System Auxiliary Building Chiller
No.2 Main Headers
OFD-116Q-1.4
Flow Diagram of AWC System Auxiliary Building Cable
Rooms
OFD-126C-1.1
Flow Diagram of Drinking Water System (Drinking Wtr.
Make-up Service Building)
OFD-126C-1.2
Flow Diagram of Plant Drinking Water System (Turbine
Bldg., Admin. Bldg., IRW Facility, & QA Radiographic
Facility Supply)
Procedures
AM/0/A/3007/066
Abnormal Procedure for Installation and Removal of RBCU
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Hale Pumps and Hoses
AM/0/A/3007/085
Abnormal Procedure for Installation and Removal of Unit 1
and 2 Cable Room AWC Coolers
AM/0/A/3007/086
Abnormal Procedure for Installation and Removal of
Nitrogen System for Auxiliary Building Air Handling Units
and Exhaust Fan Damper Control During AWC Operation
AM/0/A/3007/087
Abnormal Procedure for Installation and Removal of AWC -
Trane 500-Ton Model RTAC Chiller Make-up Water
AP/1-
2/A/1700/036
Degraded Control Room Area Cooling
OP/0/A/1106/029
C
Alternate Chilled Water System
71111.05Q Calculations
OSC-10731
Fire PRA Input to the ONS NRPA 805 Monitoring Program
003
OSC-9314
NFPA 805 Transition Risk-Informed, Performance-Based
Fire Risk Evaluation
006
OSC-9378
ONS Fire PRA (FPRA) Summary Report
004
OSC-9659
Oconee Nuclear Safety Capability Assessment for Units 1,
2, and 3
011
Drawings
O-0756-M
Fire Detection System Detector Tabulation
21
Fire Plans
CSD-ONS-FS-020 Standard Operating Guide Key Equipment List by Fire Zone
CSD-ONS-PFP-
Pre-Fire Plan for U1 Turbine Building Elevation 796
CSD-ONS-PFP-
2RB
Pre-Fire Plan for U2 Reactor Building All Elevations
CSD-ONS-PFP-
Pre-Fire Plan for U2 Turbine Building Elevation 822
CSD-ONS-PFP-
Pre-Fire Plan for U3 Turbine Building Elevation 822
Calculations
NS-TECR-102658
Oconee Mathematically Calculated Calibration Curve
Rev. 001
Calibration
Records
MIZ-80
166, 526480, 540464, 542183, 542555, 544984, 648200,
648202, 649080, 649081, 654402, 654403, 654404
Probes
11342, 12024, 14379, 23627, 24010, 24058, 24654, 25921
S000001-07-
Mechanical Rolled Tube Plug & Stabilizer Installation Field
Rev. 13
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
000015
Procedure for Replacement Once Through Steam
Generators
Corrective Action
Documents
A/R # 02294252
2HP-123 Boron Leak Containment Isolation Valve
9/27/19
ACTION
REQUEST -
2302962
NCR - ISI Visual Examination of 2-RPV-HEAD-PEN
11/17/19
Active Boric Acid Leak from Valve 2HP-110
2/10/17
2C-HPI Pump Shaft has Active Boron Leak
2/20/17
ISI Visual Examination of Component 2-SCV-011,
Containment Liner
11/16/19
Boric Acid Corrosion Evaluation
10/24/19
Corrective Action
Documents
Resulting from
Inspection
NCR-02302449
BORON OBSERVED IN PRESSURIZER HEATER PLUGS
11/14/19
NCR-02302598
Safety Concern - Fall Protection
11/14/19
Clean (Boric Acid ) Stains on Underside of Grating Below 2B
Hot Leg Elbow, Considerable deposits on the underside of
grating, below the pressurizer surge line where the hot leg
comes out.
11/9/19
Boron Observed on Pressurizer Heater Sleeves
11/13/19
Drawings
0-ISIC2-1062-
0010
Oconee Unit-2, Containment Liner Plate, In-service
Inspection Areas, Developed Elevation, Sht. 2
Rev. 2
0-ISIC2-1962-009
Oconne Unit-2, Containment line Plate, In-service Inspection
Areas, Developed Elevation, Sht. 1
Rev. 2
28719E
B&W Reactor Vessel Radio-graphic Outline and Weld
Identifiers
Rev. 3
149766E
Pressurizer Heater Bundle Assembly and Details
Rev. 8
151991 E
Arrangement Reactor Vessel Longitudinal Section
Rev. 14
5059428B
BWI Replacement OTSG EDM/ASME/WEAR Array
Calibration Standard
Rev. 0
O-1479 A
Oconee U-2, Piping Layout, Ground Floor Plan, Reactor
Building
Rev. 55
OM 1201.-
1538.001
(151991-E)
Arrangement Reactor Vessel Long Section
Rev.14
Engineering
0300-TECR-
Condition Monitoring and Preliminary Operational
Rev. 0
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Evaluations
104094
Assessment for Oconee-2 O2R29 Outage
3011-AST-101520 Steam Generator Condition Monitoring and Final
Operational Assessment for Oconee-2 O2R28 Outage
Rev. 0
AD-EG-PWR-
1813
Steam Generator Degradation Assessment
Rev. 0
Evaluation
Valve 2HP-123
9/27/19
NCR-02171026,
Corrosion
Evaluation
Evaluation of Active Boric Acid Leak at Valve 2HP-VA-110
1/10/18
Oconee Unit-2,
Cycle 29
Collective Significance Review for Leakage
2/27/19
Miscellaneous
Badge # 285307
Duke Energy, NDE Examiner Certification Review
9/5/19
Badge # 463070
Duke Energy, NDE Examiner Certification Review
9/10/19
Badge #224415
Duke Energy, NDE Examiner Certification Review
9/9/19
Badge #472208
Duke Energy, NDE Examiner Certification Review
9/5/19
C-Q-02.04-F02
Training Attendance Roster
O2R29
GTOO0808-04
ASME Section XI, Welding Procedure Specification
Technical Sheet
Rev. 4
NIS 2-A (Work Order 20083860
Owners Certificate of Conformance for Repair Replacement
Plan 20083860-03
1/17/18
Oconee UFSAR
Section 3.8
Design of Structures
2/31/17
Oconee Unit-2
Doc. ID 2015-85
Integrated Leakage Rate Test Report
2/7/2015
Personnel
Qualifications
ST3118
Completion
Information
Oconee WO 20218685 Completion Information
11/19/19
Visual Acuity
NDE Reports
UT-19-010
System ID: CONT (Containment Liner Plate), Component
11/16/19
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
ID: 2-GRID-001, Ultrasonic Examination Report IAW,
Procedure NDE-NE-ALL-6401
gRID-001
VT-17-107
Visual Examination for Boric Acid Detection, RPV Bottom
Head BMI Nozzles
1/25/18
VT-19-076
System ID: CONT (Containment), Component ID: 2-SCV-
011, Report of Visual Examination of IWE Surfaces (VT-1)
11/14/19
VT-19-110
Component ID, 2-RPV-HEAD-PEN, Reactor Pressure
Vessel Outer Head Surface -Visual Examination
11/22/19
Procedures
0300-PLAN-
103523
ROTSG ECT Inspection Plan
Rev. 1
8-QPP-761
Multifrequency Eddy Current Examination of Steam
Generator Tubing
Rev. 8
ETSS
13091.2, 27091.2, 96042.1, 96043.4
NDE-NE-ALL-
6102
Utilization of PDI-UT-2 Generic Procedure for the Ultrasonic,
Examination of Austenitic Pipe Welds
Rev. 002
NDE-NE-ALL-
6403
Straight Beam Ultrasonic Examination
Rev. 000
NDE-NE-ALL-
7402
Visual Examination of IWE Components
Rev. 1
NDE-NE-ONS-
0131
Eddy Current Guidelines for Oconee Nuclear Station's
Replacement Once-Through Steam Generators
Rev. 2
NDE-NE-ONS-
0132
ROTSG Site Technique Validation for Oconee Nuclear
Station
Rev. 2
O-ISISG-
0169.030.0050
Fifth Interval Steam Generator Inservice Inspection Plan
Rev. 1
S000001-07-
000015
Mechanical Rolled Tube Plug & Stabilizer Installation Field
Procedure for Replacement Once Through Steam
Generators
Rev. 13
Work Orders
20154083
2HP-123 Boron Leak-Containment Isolation
9/27/19
Oconee Unit-2 Alloy 600 Phase III, RCS Hot Leg Pressure
1/17/18
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Tap Safe End, Weld Pre-Fab of Instrument Valves, for
Outage 02R28
2HP-348 has 1/4 TSP. DRY BORON on PIPE CAP
11/13/19
Oconee Unit-2, Engineer (Mode 3) Reactor Bldg. Boric Acid
Leak Inspection
11/9/19
Active Boron Leak From Valve 2HP-110
11/26/19
Active Boron Leak from Valve 2HP-110
2/10/17
2HP-348 Has 1/4 TSP Dry Boron on Cap
11/13/19
71111.11Q Procedures
OP/0/A/1102/026
Operations IPTE Pre-Job Briefings
031
OP/2/A/1103/011
Draining and Nitrogen Purging RCS
101
Corrective Action
Documents
200104, 2249753, 1845371, 1773940, 1761628, 2290674,
291819, 2294220, 2291906, 2292616, 2298746, 2298508,
295613, 02296687, 02303769, 02299588
Drawings
K-0700
One Line Diagram Relays & Meters 13.8-230kV
OEE-345-105
Elementary Diagram AFIS Analog Inputs to Digital Channel
Trip Confirm (Blue)
OM 2311.D-
21.001
Oconee Unit 3 AFIS - STAR Trip Confirm Dig. CH 1 & 2
15V DC Distribution
D1
OM 351-0272.001
Circuit Board Assembly
A
OM 351-0274.001
Final Assembly - Regulator
A
OM 351-0275.001
Schematic - Remote S.V.S Regulator 3-phase with
Paralleling
A
Miscellaneous
Maintenance Rule (a)(1) evaluation for NCR 2292616
Maintenance Rule Expert Panel Meeting Minutes dated
November 7, 2019
Equipment Reliability Suite, MRule - Function Scoping
software
Oconee OAC
eSOMS - Operator Logs
Regulatory Guide 1.160 - Monitoring the Effectiveness of
Maintenance at Nuclear Power Plants
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
8003189-AFIR-1
As-Found Inspection Report for Automatic Voltage
Regulator, Repair and Return
OM 2201.C-
28.001
STAR System Instruction Manual
D07
OM 351-0164.002
SSF Diesel Generator Instructions and Parts Manual
OSS-0254.00-00-
26
(ELEC) Automatic Feedwater Isolation System
Procedures
AD-EG-ALL-1210
AD-EG-ALL-1311
Failure Investigation Process (FIP)
IP/0/A/2005/004
NEI, PP-EP SVS Static Voltage Regulator Exciter System
IP/0/A/2005/004 A
SSF Diesel Generator Automatic Voltage Regulator Bench
Test
Work Orders
208499, 2083722, 20201615, 20208939, 20357208,
20154895, 20157106
Drawings
OFD-124B-2.1
Flow Diagram of Low Pressure Service Water System
(Auxiliary Building Services)
OFD-133A-2.5
Flow Diagram of Condenser Circulating Water System (SSF
AUX. Service)
OM 245.-
28.001
Velan Bolted Cover Swing Check Valve (Cast)
Miscellaneous
Complex Activity Plan for 2LPSW-1116 during O2R29
and 1
O2R29 Shutdown Safety Overview - Outage Defense in
Effect
Oconee U2, O2R29 Summary Schedule, IRT
September
9, 2019
Procedures
MP/0/A/1200/108
Valve-Removal and Installation of Flanged Valves or Wafer
Valves to Piping
MP/0/A/1840/040
Pumps - Motors - Miscellaneous Components - Lubrication
- Oil Sampling - Oil Change
039
OP/0/A/1102/026
Operations IPTE Pre-Job Briefings
031
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
OP/2/A/1103/011
Draining and Nitrogen Purging RCS
101
Site Directive
1.3.5
Shutdown Protection Plan
Work Orders
20137409, 20352487
Calculations
OSC-5649
LPSW Test Acceptance Criteria (TAC)
Corrective Action
Documents
292821, 2286307, 02304315, 02293695, 02301011
Drawings
18ALV500X11
ALV Pump
B
OFD-124A-3.1
Flow Diagram of Low Pressure Service Water System
Turbine Building
OM 1240-002
Instruction Manual Operation-Maintenance Instructions and
Parts Catalog for Automatic Pipeline Strainer Model No. 590
& 592
OM 208-0064.001
Service Water Pump Installation Manual
OM 240-002
Zurn Strain-O-Matic Model 67 Automatic Self-Cleaning
Strainer with Exclusive Lin-A-Flo Design
OM 245-617
Chart of List 1233 F.E. Tilting Disc Check Valves with
Flexitallic Gasket
ONTC-3-124A-
0006-001
Unit 3 LPSW Pump Discharge Check Valve Leakage Test
Acceptance Criteria
OSC-10448
Environmental Qualification Evaluation for Oconee Reactor
Building Water Level Transmitters and Supporting
Equipment
OSC-2784
Oconee Fouled Coolers / High Lake Temperature
Equipment Qualification Evaluation
Miscellaneous
Results / Erosion / Corrosion Wall Thickness Acceptance
Evaluation for locations 2-FDW60-A & 2-03-18-25
UT Erosion/Corrosion Examination Summary No. O2-05927,
O2-05930
Licensees Logs via eSOMS
Oconee OAC SDS
Code for Operation and Maintenance of Nuclear Power
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2004
Plants
OSS-0254.00-00-
1004
(Mech) Design Basis Specification for Standby Shutdown
Facility Reactor Coolant Makeup System
056
OSS-0254.00-00-
28
(Mech) Design Basis Spec for the Low Pressure Injection
and Core Flood System (LPI)
059
Procedures
AP/1/A/1700/024
Loss of LPSW
28
MP/0/A/1600/031
Strainer - Zurn - LPSW Pump Maintenance
PT/0/0160/006
Reactor Building Cooling Units Performance Test performed
March 11, 2019
PT/2/A/0160/002
Reactor Building Cooling Unit Air Flow Test performed
November 16, 2017
PT/2/A/0203/008
Component Test of ES Channels 3 & 4
25
Work Orders
20346861, 2142983, 20304470
Calculations
OSC-10511
LPSW Flow to RBCUs for Environmental Qualification
Purposes
OSC-5666
Reactor Building Cooling Unit Performance Test - Unit 2
67, 68
OSC-5667
Reactor Building Cooling Unit Performance Test - Unit 3
OSC-6146
Post-LOCA Reactor Bldg Cooling Unit Capacity
OSC-8064
ROTSG Long-Term Containment Response Following a
Large Break LOCA
Corrective Action
Documents
294192, 1905036
Engineering
Changes
110165
Revise TAC Sheets for setpoints of LPSW pressure
switches and LPSW pump TAC sheets ONTC-1-12
Miscellaneous
ONEI-0400-400
Oconee Nuclear Station Revised RBCU Requirements in
Support of 1-Year Mission Times
Calculations
OSC-10826
SSF Letdown Flow Instrumentation Loop Uncertainty, 1/2/3
RC FE0016
OSC-11212
SSF RC Letdown Line Valve Data Sheet Calculation (RC-
218, RC-219, RC-223)
OSC-5675
Generic Letter 89-10 Calculation for Unit 2 Gate and Globe
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Valves
OSC-7184
Generic Letter 89-10 MOV Calculation for Units 1,2, 3 Gate
and Globe Valves at Oconee
Corrective Action
Documents
2304894
Drawings
O-1721-C
RC Makeup & Letdown and High Pressure Injection &
Purification System
2D
OFD-101A-2.5
Flow Diagram of High Pressure Injection System (SSF
Portion)
OFD-102A-2.1
Flow Diagram of Low Pressure Injection System (Borated
Water Supply And LPI Pump Suction)
OFD-104A-1.1
Flow Diagram of Spent Fuel Cooling System
OFD-107A-2.1
Flow Diagram of Coolant Storage System Quench Tank
Portion
OM 245.-
2830.001
DMV-2184, 2.5 Class 2500 SD Valve, BW Ends, with
Rotork 25NET1 Electric Actuator
OM 253.-
23.001
Solenoid Operated Valve Energize to Open (FC) On/Off 2.5-
inch BW
ONTC-2-101A-
25
Unit 2 SSF RC Letdown Line Performance Test
Engineering
Changes
Modify U2 SSF RCS Letdown Line to Support SSF
Operability in All Modes of Operation
Miscellaneous
EC403752 Post-Modification Test Exceptions Management
Review
November
14, 2018
OM 245.-
2830.003
NIB - Flow Test Two SPX Flow Copes-Vulcan 2.5-inch
Class 2500# Severe Duty Control Valves (DMV-2184 &
DMV-2198)
OM 245.-
2830.005
NIIB - (DMV-2184 & DMV-2198) Weak Link Report with
Seismic Acceleration & Fatigue Life 2.5 Class 2500
OM 245.-
2830.020
I/B - DMV-2184 & DMV-2198 25NET Hand/Auto Lever
Upgrade Instructions
Procedures
IP/0/A/3001/011 L
Diagnostic Testing Motor Operated Valves Using
Teledyne/Quicklook System
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
OP/2/A/1600/008
SSF RC Makeup and Letdown Systems
035
PT/2/A/0152/017
Reactor Coolant System Valve Stroke Test
2
PT/2/A/0400/020
SSF RC Letdown Line Discharge Test
011
PT/3/A/0203/006
A
Low Pressure Injection Pump Test - Recirculation
094
TN/2/A/403752/E1 Procedure for Implementation of EC403752 - Unit 2 SSF
RC Letdown Line Control Circuit Replacement Installation
001
Work Orders
20307071-99, 20307071-42, 20307071-43, 20367709-11,
20307071-66, 20307071-50
Corrective Action
Documents
2307084, 2167511, 2306246, 2306288, 2307084, 2934250
Drawings
OFD-124B-2.1
Flow Diagram of Low Pressure Service Water System
(Auxiliary Building Services)
OM 245.-
28.001
Bolted Cover Swing Check Valve (Cast)
Miscellaneous
Complex Activity Plan for 2LPSW-1116 during O2R29
0, 1
Oconee Nuclear Station Technical Specifications, Revised
August 8, 2019
Oconee Nuclear Station Selected Licensee Commitments
November
7, 2019
Oconee U2, O2R29 Summary Schedule, IRT
September
9, 2019
Generic Letter No. 88-17, Loss of Decay Heat Removal
October 17,
1988
Unit Shutdown/Cooldown & Depressurization JITT NIGHT
Shift
5m
Clearance OPS-2 -19-LPS-2LPSW-1116 -0455
O2R29
Shutdown Safety Overview - Outage Defense in Effect
Procedures
AD-MN-ALL-0002
AD-OP-ALL-0203
Reactivity Management
AP/1-
2/A/1700/035
Loss of SFP Cooling and/or Level
24
EP/2/A/1800/001
Restoration of Power
001
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
0P - Enclosure
5.38
FG/0/A/1900/005
Initial Assessment and FLEX Equipment Staging
005
MP/0/A/1150/002
Reactor Vessel - Closure Head - Removal
MP/0/A/1200/108
Valve-Removal and Installation of Flanged Valves or Wafer
Valves to Piping
ONEI-0400-491
Oconee 2 Cycle 29 Core Operating Limits Report
2
OP/0/A/1102/026
Operations IPTE Pre-Job Briefings
031
OP/0/A/1108/001
Curves and General Information
115
OP/0/A/1108/001
A
Reactor Core and SFP Loss of Cooling Heatup Tables
007
OP/1-
2/A/1104/006
SF Cooling System
109
OP/2/A/1102/001
Controlling Procedure for Unit Startup
279
OP/2/A/1102/004
Operation At Power
26
OP/2/A/1102/004
A
ICS Operation
014
OP/2/A/1102/010
Controlling Procedure for Unit Shutdown
2
OP/2/A/1103/004
A
RCS Boration
25
OP/2/A/1103/011
Draining and Nitrogen Purging RCS
101
OP/2/A/1105/019
Control Rod Drive System
27
PT/0/A/0711/001
Zero Power Physics Test
PT/2/A/0115/012
Unborated Water Source Isolation Verification
005
PT/2/A/0600/001
B
Instrument Surveillance Prior to Mode Change
044
PT/2/A/0600/030
NI Overlap
001
PT/2/A/1103/015
Reactivity Balance Procedure (Unit 2)
Site Directive
Manual 1.3.5
Shutdown Protection Plan
TE-MN-ALL-0002
Foreign Material Exclusion Level and Controls Screening
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Work Orders
20304120, 20137409
Calculations
OSC-4672
Unit 1 & 2 LPSW System LOCA/LOOP Response
Corrective Action
Documents
298193, 02304315
Drawings
O-422H-22-02
Instrument Detail LPSW Flow Control to Decay Heat Cooler
1B
OFD-116A-2.1
Flow Diagram of Reactor Building Purge System
OFD-124B-1.1
Flow Diagram of Low Pressure Service Water System
Engineering
Changes
2012
Equivalent Change, Use of VALCOR V70900-65-24
Miscellaneous
Licensees Logs via eSOMS
Oconee OAC SDS
Procedures
AP/1/A/1700/024
Loss of LPSW
28
PT/2/A/0150/006
Mechanical Penetration Leak Rate Data
067
PT/2/A/0150/034
Leak Rate History Record and Reactor Building Leak Rate
Verification
2
PT/2/A/0151/019
Penetration 19 Leak Rate Test
016
PT/2/A/0203/008
Component Test of ES Channels 3 & 4
25
Work Orders
20304541, 20304470
Corrective Action
Documents
222444;
200884;
207944;
211886
Miscellaneous
AD-RP-ALL-2017
Access Controls to Very High Radiation Areas and
Supplemental Access Controls for HRA and LHRA: Unit 2
December
11, 2019
Corrective Action
Documents
203837;
296924;
2166562;
241719
Miscellaneous
HP/0/B/1000/016
OTSG Platform Worker Dose Tracking; Steam Generator
Tube Plugging RWP 2221/ Task 11
November
19, 2019,
08:18
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Self-Assessments AD-PI-ALL-0300
Self Assessment and Benchmark Programs: Quick Hitter
Self-Assessment Report 02114260-05
May 05,
2017
Miscellaneous
SCBA Qualification List for the RP Group
October 31,
2019
Corrective Action
Documents
NCRs 02163071,
201294, and
221063
Procedures
AD-RP-ALL-4015
Dosimetry in Gradient Radiation Fields
Rev. 0
Corrective Action
Documents
Procedures
AD-EG-ALL-1202
Preventive Maintenance and Surveillance Testing
Administration
Rev. 8
Radiation
Surveys
ONS-M-
20181109-13
Rad Waste Room 123 Resin Batch Tk. Transfer Pump
November 9,
2018
71151
Corrective Action
Documents
200447;
241002
Miscellaneous
Unit 1, 2, and 3 MSPI Derivation Report for period ending
September 2019
MSPI Basis Document
Unit 1, 2, and 3 MSPI Margin Report for period ending
September 2019
Regulatory Assessment Performance Indicator Guideline
Calculations
OSC-11832
Evaluation of Switchyard Trenches S105 and S117
Corrective Action
Documents
1702592, 01907384, 02257729
282671,
203327,
293642
Drawings
K-0700
One Line Diagram Relays & Meters 13.8-230kV
K-0702
One Line Diagram 600 Volt Station Auxiliary Circuits
K-0708
Three Line Diagram Generator No. 1
K-0709
Three Line Diagram Transformers No. 1, 1X, 2X, CX, 1E &
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2E
Engineering
Changes
415620
Update OM-245-1931.001 vendor manual based on vendor
supplied information
415794
Keowee CX Transformer Replacement
003
Miscellaneous
CNM 1392.00-
0013.001
Doble Evaluation Criteria
DPM-1393.01-
0038.001
Rotork NQR Series Reports
EQMM-1393-01-
A01-00
Environmental Qualification Maintenance Manual -
Equipment Type: Electric Motor Actuator Manufacturer:
Rotork Model/Series: NA1
MCM 1354.00-
29.001
Overload and Short Circuit Tests of Cables
9/29/14
OM 245-0980.001
Rotork Valve Operator Nuclear Qualification (Post 1978)
OM 245-1931.001
Technical Repair Guide for Rotork Valve Actuators NA
Range Models
Procedures
AD-HS-ALL-0110
Electrical Safety
AD-MN-ALL-0002
AD-OP-ALL-0200
Clearance and Tagging
AD-PI-ALL-0100
Corrective Action Program
IP/0/A/2000/004
Doble Testing
23
OSS-0218.00-00-
0019
(ELECT) Installation Spec Cable and Wiring Separation
Criteria
OSS-0254.00-00-
4013
(MECH) Design Basis Specification for the Oconee Single
Failure
TE-MN-ALL-0202
Transformer and Apparatus Testing
000
Work Orders
20147967, 02208634, 20086331, 02164537, 02208634,
20179664, 20245600, 20008002, 20008003, 20023531