MONTHYEARL-2024-184, Radiological Emergency Plan Revision 772024-11-0505 November 2024 Radiological Emergency Plan Revision 77 L-2024-173, Response to Requests for Additional Information Regarding Turkey Point License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-31031 October 2024 Response to Requests for Additional Information Regarding Turkey Point License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums L-2024-175, Cycle 34 Core Operating Report2024-10-24024 October 2024 Cycle 34 Core Operating Report ML24291A2882024-10-24024 October 2024 Westinghouse Topical Report - Request for Withholding Information from Public Disclosure L-2024-177, Revised Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis2024-10-22022 October 2024 Revised Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis ML24276A2302024-10-16016 October 2024 Westinghouse Topical Report – Request for Withholding Information from Public Disclosure L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes ML24289A2372024-10-15015 October 2024 Transmittal of Revision 1 Additional Errata Pages for WCAP-18830-P (Proprietary) and WCAP-18830-NP (Non-Proprietary), Turkey Point Fuel Storage Criticality Analysis for 24 Month Cycles L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-157, Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-0303 October 2024 Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles IR 05000250/20243012024-10-0303 October 2024 NRC Operator License Examination Report 05000250/2024301 and 05000251/2024301 L-2024-147, Submission of Periodic Reports2024-10-0101 October 2024 Submission of Periodic Reports L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24269A1292024-09-24024 September 2024 Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis ML24260A2262024-09-18018 September 2024 NRC Examination Results Summary - Examination Reports: 05000250/2024301 and 05000251/2024301 ML24262A2272024-09-18018 September 2024 Transmittal of Additional Errata Pages for WCAP-18830-P (Proprietary) and WCAP-18830-NP (Non-Proprietary), Turkey Point Fuel Storage Criticality Analysis for 24 Month Cycles ML24158A0052024-09-17017 September 2024 Completion of Subsequent License Renewal Site Specific Environmental Review and Modification to Subsequent Renewed Facility Operating Licenses L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24207A0342024-09-13013 September 2024 – Exemption from Certain Requirements of 10 CFR 50.46 for Use of Axiom Fuel Rod Cladding – Letter ML24256A1132024-09-13013 September 2024 Regulatory Audit Summary Related to the Review of Regarding the Updated Spent Fuel Pool Criticality Safety Analysis License Amendment Request IR 05000250/20240052024-08-23023 August 2024 Updated Inspection Plan for Turkey Point Units 3 & 4 - Report 05000250/2024005 and 05000251/2024005 ML24234A0062024-08-22022 August 2024 Project Manager Assignment L-2024-106, Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-022024-08-12012 August 2024 Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-02 L-2024-122, Core Operating Limits Report2024-08-12012 August 2024 Core Operating Limits Report ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-089, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2024-07-25025 July 2024 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24184B2822024-07-16016 July 2024 – Request to Use a Later Code Edition and Addenda of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan 05000250/LER-2024-002-01, Condition Prohibited by Technical Specifications2024-07-10010 July 2024 Condition Prohibited by Technical Specifications L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal ML24173A1902024-06-28028 June 2024 Withdrawal of an Amendment Request ML24159A2652024-06-26026 June 2024 Correction of Safety Evaluation for Issuance of Amendment Nos. 298 & 291 Regarding Revising the Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update L-2024-100, Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project2024-06-19019 June 2024 Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter IR 05000250/20244012024-06-0505 June 2024 – Security Baseline Inspection Report 05000250-2024401, 05000251-2024401 and 07200062-2024401 L-2024-076, Reply to Notice of Violation; NOV 05000250, 05000251/2024010-052024-05-29029 May 2024 Reply to Notice of Violation; NOV 05000250, 05000251/2024010-05 L-2024-082, 2023 Annual Radiological Environmental Operating Report2024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000250/20240012024-05-10010 May 2024 Integrated Inspection Report 05000250/2024001 and 05000251/2024001 ML24135A0942024-05-0909 May 2024 Periodic Update to the Updated Final Safety Analysis Report ML24127A1862024-05-0909 May 2024 Request for Withholding Information from Public Disclosure L-2024-060, 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report2024-05-0909 May 2024 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-073, Cycle 34 Core Operating Limits Report2024-05-0101 May 2024 Cycle 34 Core Operating Limits Report L-2024-072, Cycle 33 Core Operating Limits Report2024-05-0101 May 2024 Cycle 33 Core Operating Limits Report L-2024-048, Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision2024-04-30030 April 2024 Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision L-2024-069, Radiological Emergency Plan Revision 762024-04-22022 April 2024 Radiological Emergency Plan Revision 76 L-2024-066, Sixth 10-Year Inservice Testing Interval Relief Request No. PR-022024-04-17017 April 2024 Sixth 10-Year Inservice Testing Interval Relief Request No. PR-02 2024-09-25
[Table view] Category:Status Report
MONTHYEARIR 05000250/20200062021-03-0303 March 2021 Annual Assessment Letter for Turkey Point Nuclear Plant, Unit 3 and Unit 4 Report 05000250/2020006 and 05000251/2020006 L-2019-046, Stations - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2019-03-25025 March 2019 Stations - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2017-040, Decommissioning Funding Status Reports/Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2017-03-30030 March 2017 Decommissioning Funding Status Reports/Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2016-068, Status of Required Actions for EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, and Submittal of FLEX Final Integrated Plan2016-06-20020 June 2016 Status of Required Actions for EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, and Submittal of FLEX Final Integrated Plan L-2015-194, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA- 12-051)2015-08-11011 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA- 12-051) L-2015-193, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-11011 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) L-2015-017, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA- 12-049)2015-02-26026 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA- 12-049) L-2014-243, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-08-27027 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events L-2014-041, Florida Power and Light Company'S Turkey Point Units 3 & 4, Second Six-Month Status Report in Response to 03/12/2012, Commission Order Modifying Licenses with to Requirements for Mitigation Strategies for Beyond-Design-Basis External Exte2014-02-26026 February 2014 Florida Power and Light Company'S Turkey Point Units 3 & 4, Second Six-Month Status Report in Response to 03/12/2012, Commission Order Modifying Licenses with to Requirements for Mitigation Strategies for Beyond-Design-Basis External Extern L-2013-249, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA- 12-049)2013-08-21021 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA- 12-049) L-2013-248, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation(Order Number EA- 12-051)2013-08-21021 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation(Order Number EA- 12-051) L-2013-103, Decommissioning Funding Status Reports2013-03-25025 March 2013 Decommissioning Funding Status Reports ML1214500142012-05-23023 May 2012 NFPA 805 LAR Status Matrix - May 2012 L-2009-055, Units 1 and 2, Decommissioning Funding Status Reports2009-03-27027 March 2009 Units 1 and 2, Decommissioning Funding Status Reports ML0709305552007-03-29029 March 2007 Decommissioning Fund Status Report ML0609601312006-03-27027 March 2006 Decommissioning Fund Status Report ML0506300702005-03-0202 March 2005 January Monthly Report on the Status of Open TIAs Assigned to NRR ML0501202612005-01-12012 January 2005 December Monthly Report on the Status of Open TIAs Assigned to NRR ML0434802422004-12-29029 December 2004 November Monthly Report on the Status of Open TIAs Assigned to NRR L-2004-163, Special Nuclear Material Reports Covering the Period from June 3, 2003 to May 26, 20042004-07-22022 July 2004 Special Nuclear Material Reports Covering the Period from June 3, 2003 to May 26, 2004 ML0224007982002-02-0101 February 2002 E-mail from Beth Wetzel Bulletin 2001-01 Status Report ML0224007812002-01-18018 January 2002 E-mail from Jacob Zimmerman, Bulletin 2001-01 Status Report 2021-03-03
[Table view] |
Text
March 3, 2021
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR TURKEY POINT NUCLEAR PLANT, UNIT 3 AND UNIT 4 - REPORT 05000250/2020006 AND 05000251/2020006
Dear Mr. Moul:
The Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance assessment of Turkey Point Nuclear Plant Unit 3 and Unit 4, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2020, through December 31, 2020. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.
The NRC determined the performance at Turkey Point Nuclear Plant Unit 3 and Unit 4 during the most recent quarter, was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2022.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the February 1, 2021 memo, Calendar Year 2021 Inspection Guidance During COVID-19 Telework Restrictions (ML21027A274). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
During this period the NRC scheduled an additional inspection per a revised version Temporary Instruction (TI) 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerability in Electrical Power Systems (NRC Bulletin 2012-01) for any sites who elect to implement the guidance of the Industry Initiative on Open Phase Condition, Revision 3 (ML19163A176), which included an option for relying on annunciation and operator manual actions instead of automatic protective features to isolate a power supply affected by an open phase condition. This inspection is scheduled for April 5, 2021.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 301-415-2934 with any questions you have regarding this letter.
Sincerely,
/RA/
Booma Venkataraman, Acting Chief Reactor Projects Branch 3 Division of Reactor Projects Docket Nos.: 50-250, 50-251 License Nos.: DPR-31, DPR-41 Enclosure:
St Lucie Inspection/Activity Plan (03/01/2021 - 12/31/2022)
cc Distribution via ListServ 2 SUBJECT: ANNUAL ASSESSMENT LETTER FOR TURKEY POINT NUCLEAR PLANT, UNIT 3 AND UNIT 4 - REPORT 05000250/2020006 AND 05000251/2020006, DATED: March 3, 2021 DISTRIBUTION:
M. Kowal, RII L. Gibson, RII S. Price, RII OE MAIL RIDSNRRDRO PUBLIC RidsNrrPMTurkeyPoint Resource ROPassessment Resource ROPreports Resource I
ADAMS Accession No. ML21061A251 OFFICE RII: DRP RII: DRP RII: DRP NAME J. Hamman A. Wilson B. Venkataraman DATA 2/24/21 2/24/21 3/3/21
IP 22 Inspection Activity Plan Report Turkey Point 03/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS 6 3, 4 03/01/2021 03/05/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 3, 4 03/29/2021 04/02/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing PROBLEM IDENTIFICATION & RESOLUTION 4 3, 4 03/08/2021 03/12/2021 IP 71152B 000747 Problem Identification and Resolution 3, 4 03/22/2021 03/26/2021 IP 71152B 000747 Problem Identification and Resolution TURKEY POINT INITIAL LICENSE EXAM 3 3, 4 03/29/2021 04/02/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
TI-194, OPEN PHASE CONDITION, REV. 2 2 3, 4 04/05/2021 04/09/2021 TI 2515/194 000512 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)
CORPORATE OFFICE AA/FFD INSPECTION 2 3, 4 04/19/2021 04/23/2021 IP 71130.01 000733 Access Authorization 3, 4 04/19/2021 04/23/2021 IP 71130.08 000740 Fitness For Duty Program SECURITY BASELINE INSPECTION 2 3, 4 05/10/2021 05/14/2021 IP 71130.01 000733 Access Authorization 3, 4 05/10/2021 05/14/2021 IP 71130.02 000734 Access Control 3, 4 05/10/2021 05/14/2021 IP 71130.08 000740 Fitness For Duty Program 3, 4 05/10/2021 05/14/2021 IP 71130.09 001656 Security Plan Changes 3, 4 05/10/2021 05/14/2021 IP 71151 001338 Performance Indicator Verification 3, 4 05/10/2021 05/14/2021 IP 81311 000831 Physical Security Requirements for Independent Spent Fuel Storage Installations TURKEY POINT REQUAL INSPECTION 2 3, 4 09/20/2021 09/24/2021 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance RP OCCUPATIONAL RAD SAFETY INSPECTION 3 3, 4 10/04/2021 10/08/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 3, 4 10/04/2021 10/08/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 3, 4 10/04/2021 10/08/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 3, 4 10/04/2021 10/08/2021 IP 71124.04 000728 Occupational Dose Assessment This report does not include INPO and OUTAGE activities. Page 1 of 3 This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report Turkey Point 03/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count RP OCCUPATIONAL RAD SAFETY INSPECTION 3 3, 4 10/04/2021 10/08/2021 IP 71124.05 000729 Radiation Monitoring Instrumentation 3, 4 10/04/2021 10/08/2021 IP 71151 000746 Performance Indicator Verification 3, 4 11/01/2021 11/05/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 3, 4 11/01/2021 11/05/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 3, 4 11/01/2021 11/05/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 3, 4 11/01/2021 11/05/2021 IP 71124.04 000728 Occupational Dose Assessment 3, 4 11/01/2021 11/05/2021 IP 71124.05 000729 Radiation Monitoring Instrumentation 3, 4 11/01/2021 11/05/2021 IP 71151 000746 Performance Indicator Verification UNIT 3 IN-SERVICE INSPECTION +SG 2 3 10/11/2021 10/15/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
EMERGENCY PREPAREDNESS PROGRAM INSPECTION 2 3, 4 01/10/2022 01/14/2022 IP 71114.02 000717 Alert and Notification System Testing 3, 4 01/10/2022 01/14/2022 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 3, 4 01/10/2022 01/14/2022 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 3, 4 01/10/2022 01/14/2022 IP 71114.05 000720 Maintenance of Emergency Preparedness 3, 4 01/10/2022 01/14/2022 IP 71151 001397 Performance Indicator Verification SECURITY BASELINE INSPECTION 1 3, 4 02/14/2022 02/18/2022 IP 71130.02 000734 Access Control 3, 4 02/14/2022 02/18/2022 IP 71130.09 001656 Security Plan Changes 3, 4 02/14/2022 02/18/2022 IP 71151 001338 Performance Indicator Verification UNIT 4 IN-SERVICE INSPECTION +SG 2 4 03/14/2022 03/18/2022 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP OCCUPATIONAL AND TRANSPORTATION BASELINE INSPECTION 2 3, 4 03/14/2022 03/18/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 3, 4 03/14/2022 03/18/2022 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &
Transportation 3, 4 03/14/2022 03/18/2022 IP 71151 000746 Performance Indicator Verification TURKEY POINT INITIAL LICENSE EXAM 5 3, 4 06/20/2022 06/24/2022 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report Turkey Point 03/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count TURKEY POINT INITIAL LICENSE EXAM 5 3, 4 07/25/2022 08/05/2022 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
TRIENNIAL HEAT SINK PERFORMANCE 1 3, 4 07/18/2022 07/22/2022 IP 71111.07T 000700 Heat Sink Performance TARGET SET INSPECTION 1 3, 4 08/08/2022 08/12/2022 IP 71130.14 000743 Review of Power Reactor Target Sets NFPA 805 TRIENNIAL FIRE PROTECTION INSPECTION 4 3, 4 10/03/2022 10/07/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
3, 4 10/17/2022 10/21/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
DESIGN BASES ASSURANCE INSPECTION (PROGRAMS) 3 3, 4 10/31/2022 11/04/2022 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements 3, 4 11/14/2022 11/18/2022 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.