IR 05000250/1980003

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-250/80-03 & 50-251/80-03 on 800107-11. Noncompliance Noted:Failure to Implement Fire Protection QA Program
ML17339A935
Person / Time
Site: Turkey Point  
Issue date: 02/20/1980
From: Elrod S, Martin R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17339A929 List:
References
50-250-80-03, 50-250-80-3, 50-251-80-03, 50-251-80-3, NUDOCS 8004240390
Download: ML17339A935 (8)


Text

~s AEoo

~o 4p o

C o

I

+w*e+

UNITEDSTATES NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100 ATLANTA,GEORGIA 30303 Report Nos. 50-250/80-03 and 50-251/80-03 Licensee:

Florida Power and I,ight Company 9250 West Flagler Street Miami, Florida 33101 Facility Name:

Turkey Point Units 3 and

Docket Nos. 50-250 and 50-251 License Nos.

DPR-31 and DPR-41 Inspection at Tu ey Point site near Homestead, Florida Inspector:

S.

A.

Qd D

e igned Approved by:

R. D. Martin, Section Chief, RONS Branch D te S'gned SUMMARY Inspection on January 7-11, 1980 Areas Inspected This routine, unannounced inspection involved 27 inspector-hours on site in the area of upgrading of the Turkey Point Fire Protection Program.

Results In the area inspected, no items of noncompliance were identified, but one apparent deviation was found (Deviation - failure to implement a fire protection quality assurance program - paragraph 6).

qno4240.i4

DETAILS 1.

Persons Contacted

+H. E. Yaeger, Site Manager

+J. K. Hays, Plant Manager-Nuclear

  • P. J. White, Maintenance Superintendent

+E. F. Baker, Construction Quality Assurance

  • C. J. Baker, Technical Department

+R. Tucker, Operations Quality Assurance-T. Essinger, Assistant Manager - Operations Quality Assurance

  • S. M. Feith, Operations Quality Assurance G. Patrissi, Fire Protection Administrator Other licensee employees contacted included operators and security force members.

NRC Resident Inspector

+R. Vogt-Lowell

+Attended exit interview 2.

Exit Interview The inspection scope and findings were summarized on January ll, 1980 with those persons indicated in Paragraph 1 above.

The completion status of fire protection modifications was discussed, as was the apparent lack of a quality assurance program addressing fire protection activities.

Subsequent to the exit interview, the plant manager-nuclear agreed to include quality requirements in the reviews, then ongoing, of fire protection related plant change/modification packages.

3.

Licensee Action on Previous Inspection Findings Not inspected.

4.

Unresolved Items Unresolved items were not identified during this inspection.

5.

Plant Modifications to Improve the Turkey Point Fire Protection Program The inspector reviewed the program stat'us of modifications addressed in Sections 3.1.1 through 3.1.19 of NRC's Fire Protection Safety Evaluation Report dated March 21, 1979, and implemented by license amendments 45 and

, 37 to facility operating licenses DPR-31 and DPR-41 respectively.

Selected modifications scheduled to be currently completed in Florida Power and Light Company letter L-79-128 of May 21, 1979, were inspected for completio The status of these items is discussed below.

The modification program appeared to be proceeding at an adequate pace for compl'etion by the committed completion date of December 1980.

One area of deviation from commitments made to the commis'sion is discussed in paragraph 6.

Other than that, the inspector had no further questions on the program at this time.

The status of plant modifications to improve the Turkey Point Fire Protection Program is as follows:

a Item 3.1.1 - Early Warning Fire Protection Devices.

Plant change/modification (PC/M)79-54A addressing all areas except the control room kitchen has been written and is under review.

Infor-mation concerning the proposed modifications in the switchgear rooms (3.1.1.(4))

and diesel generator rooms (3.1.1(5))

has been forwarded for NRC review as required.

This item also requires a fire watch patrol be established to inspect the lower level of the turbine area at a frequency of once-per-hour.

The inspector reviewed security department directives establishing the Auxiliary Feedwater System Roving Patrol and observed frequent security patrols of the subject area.

The requirement for a fire watch patrol is considered to be met.

b.

Item 3.1.2 - Fire Water Supply.

This item concerns a spoolpiece type cross connection between the screen wash pumps and firemain.

PC/M 79-99 has been developed and submitted for NRC approval as required in the Safety Evaluation Report.

The inspector had no further questions on this item at this time.

c ~

Item 3.1.3 - Yard Hydrants This item concerns the providing of a 2Q inch gate valve at the hose house and augmentation of equipment at the yard hydrant hose cabinets.

The required equipment was verified by the inspector.

This requirement is considered completed.

Item 3.1.4 - Fire House Equipment This item concerns upgrading the equipment in the (central) firehouse.

The inspector verified that the required equipment additions had been made.

This requirement is considered completed.

e.

Item 3.1.5 - Interior Hose Stations This item concerns additions to hose stations serving the control room, cable spreading room and switchgear rooms.

PC/M 79-58 has been developed and approved.

Equipment is currently being purchase Item 3.1.6 - Water Suppression System This item concerns providing of water spray protection for switchgear room doors and ventilation openings which face main and auxiliary transformers.

PC/Ms 79-71 and 79-72 have been developed and submitted for NRC approval as required.

g ~

Item 3.1.7 - Foam Suppression (1)

Adding additional portable foam suppression equipment.

The inspector verified that the additional foam suppression equipment was available for use.

This requirement is considered completed.

(2)

A means of introducing foam from the building exterior to the diesel generator rooms and fuel oil day tank rooms.

PC/Ms.79"97 and 79-98 have been developed and submitted for NRC approval as required.

h.

Item 3.1.8 - Add two portable pressurized water extinguishers in the Control Room.

The inspector verified that the extinguishers were present and in satisfactory condition.

This requirement is considered completed.

Item 3.1.9 - Add rated fire doors to several areas.

PC/M 79-54B has been developed and is under review.

J

~

Item 3.1.10 - Fire Dampers.

This item concerns addition of three-hour-rated fire dampers to certain ventilation openings in the switchgear room which faces the transformer areas and in the side wall vent openings in the containment electrical penetration rooms. It also concerns dampers in the ventilation systems for chemistry laboratories and the new laundry facility.

PC/M 79-139 has been identified for this project but not developed yet.

k.

Item 3.1.11 - Sealing of certain penetrations in the switchgear rooms and diesel generator rooms.

PCM 79-148 has been developed and is under review.

Item 3.1.12 - Smoke and heat barrier between the outdoor fuel oil storage tank and the diesel generator rooms.

No definitive action has been taken on this requirement, though some tentative steps have been taken.

m.

Item 3.1.13 - Add curbs around various doors and equipment.

PCM 79-54 has been developed and is under review.

n.

Item 3.1.14 - Fire retardant cable coatings - not inspected

-4-0 ~

Item F 1.15 - Control of combustibles.

This item concerned miscellaneous actions required to control the location and amount of combustible materials in various areas:

(1)

Remove Hydrogen supply lines from auxiliary, building corridor "

PC/M 79-54B has been developed and is under review.

(2)

Replace (plastic) radiation protective clothing barrels with fire retardant barrels.

A tour by the inspector and interviews with management indicated that this requirement is completed.

(3)

Replace hydraulic coupling oil cooler lines on the charging pumps with noncombustible material - PC/M 79-126 has been developed and is under review.

(4)

Replace the control point guard house at entrance to auxiliary building with one made of noncombustible material - PC/M 79-135 has been developed and is under review (5)

Relocate the oil dispensing station (barrel with spigot) from South end of turbine area.

This requirement is considered completed.

(6)

Relocate flammable chemical storage from turbine area ground floor.

PC/M 79"103 has been assigned but not developed.

(7)

Provide isolation valves within the diked area of the outdoor fuel oil storage tank.

PC/M 79-104 has been assinged but not developed.

po 3.1.16 - Fire Fighting Access.

(1)

Remove unused portions of cable trays in cable penetration rooms - Plant work order 4927 has been completed - this requirement is considered completed.

(2)

Provide fixed ladder access to all levels of cable penetration rooms.

This is in progress

- scheduled for completion by Janaury 31, 1980.

3.1.17 - Add smoke venting equipment.

Two portable, explosive proof, electric fan, smoke ejectors have been obtained and are ready for use.

This requirement is considered cpmpleted.

S ~

3.1.18 - Add air breathing equipment - not inspected 3.1.19 - Emergency lighting.

(1)

Provide fixed seal-beam units in various areas - PC/M 79-95 has been developed and is under revie ~

~

(2)

Provide portable seal beam battery-operated lights for the fire brigade and emergency operations personnel use.

These lights are provided in the fire house in addition to flashlights'his requirement is considered completed.

6.

Fire Protection Quality Assurance Program During the course of this inspection, the inspector inquired into the implementation status of the Fire Protection Quality Assurance (FPQA)

Program as addressed in NRC letter of February 5, 1978 "Fire Protection Guidelines",

attachment 6; Florida Power and Light Company's (FPSL) response letter L-78-197, "Fire Protection Guidelines",

enclosure 1, attachment 6;

and NRC confirming letter of June 30, 1978, "Fire Protection Guidelines".

Though evidence, in, the form of an FPSL internal presentation, entitled

"PTP Reliability/Quality Plan, Fire Protection System" and dated 3/21/78, indicated initial planning for a FPQA program, no evidence of completed FPQA program development and implementation was produced by the licensee.

The inspector also noted that EPP-QI 3.1 Revision 2, Section 7.2 (b) does task designers to "establish requirements to accommodate fire" and lists examples, but this document indicates that it applies only to items of design that (a) are currently defined as "safety related" and (b) the original design is accomplished by the Power Plant Engineering Department.

This document mitigates neither the need for a FPQA program nor the need for it to be identifiable at all levels, since some design work is accom-plished by facility personnel and plant changes deemed at the facility to

"not be safety related" do not go to the corporate office for review and approval.

This lack of development and implementation of a FPQA program is considered to be deviation from a commitment to the commission (250/251/80-03-01).