GO2-08-112, Transmittal of Response to Regulatory Issue Summary 2008-16, Preparation and Scheduling of Operator Licensing Examinations.

From kanterella
Jump to navigation Jump to search
Transmittal of Response to Regulatory Issue Summary 2008-16, Preparation and Scheduling of Operator Licensing Examinations.
ML082180438
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 07/24/2008
From: Cullen G
Energy Northwest
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GO2-08-112, RIS-08-016
Download: ML082180438 (2)


Text

Gregory V. Cullen ENERGY Regulatory Programs P.O. Box 968, Mail Drop PE20 NORTHWEST Richland, WA 99352-0968 Ph. 509-377-6105 F. 509-377-4317 gvcullen@energy-northwest.com July 24, 2008 G02-08-112 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001

Subject:

COLUMBIA GENERATING STATION, DOCKET NO. 50-397 RESPONSE TO REGULATORY ISSUE

SUMMARY

(RIS) 2008-16

Reference:

NRC Regulatory Issue Summary 2008-16, Preparation and Scheduling of Operator Licensing Examinations, dated June 27, 2008

Dear Sir or Madam:

In response to the NRC request in RIS 2008-16, Energy Northwest has enclosed an updated copy of Form 536; Operator Licensing Examination Data.

There are no new commitmernts being made. If you have any questions, please contact MC Humphreys, LicenSing Supervisor at (509) 377-4025.

Respectfully, GV Cullen Manager, Regulatory Programs

Attachment:

NRC Form 536 cc: EE. Collins, ,Jr. - NRC RIV CF Lyon- NRCNRR NRC Seniorectr/988C RN Sherman -,BPA/1399, WA Horin.-Winston & Strawn.

- - - . r

NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 08/31/2008 (8-2005) Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources for operator examinations. Send comments regarding burden OPERATOR LICENSING estimate to the Records and FOIA/Privacy Services Branch (T-5 F53), U.S.

Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information EXAMINATION DATA and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY NRC REGION Columbia Generating Station IV A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 2009 CY 2010 CY2011 CY 2012

--- ESTIMATED NUMBER OF LICENSEE-PREPARED 2 0 1 1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0 0 0 0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 2009 CY2010 CY2011 CY2012 NUMBER OF REACTOR OPERATORS 4 0 6 4 NUMBER OF SENIOR REACTOR 0.4 5 5 OPERATORS-INSTANT ""

NUMBER OF SENIOR REACTOR 0 4 3 OPERATORS - UPGRADE 0 NUMBER OF SENIOR REACTOR 00 OPERATORS - LIMITED 0 0 0 0 0 PROPOSED DATES PRIMARY DATE I/Ia /09 1/1510o 03/14/2011 10/15/2012 ALTERNATE DATE 04/11/2011 11/12/2012 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2009 CY 2011 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 0 0 0 11 0 9 0 CANDIDATES NRC FORM 536 (8-2005) PRINTED ON RECYCLED PAPER