IR 05000250/2020010
| ML20090G865 | |
| Person / Time | |
|---|---|
| Site: | Turkey Point |
| Issue date: | 03/30/2020 |
| From: | James Baptist NRC/RGN-II/DRS/EB1 |
| To: | Moul D Florida Power & Light Co |
| References | |
| IR 2020010 | |
| Download: ML20090G865 (29) | |
Text
March 30, 2020
SUBJECT:
TURKEY POINT UNITS 3 & 4 - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000250/2020010 AND 05000251/2020010
Dear Mr. Moul:
On February 14, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Turkey Point Units 3 & 4 and discussed the results of this inspection with Brian Stamp and other members of your staff. The results of this inspection are documented in the enclosed report.
Five findings of very low safety significance (Green) are documented in this report. Five of these findings involved violations of NRC requirements; one was determined to be Severity Level IV. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Turkey Point Units 3 & 4.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; and the NRC Resident Inspector at Turkey Point Units 3 & 4. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety
Docket Nos. 05000250 and 05000251 License Nos. DPR-31 and DPR-41
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000250 and 05000251
License Numbers:
Report Numbers:
05000250/2020010 and 05000251/2020010
Enterprise Identifier: I-2020-010-0021
Licensee:
Florida Power & Light Company
Facility:
Turkey Point Units 3 & 4
Location:
Homestead Florida
Inspection Dates:
January 27, 2020 to February 14, 2020
Inspectors:
P. Braxton, Reactor Inspector
T. Fanelli, Senior Reactor Inspector
C. Franklin, Reactor Inspector
J. Lizardi-Barreto, Construction Inspector
M. Schwieg, Reactor Inspector
S. Kobylarz, Contractor
M. Yeminy, Contractor
Approved By:
James B. Baptist, Chief
Engineering Branch 1
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Turkey Point Units 3 & 4, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
Incorrect Ampacity for Offsite Power Circuitry Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000251,05000250/2020010-01 Open/Closed None (NPP)71111.21M The team identified a Green non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) 50, Appendix B, Criterion III, Design Control for the licensees failure to translate electric cable ampacity design basis limits into specifications, procedures, and instructions. Specifically, the licensee incorporated unanalyzed higher ampacity limits into plant operating procedures, which could cause the plants second source of offsite power to fail under load, which was a performance deficiency.
Failure to Load Test Offsite Power Source Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000251,05000250/2020010-02 Open/Closed None (NPP)71111.21M The team identified a Green non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) 50, Criterion XI, Test Control for the licensees failure to periodically perform all testing required for the cross-tie cable to the opposite units startup transformer (SUT) and the second source of offsite A.C. power as a whole, under conditions as close to design as practical for the full operation sequence that brings the offsite A.C. source into operation, including operation of applicable portions of the protection system, and the transfer of power among the nuclear power unit, the offsite power system, and the onsite power system.
Three Examples of Inadequate Design Control for Safety Related Structural Concrete Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000251,05000250/2020010-03 Open/Closed
[H.12] - Avoid Complacency 71111.21M The inspectors identified a Green NCV of 10 CFR Part 50, Appendix B, Criterion III, "Design Control," for the licensees failure to implement adequate design control measures during repair activities on safety-related structural concrete.
Two Examples of Failure to Evaluate Design Changes that Adversely Degraded Original Plant Design
Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000251,05000250/2020010-04 Open/Closed None (NPP)71111.21M The team identified two examples of an Severity level IV Green NCV of Title 10 CFR 50.59.(d)(1), "Changes, Tests and Experiments," and of Title 10 CFR 50, Appendix B,
Criterion V, "Instructions, Procedures, and Drawings," for the failure to include a written evaluation which provides the bases for the determination that plant changes did not require a license amendment pursuant to paragraph (c)(2) of 10 CFR 50.59 by ensuring that the quality of the original plant design was neither degraded nor adversely affected by subsequent plant changes or modifications in accordance with the site Quality Assurance (QA) Program document FPL-NQA-100, Revision 2, dated 1973.
Harsh Environments from High-Energy Line Breaks Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000251,05000250/2019011-01 Closed None 71111.21N The NRC identified a Green Non-Cited Violation (NCV) of 10 CFR 50.49.(d), Environmental Qualification of Electric Equipment Important to Safety for Nuclear Power Plants, for the licensee's failure to provide the analyses of high energy line breaks (HELBs) including cracks in piping in the vicinity of onsite power equipment necessary for safe shutdown of the nuclear plant. Specifically, the licensee failed to provide the required analyses of the environmental conditions, including temperature, pressure, humidity, radiation, chemicals, and submergence at the locations in the turbine building where the equipment must perform.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
===71111.21M - Design Bases Assurance Inspection (Teams)
The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:
Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (5 Samples)
- Material condition and configuration (e.g., visual inspection during a walkdown)
- Consistency between station documentation (e.g. procedures) and vendor specifications
- Corrective maintenance records, and corrective action history
- Compliance with UFSAR, TS, and TS Bases
- Calculations: (pump head, capacity, NPSH, Vortexing)
- Normal and emergency operating procedures
- Completed surveillance tests to ensure acceptance criteria have been met
(2)125VDC Distribution Panel 3D23
- Material condition and configuration (e.g., visual inspection during a walkdown)
- Operating environment
- Consistency between station documentation (e.g. procedures) and vendor specifications
- Maintenance effectiveness
- Corrective maintenance records, and corrective action history
- Breaker short circuit capacity
- Panel loading
- Load voltage adequacy
- Overcurrent protection and coordination (3)4160V 3A Switchgear Cross-tie to Unit 4A Startup Transformer
- Material condition and configuration (e.g., visual inspection during a walkdown)
- Operating environment
- Consistency between station documentation (e.g. procedures) and design analyses
- Maintenance effectiveness
- Corrective maintenance records, and corrective action history
- Cross-tie procedure adequacy
- Cross-tie cable load current
- Adequacy of voltage during cross-tie
- Cross-tie breaker 3AA22 overcurrent setting and calibration testing
- Cross-tie maintenance, surveillance, and load testing
- (4) Unit 3 & Unit 4 EDG Sequencers
- Surveillance testing and recent test results
- Compliance with UFSAR, TS, and TS Bases
- Material condition and configuration ( i.e. visual inspection during walkdown)
- Adequacy of corrective action activities
- (5) Unit 3 & Unit 4 Emergency Diesel Generator Room Ventilation
- Visual non-intrusive inspection (walk down) to assess the installation configuration, material condition, and potential vulnerability to hazards
- Normal and emergency operating procedures
- Protection against external external events (seismic and tornado)
- Maintenance effectiveness (e.g., MR, procedures)
- Vendor specification
- Set-points and instrument uncertainty
- Room heat up/ventilation
- Flow rate tests
- System Health (Failures, CRs, OP Evals)
- Modifications
Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===
- (1) Unit 4 CCW Heat Exchangers/Pumps/Head Tanks, and TPCW isolation valve for CCW POV-4882, POV-4883
- Heat exchanger design (number of tubes, number of passes)
- Shell flow rate and tubes flow rate
- Availability of cooling water
- HX testing/cleaning
- Pump flow rates and pressure/head capacity curve/NPSH
- Vortex formation
- Head Tank design (elevation and capacity)/pressure rating/fill source and capability/interaction with the surge tank
- Relief valve location and design
- Valve size and capacity/operating conditions
- Operator capability to actuate the valve
Modification Review - Permanent Mods (IP Section 02.03) (2 Samples)
- (1) MSP-290147, Correction to Locked Rotor Accident Analysis
- (2) EC 291973, Unit 4 Fuel Handling Building Concrete Repairs EC 280927, EDP For Repair Of U3 Main Steam Platform Concrete Wall Associated With Pipe Support 3-MSH-3A
Review of Operating Experience Issues (IP Section 02.06) (1 Sample)
- (1) IN-17-06, Battery and Battery Charger Short Circuit Current Contributions to a Fault on the Direct Current Distribution System
71111.21N - Design Bases Assurance Inspection (Programs)
The inspectors evaluated [list program reviewed] program implementation through the sampling of the following components:
INSPECTION RESULTS
Incorrect Ampacity for Offsite Power Circuitry Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems
Green NCV 05000251,05000250/2020010-01 Open/Closed
None (NPP)71111.21M The team identified a Green non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) 50, Appendix B, Criterion III, Design Control for the licensees failure to translate electric cable ampacity design basis limits into specifications, procedures, and instructions. Specifically, the licensee incorporated unanalyzed higher ampacity limits into plant operating procedures, which could cause the plants second source of offsite power to fail under load, which was a performance deficiency.
Description:
Each nuclear Unit, 3 & 4, uses the opposite units startup transformer (SUT) as the required second source of Alternating Current (A.C.) offsite power per technical specification 3.8.1. For Unit 3, this is identified as an emergency cross-tie between the 3A 4160 Volt (V) switchgear, breaker 3AA05, the Unit 4 SUT (4X03) bushing, and then to Unit 4 breaker 4AA22. For Unit 4, this is identified as an emergency cross-tie between the 4A 4160V switchgear, breaker 4AA05, the Unit 3 SUT (3X03) bushing, and then to Unit 3 breaker 3AA22. The cross-tie cabling is sized to original plant design at 1250 MCM (1 MCM = 1,000 circular mills). The team observed that the Unit 3 cross-tie cable from the transformer included installation in outdoor covered cable trays with exposure to full sun, exposed conduits, and underground raceways for the routing to the 3A switchgear. The updated final safety analysis report (UFSAR) Table 8.2-1 limited 1250 MCM cables to 485 amperes. The UFSAR considered installed cable configurations to determine the ampacities. However, the team found that on 11/25/09, the plant operating procedures incorporated a maximum limit of 600 amperes for the cross-tie.
The licensee confirmed the 485 ampere UFSAR Table 8.2-1 ampacity limit in a calculation performed in 1967, but could not find the basis for the 600 ampere limit that was allowed in plant procedures since 11/25/09. The licensee stated the load on the cross-tie would normally be maintained below the 485 ampere limit as a basis for evaluating the operability for the identified condition. Loading the cable to over 485 amperes would adversely affect the reliability and availability of the offsite circuit because it could result in the failure of the cable and the loss of the second emergency source of offsite power.
Corrective Actions: The licensee entered the condition into their corrective action program.
Corrective Action References: Action Request 02343114
Performance Assessment:
Performance Deficiency: The failure to ensure that cable ampacities were controlled in accordance with the UFSAR Table 8.2-1 was a performance deficiency.
Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the 600 ampere limit in plant procedures exceeded the UFSAR design basis ampacity of the cross-tie cable which adversely affected the availability and reliability of the second source of offsite power.
Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined the finding was of very low safety significance (Green) because the finding was a design or qualification deficiency of a mitigating SSC and the SSC maintained its functionality.
Cross-Cutting Aspect: Not Present Performance. No cross cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.
Enforcement:
Violation: Title 10 CFR 50, Appendix B, Criterion III, Design Control, states, in part, that, Measures shall be established to assure that applicable regulatory requirements and the design basis, as defined in § 50.2 and as specified in the license application, for those structures, systems, and components to which this appendix applies are correctly translated into specifications, drawings, procedures, and instructions."
Contrary to the above, since 11/25/09 the site did not translate the UFSAR ampacity design basis for the cross-tie cable into procedures and instructions. Specifically, the 600 ampere limit in plant procedures adversely affected the availability and reliability of the second source of offsite power, because the limit exceeded the ampacity of the cross-tie cable and could cause the cable to fail under load.
Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
Failure to Load Test Offsite Power Source Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems
Green NCV 05000251,05000250/2020010-02 Open/Closed
None (NPP)71111.21M The team identified a Green non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) 50, Criterion XI, Test Control for the licensees failure to periodically perform all testing required for the cross-tie cable to the opposite units startup transformer (SUT) and the second source of offsite A.C. power as a whole, under conditions as close to design as practical for the full operation sequence that brings the offsite A.C. source into operation, including operation of applicable portions of the protection system, and the transfer of power among the nuclear power unit, the offsite power system, and the onsite power system.
Description:
Description: Each nuclear Unit, 3 & 4, uses the opposite units SUT, via a 1250 MCM cross-tie cable, as its required second source of A.C. offsite power per technical specification (TS) 3/4.8.1, A.C. SOURCES. The limiting conditions for operation established for TS 3.8.1.1, required, in part, as a minimum, the following A.C. electrical power sources:
a. Two startup transformers and their associated circuits
The surveillance requirement (SR) for the cross-tie circuit established that the testing consist of transferring the units power supply from the auxiliary transformer to the startup transformer. The team determined that the SR had never been performed. This was because the requisite circuit design to accomplish the testing was never installed. The UFSAR analysis section that applies to these cross-tie circuits in Section 8.2.2.1.2.1, General Design Criteria (GDC) as Defined In 10 CFR 50 Appendix A, specified, in part, that GDC 18 - Inspection and Testing of Electric Power Systems, the design of the electric power distribution system at Turkey Point does permit appropriate periodic inspection and testing of important areas and features. The testing and inspection of the electric power distribution system is governed by the surveillance requirements of Section 3/4.8 of the Turkey Point Technical Specifications. This UFSAR specification established that the surveillance for the cross-tie would periodically test:
- (1) the operability and functional performance of the cross-tie cable and
- (2) the operability of the second source of A.C. offsite power as a whole and, under conditions as close to design as practical, the full operation sequence that brings the A.C.
source into operation, including operation of applicable portions of the protection system, and the transfer of power among the nuclear power unit, the offsite power system, and the onsite power system. The team identified that the cross-ties have never been load tested during the life of the plant and the cross-tie cables insulation have never been monitored for degradation during the life of the plant.
The team found the failure to periodically test the cross-tie circuit under load does not conform with the licensing basis as described in the UFSAR and TS.
Corrective Actions: The licensee entered the condition into their corrective action program and performed an operability evaluation.
Corrective Action References: Action Request 02344617
Performance Assessment:
Performance Deficiency: The failure to periodically load test the offsite power cross-tie between units in accordance with the UFSAR Chapter 8, was a performance deficiency.
Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure to load test the unit emergency offsite power cross-tie failed to ensure the reliability and capability of the offsite power circuits.
Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined the finding was of very low safety significance (Green) because the finding was a design or qualification deficiency of a mitigating SSC and the SSC maintained its functionality.
Cross-Cutting Aspect: Not Present Performance. No cross cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.
Enforcement:
Violation: 10 CFR 50, Appendix B, Criterion XI, Test Control, states, in part, A test program shall be established to assure that all testing required to demonstrate that SSCs will perform satisfactorily in service is performed in accordance with written test procedures which incorporate the requirements and acceptance limits contained in applicable design documents. The test program shall include, as appropriate, operational tests during nuclear power plant operation.
Contrary to the above, since 1972 the site failed to establish a test program to assure that all testing required to demonstrate that the Unit emergency offsite power cross-tie will perform satisfactorily in service was performed in accordance with written test procedures which incorporate the requirements and acceptance limits contained in applicable design documents. Specifically, the licensee failed to assure the performance of all testing required to demonstrate
- (1) the operability and functional performance of the cross-tie cable and (2)the operability of the second source of A.C. offsite power as a whole and, under conditions as close to design as practical, the full operation sequence that brings the A.C. source into operation, including operation of applicable portions of the protection system, and the transfer of power among the nuclear power unit, the offsite power system, and the onsite power system.
Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
Three Examples of Inadequate Design Control for Safety Related Structural Concrete Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity
Green NCV 05000251,05000250/2020010-03 Open/Closed
[H.12] - Avoid Complacency 71111.21M The inspectors identified a Green NCV of 10 CFR Part 50, Appendix B, Criterion III, "Design Control," for the licensees failure to implement adequate design control measures during repair activities on safety-related structural concrete.
Description:
The team observed work and testing activities and reviewed design documents associated with the structural concrete repairs and cathodic protection system installation for Turkey Point Unit 4 Fuel Handling Building. The inspectors identified three examples of licensee failure to implement adequate design control measures during repair activities on safety-related structural concrete:
- Design Change Package EC 291973, "Unit 4 Fuel Handling Building Concrete Repairs," Revision 3, was issued for concrete repair work on the Fuel Handling Building. EC 291973 determined that the horizontal reinforcement steel bars within the concrete walls of the building were not structural members. However, the building code for structural concrete American Concrete Institute (ACI) 318, Building Code Requirements For Structural Concrete And Commentary, Section 14.3.3, required a minimum ratio of horizontal reinforcement (rebar) area to gross concrete area. In addition, EC 291973 Drawing CP-51, U4 FHB West Wall Cathodic Protection Cathodic Protection Details, Revision 0, illustrated the drilling of the horizontal reinforcement bars without safety related procedures or instructions controlling the work activity, for the installation of cable connections of the cathodic protection system. The holes drilled into the steel reinforcing bars reduced the cross-sectional area and strength of these horizontal reinforcement bars.
- Specification CN-2.11, "Specification for Concrete Testing, Placing, Curing and Finishing," Revision 7, required concrete cylinder tests per American Society for Testing and Materials (ASTM) C39, "Standard Test Method for Compressive Strength of Cylindrical Concrete Specimen," in accordance with ACI Code 318. However, Field Change Request (FCR) 007, Unit 4 Fuel Handling Building Concrete and Cathodic Protection System, Revision 0, for EC 291973 changed the testing to cube tests in order to align testing with the mortar vendors instructions per ASTM C109, "Standard Test Method for Compressive Strength of Hydraulic Cement Mortars." The site used a test method, intended for mortar mixtures, for the testing of concrete mixtures which was not an acceptable method for testing concrete strength and was not be in accordance with ACI Code 318 requirements.
- ACI Code 318 and 349 required the evaluation of flexural and shear loading on both vertical and horizontal direction for the selection of slab thickness and for reinforcement required to control deformation and assure adequate shear and flexural strengths. Calculation 200024-01 did not check flexural and shear loading for determining the design controlling condition, and therefore it did not determine if additional reinforcement was needed beyond the code minimum required reinforcement. Section 8.2 of Calculation 200024-01 did not check shear loading to ensure that flexural loading controls on a one-way upper wall, and Section 8.1 of the same calculation did not check flexural loading for ductility ratio on horizontal reinforcement bar. In addition, the calculations evaluated did not adequately evaluate design loading, including crane loads.
Corrective Actions: The licensee entered the issue into their corrective action program.
Corrective Action References: Action Requests 2344653 and 2344656
Performance Assessment:
Performance Deficiency: The failure to identify structural reinforcement, perform credible concrete strength testing, and perform credible structural loading evaluations in accordance with ACI 318/349, was a performance deficiency.
Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, the failure to ensure that structural concrete was designed and installed to safety standards commensurate with the safety function failed to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events.
Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The team determined the finding was of very low safety significance (Green) because it only represented a degradation of the radiological barrier function for the spent fuel pool building.
Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes. Individuals implement appropriate error reduction tools. Specifically, the licensee failed to consider and incorporate design requirements and acceptance limits contained in applicable design documents in order to perform reinforce concrete repairs in accordance with manufacturers testing instructions, design calculations and drawings.
Enforcement:
Violation: Title 10 CFR 50, Appendix B, Criterion III, Design Control, required in part, that applicable regulatory requirements and the design basis, for structures, systems, and components (SSCs), are correctly translated into specifications, drawings, procedures, and instructions; and that design changes, including field changes, shall be subject to design control measures commensurate with those applied to the original design.
Contrary to the above, since April 19, 2019, the site failed to ensure that applicable regulatory requirements and the design basis, for safety related structural concrete were correctly translated into specifications, drawings, procedures, and instructions; and that design changes, including field changes, shall be subject to design control measures commensurate with those applied to the original design.
Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
Two Examples of Failure to Evaluate Design Changes that Adversely Degraded Original Plant Design Cornerstone Significance/Severity Cross-Cutting Aspect Report Section Mitigating Systems
Green Severity Level IV NCV 05000251,05000250/2020010-04 Open/Closed
None (NPP)71111.21M The team identified two examples of an Severity level IV Green NCV of Title 10 CFR 50.59.(d)(1), "Changes, Tests and Experiments," and of Title 10 CFR 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," for the failure to include a written evaluation which provides the bases for the determination that plant changes did not require a license amendment pursuant to paragraph (c)(2) of 10 CFR 50.59 by ensuring that the quality of the original plant design was neither degraded nor adversely affected by subsequent plant changes or modifications in accordance with the site Quality Assurance (QA) Program document FPL-NQA-100, Revision 2, dated 1973.
Description:
The site Quality Assurance (QA) Program document FPL-NQA-100, Revision 2, dated 1973, stated, in part, that the quality of the original plant design is neither degraded nor adversely affected by subsequent plant changes or modifications. Procedure EN-AA-203-1102, Safety Classification Determination, Revision 7 states SSCs whose purpose is to initiate automatic safety features that are required for accident prevention and mitigation or to shut down the reactor and maintain it in a safe condition, are Safety Related. The team identified two examples where modification did not meet the above criteria.
Example 1: The team reviewed diesel room temperature calculations, PTN-3FJE-91-016, Heat Loss Calculation for EDG 3A/3B Rooms, Revision 1, JPN-PTN-SEEP-91-007, "Temperature Rating of Electrical Equipment in Emergency Diesel Generator Rooms 3A and 3B," Revision 1, and NAI-1483-001, Generator Room Heat Up Analysis, Revision 1. These calculations determined the room exhaust fans were required to maintain the diesel engine room below its maximum normal allowable temperature and thus the EDG safety function. Calculation NAI-1483-001 also determined that without the exhaust fan operating and an outside temperature of 50 degrees Fahrenheit (ºF), the maximum EDG room temperature will reach equilibrium at approximately 115.9ºF, which is above the maximum normal allowable room temperature. The licensees analyses determined that the exhaust fans are required when operating the EDGs when outside temperature is above 45ºF. The Unit 3 EDGs cannot reliably perform their safety function if the EDG room exhaust fans fail to run. This was a change to the plant design. Prior to this, the design of the plant specified that the safety related ventilation will be provided by the diesel engine radiator fans when the diesel engine is operating. It was determined that the forced ventilation due to the diesel engine cooling fans will maintain the diesel engine room below its maximum normal allowable temperature. Once this change from original plant design was identified, these fans were not treated as safety related in accordance with the site classification criteria. The design change was also not evaluated to ensure the quality of the original plant design was neither degraded nor adversely affected by this change. The team noted two design issues with the exhaust fans. First, the EDG room exhaust fans did not meet design specification 5610-M-36, Exhaust Fans for Ventilation, Revision 3, which required backdraft dampers, which were either not installed or were removed at some point in time. This allowed the fans to freewheel in reverse from breezes blowing through the rooms. Second, the exhaust fans were not seismically qualified in accordance with quality standards commensurate with their safety function. The reliance on non-Appendix B equipment and acceptance of design flaws in the exhaust fan design result in more than a minimal increase in the likelihood of occurrence of a malfunction of the safety related electrical equipment in the diesel rooms that were previously evaluated in the final safety analysis report.
Example 2: In 1983, in Plant Change and Modification (PCM)83-141 package the licensee modified the safety related load center and switchgear rooms (LCSWGR). The PCMs purpose was to upgrade fire barriers around the site including the LCSWGR. These modifications sealed both trains of LCSWGR preventing natural air flow. Prior to this, each train of the LCSWGR were vented to the outside, and were partially open to one another allowing air to flow between them. The PCM stated, in part, fan 3V15 must be removed from the 4160V Switchgear room to allow the fan opening to be closed for the purpose of installing a fire door and barrier between Switchgear rooms 3A and 3B. These prior features would allow natural air circulation to flow through the rooms. In 1992 the licensee performed calculation JPN-PTN-SENJ-92-003, Safety Assessment for Load Center and Switchgear Rooms HVAC Safety Classification. This was in response to an internal technical audit that the prior PCMs contained no basis for the statement that the HVAC facilities do not perform a safety function. The calculation stated, in part, that early post operating license modifications separated the rooms [3A & 3 B], closed the exterior wall openings and installed direct expansion air conditioning units in the rooms with condenser units located outdoors. The calculation verified that the HVAC does not perform a safety function because the LCSWGR doors could be opened as a last resort. However, it did not identify the potential high energy line breaks (HELBs) concerns that would then affect the LCSWGR. Non-safety related and non-seismically qualified high energy fluid equipment and piping surround the LCSWGR, and currently the LCSWGR doors are not HELB barriers. The quality of the original plant design was degraded and adversely affected by these changes. The reliance on non-Appendix B equipment in the new LCSWGR configurations and the failure to recognize that the LCSWGR were exposed to possible HELBs result in more than a minimal increase in the likelihood of occurrence of a malfunction of the safety related electrical equipment in the LCSWGR that were previously evaluated in the final safety analysis report.
Corrective Actions: The licensee performed a prompt operability determination to ensure the operability of the commercial components that perform safety related functions and determined that the components were operable but non-conforming.
Corrective Action References: Action Requests 2343688, 2344552, and 2344655
Performance Assessment:
Performance Deficiency: The failure to ensure that the quality of the original plant design was neither degraded nor adversely affected by changes was a performance deficiency.
Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the use of commercial components in safety related applications, aggravated by the design deficiencies, and inadequate seismic design, failed to ensure the required availability, reliability and capability for safety systems.
Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The team determined the finding was of very low safety significance (Green) because the finding was a design or qualification deficiency of a mitigating SSC and the SSC maintained its functionality.
Cross-Cutting Aspect: Not Present Performance. No cross cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.
Enforcement:
The ROPs significance determination process does not specifically consider the regulatory process impact in its assessment of licensee performance. Therefore, it is necessary to address this violation which impedes the NRCs ability to regulate using traditional enforcement to adequately deter non-compliance.
Severity:
This violation was determined to be a severity level IV violation for the failure to include a written evaluation which provides the bases for the determination that plant changes did not require a license amendment pursuant to paragraph (c)(2) of 10 CFR 50.59 by ensuring that the quality of the original plant design is neither degraded nor adversely affected by subsequent plant changes or modifications and it was evaluated as having very low safety significance (i.e., green) by the SDP.
Violation: Title 10 CFR 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, requires, in part, that activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings.
Instructions, procedures, or drawings.
Contrary to the above, since 1983 the site failed to accomplish activities affecting quality in accordance with instructions, procedures, or drawings. Specifically, the licensee failed to assure that the quality of the original plant design was neither degraded nor adversely affected by subsequent plant changes or modifications in accordance with the site Quality Assurance (QA) Program document FPL-NQA-100.
Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
Harsh Environments from High-Energy Line Breaks Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events
Green NCV 05000251,05000250/2019011-01 Closed
None 71111.21N The NRC identified a Green Non-Cited Violation (NCV) of 10 CFR 50.49.(d), Environmental Qualification of Electric Equipment Important to Safety for Nuclear Power Plants, for the licensee's failure to provide the analyses of high energy line breaks (HELBs) including cracks in piping in the vicinity of onsite power equipment necessary for safe shutdown of the nuclear plant. Specifically, the licensee failed to provide the required analyses of the environmental conditions, including temperature, pressure, humidity, radiation, chemicals, and submergence at the locations in the turbine building where the equipment must perform.
Description:
The inspectors reviewed unresolved item 05000250,05000251/2019011-01 and consulted additional NRC offices and determined that a violation existed. Per the inspection procedure 71111.21N, Design Bases Assurance Inspection (Programs), for environmental qualification, the inspectors verified that there are no potential high energy break locations (verify using review of licensing basis) located in areas determined to be a mild environment.
The Turkey Point UFSAR, Section 5.4.1, Design Basis, for Pipe Whipping Restraints, described the current licensing basis (CLB) for the postulation of HELBs outside containment.
Section 5.4.1 stated in part, an analysis was performed to analyze high energy lines outside the containment for pipe failures these requirements were initially established post Operating License as a result of a request by the Atomic Emergency Commission (AEC) in 1972. This request was clarified later to provide changes and corrections to the guide entitled General Information Required for Consideration of the Effect of a Piping System Break Outside Containment, (References 7 and 8). References 7 and 8 are the (the Giambusso Letter and errata thereto). The Giambusso letter provided the criteria, used to determine the design basis piping break locations in ASME Section III, Class 1, 2, and 3 piping systems.
These classes are specifically applied to seismically qualified safety related pipes. The breaks included the double-ended pipe rupture. The errata specified, in part, that where pipes carrying high energy fluid are routed in the vicinity of structures and systems necessary for safe shutdown of the nuclear plant, supplemental protection of those structures and systems shall be provided to cope with the environmental effects (including the effects of jet impingement) of a single postulated open crack at the most adverse location(s) with regard to those essential structures and systems.
The turbine building had high energy line configurations adjacent to unprotected onsite power equipment that are required for safe shutdown. The high energy lines in these areas were neither safety related nor seismically qualified per the updated final analysis report (UFSAR)
Appendix 5A, titled Seismic Classification & Design Basis. Some of these configurations included:
In unit three,
- a motor control center (MCC) with diesel auxiliaries adjacent to main-steam lines, high energy pumps, and multiple feedwater lines.
- a diesel main power feeder was noted adjacent to main-steam lines.
- In both units 3 & 4,
- high energy fluids sources were observed adjacent to onsite power distribution switchgear rooms without designated HELB barriers.
In addition, time critical operator actions prop-open the doors to the switchgear and load center rooms would expose the equipment to the various sources of high energy fluids mentioned above. The inspectors determined that HELBs could credibly subject onsite power equipment to harsh environments for which they were not qualified. Further, the inspectors noted that Information notice (IN) 2000-20, titled "Potential Loss of Redundant Safety Related Equipment Because of the Lack of High-Energy Line Break Barriers," described such conditions, as above, as potentially risk significant.
The inspectors noted license amendments increased the core thermal power by 16.8%. The increased power level would increase the affects evaluated in any previously completed environmental effects analyses. This power uprate was an opportunity to ensure that the previous documented break analyses of the high energy piping mentioned above was up to date. Including the evaluation of postulated open cracks in pipes carrying high energy fluid where they are routed in the vicinity of structures and systems necessary for safe shutdown of the nuclear plant as mentioned in the Giambusso Letter errata, and to which the effects of the recent changes to the mass and energy release caused by the power increases would have affected.
The inspectors asked for the documented evidence of activities affecting quality related to the HELB analyses, such as detailed licensee inspections of the piping systems, reviews of the configurations, and calculations of HELB effects supporting their environmental conclusions.
The licensee was unable to supply the documentation. It was not evident to the inspectors how the licensee implemented their power uprates without their HELB analyses on hand to verify if the 1973 HELB conclusions changed. Therefore, the effects of the impact of the power uprate may be unanalyzed in some areas of the plant.
Corrective Actions: The licensee entered this issue into their corrective action program.
Corrective Action References: Action Request 2324737
Performance Assessment:
Performance Deficiency: The failure to provide the required analyses of the environmental conditions, including temperature, pressure, humidity, radiation, chemicals, and submergence at the locations in the turbine building where the safe shutdown equipment must perform in accordance with the 10 CFR 50.49 was a performance deficiency.
Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. Specifically, HELBs in the turbine building could credibly create harsh environments surrounding the safety related power trains and challenge critical safety functions.
Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined the finding was of very low safety significance (Green) because the finding did not cause an actual reactor trip AND the loss of mitigation equipment relied upon to transition the plant from the onset of the trip to a stable shutdown condition.
Cross-Cutting Aspect: Not Present Performance. No cross cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.
Enforcement:
Violation: Title 10 CFR Part 50.49.(d) required, in part, that the licensee shall prepare a list of electric equipment important to safety covered by this section. In addition, the applicant or licensee shall include the information in paragraphs (d)(1), (2), and
- (3) of this section for this electric equipment important to safety in a qualification file. The applicant or licensee shall keep the list and information in the file current and retain the file in auditable form for the entire period during which the covered item is installed in the nuclear power plant or is stored for future use to permit verification that each item of electric equipment is important to safely meet the requirements of paragraph
- (j) of this section.
- The performance specifications under conditions existing during and following design basis accidents
- The voltage, frequency, load, and other electrical characteristics for which the performance specified in accordance with paragraph (d)(1) of this section can be ensured.
- The environmental conditions, including temperature, pressure, humidity, radiation, chemicals, and submergence at the location where the equipment must perform as specified in accordance with paragraphs (d)(1) and
- (2) of this section.
Contrary to the above, the licensee failed to prepare a list of electric equipment important to safety in the turbine building covered by this section. In addition, the licensee failed to include the information in paragraphs (d)(1), (2), and
- (3) of this section for this electric equipment important to safety in a qualification file. The licensee failed to keep the list and information in the file current and retain the file in auditable form for the entire period during which the covered item is installed in the nuclear power plant or is stored for future use to permit verification that each item of electric equipment is important to safely meet the requirements of paragraph
- (j) of this section.
- The performance specifications under conditions existing during and following design basis accidents
- The voltage, frequency, load, and other electrical characteristics for which the performance specified in accordance with paragraph (d)(1) of this section can be ensured.
- The environmental conditions, including temperature, pressure, humidity, radiation, chemicals, and submergence at the location where the equipment must perform as specified in accordance with paragraphs (d)(1) and
- (2) of this section.
Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On February 14, 2020, the inspectors presented the design basis assurance inspection (teams) inspection results to Brian Stamp and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21M Calculations
18712-473-E-01
DC Voltage Drop Calculation for Safe Shutdown
Components
Rev. 1
200024-01
Unit 4 Fuel Handling Building Wall Elevation
Rev. 1
200024-02
Units 3&4 Fuel Handling Building Wall Repair Design
Rev. 1
5177-EF-11
Cable Ampacity in Duct Bank, Maintained Space Tray,
Conduit & Free Air
Rev. 2
87-261.6008
Emergency Diesel Generator Building, Diesel Generator
Room Ventilation
Rev. 4
CN-FPL-
UPRATE-096
THD Evaluation of the Impact of Thermal Conductivity
Degration on Loss of Flow and Locked Rotor Events
Rev. 0
CN-SEE-I-11-15
Turkey Point RHR Cooldown With One CCW Heat
Exchanger Out of Service
Rev. 0
CN-SEE-III-08-32
Calculation of Turkey Point Unit 3 & 4 ECCS Injection Flows
for teh Extended Power Uprates
Rev. 0
CN-SEE-III-09-4
Turkey Point EPU RHRS Cooldown
Rev. 0
Cable Ampacity and Voltage Drop Calculation
Rev. 1
FPL023-CALC-01
Turkey Point Cask Handling Facility Cooling Load
Combination
Rev. 1
JPM-TPN-SEEP-
91-007
Temperature Rating of Electrical Equipment in Emergency
Diesel Generator Rooms 3A and 3B
Rev. 1
NAI-1396-008
Control Room Isolation by Intake Radiation Monitors RAD-
6642/6643 for the Turkey Point EPU AST Analysis
Rev. 4
NAI-1396-015
Turkey Point EPU Locked Rotor Radiological Analysis with
Rev. 4
NAI-1483-001
Turkey Point Unit 3 Emergency Diesel Generator Room
Heat-Up Analysis
Rev. 1
PTN-3FJE-91-
016
Heat Loss Calculation for EDG 3A and 3B Rooms
Rev. 1
PTN-3FJE-92-
24
Start-Up Transformer No. 4 Phase Overcurrent
Rev. 1
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
PTN-3FJN-91-
048
EDG-3A and 3B Rom Ventilation Requirements and
Temperature Rise
Rev. 1
PTN-3LJM-07-
2
Unit 3 NPSH During ECCS Recirculation
Rev. 2
PTN-BFJM-96-
004
CCW Heat Exchanger Design Basis Case and Operability
Curves
Rev. 4
PTN-BFSM-02-
006
AOV Program ICW to TPCW Isolation Valve Actuator
Capability
Rev. 0
PTN-BFSM-11-
20
MOV Program: NRC Generic Letter 89-10 MOV Design
Basis Differential Pressure Determination - Post EPU
Rev. 0
PTN-BFSM-11-
21
NRC Generic Letter 89-10 MOV Thrust Calculation - Post
Rev. 2
PTN-BFSM-11-
2
NRC Generic Letter 89-10 MOV Actuator Ecaluation - Post
Rev. 5
PTN-BFSM-14-
007
Vortex Design Evaluation of Refueling Water Storage Tank
Rev. 0
PTN-BFSM-97-04 Miscellaneous CCW Head Tank Elevation Assessment
Rev. 0
Corrective Action
Documents
2061032,
2074681,
2145289,
2183242,
202574,
2301977,
2313653,
272412,
265798,
2170901,
2131691,
22159,
Corrective Action
Documents
Resulting from
Inspection
2343114,
2344617,
2343688,
2344444,
2344327,
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2342537,
2342727,
2344112,
2344552,
2344655,
2343095,
2344112
Drawings
5177-265-EG-22
Circuit Breaker Fuse/Coordination Study
Rev. 9
561 Q-M-3075
Auxiliary Feedwater System
Rev. 29
5610-E-1
Main Single Line Unit 3, Sheet 1
Rev. 47
5610-E-1
Main Single Line Unit 4, Sht. 2
Rev. 19
5610-T-E-1591
Operational Diagram Electrical Distribution, Sht. 1
Rev. 82
5612-E-1605
Battery 3A & 3B Load Profiles
Rev. 19
5613-E-11
Electrical 125V DC & 120V Instrument AC, Sheet 1
Rev. 20
5613-E-12
Electrical 125V DC & 120V Instrument AC
Rev. 12
5613-E-25
Reactor Auxiliaries Boron Sefety Injection Valve LP 'A' Cold
Leg MOV-3-843A, Sheet 28P
Rev. 11
5613-E-25
Reactor Auxiliaries Residual Heat Removal Inlet Isolation
Valve MOV-3-751, Sheet 42A
Rev. 9
5613-E-25
Reactor Auxiliaries Residual Heat Removal Inlet Isolation
Valve MOV-3-750, Sheet 37A
Rev. 9
5613-E-25
Reactor Auxiliaries Loop A Hot Leg SI Stop Valve MOV-3-
869, Sheet 27k
Rev. 8
5613-E-25
Reactor Auxiliaries Residal Heat Removal Heat Exchanger
Outlet Valve MOV-3-863A, Sheet 31A
Rev. 8
5613-E-25
Reactor Auxiliaries Refueling Water Storage Isolation Valve
MOV-3-864A, Sheet 27H
Rev. 7
5613-E-27
Mechanical Auxiliaries Diesel Generator 3A Vent Fan 3V34A Rev. 1
5613-E-3
4KV Switchgear 3A & 3B, Sheet 1
Rev. 8
5613-E-6
Emergency Diesel Generator 3A Load List
Rev. 21
5613-M-16-69
Start and Control Circuit Diesel Generator 3B
Rev. 11
5613-M-3022
Emergency Diesel Engine and oil System DG 3B Air Starting Rev. 18
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
System
5613-M-3030
Component Cooling Water System
Rev. 27
5613-M-3050
Residual Heat Removal System
Rev. 40
5613-M-3062
Safety Injection System
Rev. 45
5613-M-3070
Turbine Building Ventilation Load Center and Switchgear
Rooms Chilled Water System Train B
Rev. 4
5613-t-L1
Logic Diagram Sequencer, Sheet 12
Rev. 3
5613-T-L1
EDG Engine Start
Rev. 5
5613-T-L1, Sheet
2A
Emergency Bus Load Sequencer Loading Logic Diagram
Rev. 2
8815-008-002
Seismic Qualification of Emergency Diesel Generator
Building Rooms A & B Vent Fans
Rev. 0
PTN-M-96-093-
001
CCW System Pressurization Tank Arrangement
Rev. 0
Engineering
Changes
EDP For Repair Of U3 Main Steam Platform Concrete Wall
Associated With Pipe Support 3-MSH-3A
Rev. 7
Unit 4 Fuel Handling Building Concrete Repairs
Rev. 3
Unit 4 Fuel Handling Building Concrete Repairs
Rev. 2
FCR-001
Unit 4 Fuel Handling Building Concrete and Cathodic
Protection System
Rev. 0
FCR-002
Unit 4 Fuel Handling Building Concrete and Cathodic
Protection System
Rev. 0
FCR-003
Unit 4 Fuel Handling Building Concrete and Cathodic
Protection System
Rev. 0
FCR-004
Unit 4 Fuel Handling Building Concrete and Cathodic
Protection System
Rev. 0
FCR-005
Unit 4 Fuel Handling Building Concrete and Cathodic
Protection System
Rev. 0
FCR-006
Unit 4 Fuel Handling Building Concrete and Cathodic
Protection System
Rev. 0
FCR-007
Unit 4 Fuel Handling Building Concrete and Cathodic
Protection System
Rev. 0
FCR-008
Unit 4 Fuel Handling Building Concrete and Cathodic
Rev. 1
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Protection System
FCR-009
Unit 4 Fuel Handling Building Concrete and Cathodic
Protection System
Rev. 1
FCR-010
Unit 4 Fuel Handling Building Concrete and Cathodic
Protection System
Rev. 0
FCR-011
Unit 4 Fuel Handling Building Concrete and Cathodic
Protection System
Rev. 1
FCR-012
Unit 4 Fuel Handling Building Concrete and Cathodic
Protection System
Rev. 1
MSP-290147
Correction to Locked Rotor Accidnet analysis.
Rev. 0
Engineering
Evaluations
Functional
Assessment AR
2303370
Unit 4 Fuel Handling Building Exterior Concrete Walls -
Degraded
Rev. 3
Miscellaneous
5610-030-DB-002
Component Cooling Water System Design Basis Document
04/19/2018
5610-030-DB-002
Component Design Requirements Document Component
Cooling Water System
04/19/2018
5610-050-DB-001
Design Basis Document: Residual Heat Removal System
Rev. 14
5610-050-DB-002
Component Design Requirements Document: Residual Heat
Removal System
Rev. 15
5610-062-DB-001
Design Basis Document: Safety Injection System
Rev. 15
5610-062-DB-002
Component Design Requirements Document: Safety
Injection System
Rev. 17
5610-E-11
General Cable Corporation 5000V Power Service
Rev. 7
5610-M-36
Specification for Exhaust Fans for Ventilation
Rev. 2
5613-M-313
Instrument Setpoint List
Rev. 54
AA1539
Limitorque Type SMB Instruction and Maintenance Manual
Rev. 3
Concrete Test
11461
Levels 0 and 1 West Wall
Rev. 0
Concrete Test
11467
Patch Pours Levels 4, 5, 7
Rev. 0
Concrete Test
195-0085
East Wall North Levels 1 & 2
Rev. 0
Concrete Test
195-0094
West Wall - ICCP
Rev. 0
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Concrete Test
195-0095
South Wall ICCP
Rev. 0
Concrete Test
195-0096
West Wall Repairs
Rev. 0
Concrete Test
195-0101
West Wall - ICCP
Rev. 0
Concrete Test
195-0104
South East Wall Repairs
Rev. 0
Concrete Test
205-0002
West Wall - ICCP
Rev. 0
Structural
Deficiency Report
Spent Fuel Building Exterior (Reinforced Concrete)
8/31/2012
tca 13-21 SGTR
w Loop.xlsm
Time Critical Actions 13-21 during a SGTR with LOOP event
2/11/2020
TCA CCW
Makeup.xlsx
Time Critical Action for CCW makeup excel
2/11/2020
Turkey Point
Plant Units 3 and
Subsequent
Application
Rev. 1
V00506B
Instruction Manual for the Emergency Bus Load Sequencer
Volume III
Rev. 0
V00506D
Technical Manual for the Emergency Bus Load Sequencers
Rev. 0
Z273
Limitorque HBC Series Installation and Maintenance
Rev. 7
Procedures
0-ADM-561
Structures Monitoring Program
Rev. 9A
0-ONOP-103.2
Cold/Hot Weather Conditions
Rev. 10
0-ONOP-103.3
Severe Weather Preparations
Rev. 28A
0-PME-003.31
Vital 120 VAC and 125 VDC Breaker Maintenance
Rev.10
3-EOP-ECA-0.0
Loss of All AC Power
Rev.14B
3-EOP-ECA-0.1
Loss of All AC Power Recovery Without SI Required
Rev. 5
3-EOP-ECA-0.2
Loss of All AC Power Recovery with SI Required
Rev. 5
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
3-NOP-05
4KV Buses A, B, and D
Rev. 13
3-NOP-070
Vital Load Center and Switchgear Rooms Chilled Water Air
Conditioning System
Rev. 12
3-ONOP-004
Rev. 11A
3-ONOP-004.1
System Restoration Following Loss of Offsite
Power
Rev. 3A
3-ONOP-004.2
Loss of 3A 4KV Bus
Rev. 4C
3-OSP-023.1
Diesel Generator Operability Test
Rev. 12
3-OSP-203.1
Train A Engineered Safeguards Test
Rev. 28
4-NOP-030
Component Cooling Water System
Rev. 36
4-NOP-075.02
AFW Backup Nitrogen System Alignment And Bottle
Changeout
Rev. 8
4-ONOP-075
Auxiliary Feedwater System Malfunction
Rev. 12
4-OPS-062.2D
Safety Injection Pump 4A Comprehensive Pump Test
Rev. 9
4-OSP-050.2A
Residual Heat Removal Train A Test - Standby Alignment
Rev. 7
4-OSP-050.2B
Residual Heat Removal Train B Test - Standby Alignment
Rev. 9
4-OSP-050.2C
Residual Heat Removal Train A Comprehensive Test -
Cooldown Alignment
Rev. 17
4-OSP-050.2D
Residual Heat Removal Tran B Comprehensive Test -
Cooldown Alignment
Rev. 15
4-OSP-050.2E
RHR Check Valve Inservice Testing
Rev. 3
4-OSP-062.2A
Safety Injection Pump 4A Group B Pump Test
Rev. 9
4-OSP-062.2B
Safety Injection Pump 4B Group B Pump Test
Rev. 10
4-OSP-062.2C
Safety Injection System Inservice Valve Testing
Rev. 5
4-OSP-062.2E
Safety Injection Pump 4B Comprehensive Pump Test
Rev. 9
4-OSP-062.4
Safety Injection System - Full Flow Test
Rev. 5
4-OSP-075.5
AFW Operations Surveillance Procedure
Rev. 4
499983-01
Pull-Off Test Validation & Implementation Plan
Rev. 0
CN-2.11
Specification for Concrete Testing, Placing, Curing and
Finishing
Rev. 7
CN-2.24
Drilled-In Expansion Anchors in Concrete St. Lucie Units 1 &
and Turkey Point Units 3 & 4
Rev. 13
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
CN-2.9
Specification for Concrete Materials and Mixes, Concrete
Mixing and Transportation
Rev. 4
U4 FHB West Wall Cathodic Protection Cathodic Protection
Details
Rev. 0
Safety Classification Determination
Rev. 7
FPLCORP020-
REPT-107
Aging Management Program Basis Document - Structures
Monitoring
Rev. 1
O-ADM-232
Time Critical Operator Action Program
Rev. 12
PTN-ENG-LRAM-
00-0042
Systems and Structures Monitoring Program - Licensee
Renewal Basis Document
Rev. 13
SPEC-C-042
Specification for Grout
Rev. 0
Work Orders
252535-14
U3 MN STM Line Support, Cracked/Spalled Concrete
05/25/17
40014583,
40014584,
299561-01,
40526372-01,
RWO 07-12,
217030-01,
40437521-01,
257313-01,
40630058,
40648530,
40547572-01,
281822-01,
40542167-01,
40632651-01,
40469953-01,
40469919-01,
40469919-03,
40632645-01,
40649640-01,
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
217063-01,
40571153-01,
40441768-01,
40650889-01,
217063-04
252535-15
U3 MN STM Line Support, Cracked/Spalled Concrete
05/03/17