Responds to NRC Re Violation Noted in IE Insp Repts 50-250/80-03 & 50-251/80-03.Corrective Actions:Fire Protection QA Program Will Be Implemented by 800731
ML17339A931
Person / Time
Site: Turkey Point  
Issue date: 03/21/1980
From: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML17339A929 List:
References
L-80-99, NUDOCS 8004240378
Download: ML17339A931 (3)


Text

P.O. BOX 629100, MIAMI,FL 33162 I-~

C FLORIDA POWER 4 LIGHTCOMPANY

.'3 t'lhR2q Ala: g f March 21, 1980 L-80-99 Mr. James P. O'Reilly, Director, Region II Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303

Dear Mr. O'Reilly:

Re:

RII:SAE 50-250/80-3 50-251/80-3 Florida Power 8 Light Company has reviewed the subject inspection report and a response is attached.

There is no proprietary information in the report.

Very truly yours, Robert E. Uhrig Vice President Advanced Systems

& Technology REU/GDW/ah Attachment cc:

Harold F. Reis, Esquire BII04s 4< '37+

co Qi g PEOPLE... SERVING PEOPLE

ATTACHMENT Re:

RII:SAE 50-250/80-3 50-251/80-3

~Findin Based on the results of the NRC inspection conducted on January 7-11, 1980, certain of your activities appear to deviate fr-m your commitments to the Commission NRC letter of February 5, 1978, "Fire Protection Guidelines," ; Florida Power

& Light Company's (FP&L) response letter L-78-197, "Fire Protection Guidelines,"

Enclosure 1,

section labeled "attachment 6"; and NRC confirming letter of June 30, 1978, "Fire Protection Guidelines" comprise a

commitment made and accepted that FP&L establish a Fire Protection equality Assurance (FPgA) Program based on draft Regulatory Guide 1.120, June 1976 with a "levels of quality" approach.

Contrary to the above, during the week of January 7-11,

1980, the licensee could furnish no evidence of completed FP(A Program development and implementation.

~Res ense As corrective action, a Fire Protection guality Assurance Program will be developed and implemented at Turkey Point by July 31, 1980.

A recently implemented system for tracking commitments to the NRC should prevent future deviations of this type.

Compliance will be achieved by July 31, 1980.