DCL-17-038, Diablo Canyon Power Plant, Units 1 & 2, Revised Updated Final Safety Analysis Report, Rev. 23, Chapter 10, Steam and Power Conversion System

From kanterella
Jump to navigation Jump to search
Diablo Canyon Power Plant, Units 1 & 2, Revised Updated Final Safety Analysis Report, Rev. 23, Chapter 10, Steam and Power Conversion System
ML17206A049
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 12/31/2016
From:
Pacific Gas & Electric Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML17206A046 List:
References
DCL-17-038
Download: ML17206A049 (101)


Text

i Revision 23 December 2016 Chapter 10 STEAM AND POWER CONVERSION SYSTEM CONTENTS Section Title Page

10.1

SUMMARY

DESCRIPTION 10.1-1

10.1.1 REFERENCE DRAWINGS 10.1-2

10.2 TURBINE-GENERATOR 10.2-1

10.2.1 DESIGN BASES 10.2-1 10.2.1.1 Turbine-Generator System Safety Functional Requirements 10.2-1 10.2.1.2 10 CFR 50.62 - Requirements for Reduction of Risk from Anticipated Transients Without Scram (ATWS) Events for Light-Water-Cooled Nuclear Power Plants 10.2-1 10.2.1.3 Generic Letter 89-08, May 1989 - Erosion/Corrosion-Induced Pipe Wall Thinning 10.2-1

10.2.2 SYSTEM DESCRIPTION 10.2-1 10.2.2.1 Turbine 10.2-2 10.2.2.2 Performance Requirements 10.2-2 10.2.2.3 Operating Characteristics 10.2-2 10.2.2.4 Functional Limitations 10.2-3 10.2.2.5 Lubrication 10.2-4 10.2.2.6 Cooling 10.2-5 10.2.2.7 Turbine Electrohydraulic Control System 10.2-5 10.2.2.8 Turbine Steam Flow Control 10.2-6 10.2.2.9 Partial Loss of Load 10.2-7 10.2.2.10 Complete Loss of Load 10.2-7 10.2.2.11 Overspeed Action 10.2-7 10.2.2.12 Speed Channel System 10.2-8 10.2.2.13 Automatic Runbacks and Programmed Ramps 10.2-8 10.2.2.14 Trip System Operability 10.2-8 10.2.2.15 Protective Features 10.2-8 10.2.2.16 Design Codes 10.2-10

10.2.3 SAFETY EVALUATION 10.2-10 10.2.3.1 Turbine-Generator System Safety Functional Requirements 10.2-10 10.2.3.2 10 CFR 50.62 - Requirements for Reduction of Risk from Anticipated Transients Without Scram (ATWS) Events for Light-Water-Cooled Nuclear Power Plants 10.2-11 DCPP UNITS 1 & 2 FSAR UPDATE Chapter 10 Contents (Continued)

Section Title Page ii Revision 23 December 2016 10.2.3.3 Generic Letter 89-08, May 1989 - Erosion/Corrosion-Induced Pipe Wall Thinning 10.2-11

10.2.4 TESTS AND INSPECTIONS 10.2-11

10.2.5 INSTRUMENTATION APPLICATIONS 10.2-11

10.

2.6 REFERENCES

10.2-12

10.3 MAIN STEAM SYSTEM 10.3-1 10.3.1 DESIGN BASES 10.3-1 10.3.1.1 General Design Criterion 2, 1967 - Performance Standards 10.3-1 10.3.1.2 General Design Criterion 3, 1971 - Fire Protection 10.3-1 10.3.1.3 General Design Criterion 4. 1967 - Sharing of Systems 10.3-1 10.3.1.4 General Design Criterion 11, 1967 - Control Room 10.3-1 10.3.1.5 General Design Criterion 12, 1967 - Instrumentation and Control Systems 10.3-1 10.3.1.6 General Design Criterion 15, 1967 - Engineered Safety Features Protection Systems 10.3-2 10.3.1.7 General Design Criterion 17, 1967 - Monitoring Radioactivity Releases 10.3-2 10.3.1.8 General Design Criterion 21, 1967 - Single Failure Definition 10.3-2 10.3.1.9 General Design Criterion 49, 1967 - Containment Design Basis 10.3-2 10.3.1.10 General Design Criterion 54, 1971 - Piping Systems Penetrating Containment 10.3-2 10.3.1.11 General Design Criterion 57, 1971 - Closed System Isolation Valves 10.3-2 10.3.1.12 Main Steam System Safety Function Requirements 10.3-3 10.3.1.13 10 CFR 50.49 - Environmental Qualification 10.3-3 10.3.1.14 10 CFR 50.55a(f) - Inservice Testing Requirements 10.3-3 10.3.1.15 10 CFR 50.55a(g) - Inservice Inspection Requirements 10.3-3 10.3.1.16 10 CFR 50.63 - Loss of All Alternating Current Power 10.3-4 10.3.1.17 10 CFR Part 50 Appendix R (Sections III.G, J, and L) - Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979 10.3-4 10.3.1.18 Regulatory Guide 1.97, Revision 3, May 1983 - Instrumentation for Light-Water-Cooled Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident 10.3-4 10.3.1.19 NUREG-0737 (Item II.F.1), November 1980 - Clarification of TMI Action Plan Requirements 10.3-4 DCPP UNITS 1 & 2 FSAR UPDATE Chapter 10 Contents (Continued)

Section Title Page iii Revision 23 December 2016 10.3.1.20 Generic Letter 89-08, May 1989 - Erosion/Corrosion-Induced Pipe Wall Thinning 10.3-5

10.3.2 SYSTEM DESCRIPTION 10.3-5 10.3.2.1 Capability of Main Steam Isolation and Check Valves to Withstand Closure Loads following a Postulated Main Steam Line Break 10.3-7

10.3.3 SAFETY EVALUATION 10.3-10 10.3.3.1 General Design Criterion 2, 1967 - Performance Standards 10.3-10 10.3.3.2 General Design Criterion 3, 1971 - Fire Protection 10.3-11 10.3.3.3 General Design Criterion 4, 1967 - Sharing of Systems 10.3-11 10.3.3.4 General Design Criterion 11, 1967 - Control Room 10.3-11 10.3.3.5 General Design Criterion 12, 1967 - Instrumentation and Control Systems 10.3-12 10.3.3.6 General Design Criterion 15, 1967 - Engineered Safety Features Protection Systems 10.3-12 10.3.3.7 General Design Criterion 17, 1967 - Monitoring Radioactivity Releases 10.3-12 10.3.3.8 General Design Criterion 21, 1967 - Single Failure Definition 10.3-12 10.3.3.9 General Design Criterion 49, 1967 - Containment Design Basis 10.3-13 10.3.3.10 General Design Criterion 54, 1971 - Piping Systems Penetrating Containment 10.3-13 10.3.3.11 General Design Criterion 57, 1971 - Closed System Isolation Valves 10.3-13 10.3.3.12 Main Steam System Function Requirements 10.3-13 10.3.3.13 10 CFR 50.49 - Environmental Qualification 10.3-14 10.3.3.14 10 CFR 50.55a(f) - Inservice Testing Requirements 10.3-15 10.3.3.15 10 CFR 50.55a(g) - Inservice Inspection Requirements 10.3-15 10.3.3.16 10 CFR 50.63 - Loss of All Alternating Current Power 10.3-15 10.3.3.17 10 CFR Part 50 Appendix R (Sections III.G, J, and L) - Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979 10.3-15 10.3.3.18 Regulatory Guide 1.97, Revision 3, May 1983 - Instrumentation for Light-Water-Cooled Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident 10.3-16 10.3.3.19 NUREG-0737 (Item II.F.1), November 1980 - Clarification of TMI Action Plan Requirements 10.3-16 10.3.3.20 Generic Letter 89-08, May 1989 - Erosion/Corrosion-Induced Pipe Wall Thinning 10.3-16

10.3.4 TESTS AND INSPECTIONS 10.3-16

DCPP UNITS 1 & 2 FSAR UPDATE Chapter 10 Contents (Continued)

Section Title Page iv Revision 23 December 2016 10.3.5 WATER CHEMISTRY 10.3-17 10.3.6 INSTRUMENTATION APPLICATIONS 10.3-17 10.

3.7 REFERENCES

10.3-17 10.3.8 REFERENCE DRAWINGS 10.3-18 10.4 OTHER FEATURES OF STEAM AND POWER CONVERSION SYSTEM 10.4-1 10.4.1 MAIN CONDENSER 10.4-1 10.4.1.1 Design Bases 10.4-1 10.4.1.2 System Description 10.4-1 10.4.1.3 Safety Evaluation 10.4-2 10.4.1.4 Tests and Inspections 10.4-2 10.4.1.5 Instrumentation Applications 10.4-2 10.4.2 MAIN CONDENSER EVACUATION SYSTEM 10.4-2 10.4.2.1 Design Bases 10.4-2 10.4.2.2 System Description 10.4-3 10.4.2.3 Safety Evaluation 10.4-4 10.4.2.4 Tests and Inspections 10.4-4 10.4.2.5 Instrumentation Applications 10.4-4 10.4.3 TURBINE GLAND SEALING SYSTEM 10.4-4 10.4.3.1 Design Bases 10.4-5 10.4.3.2 System Description 10.4-5 10.4.3.3 Safety Evaluation 10.4-6 10.4.4 TURBINE BYPASS SYSTEM 10.4-6 10.4.4.1 Design Bases 10.4-7 10.4.4.2 System Description 10.4-9 10.4.4.3 Safety Evaluation 10.4-10 10.4.4.4 Tests and Inspections 10.4-13 10.4.4.5 Instrumentation Applications 10.4-14 10.4.5 CIRCULATING WATER SYSTEM 10.4-14 10.4.5.1 Design Bases 10.4-14 10.4.5.2 System Description 10.4-14 10.4.5.3 Safety Evaluation 10.4-16 10.4.5.4 Tests and Inspections 10.4-17 10.4.5.5 Instrumentation Applications 10.4-17 DCPP UNITS 1 & 2 FSAR UPDATE Chapter 10 Contents (Continued)

Section Title Page v Revision 23 December 2016 10.4.6 CONDENSATE POLISHING SYSTEM 10.4-18 10.4.6.1 Design Bases 10.4-18 10.4.6.2 System Description 10.4-19 10.4.6.3 Safety Evaluation 10.4-19 10.4.6.4 Tests and Inspections 10.4-20 10.4.6.5 Instrumentation Applications 10.4-20 10.4.7 CONDENSATE AND FEEDWATER SYSTEM 10.4-20 10.4.7.1 Design Bases 10.4-21 10.4.7.2 System Description 10.4-25 10.4.7.3 Safety Evaluation 10.4-27 10.4.7.4 Tests and Inspections 10.4-33 10.4.7.5 Instrumentation Applications 10.4-33

10.4.8 STEAM GENERATOR BLOWDOWN SYSTEM 10.4-33 10.4.8.1 Design Bases 10.4-33 10.4.8.2 System Description 10.4-36 10.4.8.3 Safety Evaluation 10.4-38 10.4.8.4 Tests and Inspections 10.4-42 10.4.8.5 Instrumentation Applications 10.4-42

10.4.9 CONDENSATE AND FEEDW ATER CHEMICAL INJECTION SYSTEM 10.4-43 10.4.9.1 Design Bases 10.4-43 10.4.9.2 System Description 10.4-44 10.4.9.3 Safety Evaluation 10.4-45 10.4.9.4 Tests and Inspections 10.4-47 10.4.9.5 Instrumentation Applications 10.4-48

10.4.10 REFERENCES 10.4-48

10.4.11 REFERENCE DRAWINGS 10.4-48

DCPP UNITS 1 & 2 FSAR UPDATE vi Revision 23 December 2016 Chapter 10 TABLES Number Title

10.0-1 Applicable Design Basis Criteria

10.1-1 Steam Bypass and Relief Valves

10.1-2 Secondary System Operating Parameters at 100 percent Rated Power

10.3-1 Main Steam Line Valve Plant Startup Leakage Test Results (Historical)

10.3-2 Summary of Results Under Pipe Rupture Conditions

10.4-1 Main Condenser Performance Data

10.4-2 Deleted in Revision 11

DCPP UNITS 1 &

2 FSAR UPDATE vii Revision 23 December 2016 Chapter 10 FIGURES Figure Title

10.1-1 (a) Unit 2: Heat Balance Diagram - Maximum Calculated - Post LP Retrofit

10.1-2 (a) Unit 2: Heat Balance Diagram - 100% RTO - Post LP Retrofit

10.1-3 Deleted in Revision 14

10.1-4 Deleted in Revision 14

10.1-5 (a) Unit 1: Heat Balance Diagram - Maximum Calculated - Post LP Retrofit

10.1-6 (a) Unit 1: Heat Balance Diagram - 100% RTO - Post LP Retrofit

10.2-1 Steam Generator Characteristic Pressure Curves

10.3-1 Deleted in Revision 16

10.3-2 Deleted in Revision 16

10.3-3 Deleted in Revision 16

10.3-4 Deleted in Revision 16

10.3-5 Deleted in Revision 16

10.3-6 Location of Steam Lines and Valves

10.4-1 Deleted in Revision 8

10.4-2 Revision of Steam Generator Feedwater Piping Steam Generators 1 and 4

10.4-3 Revision of Steam Generator Feedwater Piping Steam Generators 2 and 3

NOTE:

(a) This figure corresponds to a controlled engineering drawing that is incorporated by reference into the FSAR Update. See Table 1.6-1 for the correlation between the

FSAR Update figure number and the corresp onding controlled engineering drawing number.

DCPP UNITS 1 &

2 FSAR UPDATE 10.1-1 Revision 23 December 2016 Chapter 10 STEAM AND POWER CO NVERSION SYSTEM This chapter provides information concerning the plant steam power conversion (heat utilization) system. The steam and power conversion system (SPCS) includes the

turbine-generator, steam supply system, feedwater system, main condenser, and

related subsystems. The auxiliary feedwater (AFW) system is discussed in Section 6.5.

Descriptive information is provided to allow understanding of the system, with emphasis

on those aspects of design and operation that affect the reactor and its safety features, or contribute to the control of radioactivity.

The radiological aspects of normal system operation are summarized in this chapter and are presented in detail in Chapter 11.

Design and quality code classifications applied to the SPCS are discussed in Chapter 3.

10.1

SUMMARY

DESCRIPTION The SPCS is designed to convert the heat produced in the reactor to electrical energy.

In each unit, reactor heat absorbed by the reactor coolant system (RCS) produces sufficient steam in four steam generators to supply the turbine-generator.

The SPCS is designed to operate on a closed, condensing cycle, with full flow condensate demineralization, and six stages of regenerative feedwater heating.

Turbine exhaust steam is condensed in a single shell, surface-type condenser and

returned to the steam generators through three stages of feedwater pumping. All three

low-pressure turbine elements exhaust into a common condenser steam space. The

arrangement of the equipment associated with the SPCS is shown in Figures 3.2-2, 3.2-3, 3.2-4, and 10.3-6.

The SPCS is designed to receive the heat absorbed by the RCS during normal power operation, as well as following an emergency shutdown of the turbine-generator from full load. Heat rejection under the latter condition is accomplished by steam bypass to

the condenser and pressure relief to the atmosphere. Either the turbine bypass or the

pressure relief system (without operation of safety valves) can dissipate the heat from

the RCS following a turbine trip and a reactor trip. Trips, automatic control actions, and alarms are initiated by deviations of system v ariables from preset values. In every instance, automatic control functions are programmed so that appropriate corrective

action is taken to protect the RCS (refer to Chapter 7).

The SPCS does not normally contain radioa ctivity. The vents and drains associated with the secondary cycle are arranged in a manner similar to those in a conventional

fossil fuel generating station. However, the condenser air removal equipment will

handle radioactive noncondensabl e gases during a steam generator primary-to-secondary tube leak. Means are provided to monitor (refer to Section 11.6) the discharge of radioactive material to the environment, to ensure that it is within the

limits of 10 CFR Part 20 under normal operating conditions, or in the event of DCPP UNITS 1 &

2 FSAR UPDATE 10.1-2 Revision 23 December 2016 anticipated system malfunctions or accident conditions. Detection of these gases is described in Sections 10.4.2 and 11.4.

All SPCS equipment required for nuclear safety is classified as PG&E Design Class I, and the appropriate systems are sufficiently redundant to ensure maintenance of their

safety functions. Specifically, the AFW system and portions of the main steam and main feedwater systems are required to perform various safety functions involving

removal of decay heat and are classified as PG&E Design Class I. Safety functions relative to the auxiliary feedwater system are presented in Section 6.5.

Turbine heat balances at maximum calculated and full load conditions are shown, respectively, in Figures 10.1-1 and 10.1-2 for Unit 2, and Figures 10.1-5 and 10.1-6 for

Unit 1. Typical operating parameters for the secondary system are listed in

Table 10.1-2.

Tables 10.1-1 and 10.1-2 summarize important design and performance characteristics

of equipment upon which the safety of the SPCS operation depends. The design

performance characteristics and PG&E Design Class I design features are described in the remainder of Chapter 10.

10.1.1 REFERENCE DRAWINGS Figures representing controlled engineering drawings a re incorporated by reference and

are identified in Table 1.6-1. The contents of the drawings are controlled by DCPP

procedures.

DCPP UNITS 1 &

2 FSAR UPDATE 10.2-1 Revision 23 December 2016 10.2 TURBINE-GENERATOR The basic function of the turbine-generator is to convert thermal energy initially to mechanical energy and finally to electrical energy. The turbine-generator receives

saturated steam from the four steam generators through the main steam system.

Steam is exhausted from the turbine-generat or to the main condenser.

10.2.1 DESIGN BASES

10.2.1.1 Turbine-Generator System Safety Functional Requirements

1) Protection from Missiles

The turbine-generator is designed to ensure that failure of the turbine-generator is

minimized and will not result in the generation of missiles that could affect safe

shutdown of either unit.

10.2.1.2 10 CFR 50.62 - Requirements for Reduction of Risk from Anticipated Transients Without Scram (ATWS) Events for Light-Water-Cooled

Nuclear Power Plants

The turbine-generator meets the requirement of 10 CFR 50.62 by responding to an AMSAC signal to trip the turbine under ATWS conditions.

10.2.1.3 Generic Letter 89-08, May 1989 - Erosion/Corrosion-Induced Pipe Wall Thinning DCPP has implemented formalized procedures and administrative controls in

accordance with Generic Letter 89-08 to assure long-term implementation of its

erosion/corrosion monitoring program for the turbine-generator.

10.2.2 SYSTEM DESCRIPTION The Siemens-Westinghouse BB96 high pressure (HP) turbine is coupled to three

Alstom ND56R low pressure (LP) turbines in a four-casing, tandem-compound, six-flow

exhaust, 1800 rpm unit, with 57-inch last-stage blades. The ac generator is connected

to the turbine shaft, and a brushless exciter is coupled to the generator.

DCPP UNITS 1 &

2 FSAR UPDATE 10.2-2 Revision 23 December 2016 10.2.2.1 Turbine The turbine consists of one double-flow, high-pressure element in tandem with three

double-flow, low-pressure elements. Moistur e separation and reheating of the steam are provided between the high-pressure and low pressure turbines by six horizontal

axis, two-stage reheat cylindrical shell combined moisture separator-reheater (MSR)

assemblies. Three of these assemblies are located on each side of the low-pressure

turbine elements.

Steam from the exhaust of the high-pressure turbine element enters one end of each

MSR assembly, where internal manifolds in the lower section distribute the wet steam.

The steam then flows through a moisture separator where the moisture is removed and

the condensate drained to a drain tank from which it is pumped to the suction of the

main feedwater pumps. The steam leaving the separator flows over two tube bundles

where it is reheated in two stages. The reheated steam leaves through nozzles in the

top of the assemblies and flows to the low pressure turbines through a stop valve and

an intercept valve in each reheat steam line. Two MSR assemblies furnish steam to

each of the three low-pressure turbine elements. The first stage tube bundle in the

reheater is supplied with extraction steam from the high-pressure turbine, and the

second-stage tube bundle is supplied from the main steam lines ahead of the high-

pressure turbine. The supply steam condenses in the tubes; the condensate from the

high-pressure tube bundle flows to the shell of the high-pressure feedwater heaters, while the condensate from the low-pressure tube bundle flows to the heater 2 drain

tank.

A turbine shaft sealing system, using steam to seal the annular openings where the shaft penetrates the casings, prevents steam outleakage or air inleakage along the shaft. Turbine steam extraction connections are provided for six stages of feedwater

heating.

10.2.2.2 Performance Requirements The main turbine-generators and their auxiliary systems are designed for steam flow

corresponding to 3,500 MWt and 3,580 MWt, which in turn correspond to the maximum

calculated thermal performance data of the Units 1 and 2 nuclear steam supply systems (NSSS), respectively, at the original design ultimate expected thermal power. The

Unit 2 turbine-generator has a higher power rating because of subsequent uprating of

the Unit 2 NSSS. The intended mode of operation of both Unit 1 and Unit 2 is base

loaded at levels limited to the lower licensed reactor level of 3,411 MWt (refer to

Table 15.1-1).

10.2.2.3 Operating Characteristics The steam generator characteristic pressure curves (Figure 10.2-1) are the bases for

design of the turbine. The steam generator pressure curve shown in Figure 10.2-1

corresponds to the SG outlet pressure. The calculated curve is based on thermal DCPP UNITS 1 &

2 FSAR UPDATE 10.2-3 Revision 23 December 2016 design conditions with vessel T avg of 577.6ºF and 10 percent steam generator tube plugging (Reference 1). The pressure at the turbine main steam valves does not exceed the pressure shown on the steam characteristic pressure curve for the

corresponding turbine load. With a pressurized water reactor, it is recognized that the

pressure at the turbine steam valves rises as the load on the turbine is reduced below

rated load. During abnormal conditions at any given load, the pressure may exceed the

pressure on the steam generator characteristic pressure curve by 30 percent on a

momentary basis, but the total aggregate duration of such momentary swings above

characteristic pressure over the whole turbine load range does not exceed a total of

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> per 12-month operating period.

The turbine inlet pressure is not directly controlled. A load index from the turbine

first-stage pressure is compared to the reactor coolant loop T avg; the control rods are then positioned accordingly (refer to Section 7.7.2.8).

10.2.2.4 Functional Limitations The plant is designed to sustain sudden large load decreases, as described in

Section 5.1.7.2 This capability is provided by the use of controlled steam dump (turbine bypass) from the secondary system. This dump serves as a short-term artificial load, allowing the reactor to automatically cut back power without tripping. The reactor

control system itself is not rapid enough to follow a sudden loss of load without allowing

certain reactor plant variables (e.g., pressure and temperature) to exceed allowable operating limits. Therefore, a sufficiently large controlled steam dump, capable of

simulating an external load on the reactor, is used to prevent the reactor from tripping.

The rates at which electrical load may be increased or decreased without tripping the reactor, including operation of the steam dump (bypass system), are as follows:

(1) Without steam bypass - If electrical load decrease does not exceed a step change of 10 percent, or a sustained ramp load decrease of 5 percent per

minute, then the steam bypass will not operate. Steam bypass is not used

to control load increases.

(2) With steam bypass - If electrical load decrease does exceed a step change of 10 percent or a sustained ramp load decrease of 5 percent per

minute, then a combination of steam dump groups 1, 2, and 3 of the turbine bypass system (refer to Section 10.4.4.2) will operate. If the decrease is less than 50 percent, then a step change with control rods will

account for a 10 percent load decrease, and the turbine bypass system

will operate and control up to 40 percent of the remaining load decrease.

(3) Electrical load increases are limited by the reactor control system to 5 percent full power per minute, or step changes of 10 percent of full

power within the power range of 15 to 100 percent of full power.

DCPP UNITS 1 &

2 FSAR UPDATE 10.2-4 Revision 23 December 2016 For further explanation of the steam bypass and relief system, refer to Section 10.4.4.

Steam bypass and relief valves are listed in Table 10.1-1.

For electrical loading, refer to Chapter 8, Electric Power.

The functional limitations imposed by the design or operational characteristics of the

turbine-generator are:

(1) Retrofitted with Alstom LP turbines, the units are suitable for continuous full load underfrequency operation down to 56.4 Hz. Operation below

56.4 Hz is limited to 10 seconds per event. There is no specific

accumulated time limit for operation below 56.4 Hz. A trip within

0.5 seconds is required below 54.9 Hz.

(2) Under frequency set points and time delays are coordinated with PG&Es Under Frequency Load Shedding (UFLS) Program, per Utility Operations

Standard UO S1426, which conservatively bounds turbine vendor

requirements.

(3) Load changes cause thermal stress in the turbine rotor, which persists as long as there are differences between the surface and interior

temperatures of the rotor body. Operationa l procedures for changing load, that tend to ensure a maximum time period before the appearance of

fatigue cracking, are required. Load changing recommendations are

based on 10,000 cycles of general turbine operation. For example, the

following load changes can be made instantaneously, without exceeding the 10,000-cycle recommendations: 0-10 percent, 10-30 percent, 20-53 percent, 30-78 percent, 40-85 percent, and 50-100 percent.

(4) Operation at less than 5 percent rated load should be avoided; however, when necessary, auxiliary load may be carried indefinitely on the main generator following rejection of the main load, provided; (a) Low-pressure turbine exhaust hood spray is placed in service when hood temperature exceeds 175

°F; and if hood temperature increases to 250

°F for more than 15 minutes, the turbine is tripped (b) All supervisory instrument readings are within allowable alarm limits

10.2.2.5 Lubrication Turbine-generator bearings are lubricated by a conventional oil system. The volute

type, centrifugal main oil pump is mounted on the turbine rotor and supplies all of the oil

requirements for the lubrication system during normal operation. An ac motor-driven

centrifugal pump supplies bearing oil for operating the turbine-generator on turning gear

during coastdown after a trip, and during startup. A backup dc motor-driven bearing oil

pump operates, in case of loss of ac power or if the ac pump fails to start, to lubricate DCPP UNITS 1 &

2 FSAR UPDATE 10.2-5 Revision 23 December 2016 the turbine-generator bearings during coastdown of the unit after tripout. Air-side and hydrogen-side ac motor-driven seal oil pumps are provided to supply oil to the generator

hydrogen seal oil systems. An air side dc motor-driven seal oil backup pump operates in case of loss of ac power, to prevent leakage of the generator hydrogen. A lift pump is

provided for bearings 3, 4, 5, 6, and 7 to lift the turbine rotor shaft off the journal bearing to reduce the starting load on the turning gear motor. Bearing 8 was retrofitted with an

integral bearing lift system.

10.2.2.6 Cooling The cooling water requirements of the turbine-generator are met partially by the service

cooling water system (refer to Section 9.2.1), and partially by the main condensate and feedwater system (refer to Section 10.4.7).

The following main turbine-generator heat e xchangers are cooled by the service cooling water system:

(1) Turbine lubricating oil coolers (2) Generator hydrogen seal oil coolers (3) Exciter air-to-water heat exchangers (4) Electrohydraulic control fluid cooler (5) Main generator isophase bus duct cooler

The following main turbine-generator heat exchangers are cooled by the main

condensate and feedwater system:

(1) Generator hydrogen coolers (2) Generator stator water coolers (3) Gland steam condenser 10.2.2.7 Turbine Electrohydraulic Control System The turbine is equipped with a dig ital electrohydraulic (DEH) control system that uses programmable triple modular redundant (TMR) digital controllers, dual redundant digital

servo position controllers, input/output modules, and a high-pressure, fire-resistant, fluid

supply system to operate the turbine control valves. By regulating the flow of steam

through the turbine, the control system regulates turbine speed prior to the time that the

generator is synchronized, and controls unit power output when the generator is

connected to the PG&E transmission system. The control system also provides DCPP UNITS 1 &

2 FSAR UPDATE 10.2-6 Revision 23 December 2016 overspeed protection. Retrofitted with Alstom LP turbines, the control system also provides low condenser vacuum and low bearing oil protection.

Unit electrical loading is completely under the control of the reactor operator except

when automatic runbacks are in progress. No automatic offsite load dispatching is

utilized.

10.2.2.8 Turbine Steam Flow Control The flow control of the main inlet steam is accomplished by four main stop valves in

series with four governor control valves.

Each main stop valve operates in either a fully opened or fully closed position. The

valve is opened when high-pressure fluid enters the hydraulic actuator cylinder and

forces the piston to overcome spring closing pressure. It is closed immediately upon

the dumping of main stop valve emergency trip fluid to provide quick closing

independent of the electrical system. The v alve may also be closed upon activation of the solenoid valve for periodic test of valve stem freedom. The purpose of the main stop valve, which is installed in the main steam line ahead of the governor control valve, is to provide an additional safety device to limit turbine overspeed. On a unit trip, stop and governing valves are spring-closed to provide redundancy for turbine overspeed protection.

Each governor control valve is of the single-seat, plug type design. The valve is opened

when high pressure electrohydraulic (EH) fluid enters the actuator and overcomes the

spring force of the valve as transmitted by the operating levers. During normal operation, control of the governor control valve is by a servo valve that regulates oil pressure in the actuator, based on information supplied from the DEH system controller.

A linear variable differential transformer (LVDT) develops an analog signal proportional

to the valve position, which is fed back to the controller to complete the control loop.

The controller signal positions the control valves over a wide range of turbine speeds during startup and for load control after the unit is synchronized. The governor control

valve is closed by reducing pressure on the dump valve. The dump valve can be activated by means of the emergency trip system, or by the auxiliary governor trip, to provide quick closing independent of the electrical system.

The flow control of steam to the low-pressure sections of the turbine is accomplished by

six reheat stop valves in series with six interceptor valves.

Each reheat stop valve operates in either the fully opened or fully closed position. The

valve is opened when high-pressure fluid enters the actuator hydraulic cylinder and

forces the piston to overcome spring closing pressure. It is closed immediately upon

dumping of main stop valve emergency trip fluid, on actuation of the emergency trip

device. It may also be closed upon activatio n of the solenoid valve for periodic testing of valve stem freedom. The major function of the reheat stop valves is to shut off the flow of steam to the low-pressure turbines, when required.

DCPP UNITS 1 &

2 FSAR UPDATE 10.2-7 Revision 23 December 2016 Each interceptor valve normally operates in a fully opened position. The valve is

opened when high-pressure fluid is admitted through an orifice to the hydraulic cylinder

operating piston. As the fluid pressure increases beneath the piston, it overcomes the

force of the closing springs and opens the steam valve. It is quickly closed when the

emergency trip fluid is released to drain. The purpose of this valve is to limit the flow of

steam from the MSRs to the low-pressure turbines after a sudden load reduction.

10.2.2.9 Partial Loss of Load A feature called close-intercept valve (CIV) was built into the original turbine control

system to close the intercept valves. This CIV feature was designed to sense a load

mismatch between high pressure exhaust pressure and generated power. CIV

actuation would close the intercept valves for a preset time period. This feature was disabled on the original Westinghouse-supp lied turbine control system and is not present in the new system.

10.2.2.10 Complete Loss of Load When a mismatch of LP turbine inlet pressure and generator output megawatts occurs, and the breaker opens, this con dition is detected as a complete load loss. When the generator breaker opens, the load drop anticipation (LDA) is set, requesting overspeed protection control (OPC) action. Refer to Section 10.2.3.1 for a description of the OPC system.

All governor and interceptor valves are then rapidly closed. The LDA load loss circuit is inoperable below 22 percent of load, as measured by LP turbine inlet pressure.

10.2.2.11 Overspeed Action OPC action also occurs when turbine speed is equal to, or greater than, 103 percent of

rated speed. Governor and interceptor valves are closed until the speed drops below

103 percent.

The OPC system may be tested by using the OPC test function. If the breaker is open and the OPC test function is activated, a signal is generated; this signal indicates that the speed of the turbine is over 103 percent.

The OPC system then closes the valves as though an actual overspeed condition had occurred.

DCPP UNITS 1 &

2 FSAR UPDATE 10.2-8 Revision 23 December 2016 10.2.2.12 Speed Channel System Three separate electromagnetic pickups input speed information to the turbine control

system. These inputs are validated against a high and low reference to determine when

a transducer fails high or low. The control system uses a median signal select logic to

determine the controlling speed signal for turbine speed control, OPC, and redundant

overspeed protection.

10.2.2.13 Automatic Runbacks and Programmed Ramps The turbine control system implements protective runbacks and programmed ramps (load reductions). The OTT and OPT protective runbacks are described in Section 7.7.2.4.2. The loss of main generator stator cooling protective runback is discussed in Section 10.2.2.15. Main turbine programmed ramps anticipating loss of

steam flow are main feedwater pump trip and heater drip pump trip. A turbine runback anticipating a loss of heat sink is a trip of a circulating water pump.

10.2.2.14 Trip System Operability The operability of the main turbine inlet valves and turbine trip system is verified by

periodic functional tests. Operability of the trip system in the event of postulated

accidents has also been reviewed. The trip system is protected from falling debris and

will remain operational during and following postulated accidents (refer to Section

3.5.2.2.1.2).

Administrative operating requirements ensure that the turbine building crane is parked

away from the steam inlet valves during turbine operation, to preclude damage to the valves from a postulated crane fall.

10.2.2.15 Protective Features Post Alstom LP turbine retrofit, the low vacuum mechanical trip feature has been

removed and low vacuum trip is now provided through the DEH. The following other

protective devices are independent of the electronic controller and, when initiated, will cause tripping of all turbine valves:

(1) Mechanical overspeed trip (refer to description in 10.2.3.1)

(2) Low bearing oil pressure trip (this is provided by both the mechanical trip, independent of the electronic controller, as well as through the DEH).

(3) Thrust bearing trip (4) Electrical solenoid trip, actuated by:

(a) Safety injection system or steam generator high-high level DCPP UNITS 1 &

2 FSAR UPDATE 10.2-9 Revision 23 December 2016 (b) Generator loss of field (c) Reactor trip (d) Unit trip (e) Manual trip switches in control room (f) Turbine speed 111.5 percent or dc bus trip (DEH)

(g) ATWS mitigation system actuation circuitry (5) Manual lever located at the turbine Each of the above tripping devices releases autostop oil. The oil release results in a

decrease of autostop oil pressure that opens a diaphragm-operated trip valve in the EH

high-pressure fluid system to release the pressure and close all steam valve actuators.

The generator is protected by a load runback feature on loss of cooling water to the

generator stator. The runback is accomplished at a rate of approximately 40 percent

load drop per minute by the turbine control system. If the generator runback fails to

start in 45 seconds, the generator is additionally protected by a time delay trip, which

results in a unit trip. Reverse power and antimotoring protection is also provided for the

generator.

High-high steam generator water level signals in two-out-of-three channels for any steam generator actuate a turbine trip, trip the main feedwater pumps, and close the

main feedwater control valves and feedwater bypass valves. The purpose is to protect

the turbine and steam piping from excessive moisture carryover caused by high-high

steam generator water level.

In addition to the devices described above, the turbine and steam system are protected

by the following indicators and design features:

(1) Dropped reactor control rod signal light on the main control board (2) Isolation valve in each steam generator steam line (3) Check valve in each steam generator steam line (4) Safety valves in each steam generator steam line (5) Safety valves in the MSR inlet (cold reheat) piping (6) Extraction line nonreturn valves DCPP UNITS 1 &

2 FSAR UPDATE 10.2-10 Revision 23 December 2016 (7) Exhaust casing rupture diaphragms (8) Turbine steam and casing drains which open automatically at loads less than 20 percent The turbine-generator and associated steam handling equipment have received extensive mechanical, electrical, and radiological safety evaluations. Protective

features regarding personnel and equipment safety are presented in this section.

Safety features for reactor protection, in the event of a turbine-generator trip or sudden load reduction, are presented in Section 10.4.4.

10.2.2.16 Design Codes The turbine-generator and associated components are classified as PG&E Design Class II. Section 3.2 presents a discussi on of design classifications and code requirements.

10.2.3 SAFETY EVALUATION 10.2.3.1 Turbine-Generator System Safety Functional Requirements (1) Protection from Missiles

Tests and analyses regarding the potential generation and effects of missiles, caused

by the turbine-generator are discussed in Section 3.5.2.2.1. Criteria for determining the turbine inspection scope and frequency required to prevent missile generation are also discussed in Section 3.5.2.2.1.

The overspeed protection control (OPC) system controls turbine overspeed in the event

of a partial or complete loss of load, or if the turbine reaches or exceeds 103 percent of

rated speed. In the event that turbine shaft speed exceeds 103 percent of rated speed, overspeed protection is afforded through information (in rpm) supplied by three speed

transducers to the OPC system. The signals from the transducers are validated against a high and low reference to determine when a transducer fails high or low. The turbine

control system uses a median signal select logic to determine the controlling speed signal.

A mechanical overspeed trip device is also provided that will automatically trip the unit

at 111 percent of rated speed. The mechanism consists of a spring-loaded plunger

located in the turbine shaft, which extends radially outward when 111 percent of rated

speed is reached. When extended, the plunger contacts a lever, which in turn dumps

control hydraulic fluid (autostop oil), causing all turbine steam inlet control and stop

valves to close.

DCPP UNITS 1 &

2 FSAR UPDATE 10.2-11 Revision 23 December 2016 An electronic trip signal is generated by the DEH control system, at 111.5 percent of rated speed, as redundant overspeed protection. With the retrofitted Alstom LP

turbines, this trip signal is used to energize two solenoid valves, either of which dumps

autostop oil. This trip signal is set approximately 10 rpm higher than the mechanical overspeed device previously described.

Overspeed protection is necessary to preclude turbine rotor failure and associated

turbine generated missiles (refer to Section 3.5.2.2.1).

10.2.3.2 10 CFR 50.62 - Requirements for Reduction of Risk from Anticipated Transients Without Scram (ATWS) Events for Light-Water-Cooled

Nuclear Power Plants

The turbine-generator meets the requirement of 10 CFR 50.62 by responding to an AMSAC signal to trip the turbine under ATWS conditions. The main turbine must have

equipment from sensor output to final actuation device, that is diverse from the reactor trip system, to automatically initiate the auxi liary (or emergency) feedwater system and initiate a turbine trip under conditions indicative of an ATWS (refer to Section 7.6.3.5).

10.2.3.3 Generic Letter 89-08, May 1989 - Erosion/Corrosion-Induced Pipe Wall Thinning DCPP has implemented formalized procedures and administrative controls in accordance with Generic Letter 89-08 to assure long-term implementation of its

erosion/corrosion monitoring program for the turbine-generator.

10.2.4 TESTS AND INSPECTIONS Turbine-generator tests and inspections are described in Sections 3.5.2.2.1, 10.2.2.11, 10.2.2.14 and 10.2.3.1.

10.2.5 INSTRUMENTATION APPLICATIONS Instrumentation is provided to continuously monitor and alarm the following

turbine-generator parameters:

(1) Shaft vibration at main bearings (2) Shaft eccentricity (3) Shell expansion (4) Differential expansion between turbine shell and rotor (5) Turbine speed

DCPP UNITS 1 &

2 FSAR UPDATE 10.2-12 Revision 23 December 2016 (6) Turbine metal temperatures (7) Bearing temperatures (8) Hydrogen gas and stator cooling water temperatures (9) Exhaust hood temperatures (10) Condenser vacuum

(11) Thrust bearing wear 10.

2.6 REFERENCES

1. Delta 54 Replacement Steam Ge nerator Thermal and Hydraulic Design Analysis Report for Diablo Canyon, WCAP-16573-P, August 2007.

DCPP UNITS 1 &

2 FSAR UPDATE 10.3-1 Revision 23 December 2016 10.3 MAIN STEAM SYSTEM The main steam system conveys the generated steam from the nuclear steam supply

system to the turbine generator, t urbine driven feedwater pumps, steam dump, reheaters, and via the auxiliary steam syste m, to the gland steam system and air ejectors. Main steam is also provided to the turbine driven auxiliary feedwater pump.

Refer to Section 10.4.4 for details on the 10 percent atmospheric dump valves.

The main steam system SSCs from the s team generators up to and including the main steam isolation valves (MSIVs) outside of the containment are PG&E Design Class I.

The main steam system SSCs downstream of the MSIVs are PG&E Design Class II.

10.3.1 DESIGN BASES 10.3.1.1 General Design Criterion 2, 1967 - Performance Standards The PG&E Design Class I portion of the main steam system is designed to withstand the effects of, or is protected against, natural phenomena such as earthquakes, winds, floods and tsunamis, and other local site effects. The effects of a tornado on the main

steam system are addressed to ensure plant safe shutdown can be achieved.

10.3.1.2 General Design Criterion 3, 1971 - Fire Protection

The PG&E Design Class I portion of the main steam system is designed and located to minimize, consistent with other safety requirements, the probability and effect of fires and explosions.

10.3.1.3 General Design Criterion 4, 1967 - Sharing of Systems

The PG&E Design Class I portion of the main steam system and its components are not shared by the DCPP Units unless safety is shown not to be impaired by the sharing.

10.3.1.4 General Design Criterion 11, 1967 - Control Room

The PG&E Design Class I portion of the main steam system is designed to support actions to maintain and control the safe operational status of the plant from the control

room or from an alternate location if control room access is lost due to fire or other

causes. 10.3.1.5 General Design Criterion 12, 1967 - Instrumentation and Control Systems Instrumentation and controls are provided as required to monitor and maintain the PG&E Design Class I portion of the main steam system variables within prescribed

operating ranges.

DCPP UNITS 1 &

2 FSAR UPDATE 10.3-2 Revision 23 December 2016 10.3.1.6 General Design Criterion 15, 1967 - Engineered Safety Features Protection Systems

The PG&E Design Class I portion of the main steam system provides for sensing accident situations.

10.3.1.7 General Design Criterion 17, 1967 - Monitoring Radioactivity

Releases Means are provided for monitoring the facility effluent discharge path for radioactivity

that could be released from the main steam system. The effluent discharge path includes both the PG&E Design Class I and PG&E Design Class II portions of the system.

10.3.1.8 General Design Criterion 21, 1967 - Single Failure Definition The PG&E Design Class I portion of the main steam system is designed to remain operable after sustaining a single failure. Multiple failures resulting from a single event

are treated as a single failure.

10.3.1.9 General Design Criterion 49, 1967 - Containment Design Basis

The main steam system is designed so that the containment structure can accommodate, without exceeding the design leakage rate, the pressures and

temperatures resulting from the largest credible energy release following a LOCA, including a considerable margin for effec ts from metal-water or other chemical reactions that could occur as a consequence of failure of emergency core cooling systems.

10.3.1.10 General Design Criterion 54, 1971 - Piping Systems Penetrating Containment

The PG&E Design Class I portion of the main steam system provides capability for testing the functional operability of valves essential to the containment isolation function.

10.3.1.11 General Design Criterion 57, 1971 - Closed System Isolation Valves

The PG&E Design Class I portion of the main steam system is designed to provide isolation valves outside the containment capable of automatic and manual closure.

DCPP UNITS 1 &

2 FSAR UPDATE 10.3-3 Revision 23 December 2016 10.3.1.12 Main Steam System Safety Function Requirements (1) Protection from Missiles and Dynamic Effects

The PG&E Design Class I portion of the main steam system is designed to be protected

against the effects of missiles and dynamic effects which may result from plant

equipment failures.

(2) Decay Heat Removal

The PG&E Design Class I portion of the main steam system is designed to remove

decay heat from the reactor coolant system through the steam generator safety valves and by providing steam to power the auxiliary feedwater (AFW) pump turbine.

(3) Main Steam Isolation

The MSIVs are designed to isolate automatically in the event of a main steam line break (MSLB) either upstream or downstream of the MSIVs to prevent uncontrolled steam

release and limit the steam release to the contents of a single steam generator.

(4) Secondary Side Pressure Control

The main steam system is designed with safety valves to protect the system from

overpressurization.

(5) Steam Flow Restriction

The main steam system is designed with flow restrictor s that limit the steam flow in the event of a MSLB at any location on the steam line.

10.3.1.13 10 CFR 50.49 - Environmental Qualification The PG&E Design Class I main st eam system components that require environmental qualification (EQ) are qualified to the requirements of 10 CFR 50.49.

10.3.1.14 10 CFR 50.55a(f) - Inservice Testing Requirements American Society of Mechanical Engineers (ASME) code components within the PG&E Design Class I portion of the main steam sy stem are tested to the requirements of 10 CFR 50.55a(f)(4) and 10 CFR 50.55a(f)(5) to the extent practical.

10.3.1.15 10 CFR 50.55a(g) - Inservice Inspection Requirements ASME code components within the PG&E Design Class I portion of the main steam system are inspected to the requirements of 10 CFR 50.55a(g)(4) and 10 CFR 50.55a(g)(5) to the extent practical.

DCPP UNITS 1 &

2 FSAR UPDATE 10.3-4 Revision 23 December 2016 10.3.1.16 10 CFR 50.63 - Loss of All Alternating Current Power The PG&E Design Class I portion of the main steam system provides a means for

removing decay heat from the reactor coolant system by discharging steam from the

steam generators to the atmosphere, and also provides steam to power the AFW pump

turbine in the event of a station blackout (SBO) event.

10.3.1.17 10 CFR Part 50 Appendix R (Sections III.G, J, and L) - Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979 Section III.G - Fire Protection of Safe Shutd own Capability: Fire protection of the PG&E Design Class I portion of the main steam system is provided by a combination of

physical separation, fire-rated barriers, and/or automatic suppression and detection.

Section III.J - Emergency Lighting: Emergency lighting or BOLs are provided in areas

where operation of the PG&E Design Class I portions of the main steam system may be required to safely shut down the unit following a fire.

Section III.L - Alternative and Dedicated Shutdown Capa bility: Safe shutdown capabilities are provided in the control room and at an alternate location via the hot

shutdown panel (HSP) as required for the safe shutdown of the plant following a fire

event.

10.3.1.18 Regulatory Guide 1.97, Revision 3, May 1983 - Instrumentation for Light-Water-Cooled Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident

The main steam system provides instrumentation to monitor main steam flow and

radiation release from the steam generator safety valves during and following an accident.

10.3.1.19 NUREG-0737 (Item II.F.1), November 1980 - Clarification of TMI Action Plan Requirements Item II.F.1 - Additional Accident Monitoring Instrumentation:

Position (1) - The PG&E Design Class I display instrumentation is designed to include

the noble gas effluent radiological monitor.

The radiation monitoring system provides instrumentation to monitor venting from the steam generator safety valves during and

following an accident.

DCPP UNITS 1 &

2 FSAR UPDATE 10.3-5 Revision 23 December 2016 10.3.1.20 Generic Letter 89-08, May 1989 - Erosion/Corrosion-Induced Pipe Wall Thinning DCPP has implemented formalized procedures and administrative controls to assure

long-term implementation of its erosion/corrosion monitoring program for the main

steam system.

10.3.2 SYSTEM DESCRIPTION The arrangement of the equipment associated with the main steam system is shown in

Figures 3.2-4 and 10.3-6. Steam from the fo ur steam generators is supplied to the turbine-generator (refer to Section 10.2).

Saturated steam from the four steam generators passes through the containment wall in

carbon steel pipes arranged to satisfy flexibility and PG&E Design Class I requirements.

Each main steam line is anchored to the containment wall at the penetration.

The measured steam flow has a functional PG&E Design Class II application. The flow signal is used by the PG&E Design Class II three-element feedwater controller and as a

PG&E Design Class II load inde x signal for the main feedwater pumps (refer to Section 7.7.2.7).

Steam flow restrictors are installed in each steam line inside the containment. The

pressure drop at rated load between the steam generators and the turbine throttle is

approximately 40 psi. Steam flow is measured by monitoring dynamic head in nozzles

inside the steam pipes. The nozzles, which are of smaller diameter than the main steam pipe, are located inside the containment near the steam generators.

Connections are provided in the four main steam lines, between the containment and

the isolation valves, for spring-loaded safety valves and power-operated relief valves, and (in two of the four) steam lines to the auxiliary feed pump drive turbine, as shown in

Figures 3.2-4 and 10.3-6.

The steam supply to the auxiliary feedwater pump turbine is PG&E Design Class I because of the ESF requirements of the auxil iary feedwater system (refer to Section 6.5). The steam supply lines from two of the four steam generators are interconnected upstream of the steam line stop valve to provide both redundancy and balanced steam

flow. Both isolation and check valves in series in each of these lines provide the

required valve redundancy that acts to prevent reverse flow.

The function of the MSIV is provided by a quick-acting isolation valve and a check valve

installed in each main steam line. These valves are located outside of the containment

structure and downstream of the safety valves. This design ensures that steam line

isolation occurs for breaks either upstream or downstream of the valves. These check valves prevent reverse flow from an unfaulted steam generator in the event of a pipe break upstream of the check valves. Additional data on these valves are provided in DCPP UNITS 1 &

2 FSAR UPDATE 10.3-6 Revision 23 December 2016 Section 10.3.2.1 regarding a discussion of the capability of the main steam isolation and check valves to withstand closure loads following a postulated MSLB.

The main steam system is designed so that a failure of a main steam line at any point

along its length, or a malfunction of a valve installed therein, or any consequential damage, will not:

(1) Reduce the flow capacity of the AFW system (2) Render inoperable any engineered safety feature (i.e., controls, power or instrumentation cables, emergency core cooling, or containment heat

removal piping)

(3) Cause gross failure of any other steam or feedwater line valve (4) Initiate a loss-of-coolant accident (LOCA)

Discussion of containment integrity for an MSLB is presented in Chapters 6 and 15.

Furthermore, an MSLB between the exterior of the containment and the quick-acting

isolation valve will not compromise the effectiveness of any containment barrier other

than the broken steam line itself. Since the MSIVs are a secondary barrier that serve to back up the steam generator tubes, containment leaktight integrity will not be degraded

as a result of a steam line break in this case.

The steam lines and the shell-sides of the steam generators are considered an

extension of the containment boundary and, as such, are not to be damaged as a consequence of damage to the reactor coolant system. The steam generator shells and steam lines are, therefore, designed to be protected against reactor coolant system

missiles (refer to Section 3.6.1.1).

Applicable design and quality code classifications are discussed in Chapter 3. The classification and applicable codes for the main steam system are identified in the

DCPP Q-List (refer to Reference 8 of Section 3.2). Faults involving the main steam

system are discussed in Sections 15.3.2 and 15.4.2.

The MSIVs can be operated manually from the control room as described in Section

10.3.3.4. There are also manual bypass valves around those air-operated MSIV bypass

valves on main steam leads 2 and 3. These local manual bypass valves can be used to

drain condensate accumulated in piping upstream of the MSIVs upon a loss of

instrument air supply prior to the startup of the auxiliary feedwater pump turbine.

DCPP UNITS 1 &

2 FSAR UPDATE 10.3-7 Revision 23 December 2016 10.3.2.1 Capability of Main Steam Isolation and Check Valves to Withstand Closure Loads following a Postulated Main Steam Line Break 10.3.2.1.1 Summary During the postulated event of a pipe rupture in the main steam system, the check and isolation valves close under loading conditio ns that are much more severe than those encountered during normal plant operation. The analyses presented here demonstrate that both the main steam line check and isolation valves are capable of successfully performing their functions during this event.

10.3.2.1.2 Results Impact energy levels for the most severe pipe rupture conditions are given in Table 10.3-2. The highest level is 0.888 x 10 6 in-lb for the isolation valve disc. The disc is capable of absorbing energy levels exceeding twice this predicted value without developing excessive deflections.

The check valve disc, which has the same capability, is subjected to lower energy levels.

The bearing stress at the valve seat is deter mined from the disc-to-seat reaction. The results are within the typical allowable stresses for this type of application.

For the most part, the tail link is n ot stressed beyond the elastic limit; where the elastic limit is exceeded, the incursion into the plastic range is slight. The maximum tail link deflection is determined to be 0.0425 inches. This deflection will not prevent proper valve closure.

The maximum shearing stress developed in the rockshaft is 21.5 ksi, well within the elastic range of the material. The deflection in the rockshaft will be insignificant.

10.3.2.1.3 Basic Criteria and Assumptions The following criteria and assumptions were used in the analysis:

(1) The initial angle of the isolation and check valve discs are 80 and 70° from the closed position, respectively.

(2) The postulated break locations that were selected will result in the most severe disc impact energy for each valve. Postulated break locations are established and defined in Reference 2, page 3.6A-41.

DCPP UNITS 1 &

2 FSAR UPDATE 10.3-8 Revision 23 December 2016 (3) The postulated break type that will result in the most severe disc impact energy is used. Types of breaks considered include circumferential, longitudinal, and crack as defined in Reference 3. The circumferential break is used in this analysis.

(4) The ruptured pipe is assumed to separate to full flow area instantaneously. A discharge coefficient of 1 is conservatively assumed for flow through the break area.

(5) It is conservatively assumed that there is no obstruction to discharging flow from the break that would prevent maximum blowdown flow from being developed.

(6) Isolation valve trip is conservatively assumed to occur 0.5 seconds (minimum) after a pipe rupture. Evaluation of larger time delays between pipe rupture and disc release shows that the shorter time is a more severe condition on the valve; and therefore, the shortest possible release time is used in the analysis.

(7) It is assumed that there is no frictional resistance to the valve rockshaft rotation; and that the pneumatic actuators offer no resistance to closure after a trip signal.

(8) Initial steam conditions used in the analysis are as follows:

Hot Standby: Line pressure = 1020 psia Line flow = 0 lb/sec Full Load: Line pressure = 800 psia Line flow = 1010 lb/sec Under a postulated pipe rupture, the maximu m flow through the isolation valve occurs under a plant hot standby condition. This results in a maximum acceleration of the valve disc. For the check valve, the plant operating condition that will result in the maximum disc impact energy is full load.

10.3.2.1.4 Analysis 10.3.2.1.4.1 Maximum Disc Impact Energy The check valve computer program used to solve the equations of motion for the valve disc to determine angular velocity and energy at impact is a modification of RELAP 3 (Reference 4). The modification consists of incorporating the equations of motion for the valve disc.

The equations incorporated into the program to mathematically describe the valve disc motion include the equations of motion, valve pressure drop as a function of flow rate, DCPP UNITS 1 &

2 FSAR UPDATE 10.3-9 Revision 23 December 2016 actuator return spring forces, and valve flow area as a function of disc position.

Because of the similarity in construction, these equations are the same (except for spring forces) for both the isolation and check valves. The isolation valve calculations are initiated following a trip signal. For the check valve, initiation is when the flow reverses in the pipe creating forces to close the disc.

The disc angular acceleration and velocity and the maximum disc impact energy are calculated as a function of the torque acting on the disc. This torque is comprised of gravitational, fluid flow, actuator, frictional, and viscous components. In this analysis, the frictional and viscous torque components act to delay the closure and thus are conservatively neglected. The gravity torque is a function of disc position and the actuator torque is a function of spring displacement. The fluid flow torque is caused by pressure differential across the disc. The pressure differential across the disc, in the non-choking flow region, is the frictional press ure drop across the disc calculated from the valve loss coefficients established by the valve manufacturer (Schutte and Koerting Company). To determine the pressure drop across the disc in the choking flow region, a static pressure difference in volumes upstream and downstream of the disc is used.

10.3.2.1.5 Component Analysis 10.3.2.1.5.1 Load Generation The loads acting on the valve components are generated by the disc angular velocity, disc angular acceleration, and the kinetic energy developed in the disc at instant of impact. These quantities are given in Table 10.3-2. The maximum of these values for the isolation of check valves wer e used in the analysis.

10.3.2.1.5.2 Disc Analysis Analysis of disc closure is accomplished by an equivalent static method whereby the disc is loaded with a pseudoloading which approximates the inertia forces acting on the disc. The magnitude of this loading is varied and a relationship between the strain energy developed in the disc and the pseudoloading is established. The maximum displacements experienced by the disc are taken to correspond to the point at which the strain energy developed under the pseudoloading equals the kinetic energy at instant of impact. Subsequently, a reanalysis was p erformed for evaluating an alternative valve disc material with lower material strengths.

10.3.2.1.5.3 Valve Body Seat Area Analysis The valve body seat area is analyzed by determining the reaction of the valve seat due to the impact of the disc. This reaction is found from the load-energy relationship derived in the analysis for the valve disc as described above. The load corresponding

DCPP UNITS 1 &

2 FSAR UPDATE 10.3-10 Revision 23 December 2016 to the initial kinetic energy in the disc is determined from this load-energy relationship.

The reaction at the valve disc is determined by dividing this load by the circumferential area of the valve seat.

10.3.2.1.5.4 Tail Link Analysis The critical loading conditions on the tail link occur during travel when the tail link is acted upon by centrifugal forces. In this mode the tail link structure may be considered statically determinate with the centrifugal force resultant applied at the rock shaft and reacted at the disc connection. The maximum loads in the travel mode occur just prior to disc impact, and since the tail link structure is taken as statically determinate, the moment and force resultants throughout for t his condition are determined from equilibrium considerations. With the axial and moment resultants known throughout the tail link, deflections are determined by dividing the structure into an appropriate number of sections, then determining and summing the deflections of these individual sections.

10.3.2.1.5.5 Rockshaft Analysis The design loading condition occurs just pri or to valve closure when the rockshaft sees the peak centrifugal forces developed in the tail link. These centrifugal forces are applied as shearing forces to the rockshaft.

No coupling between this loading condition and the torque carried by the rockshaft in the open position is considered, since this torque diminishes as the valves close and is zero at instant of valve closure.

10.3.3 SAFETY EVALUATION 10.3.3.1 General Design Criterion 2, 1967 - Performance Standards The main steam lines, together with their supports and structures between each steam

generator and its associated isolation valves (including the check valves), are PG&E

Design Class I.

The main steam lines are designed to perform their safety functions under the effects

of earthquakes (refer to Section 3.7.2.1.7.3). The main steam system downstream of

the MSIVs is PG&E Design Class II, however the main steam piping downstream of

the MSIVs up to the column line G pipe anchor is considered PG&E QA Class S, and

seismic analyses of piping up to the column line G pipe anchor have determined that a

seismic event will not prevent the MSIVs from performing their PG&E Design Class I

isolation function.

The main steam lines are designed to perform their safety functions under the effects

of floods and tsunamis (refer to Section 2.4.3.5).

The containment structure, pipeway structure, and auxiliary building, which contain the

main steam systems PG&E Design Class I SSCs, are PG&E Design Class I (refer to Section 3.8). These buildings, or appl icable portions thereof, are designed to DCPP UNITS 1 &

2 FSAR UPDATE 10.3-11 Revision 23 December 2016 withstand the effects of winds (refer to Sect ion 3.3), floods and tsunamis (refer to Section 3.4), external missiles (refer to Section 3.5), and earthquakes (refer to Section 3.7). These designs protect the main steam system, ensuring its safety functions will be performed.

Portions of main steam lines, including the MSIVs, are located outside and on the roof

of the auxiliary building and are partially resistant to tornadoes, however, the capability of the system to support plant safe shutdown is maintained (refer to Section 3.3.2.3.2.7).

10.3.3.2 General Design Criterion 3, 1971 - Fire Protection The main steam system has been evaluated, in accordance with the guidelines of Branch Technical Position APCSB 9.5-1, for safe shutdown follo wing a fire (refer to Appendix 9.5A).

As described in Appendix 9.5B, Table B-1, plant layouts isolate PG&E Design Class I

systems from unacceptable fire hazards. Therefore, a fire will not affect the main steam system's ability to safely shutdown the plant.

Each MSIV is opened by air and closes when either of the solenoid valves (powered

from separate Class 1E 125-Vdc power supplies) in its vent line is energized, releasing

the air. In the event of a fire at th e nearby main transformer bank, solenoid valve wiring could conceivably be burned, shorted, or opened, thus preventing solenoid energization and MSIV closure. To ensure MSIV closure in this event, a valve with a thermal fuse (automatic sprinkler type) has been installed in the vent lines of MSIV 41 and MSIV 42 on Unit 1 and Unit 2.

10.3.3.3 General Design Criterion 4, 1967 - Sharing of Systems Each DCPP unit can supply portions of the other units auxiliary steam from its PG&E Design Class II portion of the main steam system downstream of the MSIVs. Check valves in the supply lines prevent cross-flow of the main steam if this feature is utilized.

Failure of this check valve would not affect either Unit because both units operate

within the same design parameters.

The PG&E Design Class I portion of the main steam system is not affected by this feature. 10.3.3.4 General Design Criterion 11, 1967 - Control Room The MSIVs can be operated manually from the control room. The MSIVs have

remote-manual, air-operated bypass valves for the pressure equalization that is

necessary to open the valves. The bypass valves are operated from the control room

and automatically close on the same signals that automatically close the MSIVs.

DCPP UNITS 1 &

2 FSAR UPDATE 10.3-12 Revision 23 December 2016 Position indication is provided on the main control board for all MSIVs and bypass valves. Additionally, the main control board provides indications of main steam flow

and steam generator pressure.

If access to the control room is lost, necessary main steam system valves can be operated locally with steam generator pressure indicated on the hot shutdown panel.

10.3.3.5 General Design Criterion 12, 1967 - Instrumentation and Control Systems The MSIVs automatically close on high negative steam line pressure rate, low steam

line pressure, or on a high-high containment pressure signal. Instrumentation and controls for the main steam system are disc ussed in Sections 6.2.4, 7.3, and 9.3.1.3.

Refer to Section 10.3.3.7 for radiation monitoring instrumentation.

10.3.3.6 General Design Criterion 15, 1967 - Engineered Safety Features Protection Systems

The main steam system monitors steam pressure and provides the signal to ESFAS (refer to Section 7.3).

10.3.3.7 General Design Criterion 17, 1967 - Monitoring Radioactivity

Releases

The radiation monitoring system continuously monitors the main steam system (refer to Section 11.4.2.1.2.1).

Steam generated in the steam generators is not normally radioactive. However, in the

event of primary-to-secondary system leakage due to a steam generator tube leak, it is

possible for the main steam to become radioactively contaminated. A full discussion of the radiological aspects of primary-to-secondary leakage, including anticipated

operating concentration of radioactive contaminants, means of detection of radioactive contamination, anticipated releases to the environment, and limiting conditions for

operation, is included in Sections 7.5.2.3, 11.1.6, 11.4.2.1.2.1, and 15.5.

10.3.3.8 General Design Criterion 21, 1967 - Single Failure Definition The instrumentation and control circuits for steam line isolation (refer to Section 7.3) are redundant in the sense that a single failure cannot prevent isolation. Each MSIV is

opened by air and closes when either of the solenoid valves (powered from separate

Class 1E 125-Vdc sources) in its vent line is energized, releasing the air.

DCPP UNITS 1 &

2 FSAR UPDATE 10.3-13 Revision 23 December 2016 The instrumentation and control circuits for the main steam system pressure provided to ESFAS are redundant in that a single failure cannot prevent the safety injection signal actuation. Each steam header employs two-out-of-three logic for its signal.

The main steam supply to the turbine-driven AFW pump is provided from both the

number 2 and number 3 steam headers.

10.3.3.9 General Design Criterion 49, 1967 - Containment Design Basis

The main steam line containment penetrations are designed and analyzed to withstand the pressures and temperatures that could result from a LOCA without

exceeding design leakage rates. Refer to Section 3.8.2.1.1.3 for additional details.

10.3.3.10 General Design Criterion 54, 1971 - Piping Systems Penetrating

Containment

The main steam system isolation valves required for containment closure are periodically tested for operabi lity. Testing of the components required for the CIS is discussed in Section 6.2.4.1.4.

10.3.3.11 General Design Criterion 57, 1971 - Closed System Isolation Valves

The main steam system containment penetrations and isolation valves are part of the containment isolation system (CIS). Refer to Section 6.2.4 and Table 6.2.-39 for

penetration details.

10.3.3.12 Main Steam System Safety Function Requirements

(1) Protection from Missiles and Dynamic Effects

The PG&E Design Class I portion of the main steam system is protected from the

effects of missiles and dynamic effects as described in Sections 3.5.1 and 3.6.1.1, respectively.

(2) Decay Heat Removal

The main steam system provides means for removing decay heat from the reactor coolant system by discharging steam from the steam generators to the atmosphere through the steam generator safety valves and also by providing steam to power the

AFW pump turbine (refer to Sections 6.5.2 and 7.4.2).

(3) Main Steam Isolation

The MSIVs and check valves (MSIV/CV) are located outside of the containment

structure and downstream of the safety valves. The fast-acting isolation valves are

provided in each main steam line and will fully close within 10 seconds of a large steam DCPP UNITS 1 &

2 FSAR UPDATE 10.3-14 Revision 23 December 2016 line break. This design ensures that steam line isolation occurs for breaks either upstream or downstream of the valves. The MSIV/CV are credited to prevent reverse

flow from the steamline header and intact st eam generators. For breaks downstream of the isolation valves, closure of all valves would completely terminate the blowdown. For

any break, in any location, no more than one steam generator would blow down even if

one of the isolation valves fails to close. Cases that postulate the failure of the

MSIV/CV are discussed in Section 6.2D.3.3. The MSIVs automatically close on high

negative steam line pressure rate, low steam line pressure, or on a high-high

containment pressure signal and can also be operated from the control room (refer to

Sections 10.3.3.4 and 10.3.3.5).

Uncontrolled steam release as a result of a main steam line failure is therefore limited to

the contents of one steam generator, thus keeping the related effect upon the reactor

core within the prescribed bounds. (The main steam line rupture event is discussed in

detail in Appendix 6.2D, Section 15.3.2, and Section 15.4.2.) This results in the need for both isolation valves and check valves, as well as special design considerations for

the main steam lines themselves. These considerations are necessary to ensure that

damage to a portion of one steam line does not result in damage to the corresponding

portion of the other steam lines or the other steam generators. They are covered in detail in the MSLB discussion (refer to Section 15.4.2).

(4) Secondary Side Pressure Control

Five spring loaded safety valves are installed on each main steam line, upstream of the

MSIVs, to protect the main steam system from overpressurization. The pressure setpoints for these valves are progressively set from 1065 psig to 1115 psig as shown in Table 10.1-1. Refer to Section 3.9.2.2.5 for additional discussio n regarding the safety valves.

(5) Steam Flow Restriction

Each main steam line includes an in-line 16-inch diameter flow restrictor that acts to limit the maximum flow and the resulting thrust forces created by a steam line break.

The flow restrictors are discussed in more detail in Sections 5.5.4 and 15.4.2. These flow restrictors are separate from the integral flow restrictors in the SG outlet nozzles.

Refer to Section 5.1.8.17(6) for a discussion of the SG integral flow restrictor.

10.3.3.13 10 CFR 50.49 - Environmental Qualification Main steam system components required to function in harsh environments under accident conditions are qualified to the applicable environmental conditions to ensure that they will continue to perform their safety functions. The affected equipment is

listed on the EQ Master List. Main steam EQ components include solenoid valves and

position switches for the MSIVs and MSIV bypass valves, and steam flow and

pressure transmitters. Section 3.11 describes the DCPP EQ Program and the DCPP UNITS 1 &

2 FSAR UPDATE 10.3-15 Revision 23 December 2016 requirements for the environmental design of electrical and related mechanical equipment.

10.3.3.14 10 CFR 50.55a(f) - Inservice Testing Requirements Main steam system components that are within the IST program are the MSIVs, MSIV bypass valves, the isolation valves for the 10% steam dumps (the steam dump valves

themselves are discussed in Section 10.4.4), and the safety valves.

The inservice testing (IST) requirements for these components are contained in the

IST Program Plan and comply with the ASME code for Operation and Maintenance of

Nuclear Power Plants.

10.3.3.15 10 CFR 50.55a(g) - Inservice Inspection Requirements The main steam system piping has a periodic inservice inspection (ISI) program in accordance with the ASME BPVC,Section XI.

10.3.3.16 10 CFR 50.63 - Loss of All Alternating Current Power Decay heat is removed from the core by natural circulation of the reactor coolant. This heat is then transferred to the secondary side of the steam generators and discharged

to the atmosphere through the atmospheric steam dumps. Main steam provides

steam to power the turbine-driven AFW pump.

10.3.3.17 10 CFR Part 50 Appendix R (Sections III.G, J, and L) - Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979 10 CFR Part 50 Appendix R requires the evaluation of the safe shutdown capability for DCPP in the event of a fire and the loss of offsite power. The main steam system satisfies the applicable requirements of 10 CFR Part 50 Appendix R, Sections III.G, J, and L.

Section III.G - Fire Protection of Safe Shutd own Capability: Tables 9.5G-1 and 9.5G-2 for DCPP Unit 1 and Unit 2, respectively, list the minimum equipment required to bring

the plant to a cold shutdown condition as defined by 10 CFR Part 50, Appendix R, Section III.G. Specifically, all four MSIVs (required to close to maintain steam

generator water inventory) and the MSIV bypass valves (considered for spurious

operation only) are the minimum required equipment to bring the plant to a cold

shutdown condition. These components are provided fire protection features

appropriate to the requirements of Section III.

G. The actions necessary for safe shutdown for fires in certain fire areas involv e manually aligning valves.

Section III.J - Emergency Lighting:

Emergency lighting or battery operated lights (BOL) are provided in areas where operation of main steam system valves may be required DCPP UNITS 1 &

2 FSAR UPDATE 10.3-16 Revision 23 December 2016 for safe shutdown following a fire as defined by 10 CFR Part 50, Appendix R, Section III.J (refer to Appendix 9.5D).

Section III.L - Alternative and Dedicated Shutdown Capa bility: Safe shutdown capabilities are provided in the control room and at alternate locations via the hot shutdown panel and/or local operation of valves in accordance with 10 CFR Part 50

Appendix R,Section III.L (refer to Section 7.4). The ability to safely shut down the plant following a fire in any fire area is summarized in Section 4.0 of Appendix 9.5A.

10.3.3.18 Regulatory Guide 1.97, Revision 3, May 1983 - Instrumentation for Light-Water-Cooled Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident

Category 2 main steam flow indication and radiation monitoring for the vents from the steam generator safety valves ar e provided in the c ontrol room for Regulatory Guide 1.97, Revision 3 monitorin g (refer to Table 7.5-6).

10.3.3.19 NUREG-0737 (Item II.F.1), November 1980 - Clarification of TMI Action Plan Requirements Item II.F.1 - Additional Accident Monitoring Instrumentation:

Position (1) - The PG&E Design Class I display instrumentation for main steam line

activity monitoring when venting from the steam generator safety valves during and

following an accident is provided and is described in Section 7.5.2.3 and Section

11.4.2.1.2.1.

10.3.3.20 Generic Letter 89-08, May 1989 - Erosion/Corrosion-Induced Pipe Wall Thinning DCPP procedures identify the interdepartmental responsibilities and interfaces for the

Flow-Accelerated Corrosion (FAC) Monitoring Program for all plant systems, including

the main steam system.

10.3.4 TESTS AND INSPECTIONS The piping from the steam generator, up to and including the main steam line isolation valves, is equipped with removable insulation for inservice inspection of welds. The tests and inspections that apply to the main steam line isolation valves are in

accordance with the DCPP Technical Specifications (Reference 1). Main steam line isolation valves are tested periodically to verify their ability to close within the required

time (refer to Section 7.3 for a discussion of the response times for the steam line isolation signal).

Preoperational and startup testing requirements applicable to the main steam system

are discussed in Chapter 14.

DCPP UNITS 1 &

2 FSAR UPDATE 10.3-17 Revision 23 December 2016 Since the major components of the steam and power conversion system are accessible

during normal power operation, leakage from the valves located upstream of the MSIVs

is monitored by routine visual inspection by the operators.

The MSIVs, and the valves upstream of them and outside the containment, are

designed and packed to have the capability of limiting gland leakage along the stem to no more than one cubic centimeter of water per hour per inch of stem diameter, when subjected to a hydrostatic test pressure of 1100 psig, or 0.03 scf of air per hour per inch

of stem diameter with a differential pressure of 80 psi. They are designed to have the

capability to limit the valve seat leakage rate to 0.1 scf per hour per inch of seat

diameter, when subjected to a pneumatic pressure of 80 psig. Table 10.3-1

summarizes the potential leakages for valves located upstream of the steam line

isolation valves, and lists the leak rates measured through these leak paths during initial plant startup testing.

However, since the secondary system is a closed system inside containment whose

integrity is not damaged by a LOCA, the offsite dose consequences via the leak paths

identified in Table 10.3-1 are small when compared to the consequences from the

containment atmosphere leakage assumed in the offsite dose analysis. Hence, pursuant to Table 6.2-39, there are no local leak rate limits established for these

leakage paths, since in accordance with 10 CFR Part 50, Appendix J, this leakage is not

required to be measured.

10.3.5 WATER CHEMISTRY

The secondary water chemistry control program is discussed in Section 5.5.2.3.5.

Steam generator blowdown for chemistry control is discussed in Section 10.4.8. The

main steam sampling system is discussed in Section 9.3. Chemical treatment of the secondary system water for corrosion control is discussed in Section 10.4.9.

10.3.6 INSTRUMENTATION APPLICATIONS Instrumentation for the main steam system is discussed in Sections 10.3.3.4 and 10.3.3.5.

10.

3.7 REFERENCES

1. Technical Specifications, Diablo Canyon Power Plant Units 1 and 2, Appendix A to License Nos. DPR-80 and DPR-82, as amended.
2. Nuclear Services Corporation, Evaluation for Effects of Postulated Pipe Break Outside Containment for Diablo Canyon Unit 1, Revision 2, June 26, 1974.
3. Letter (Docket Nos. 50-275 and 50-323) from A. Giambusso of the U.S. Atomic Energy Commission to F.T. Searls of the Pacific Gas and Electric Company, DCPP UNITS 1 &

2 FSAR UPDATE 10.3-18 Revision 23 December 2016 dated December 18, 1972, including the attachment "General Information Required for Consideration of the Effects of Piping System Break Outside Containment." 4. W.H. Rettig, et al, "RELAP 3 -

A Computer Program for Reactor Blowdown Analysis," IN-1321, June 1970. Also Supplement of June 1971.

10.3.8 REFERENCE DRAWINGS Figures representing controlled engineering drawings a re incorporated by reference and

are identified in Table 1.6-1. The contents of the drawings are controlled by DCPP

procedures.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-1 Revision 23 December 2016 10.4 OTHER FEATURES OF STEAM AND POWER CONVERSION SYSTEM 10.4.1 MAIN CONDENSER The main condenser provides a heat sink and collection volume for steam and

condensate discharged from the main turbine, feedwater pump turbines, turbine bypass

system, feedwater heater drains, and other miscella neous flows, drains, and vents.

10.4.1.1 Design Bases The main condenser is classified as PG&E Design Class II. There are no regulatory

requirements associated with the main condenser. Radioactive leak detection is

discussed in Section 10.4.2.

10.4.1.2 System Description The main condenser is designed to condense full load steam and maintain a nominal

absolute pressure of 1.71 inches of mercury at 85 percent cleanliness. Sufficient surface (618,150 square feet) is provided to condense turbine bypass system steam (up to 40 percent of maximum calculated capability flow), following a load reduction, or under controlled startup conditions, or from residual and decay heat at shutdown.

The condenser hotwells are sized to provide adequate storage of water

(138,000 gallons) to allow for the water lost to the atmosphere and "shrinkage" on a

50 percent load reduction. The condensate leaving the hotwells is deaerated to

0.005 cc/liter dissolved oxygen level. The main condenser is provided with a means of detecting saltwater leakage.

During operation, air is removed from the co ndenser by steam jet air ejectors and discharged to the plant vent. The discharged air is continuously monitored for radioactivity. No control functions are associated with this radiation monitor. For

drawing initial vacuum, the condenser is evacuated by a wet-type rotary vacuum pump

which discharges air to the atmosphere.

The condenser vacuum pump may also be

placed into service in the event of degraded condenser vacuum. Refer to Section

10.4.2 for a discussion of the main condenser evacuation system.

The main condensing surface is mounted beneath the low-pressure turbine elements in

two shells with interconnected steam spaces. The tubes are arranged parallel to the

turbine shaft. The performance data for both the Unit 1 and Unit 2 condensers are

summarized in Table 10.4-1.

The following materials are used in the condenser:

(1) Shell and tube supports - carbon steel, ASTM A285, Grade C

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-2 Revision 23 December 2016 (2) Tubesheets 10 copper nickel, ASTM B171 (with corrosion-resistant coating on the saltwater side)

(3) Water boxes - carbon steel, ASTM A285, Grade C, lined with corrosion resistant coating on the saltwater side (4) Tubes - titanium

The condenser will condense up to 40 percent of the full load main steam flow during a

load reduction, startup, or shutdown. As discussed in Chapter 15, the steam generator

safety valves protect the NSSS from overpressure if the condenser is not available or if the steam flow exceeds the capacity of the condenser. The secondary system is normally not radioactive. However, in the event of primary-to-secondary leakage

through leaking steam generator tubes, it is possible for the main steam to become

radioactively contaminated. A discussion of the assumed leakage rates, treatment

methods, and calculated activity levels is included in Section 11.1.6, and an inventory of

radionuclides in the condenser for an assumed leak rate is shown in Table 11.1-27.

10.4.1.3 Safety Evaluation The main condenser is classified as PG&E Design Class II. There are no regulatory requirements associated with the main condenser. Radioactive leak detection is

discussed in Section 10.4.2.

10.4.1.4 Tests and Inspections

Tests and inspections of the main condenser are done in accordance with plant procedures.

10.4.1.5 Instrumentation Applications Instrumentation is provided to monitor and control main condenser operation.

10.4.2 MAIN CONDENSER E VACUATION SYSTEM The main condenser evacuation system (MCES) removes noncondensable gases from the main condenser during plant startup, cooldown, and normal operation. The system

is classified as PG&E Design Class II.

10.4.2.1 Design Bases 10.4.2.1.1 General Design Criterion 17, 1967 - Monitoring Radioactivity Releases The MCES is provided with means for monitoring the release of radioactivity in facility

effluent discharge paths.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-3 Revision 23 December 2016 10.4.2.1.2 NUREG-0737 (Item II.F.1), November 1980 - Clarification of TMI Action Plan Requirements Item II.F.1 - Additiona l Accident-Monitoring Instrumentation:

Position (1) - The MCES is designed with noble gas effluent monitors that are installed

with an extended range designed to function during accident conditions.

Position (2) - The MCES is designed with provisions for sampling of plant effluents for

post-accident releases of radioactive iodines and particulates and onsite laboratory capabilities.

10.4.2.2 System Description The MCES consists of a wet-type rotary vacuum pump and steam jet air ejectors. The

vacuum pump is common to both units and is used to draw an initial vacuum in the

condenser of either unit and may be used during degraded vacuum conditions. The

steam jet air ejectors are used after the initial pumpdown and are designed to remove air that may degrade the ability of the condenser to maintain a nominal absolute

pressure of 1.71 inches of mercury, as described in Section 10.4.1.2.

The wet-type rotary vacuum pump has a capacity of approximately 7000 cubic feet per

minute.

The steam jet air ejector system consists of two stages of steam jets mounted on a combined inter-after surface condenser. The air ejector system is designed to remove 360 pounds per hour of air saturated with water vapor at 71.5°F, and a suction pressure

of 1 inch of mercury absolute pressure when supplied with steam at 85 psig. The first

stage consists of eight 25 percent capacity jets and the second stage consists of twin

100 percent capacity jets.

Refer to Section 5.5.2 for information on PG&E's implementation of Electric Power

Research Institute primary-to-secondary leak guidelines.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-4 Revision 23 December 2016 10.4.2.3 Safety Evaluation

10.4.2.3.1 General Design Criterion 17, 1967 - Monitoring Radioactivity Releases Air is discharged from the vacuum pump through a local vent. During vacuum pump

operation, grab samples are taken at the local vent in support of the Radioactive

Effluent Controls Program. In addition, evaluations have been performed that

demonstrate potential radioactive discharges remain within 10 CFR 100 limits.

Noncondensables vented from the steam jet air ejectors while the plant is at power operation are discharged through the plant vent that is continuously monitored for

radioactivity. Further discussion of releases due to steam generator leakage and the

radiation monitoring of the plant vent is given in Sections 7.5.2.3, 9.4.2, 11.1.6 and 11.4.

10.4.2.3.2 NUREG-0737 (Item II.F.1), November 1980 - Clarification of TMI Action Plan Requirements Item II.F.1 - Additiona l Accident-Monitoring Instrumentation:

Position (1) - Extended range noble gas effluent monitoring is installed in the plant vent, which includes exhaust from the steam jet air ejectors , and is designed to function during accident conditions. Refer to Section 9.4.2 for information on the plant vent and

Figures 3.2-2 and 3.2-23 for a depiction of steam jet air ejector after-condenser exhaust routing to the plant vent. Refer to Section 11.4 for discussion of radiation monitors.

Position (2) - Installed capability is provided in the plant to obtain samples of the

particulate and iodine radioactivity concentrations that may be present in the gaseous effluent being discharged to the environment fro m the plant vent, which includes the steam jet air ejector exhaust, under accident and post-accident conditions. The technical support center laboratory is available for onsite testing of the air samples.

Refer to Section 9.4.2 for information on the plant vent and Figures 3.2-2 and 3.2-23 for

a depiction of steam jet air ejector after-condenser exhaust routing to the plant vent.

Refer to Section 11.4 for discussion of radiation monitors.

10.4.2.4 Tests and Inspections Tests and inspections of the MCES are done in accordance with plant procedures.

10.4.2.5 Instrumentation Applications Instrumentation is provided to monitor and control MCES operation.

10.4.3 TURBINE GLAND SEALING SYSTEM The turbine gland sealing system provides shaft sealing for the main turbine and feedwater pump turbine.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-5 Revision 23 December 2016 10.4.3.1 Design Bases The turbine gland sealing system is designed to prevent the leakage of air into, or

steam out of, the turbines along the turbine shaft. The system has no PG&E Design

Class I functions and is classified as PG&E Design Class II.

10.4.3.1.1 General Design Criterion 17, 1967 - Monitoring Radioactivity Releases Means shall be provided for monitoring the containment atmosphere, the facility effluent discharge paths, and the facility environs for radioactivity that could be released from

normal operations, from anticipated transients, and from accident conditions.

10.4.3.1.2 NUREG-0737 (Item II.F.1), November 1980 - Clarification of TMI Action Plan Requirements Item II.F.1 - Additional Accident-Monitoring Instrumentation:

Position (1) - Item II.F.1, Position (1) requires monitoring of post-accident effluent noble gas releases from the turbine gland sealing system.

Position (2) - Item II.F.1, Position (2) requires monitoring of post-accident effluent radioactive iodine and particulate releases from the turbine gland sealing system.

10.4.3.2 System Description The turbine glands are of the labyrinth type.

When the unit is being started, and partially during normal operation, steam is supplied to the gland header from the main

steam line to seal the high-pressure and lo w-pressure turbine glands. The auxiliary boiler also can be used to supply sealing steam during startup. When the turbine is

operating under load, the steam pressure inside the high-pressure turbine increases

and steam leaks outward toward the rotor ends. The leakage from the high-pressure

glands partially supplies the steam requirements for the low-pressure glands, while the remainder is furnished by the main steam gland regulator. Adequate steam pressure is

maintained in the gland area at all times to prevent the leakage of air into, or steam out

of, the turbine along the turbine shaft.

At normal operating conditions, the exhaust from the gland seals is approximately

3000 pounds per hour of air saturated with water vapor at 150°F. The gland steam

condenser maintains a pressure slightly below atmosphere in the gland leak-off system

to prevent the escape of steam from the glands. The air and noncondensable gases

from the turbine gland seal condenser are exhausted to the plant vent, which is

continuously monitored (refer to Section 11.4.2.1.2.1).

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-6 Revision 23 December 2016 10.4.3.3 Safety Evaluation 10.4.3.3.1 General Design Criterion 17, 1967 - Monitoring Radioactivity Releases The turbine gland sealing system has no PG&E Design Class I function. In the event of

steam generator leakage and continued plant operation, the gland sealing system

prevents the release of radioactive steam to the turbine building. If gland seals are lost due to a malfunction of the system, a small amount of steam could be released depending on the type of equipment malfunction. Upon the loss of gland sealing steam, the turbine would be tripped to prevent seal or rotor damage. A turbine trip would

prevent additional radioactive steam from entering the turbine.

The air and noncondensable gases from the gland seal condenser are routed to the

plant vent (refer to Sections 9.4.2 and 11.4.2.1.2.1).

In the event that the gland steam becomes contaminated, it will be detected by radiation detectors located in the plant

vent (normal range [NR] and redundant normal range [RNR] radiation monitors). The

turbine building is not monitored for leakage from the glands. Details of the radiological

evaluation of the system are included in Section 11.3.2.3.

10.4.3.3.2 NUREG-0737 (Item II.F.1), November 1980 - Clarification of TMI Action Plan Requirements Item II.F.1 - Additional Accident-Monitoring Instrumentation:

Position (1) - Radiation detection instruments are provided in the plant vent to monitor

post-accident effluent noble gas releases from the turbine gland sealing system. Refer to Section 9.4.2 for information on the plant vent and Figure 3.2-23 for a depiction of

turbine gland steam condenser exhaust routing to the plant vent. Refer to Section 11.4

for discussion of radiation monitors.

Position (2) - Radiation detection instruments are provided in the plant vent to monitor

post-accident effluent radioactive iodine an d particulate releases from the turbine gland sealing system. Refer to Section 9.4.2 for information on the plant vent and Figure 3.2-

23 for a depiction of turbine gland steam condenser exhaust routing to the plant vent.

Refer to Section 11.4 for discussion of radiation monitors.

10.4.4 TURBINE BYPASS SYSTEM The turbine bypass system (TBS) bypasses main steam directly to the main condenser

and atmosphere, depending on the required capacity, during the emergency condition

caused by a sudden load reduction by the turbine-generator or turbine trip, and during

plant startup and shutdown.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-7 Revision 23 December 2016 10.4.4.1 Design Bases Of the 25 turbine bypass valves (refer to Section 10.4.4.2), only the four 10 percent atmospheric dump valves have a safety function (refer to Section 10.4.4.3.7).

Therefore, the design bases in this section apply only to these valves and their

associated upstream piping systems.

10.4.4.1.1 General Design Criterion 2, 1967 - Performance Standards The 10 percent atmospheric dump valves are designed to withstand the effects of, or

shall be protected against, natural phenomena, such as earthquakes, flooding, tornadoes, winds, and other local site effects.

10.4.4.1.2 General Design Criterion 3, 1971 - Fire Protection The 10 percent atmospheric dump valves are designed and located to minimize, consistent with other safety requirements, the probabil ity and effect of fires and explosions.

10.4.4.1.3 General Design Criterion 11, 1967 - Control Room The 10 percent atmospheric dump valves are designed to support actions to maintain

and control the safe operational status of the plant from the control room or from an alternate location if control room access is lost due to fire or other causes.

10.4.4.1.4 General Design Criterion 12, 1967 - Instrumentation and Control Systems Instrumentation and controls are provided as required to monitor and maintain the 10

percent atmospheric dump valves variables within prescribed operating ranges.

10.4.4.1.5 General Design Criterion 54, 1971 - Piping Systems Penetrating Containment The piping system associated with the 10 percent atmospheric dump valves is provided with leakage detection, isolation, and containment capabilities having redundancy, reliability, and performance capabilities which reflect the importance to safety of

isolating this system. The piping system associated with the 10 percent atmospheric dump valves shall be provided with a capability to test periodically the operability of the isolation valves and associated apparatus and to determine if valve leakage is within acceptable limits.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-8 Revision 23 December 2016 10.4.4.1.6 General Design Criterion 57, 1971 - Closed System Isolation Valves The main steam system headers associated with the 10 percent atmospheric dump

valves contain piping connected to containment penetrations that are neither part of the

reactor coolant pressure boundary nor connected directly to the containment

atmosphere. These penetrations are provided with one local or remote-manual valve

outside the containment.

10.4.4.1.7 Turbine Bypass System Safety Function Requirements (1) Protection from Missiles and Dynamic Effects

The 10 percent atmospheric dump valves are designed to be protected against the effects of missiles and dynamic effects, which may result from equipment failures.

(2) Reactor Coolant System Cooldown

The 10 percent atmospheric dump valves are designed to provide a method for reactor

coolant system (RCS) cooldown.

10.4.4.1.8 10 CFR 50.55a(f) - Inservice Testing Requirements The 10 percent atmospheric dump valves are tested to the requirements of 10 CFR

50.55a(f)(4) and a(f)(5) to the extent practical.

10.4.4.1.9 10 CFR 50.55a(g) - Inservice Inspection Requirements The 10 percent atmospheric dump valves are inspected to the requirements of 10 CFR

50.55a(g)(4) and a(g)(5) to the extent practical.

10.4.4.1.10 10 CFR 50.63 - Loss of All Alternating Current Power The 10 percent atmospheric dump valves are required to perform their safety function of

supporting reactor coolant system cooldown in the event of a station blackout (SBO).

10.4.4.1.11 10 CFR Part 50 Appendix R (Sections III.G, III.J, and III.L) - Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979 Section III.G - Fire Protection of Safe Shutdown Capability: Fire protection of the 10

percent atmospheric dump valves is provided by a combination of physical separation, fire-rated barriers, and/or automatic suppression and detection.

Section III.J - Emergency Lighting: Emergency lighting or battery operated lights (BOLs) is provided in areas where operation of the 10 percent atmospheric dump valves

may be required to safely shut down the Unit following a fire.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-9 Revision 23 December 2016 Section III.L - Alternative and Dedicated Shutdown Capability: Safe shutdown

capabilities are provided in the control room and at an alternate location via the hot

shutdown panel (HSP) or locally at the 10 percent atmospheric dump valves as required

for the safe shutdown of the plant following a fire event.

10.4.4.2 System Description The TBS consists of 25 power relief valves. Four of these valves (10 percent dump

valves) take steam from each main steam line and discharge to the atmosphere. The

remaining 21 valves take steam from the dump headers (connected to all main steam

lines)and discharge either into spray distribution headers in the condenser (40 percent

dump valves) or to the atmosphere (35 percent dump valves). The system thus provides an artificial load on the reactor coolant system during the emergency condition of a

sudden load reduction by the turbine-generator or a turbine trip (four of the 40 percent dump valves are used during cooldown).

The valve groups are opened in the following sequence:

(1) Cooldown valves (four of twelve 40 percent dump valves)

(2) Bypass valves (remaining eight of twelve 40 percent dump valves)

NOTE: Plant capability is provided to use all 12 valves for cooldown during Mode 3 after boration to cold shutdown conditions.

(3) Atmospheric relief valves (nine 35 percent atmospheric dump valves downstream of the main steam isolation valves (MSIVs))

(4) Atmospheric relief valves (four 10 percent atmospheric dump valves upstream of the MSIVs)

NOTE: Group 4 of the atmospheric dump valves (ADVs) are set at a lower pressure than the spring-loaded safety valves.

The TBS is thus designed with a capacity to bypass a range of approximately 66 to 79

percent of the full load steam flow over the range of full load operating conditions to the

main condenser and the atmosphere combined. The exact capacities of these relief

valves depend on the full load operating con ditions. Valve groups 1, 2, and 3 are credited in determining this capacity. The steam dump capacity to the main condenser

alone (groups 1 and 2 ) has a range of approximately 35 to 41 percent of the full load

steam flow over the range of full load operating conditions.

The capacity of the TBS, combined with the 10 percent step-load-change characteristics

of the reactor, provides the capability of accepting a sudden load reduction of up to

50 percent, without reactor trip or operation of the spring-loaded safety valves or 10

percent atmospheric dump valves.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-10 Revision 23 December 2016 The total amount of steam released to the atmosphere during a loss of generator

external load assuming that the condenser is not available for steam dump is discussed in Section 15.5.10.2.

With the exception of group 4 of the atmospheric dump valves, the TBS is not

essential to the safe operation of the plant; it is required to give the plant flexibility of

operation and a controlled cooldown. The steam generator safety valves provide

relieving capacity during a period when all va lves are out of service (refer to Section 10.3.2).

Failure of the 40 percent dump valves, the 35 percent atmospheric dump valves downstream of the main steam isolation valves, or any pipe downstream of the MSIVs could result in a rapid cooldown and depressurization of the steam generators until the MSIVs close on high negative steam line pressure rate or low steam line pressure

signals. The transients and radiologic al consequences associated with such a failure would not be as severe as the double-ended severance of a main steam line, as

discussed in Section 15.5.18. Failure of any of these components (or pipe associated

with them) downstream of the MSIVs could not cause overpressurization of a steam

generator because of the location of the spring-loaded safety valves upstream of the

MSIVs.

The TBS has been analyzed for potential effects of piping rupture on nearby

safety-related equipment. Details of this analysis are presented in Section 3.6.4.

10.4.4.2.1 Design Codes and Standards The piping and valves associated with the 40 percent and 35 percent dump valves are

classified as PG&E Design Class II because they are not required for RCS cooldown, as discussed in Section 10.4.4.3.

The 10 percent atmospheric dump valves and associated upstream piping are classified

as PG&E Design Class I because they are required for RCS cooldown, as discussed in Section 10.4.4.3.7.

Applicable codes and standards for piping, valves, and fittings are discussed in Section

3.2. 10.4.4.3 Safety Evaluation 10.4.4.3.1 General Design Criterion 2, 1967 - Performance Standards The 10 percent atmospheric dump valves are PG&E Design Class I components and

are located either on the roof of the PG&E Design Class I auxiliary building at elevation 143 feet (steam leads 3 and 4) or on a support structure external to the containment at DCPP UNITS 1 &

2 FSAR UPDATE 10.4-11 Revision 23 December 2016 elevation 112 feet-6 inches (steam leads 1 and 2). These elevations are above the level affected by floods and tsunamis.

PG&E Design Class I SSCs in locations exposed to the weather are evaluated against

tornado-related effects including impact by tornado-induced missiles. Refer to Section

3.3.2.3 for the results of the evaluation.

The 10 percent atmospheric dump valves are required to function following a DE, DDE, and HE (refer to Sections 3.7.1.1 and 3.7.6.1).

10.4.4.3.2 General Design Criterion 3, 1971 - Fire Protection The 10 percent atmospheric dump valves have been evaluated for safe shutdown following a fire (refer to Appendix 9.5G). Only one of the four valves is required for safe

shutdown and the valves' steam relief functions are backed up by the main steam code

safety valves. Therefore, a fire will not affect the valves' abilities to safely shutdown the

plant.

10.4.4.3.3 General Design Criterion 11, 1967 - Control Room The 10 percent atmospheric dump valves can be controlled manually from within the

control room in order to maintain safe operational status of the plant. In the event that

control room access is lost due to fire or other causes, the valves can be controlled

manually from the hot shutdown panel (refer to Section 7.4.2.1.2.3).

10.4.4.3.4 General Design Criterion 12, 1967 - Instrumentation and Control Systems Instrumentation for manually operating the 10 percent atmospheric dump valves is

provided in the main control room, at the hot shutdown panel, and locally at the valve (refer to Section 7.4.2.1.2.3). Valve position indication is provided on the Emergency

Response Facility Data System (ERFDS) (refer to Section 7.5.2.9).

10.4.4.3.5 General Design Criterion 54, 1971 - Piping Systems Penetrating Containment The 10 percent atmospheric dump valves, required for containment closure, are periodically tested for operability.

Testing of the components required for the containment isolation system (CIS) is discussed in Section 6.2.4.

10.4.4.3.6 General Design Criterion 57, 1971 - Closed System Isolation Valves The containment penetrations associated with the 10 percent atmospheric dump valves

comply with the requirements of GDC 57, 1971, as described in Section 6.2.4 and Table

6.2-39.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-12 Revision 23 December 2016 10.4.4.3.7 Turbine Bypass System Safety Function Requirements (1) Protection from Missiles and Dynamic Effects The 10 percent atmospheric dump valves are protected against postulated missile

sources as described in Section 3.5.1.2.

The 10 percent atmospheric dump valves are PG&E Design Class I equipment and

therefore are designed to be protected against dynamic effects which may result from

equipment failures as described in Section 3.6.

(2) Reactor Coolant System Cooldown

The 10 percent atmospheric dump valves provide a means for plant cooldown by

discharging steam to the atmosphere when the condenser, the condenser circulating

water pumps, or steam dump to the condenser is not available. Under such

circumstances, the 10 percent atmospheric dump valves, in conjunction with the

auxiliary feedwater system, permit the plant to be cooled down from the pressure

setpoint of the lowest-set MSSVs to the point where the residual heat removal system

can be placed in service. In the event of a steam generator tube rupture (SGTR) event in conjunction with loss of offsite power, the 10 percent atmospheric dump valves are

used to cool down the RCS to a temperature that permits equalization of the primary

and secondary pressures at a pressure below the lowest-set MSSV.

With the loss of both the normal air supply and the backup nitrogen supply to the 10

percent atmospheric dump valves, the normal supplies are blocked and the PG&E Design Class I backup air bottle system is activated (refer to Section 9.3.1.6). With the backup air bottle system activated, control of the valves is remote manual via the PG&E Design Class I control circuit from the control room ensuring the valves can cooldown

the RCS.

10.4.4.3.8 10 CFR 50.55a(f) - Inservice Testing Requirements The TBS components that are within the IST program are the four 10 percent

atmospheric dump valves.

The inservice testing (IST) requirements for these components are contained in the IST

Program Plan and comply with the ASME code for Operation and Maintenance of

Nuclear Power Plants.

10.4.4.3.9 10 CFR 50.55a(g) - Inservice Inspection Requirements The 10 percent atmospheric dump valves have a periodic inservice inspection (ISI)

program in accordance with the ASME B&PV Code,Section XI (refer to Section

5.2.3.15).

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-13 Revision 23 December 2016 10.4.4.3.10 10 CFR 50.63 - Loss of All Alternating Current Power During an SBO, decay heat is removed fro m the core by natural circulation of the reactor coolant. This heat is then transferred to the secondary side of the steam

generators and discharged to the atmosphere through the 10 percent atmospheric

dump valves.

The 120-Vac system provides power to the analog control portion and the enabling logic of the steam dump control system. It also provides 120-Vac power to the controls for the 10 percent atmospheric dump valve backup air controls ensuring they can perform

their safety function of supporting RCS cooldown in the event of an SBO.

10.4.4.3.11 10 CFR Part 50 Appendix R (Sections III.G, J, and L) - Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979 10 CFR Part 50 Appendix R requires the evaluation of the safe shutdown capability for DCPP in the event of a fire and the loss of offsite power. The 10 percent atmospheric

dump valves satisfy the applicable requirements of 10 CFR Part 50 Appendix R, Sections III.G, J, and L.

Section III.G - Fire Protection of Safe Shutdown Cap ability: For the TBS, one out of four 10 percent atmospheric dump valves is the minimum required equipment to bring

the plant to a cold shutdown condition. The 10 percent atmospheric dump valves are

provided with fire protection features appropriate to the requirements of Section III.G.

Section III.J - Emergency Lighting: Emergency lighting or battery operated lights (BOL) are provided in areas where operation of the 10 percent atmospheric dump valves may

be required for safe shutdown following a fire as defined by 10 CFR Part 50, Appendix R, Section III.J (refer to Appendix 9.5D).

Section III.L - Alternative and Dedicated Shutdown Capability: Safe shutdown

capabilities are provided in the control room and at alternate locations in accordance with 10 CFR Part 50 Appendix R, Section III.L (refer to Section 7.4 and Appendix 9.5E).

The ability to safely shut down the plant following a fire in any fire area is summarized in

Section 4.0 of Appendix 9.5A.

10.4.4.4 Tests and Inspections Local test facilities for the bypass flow control valves are not provided. The 40 percent

dump valves and the 35 percent dump valves are PG&E Design Class II and are tested

at reactor low power levels.

Each 10 percent atmospheric dump valve , associated block valve, and associated

remote manual controls, including the backup air bottles, is demonstrated operable on a

frequency interval required by the Technical Specifications.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-14 Revision 23 December 2016 Additionally, each 10 percent atmospheric dump block valve is verified open at least

once per 31 days

Should evidence indicate that radioactivity is being released as a result of leakage through these valves during the post-accident recovery period, action such as tightening

packing will be taken to eliminate the source.

10.4.4.5 Instrumentation Applications During normal operating transients for which the plant is designed, the TBS is

automatically regulated by the reactor coolant temperature control system to maintain the programmed coolant temperature.

When a transient results in a plant trip, the operator transfers bypass control to the pressure control mode and regulates the system to maintain no-load steam pressure.

Lower pressures can be maintained automatically by adjustment of the pressure

setpoint. During a plant cooldown, the bypass system is manually controlled to achieve

the required cooling rate. This is accomplished by manual adjustment of the pressure

setpoint in the control room and requires a minimum operation of four bypass valves to

the condenser.

Refer to Section 10.4.4.3.4 for additional information on instrumentation and controls.

10.4.5 CIRCULATING WATER SYSTEM

The circulating water system provides the heat sink required for removal of waste heat in the power plant's thermal cycle. The system has the principal function of removing

heat by absorbing this energy in the main condenser.

10.4.5.1 Design Bases 10.4.5.1.1 Circulating Water System Safety Function Requirements (1) Internal Flooding Protection

The circulating water system is designed to prevent flooding of PG&E Design Class I

equipment.

10.4.5.2 System Description The circulating water system is designed to provide cooling water necessary to

condense the steam entering the main condenser. The system also serves the intake

coolers, condensate cooler, and service cooling water heat exchangers. The design

temperature rise in the circulating water system at full load operation is 18°F. The

design flow per unit is nominally 862,000 gpm.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-15 Revision 23 December 2016 The circulating water system is classified as PG&E Design Class II.

Condenser circulating water is seawater from the Pacific Ocean. The ocean water level

normally varies between zero and +6 feet mean lower low water (MLLW) datum. Mean sea level (MSL) zero is equivalent to +2.6 feet MLLW.

A curtain wall at the front of the intake structure limits the amount of floating debris

entering the intake structure. Bar racks near the front of the intake structure intercept large submerged debris. The bar racks have 3/8-inch thick bars at 3-3/8 inch centers.

Traveling screens intercept all material larger than the screen mesh opening (3/8 inch

clear square openings).

The total flow in each unit's circulating water system is nominally 862,000 gpm, which is

pumped by two circulating water pumps per unit through two circulating water conduits

per unit to the condenser inlet water boxes. Each pump has a discharge valve and

bypass line around the valve. Approximately 4000 gpm of the circulating water flow is

used per unit to cool the service cooling water heat exchangers and 1000 gpm to cool

the pump motor cooling water.

At the intake structure, each circulating water system consists of two circulating water

pumps with 12-kV motors cooled by an air-to-water heat exchanger. The cooling water

is provided from a closed-loop cooling system.

The chlorination system provides chemical treatment of the circulating water to control

macro and micro fouling in the intake tunnels, piping, and the condenser tubes. The system is used as needed.

The chlorination system, which is shown as part of Figure 3.2-17, provides an oxidizing

biocide to the suction of the circulating water pumps for control of macro and micro

fouling. Liquid sodium hypochlorite and a supplemental chemical are stored in tanks at

the intake structure (common to both units).

Adequate valving is provided for isolating any of the tanks from the system. Each tank is within a containment tank sized to

contain the entire contents of the storage tank. When chlorination is required (based on

a time schedule), the chemicals are injected via metering pumps and injected into the

intake structure. In addition, dechlorinating injections are made between the outlet of

the main condenser and the discharge structure as required to ensure National

Pollutant Discharge Elimination System (NPDES) permit requirements are met.

Concentrations of chlorine in the circulation water system outfall are discussed in detail

in Reference 1 and the NPDES permit.

The circulating water pumps are not required for safety of the units. Dependable pump

operation is necessary, however, for reliable operation of electric generating plants and

provisions to ensure their operation are incorporated in the design.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-16 Revision 23 December 2016 10.4.5.3 Safety Evaluation 10.4.5.3.1 Circulating Water System Safety Function Requirements (1) Internal Flooding Protection

Due to the low operating pressure of the circulating water system, the probability of a

line, expansion joint, or waterbox failure is very low. The differential head across the

circulating water pumps at shutoff is a nominal 160 feet. At high tide, the pump

discharge head at shutoff would be 163.4 feet (refer to Section 10.4.5.2), measured at

elevation zero, MSL datum. However, provisions exist in the design of the circulating

water system that prevent the circulating water pumps from operating at shutoff head.

The design of the inlet and outlet of the circulating water to the condenser consists of

several components. The circulating water flows through the embedded supply conduit, the inlet transition spool piece, the inlet ex pansion joint, and inlet condenser water box prior to entering the condenser tubes. Similarly, upon exiting the tubes, the circulating

water passes through the outlet waterbox, expansion joint, transition spool piece, and

embedded discharge conduit prior to being discharged to the ocean. The transition spool pieces, expansion joints, and condenser (including waterboxes) are located in the

turbine building. The discharge gates are located in the embedded discharge conduit in

the yard.

The design pressure of the rubber expansion joints on the inlet and outlet of the

condenser (located at an elevation of 85 feet) is 81 feet.

Thus, if a circulating water pump were to pump against closed discharge gates, the

pressure on the expansion joint (the pump discharge head minus the static elevation

head) would be less than the design pressure. The design pressure of the transition

inlet and outlet spool pieces (located at an elevatio n of 81 feet) is 58 feet. Similarly, the design pressure of the condenser water boxes (located at an elevation of 85 feet) is

58 feet. To prevent operating the circulating water pump and system in a configuration

that could result in overpressurizing the transition spool pieces and waterboxes, mechanical stops on the condenser discharge gate operators and structural stops on

the gate guide tracks inhibit the complete closing of the discharge gates. Dynamic

water hammer pressures will not occur due to inadvertent closing of the water gates

because the motor operators close the gates at a rate of only 15 inches per minute.

These measures make circulating water system overpressurization a highly improbable

event.

Inlet spool pieces and water boxes are constructed of ductile carbon steel with a

corrosion-resistant internal coating, and their catastrophic failure, such that significant

seawater could flood the turbine building, is not a credible assumption. The cast iron

outlet spool piece was hydrotested to 1.5 times the maximum attainable circulating

water system pressure.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-17 Revision 23 December 2016 A flooding analysis was performed based on the failure of an operator to properly

secure a condenser waterbox manway cover. In order to obtain a conservative flooding

rate for this scenario, waterbox manhole cover failure was assumed to be coincident

with an operating error in which both circulating water pumps were running and both

discharge gates were closed to the stops. In this event, approximately 43,000 gpm or

5,700 cfm of water could be expected to flow from a lower inlet waterbox manhole (the

manholes with the greatest incident head of water). This flow would fill the sump and

equipment pit storage areas below elevation 85 feet in 15 minutes, if the building drains are assumed to be functioning, and in 10 minutes, if the drains are not functioning.

During this time, alarms would be given for turbine building sump high level and for

water in the condenser pit. It may be assumed that the condensate pumps, being

flooded, would have tripped, giving dramatic indication of an irregular condition.

In order to provide additional time for operators to react to this flooding casualty, a fire door was installed between the main condensers and the corridor to the emergency diesel generator rooms in order to minimize the amount of water that could enter the compartments. The door is locked closed and monitored through the security system.

This door will allow at least 12 more minutes (assuming no flow of water from the

building) for the postulated manhole failure flow after sumps and pits are flooded.

Subsequent to the fire door install ation, a float switch system was mounted on the walls of the condenser pit. This instrumentation system eliminated the need for operator

action in order to protect PG&E Design Class I equipment from any type of circulating

water system leakage. The system will automatically trip the circulating water pumps if

water fills the condenser pit thereby assuring that the turbine building cannot be flooded by a circulating water system leak. The system employs two-out-of-three logic for a high degree of reliability and it provides a high condenser pit level alarm indication in the control room.

10.4.5.4 Tests and Inspections Tests and inspections of the circulating water system are done in accordance with plant

procedures.

10.4.5.5 Instrumentation Applications Instrumentation is provided to monitor and control circulating water system operation.

As described in Section 10.4.5.3.1(1), high water level in the turbine building condenser

pit will trip the circulating water pumps and provide an alarm in the control room.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-18 Revision 23 December 2016 10.4.6 CONDENSATE POLISHING SYSTEM The PG&E Design Class II condensate polishing system removes both dissolved and

suspended corrosion products and impurities from the condensate. The system is

important to maintaining secondary water chemistry and minimizes the buildup of

sludge in the steam generators.

10.4.6.1 Design Bases 10.4.6.1.1 General Design Criterion 3, 1971 - Fire Protection The condensate polishing system is designed and located to minimize, consistent with other safety requirements, the probability and effect of fires and explosions.

10.4.6.1.2 General Design Criterion 9, 1967 - Reactor Coolant Pressure Boundary The materials of construction of the pressure-retaining boundary of the steam generator tubes are protected by control of secondary chemistry from corrosion that might

otherwise reduce the system structural integrity during its service lifetime. The

condensate polishing system functions to contribute to the secondary chemistry control.

10.4.6.1.3 Condensate Polishing System Function Requirement

(1) Internal Flooding The condensate polishing system shall be designed to be protected against the effects of internal flooding which may result from equipment failures.

10.4.6.1.4 Regulatory Guide 1.78, June 1974, Assumptions for Evaluating the Habitability of a Nuclear Power Plant Control Room During a

Postulated Hazardous Chemical Release The DCPP control room should be appropriately protected from hazardous chemicals that may be discharged as a result of equipment failures, operator errors, or events and

conditions outside the control of the plant.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-19 Revision 23 December 2016 10.4.6.2 System Description The condensate polishing system is comprised of seven mixed bed demineralizers.

Either six or seven demineralizers are in service processing the full condensate flow (approximately 21,000 gpm) depending on whether any one of the demineralizers is in the regeneration mode or not. The demineralizer in the regeneration mode is taken out

of service and is regenerated externally in order to minimize the possibility of

introducing regenerant chemicals in the condensate and feedwater system. The

external regeneration process for one demineralizer normally takes about 12 to

16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />.

Components of the condensate p olishing system, including demineralizers, regenerators, and associated equipment, are located in the turbine building buttresses.

The system is capable of either automatic or manual operation, and can be bypassed if

necessary.

The vessels are designed to Section VIII of the ASME code. The system piping is

designed to ANSI B31.1 (refer to Section 3.2).

The condensate polishing system is classified as PG&E Design Class II. Although

located within the PG&E Design Class I turbine building buttresses, the system and component supports, including enclosures, do not compromise the PG&E Design Class I seismic requirement of the turbine building buttress structure.

Personnel safety provisions include smoke detectors and portable fire extinguishers in compartments where potential for fire exists. Eyewashes and a safety shower are also provided in the chemical storage and chemical feed pump areas.

10.4.6.3 Safety Evaluation 10.4.6.3.1 General Design Criterion 3, 1971 - Fire Protection The chemicals of the condensate polishing system (sodium hydroxide and sulfuric scid) are stored in accordance with the requirements of Branch Technical Position 9.5-1 (refer to Appendix 9.5B, Table B-1).

10.4.6.3.2 General Design Criterion 9, 1967 - Reactor Coolant Pressure Boundary The condensate polishing system is designed to polish the full condensate flow during

startup and normal plant operation. During startup, the system allows recirculation of

condensate at approximately 5500 gpm through the condensate polishing demineralizers and feedwater heaters, returning it to the main condenser. This design provision allows a more complete cleanup of secondary water prior to system startup.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-20 Revision 23 December 2016 The condensate polishing system monitors the secondary chemistry to protect the steam generator tubes which are a part of the reactor coolant pressure boundary from

degradation during the course of its lifetime. This is in compliance with the steam

generator tube integrity requirements of Generic Letter 85-02.

10.4.6.3.3 Condensate Polishing Sy stem Safety Function Requirement (1) Internal Flooding

The condensate polishing system is designed so that its failure will not impact the

PG&E Design Class I SSCs in the turbine buttress building.

10.4.6.3.4 Regulatory Guide 1.78, June 1974, Assumptions for Evaluating the Habitability of a Nuclear Power Plant Control Room during a

Postulated Hazardous Chemical Release

The DCPP control room is adequately protected from hazardous chemicals that may be

discharged from the condensate polishing system, including sodium hydroxide and sulfuric acid. These chemicals have been analyzed to show that they do not adversely

impact the control room.

Details of the control room habitability evaluations are discussed in Sections 6.4.1 and

9.4.1.

10.4.6.4 Tests and Inspections Tests and inspections of the condensate polishing system are done in accordance with plant procedures.

10.4.6.5 Instrumentation Applications Instrumentation is provided to monitor and control the condensate polishing system

operation.

10.4.7 CONDENSATE AND FEEDWATER SYSTEMS The condensate and main feedwater systems, shown in Figures 3.2-2 and 3.2-3, receive condensate from the main condenser hotwells and deliver it as feedwater to the steam generator (SG) at the required pressure and tem perature. In the SG, the feedwater removes heat from the reactor coolant and is converted into steam.

The PG&E Design Class I portion of the main feedwater system extends from the upstream side of the main feedwater check valves to the SG nozzles. Additionally the main feedwater regulating valves (MFRVs) that are located upstream of the main feedwater check valves, along with their respective MFRV bypass valves, are PG&E Design Class I and are located in PG&E Design Class II piping that has been DCPP UNITS 1 &

2 FSAR UPDATE 10.4-21 Revision 23 December 2016 seismically qualified. Refer to the DCPP Q-list (Reference 8 of Section 3.2) for a listing of PG&E Design Class II equipment that is included in the condensate and main feedwater systems.

The auxiliary feedwater (AFW) system connects to the main feedwater lines outside of containment between the motor-operated main feedwater isolation valves (MFIVs) and the containment penetrations. This interface provides a PG&E Design Class I flow path for the AFW system to feed the SGs.

The main feedwater ring and SG tubes are further discussed in Section 5.5.2.

10.4.7.1 Design Bases 10.4.7.1.1 General Design Criterion 2, 1967 - Performance Standards Certain portions of the main feedwater system are designed to withstand the effects of, or are protected against, natural phenomena, such as earthquakes, tornadoes, flooding, winds, tsunamis, or other local site effects.

The effects of a tornado on the main feedwater system are addressed to ensure that plant safe shutdown can be achieved.

10.4.7.1.2 General Design Criterion 3, 1971 - Fire Protection The condensate and main feedwater systems are designed and located to minimize, consistent with other safety requirements, the probabil ity and effect of fires and explosions.

10.4.7.1.3 General Design Criterion 11, 1967 - Control Room The condensate and main feedwater systems are designed or contain instrumentation and controls that support actions to maintain the safe operational status of the plant from the control room or from an alternate location if control room access is lost due to fire or other cause.

10.4.7.1.4 General Design Criterion 12, 1967 - Instrumentation and Control Systems Instrumentation and controls are provided as required to monitor and maintain the variables associated with the condensate and main feedwater systems within prescribed operating ranges.

10.4.7.1.5 General Design Criterion 15, 1967 - Engineered Safety Features Protection Systems The SG level transmitters provide for sensing accident situations.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-22 Revision 23 December 2016 10.4.7.1.6 General Design Criterion 21, 1967 - Single Failure Definition The PG&E Design Class I portion of the main feedwater system is designed to remain operable after sustaining a single failure. Multiple failures resulting from a single event are treated as a single failure.

10.4.7.1.7 General Design Criterion 49, 1967 - Containment Design Basis The PG&E Design Class I portion of the main feedwater system is designed to support the capability of the containment structure to accommodate, without exceeding the design leakage rate, the pressures and temperatures resulting from the largest credible energy release following a loss-of-coolant accident (LOCA), including a considerable margin for effects from metal-water or o ther chemical reactions that could occur as a consequence of failure of emergency core cooling systems.

10.4.7.1.8 General Design Criterion 54, 1971 - Piping Systems Penetrating Containment The PG&E Design Class I portion of the main feedwater system provides the capability for testing the functional operability of valves essential to the containment isolation function. 10.4.7.1.9 General Design Criterion 57, 1971 - Closed System Isolation Valves The PG&E Design Class I portion of the main feedwater system is designed to provide isolation valves outside the containment capable of automatic and manual closure.

10.4.7.1.10 Condensate and Feedwater Systems Safety Function Requirements (1) Protection from Missiles and Dynamic Effects The PG&E Design Class I portion of the main feedwater system is designed to be protected against the effects of missiles and dynamic effects that may result from equipment failures. The main feedwater pump turbines are located to ensure that their failure would not result in the generation of missiles that could affect safe shutdown of either unit.

(2) Internal Flooding Protection Rupture of the PG&E Design Class II portion of the condensate and main feedwater systems would not impact PG&E Design Class I SSCs.

The PG&E Design Class I portion of the main feedwater system is designed to be protected from the effects of internal flooding.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-23 Revision 23 December 2016 (3) Main Feedwater Isolation The main feedwater system is capable of isolating main feedwater flow to the SGs to prevent overfilling the SGs or over-cooling the RCS, and to minimize mass and energy release following a secondary system pipe rupture.

10.4.7.1.11 10 CFR 50.49 - Environmental Qualification of Electric Equipment Important to Safety for Nuclear Power Plants Main feedwater system components that require environmental qualification (EQ) are qualified to the requirements of 10 CFR 50.49.

10.4.7.1.12 10 CFR 50.55a(f) - Inservice Testing Requirements The main feedwater system American Society of Mechanical Engineers (ASME) Code components are tested to the requirements of 10 CFR 50.55a(f)(4) and 10 CFR 50.55a(f)(5) to the extent practical.

10.4.7.1.13 10 CFR 50.55a(g) - Inservice Inspection Requirements The main feedwater system ASME Code components are inspected to the requirements of 10 CFR 50.55a(g)(4) and 10 CFR 50.55a(g)(5) to the extent practical.

10.4.7.1.14 10 CFR 50.62 - Requirements for Reduction of Risk from Anticipated Transients Without Scram (ATWS) Events for Light-Water-Cooled Nuclear Power Plants The SG level transmitters provide signals to initiate ATWS Mitigation System Actuation Circuitry (AMSAC) following an ATWS transient.

10.4.7.1.15 10 CFR Part 50 Appendix R (Section I II.G, J, and L) - Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979 The PG&E Design Class I portion of the main feedwater system is designed to provide a decay heat removal flowpath to achieve and maintain a safe shutdown condition for fire events. The decay heat flowpath is within the PG&E Design Class I portion of the system.Section III.G - Fire Protection of Safe Shutdown Capability: The PG&E Design Class I portion of the main feedwater system is designed with fire protection features that are capable of limiting fire damage so that the main feedwater SSCs necessary to achieve and maintain safe shutdown conditions from either the control room or hot shutdown panel are free of fire damage.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-24 Revision 23 December 2016 Section III.J - Emergency Lighting: Emergency lighting units with at least an 8-hour battery power supply are provided in all areas needed for operation of the main feedwater system and in access and egress routes thereto.

Section III.L - Alternative and Dedicated Shutdown Capability: Alternate shutdown capability is provided to achieve and maintain hot standby conditions, achieve cold shutdown conditions within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, and maintain cold shutdown conditions thereafter.

10.4.7.1.16 Generic Letter 89-10, June 1989 - Safety-Related Motor-Operated Valve Testing and Surveillance PG&E Design Class I motor-operated valves (MOVs) in the main feedwater system meet the requirements of Generic Letter 89-10, June 1989, and associated Generic Letter 96-05, September 1996.

10.4.7.1.17 Generic Letter 89-08, May 1989 - Erosion/Corrosion-Induced Pipe Wall Thinning DCPP has implemented formalized procedures and administrative controls to assure long-term implementation of its erosion/corrosion monitoring program for the condensate and main feedwater systems.

10.4.7.1.18 Regulatory Guide 1.97, Revision 3, May 1983 - Instrumentation for Light-Water-Cooled Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident The main feedwater system provides instrumentation to monitor system variables during and following an accident.

10.4.7.1.19 Branch Technical Position ASB 10-2, March 1978 - Design Guidelines for Water Hammers in Steam Generators with Top Feedring Designs The main feedwater system is designed to eliminate or reduce possible water hammer in the system, as follows:

1) The main feedwater system is designed to prevent or delay water draining from the feedring following a drop in SG level.
2) The main feedwater system is designed to minimize the volume of feedwater piping external to the SG that could pocket steam by using the shortest possible (less than seven feet) horizontal run of inlet piping to the SG feedring.
3) Tests acceptable to the NRC were performed to verify that unacceptable feedwater hammer would not occur using the plant operating procedures for DCPP UNITS 1 &

2 FSAR UPDATE 10.4-25 Revision 23 December 2016 normal and emergency restoration of SG water level following a loss of normal feedwater and possible draining of the feedring.

10.4.7.2 System Description The condensate and main feedwater systems are primarily PG&E Design Class II systems except for a part of the main feedwat er system that supplies heated water to the SGs. The main feedwater pumps are designed for maximum calculated load operating conditions (refer to Figures 10.1-5 and 10.1-1 for DCPP Units 1 and 2, respectively), and are capable of supplying the required main feedwater flow to the SGs under transient load reduction conditions.

The condensate pumps and condensate booster pumps provide adequate suction pressure to the main feedwater pumps under load transient conditions. During a main turbine control system load drop anticipate

transient or a loss of feedwater pump load reduction, the standby condensate pump /

condensate booster pump set will start, the stator coil and cooling water flow for valve

FCV-31 will open, and hotwell rejection valve LCV-12 will close to provide adequate suction to the feedwater pumps.

The pressure-retaining components, or comp artments of components, conform to the following codes as minimum design criteria:

(1) System pressure vessels and feedwater heaters - ASME Boiler and Pressure Vessel Code (BPVC),Section VIII (2) System valves, fittings, and piping - ANSI Code for Pressure Piping B31.1 and B31.7 where applicable. The main feedwater lines from the MFIVs to the SGs are covered by the ASME BPVC,Section I

The condensate and main feedwater systems are of the closed type, with deaeration accomplished in the main condenser. Condensate is pumped through the generator hydrogen coolers and stator coolers, the gland steam condenser, and the air ejector

condensers to the suction of the condensate booster pumps, which pump the

condensate though the condensate polishing system and five stages of low-pressure

feedwater heaters to the main feedwater pumps. The water discharged from the main feedwater pumps flows through the single stage of high-pressure feedwater heaters into the SGs. All feedwater heaters are horizontal, one-third-size units (three in parallel), except the No. 6 heater drain cooler, which is a single, full-size, straight-tubed heat exchanger.

Three nominal half-capacity, three-stage, ve rtical, can-type, centrifugal, motor-driven condensate pumps are provided with separate hotwell suction lines and a common

discharge manifold. Three condensate booster pumps are provided. These are

nominal half-capacity, horizontal, split-case, centrifugal, motor-driven pumps with common suction and discharge manifolds. Two nominal half-capacity, high-speed, turbine-driven main feedwater pumps are provided, with common suction and discharge manifolds. All pumps are equipped with minimum flow protective devices.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-26 Revision 23 December 2016 Main feedwater flows to the SGs through four lines penetrating the containment, one line for each SG. An MFRV with an MFRV bypass valve, a check valve, and an MFIV are installed in each line outside the containment.

Warmup lines are provided on the discharge of the feedwater pumps to circulate heated feedwater back through an idle feedwater pump to keep it warm and ready for service.

Drains from the No. 1 and No. 2 feedwater heaters flow to the No. 2 heater drain tank, with the flashed steam from the drain tank vented to the No. 2 heater. The No. 2 heater drain pump takes suction from the No. 2 heater drain tank and discharges to the main feedwater pump suction manifold. Drains from the four lower pressure feedwater heaters cascade to the No. 6 heater drain cooler and then to the main condenser.

The condensate and main feedwater systems do not have to operate to ensure safe shutdown of the NSSS. The AFW system, described in Section 6.5, provides adequate feedwater to the SGs from the condensate storage tank (CST) in the event of a loss of main feedwater. The reactor transient and radiological consequences of a main feedwater line break are discussed in Section 15.4.2.

In the event leakage develops from one of the feedwater heaters, that heater can be

isolated and repaired while the generating unit remains on line. Since the secondary

side is normally not radioactive, most leakage through valve seals will not present any

radiological problems. The consequences of having the secondary side of the plant

radioactive due to SG leakage are discussed in Chapters 11 and 15.

The active components in the main feedwater system required to operate in the event of a design basis accident are the check valves upstream of the AFW nozzles on the main feedwater lines, the MFIVs, the MFRVs, and the MFRV bypass valves.

The main feedwater control system consists of, in addition to the MFRVs, MFRV bypass valves, and the main feedwater pump turbine governor, individual manual controls for each MFRV and MFRV bypass valve, main feedwater pump turbine startup and speed governor controls, and the digital main feedwater control system (DFWCS). The DFWCS controls SG level using SG level, main feedwater flow, and SG density-compensated steam flow measurements. The main feedwater pump is controlled by the DFWCS using main feedwater header pressure and SG pressure. The DFWCS includes signal validation algorithms that will prevent an input channel failure from causing a control system transient requiring protective action. Refer to Sections 7.2.2.11.5 and 7.7.2.7.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-27 Revision 23 December 2016 10.4.7.3 Safety Evaluation 10.4.7.3.1 General Design Criterion 2, 1967 - Performance Standards The containment structure, pipeway structure, and auxiliary building, which contain the PG&E Design Class I portion of the main feedwater system, are PG&E Design Class I; refer to Section 3.8 and the DCPP Q-List (Reference 8 of Section 3.2). These structures or applicable portions thereof and exterior components are designed to withstand the effects of winds (refer to Sect ion 3.3.1), floods and tsunamis (refer to Section 3.4), and earthquakes (refer to Section 3.7), and to protect the PG&E Design Class I portion of the main feedwater syste m to ensure its safety functions are maintained. The tornado resistance capability for certain PG&E main feedwater system components supports plant safe shutdown as discussed in Section 3.3.2.

The PG&E Design Class I components and associated feedwater piping has been seismically qualified.

Portions of feedwater system are located outside are partially resistant to tornadoes, however, the capability of the system to support plant safe shutdown is maintained (refer to Section 3.3.2.3.2.7)

The main feedwater system components required to perform their PG&E Design Class 1 functions are located at higher elevations such that they are not affected by floods and tsunamis.

10.4.7.3.2 General Design Criterion 3, 1971 - Fire Protection The condensate and main feedwater systems are designed and located to minimize the probability and effect of fires and explosio ns per the fire protection guidelines of Appendix A of Branch Technical Position APCSB 9.5-1 (refer to Appendix 9.5B Table B-1). Appendix 9.5A provides the fire hazards analysis and is organized by fire zone.

10.4.7.3.3 General Design Criterion 11, 1967 - Control Room PG&E Design Class I controls and indications for the main feedwater system are provided in the control room such that the system may be operated to perform its design function. If access to the control room is lost, the MFIVs can be operated locally.

Indication of SG level and pressure are available in the control room and on the hot shutdown panel.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-28 Revision 23 December 2016 10.4.7.3.4 General Design Criterion 12, 1967 - Instrumentation and Control Systems Instrumentation and controls for the condensate and main feedwater systems, including the MFIVs, MFRVs, and MFRV bypass valves, along with SG level indication, are discussed in Sections 6.2.4, 7.3, 9.3.2.3, 10.4.7.3.10(3), and 10.4.7.5.

10.4.7.3.5 General Design Criterion 15, 1967 - Engineered Safety Features Protection Systems A main feedwater isolation signal is initiated when 2-out-of-3 SG channels in any loop read SG levels that are at the high-high actuation setpoint.

A low-low SG level signal is provided as input to the engineered safety features actuation system (ESFAS).

Any safety injection (SI) signal develops a feedwater isolation signal.

10.4.7.3.6 General Design Criterion 21, 1967 - Single Failure Definition The PG&E Design Class I portion of the main feedwater system is designed with a diverse Class 1E power supply for the MFIVs. Additionally the main feedwater system provides independent flow paths for AFW to the SGs.

Redundant main feedwater isolation is provided by the MFRVs with their respective MFRV bypass valves and the MFIVs, along with trip of the main feedwater pumps (refer to Sections 15.2.14 and 15.4.2).

The redundancy and single failure features of the SG level instrumentation are addressed in Section 7.3.3.

10.4.7.3.7 General Design Criterion 49, 1967 - Containment Design Basis The PG&E Design Class I portion of the main feedwater piping routed into containment and the associated containment penetrations are designed and analyzed to withstand the pressures and temperatures that could result from a LOCA without exceeding containment design leakage rates. Refer to Section 3.8.2.1.1.3 for additional details.

10.4.7.3.8 General Design Criterion 54, 1971 - Piping Systems Penetrating Containment Isolation valves that are required for containment closure are periodically tested for operability and are contained in the PG&E Design Class I portion of the main feedwater system. Refer to DCPP Technical Specifi cation Section 3.7.3. Testing of the components required for the containment isolation system (CIS) is discussed generally DCPP UNITS 1 &

2 FSAR UPDATE 10.4-29 Revision 23 December 2016 in Section 6.2.4. However, note that leak testing of the MFIVs is not required under Option B of 10 CFR Part 50, Appendix J, as noted in Table 6.2-39.

10.4.7.3.9 General Design Criterion 57, 1971 - Closed System Isolation Valves The containment penetrations for the main feedwater system are part of penetration Group C. A description of the isolation valves and piping configuration for each penetration is provided in Table 6.2-39. Group C piping conforms to the requirements of GDC 57, 1971.

10.4.7.3.10 Condensate and Feedwater Systems Safety Function Requirements (1) Protection from Missiles and Dynamic Effects Protection of the PG&E Design Class I portion of the main feedwater system from internal missiles and dynamic effects are discussed in Sections 3.5 and 3.6, respectively.

The rupture of a main feedwater line is one of the principal breaks considered in the analysis of dynamic effects of pipe breaks outside the containment. Additional barriers

and restraints have been added, as required, to protect PG&E Design Class I SSCs from a main feedwater line rupture, or pro tect the feedwater line from another line rupture.

The main feedwater pump turbines are located to minimize the likelihood of generation of missiles that could affect the safe shutdown of either unit. Refer to Section 3.5. (2) Internal Flooding Protection The PG&E Design Class I portion of the main feedwater system is physically located well above ground elevation and is not susceptible to failure by flooding from other

ruptured systems.

A postulated failure of the condensate or main feedwater PG&E Design Class II piping in the turbine building would result in approximately 19,800 cubic feet of the water being released to the turbine building floor, if the entire contents of the hotwell and heater drain tank were discharged. Maloperation of the condensate or main feedwater system due to a broken pipe would be detected by changes in plant variables, alarms, feedwater heater temperature transients, or pump t rips due to runout overcurrent. In addition, level switches, which alarm in the control room, are installed in the turbine building sump and in the condenser pit near the diesel generators of each unit to alert the operator to the flooding condition. Spillage from most broken pipes could be

detected and isolated before significant flooding occurred.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-30 Revision 23 December 2016 A rupture of a feedwater line within the turbine building will result in a temperature and humidity rise. Environmental effects due to high energy pipe ruptures outside the containment are more fully evaluated and discussed in Section 3.6.4.

In the event that the entire contents of the hotwell and heater drain tanks are discharged

to the turbine building, the operability of PG&E Design Class I equipment (diesel generators and component cooling water heat exchangers) in the building is not endangered. The volume of water that would be discharged is within the capacity of the

turbine building drain system. This system inclu des one 18-inch drain line from the turbine building sump of each unit to the circulating water system discharge canal (refer to Figure 3.2-27). If this drain were clogged, the water flow would begin to fill the turbine building sumps and equipment pits below 85 feet (refer to Figures 1.2-16 and 1.2-20). The entire quantity of discharge water can be accommodated in the sumps.

Water would not endanger the operability of the diesel generators since a fire door is installed at the entrance to the corridor to the emergency diesel generator rooms for purposes of protection from circulating water system ruptures in the turbine building (refer to Section 10.4.5.3.1). The door is locked closed and monitored through the security system. Because of their elevation above the turbine building floor, the component cooling water heat exchangers are not susceptible to flooding damage.

These provisions also protect PG&E Design Class I equipment from flooding damage caused by the failure of other PG&E Design Class II piping or components located in the turbine building.

The PG&E Design Class I equipment in the auxiliary building is not endangered by turbine building flooding. The area of the au xiliary building housing PG&E Design Class I equipment is separated from the turbine building by 70 feet of doors and

passageways. If water does enter the auxiliar y building, it will drain to the building pipe tunnel, which has a capacity of approximately 345,000 gallons. The auxiliary building drain system is completely separate from the turbine building system so back flow

through the drain system is not possible.

(3) Main Feedwater Isolation SG high-high level signal (P-14 interlock) or an SI signal closes the MFRVs, MFRV bypass valves, and MFIVs, and trips both main feedwater pumps to prevent SG overfill and excessive overcooling.

A low T avg signal coincident with a reactor trip (P-4 interlock) initiates main feedwater isolation by closing the MFRVs and MFRV bypass valves in order to protect the reactor from excessive cooldown.

Main feedwater isolation minimizes the mass and energy release into containment following a main steam line break event by isolating feedwater within 9 seconds (refer to Section 6.2D.4.1.3).

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-31 Revision 23 December 2016 10.4.7.3.11 10 CFR 50.49 - Environmental Qualification of Electric Equipment Important to Safety for Nuclear Power Plants Main feedwater system SSCs required to function in harsh environments under accident conditions are qualified to the applicable environmental conditions to ensure that they will continue to perform their safety functions. Section 3.11 describes the DCPP EQ Program and the requirements for the environmental design of electrical and related mechanical equipment. The affected equip ment includes valves and switches and is listed on the EQ Master List.

10.4.7.3.12 10 CFR 50.55a(f) - Inservice Testing Requirements The IST requirements for the PG&E Design Class I components of the main feedwater system are contained in the IST Program Plan and comply with the ASME BPVC.

10.4.7.3.13 10 CFR 50.55a(g) - Inservice Inspection Requirements The PG&E Design Class I portion of the main feedwater system piping has a periodic ISI program in accordance with ASME BPVC Section XI.

10.4.7.3.14 10 CFR 50.62 - Requirements for Reduction of Risk from Anticipated Transients Without Scram (ATWS) Events for Light-Water-Cooled Nuclear Power Plants The AMSAC is initiated by an AMSAC low SG water level signal, which is derived separately from the low-low SG water level signal (refer to Sections 7.6.2.3 and 7.6.3.5).

10.4.7.3.15 10 CFR Part 50 Appendix R (Section I II.G, J, and L) - Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979 10 CFR Part 50 Appendix R requires the evaluation of the safe shutdown capability for DCPP in the event of a fire and the loss of offsite power. The PG&E Design Class I portion of the main feedwater system satisfies the applicable requirements of 10 CFR Part 50 Appendix R, Sections III.G, J, and L, as follows:

Section III.G - Fire Protection of Safe Shutdown Capability: As discussed in Appendix 9.5A, the MFRVs and MFRV bypass valves are considered as safe shutdown equipment that may be affected by a fire.

The same is true for the level transmitters that provide SG level indication at the dedicated shutdown panel.

Section III.J - Emergency Lighting: Appendix 9.5D contains a description and evaluation of the DCPP Unit 1 and Unit 2 emergency lighting system in accordance with 10 CFR Part 50 Appendi x R,Section III.J.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-32 Revision 23 December 2016 Section III.L - Alternative and Dedicated Shutdown Capability: Safe shutdown capabilities are provided in the control room and at alternate locations via the hot shutdown panel, dedicated shutdown panel, and/or local operation of valves in accordance with 10 CFR Part 50 Appendix R, Section III.L (refer to Section 7.4). The ability to safely shut down the plant following a fire in any fire area is summarized in Section 5.0 ("Conclusion") of the fire hazard analysis for that area contained in Appendix 9.5A.

10.4.7.3.16 Generic Letter 89-10, June 1989 - Safety-Related Motor-Operated Valve Testing and Surveillance The PG&E Design Class I main feedwater system MOVs are included in the DCPP MOV Program, which was developed to meet the requirements of Generic Letter 89-10, June 1989, and associated Generic Letter 96-05, September 1996.

10.4.7.3.17 Generic Letter 89-08, May 1989 - Erosion/Corrosion-Induced Pipe Wall Thinning DCPP procedures implement the DCPP flow-accelerated corrosion (FAC) monitoring program requirements. Portions of the condensate and main feedwater systems are considered in the program for erosion/corrosion monitoring.

10.4.7.3.18 Regulatory Guide 1.97, Revision 3, May 1983 - Instrumentation for Light-Water-Cooled Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident Table 7.5-6 summarizes DCPP's compliance with Regulatory Guide 1.97, Revision 3. Main feedwater flow is a Type D variable, and SG level is both a Type A and a Type D variable. Additionally, position indication for the MFIVs is designated as a Type B variable, but is not credited for compliance with Regulatory Guide 1.97, Revision 3, Category 1 criteria.

10.4.7.3.19 Branch Technical Position ASB 10-2, March 1978 - Design Guidelines for Water Hammers in Steam Generators with Top Feedring Designs The SGs include top-discharge spray nozzles that reduce the possibility of steam pockets being trapped in the feedwater ring (refer to Section 5.5.2).

The main feedwater system has been designed to minimize the length of horizontal feedwater piping that could be emptied when the SG water level drops below the level of the feedwater ring. This piping has been modified as shown in Figures 10.4-2 and 10.4-3 to minimize the possibility of a damaging water hammer.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-33 Revision 23 December 2016 Testing was performed to verify that feedwater hammer will not occur using the plant operating procedures for normal and emergency restoration of SG water level following a loss of normal feedwater and possible draining of the feedring.

10.4.7.4 Tests and Inspections Tests and inspections of the condensate and main feedwater systems are done in accordance with plant procedures.

10.4.7.5 Instrumentation Applications

A main feedwater pump control system controls the speed of the turbine-driven main feedwater pumps to achieve a programmed pressure differential between the main feedwater header leaving the No. 1 feedwater heaters and the main steam common header. The programmed pressure differential varies as a function of unit load. Main feedwater header-steam-header differential pressure indication is also provided in the control room.

SG level and feedwater flow indi cation is also provided.

Each MFRV and MFRV bypass valve is positioned by its own digital control system (refer to Section 7.7.2.7).

10.4.8 STEAM GENERATOR BLOWDOWN SYSTEM The steam generator blowdown system is used in conjunction with the condensate and

feedwater chemical injection system and the condensate polishing system to maintain steam generator water chemistry within the plant-specific limits.

The steam generator blowdown system functions are primarily PG&E Design Class II.

The only PG&E Design Class I function performed by the system is containment

isolation. The portions of the system from the steam generator nozzles to the isolation valves outside containment that perform this function are PG&E Design Class I.

10.4.8.1 Design Bases 10.4.8.1.1 General Design Criterion 2, 1967 - Performance Standards The PG&E Design Class I portion of the steam generator blowdown system is designed to withstand the effects of, or is protected against, natural phenomena such as earthquakes, floods, tornadoes, winds, and other local site effects.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-34 Revision 23 December 2016 10.4.8.1.2 General Design Criterion 3, 1971 - Fire Protection The PG&E Design Class I portion of the steam generator blowdown system is designed and located to minimize, consistent with other safety requirements, the probability and effect of fires and explosions.

10.4.8.1.3 General Design Criterion 9, 1967 - Reactor Coolant Pressure Boundary The materials of construction of the pressure-retaining bounda ry of the steam generator tubes are protected by control of secondary chemistry from corrosion that might otherwise reduce the system structural in tegrity during its service l ifetime. The steam generator blowdown system functions to contribute to the sec ondary chemistry control.

10.4.8.1.4 General Design Criterion 11, 1967 - Control Room

The PG&E Design Class I portion of the steam generator blowdown system is designed to support actions to maintain the safe operational status of the plant from the control room or from an alternate location if control room access is lost due to fire or other

causes. 10.4.8.1.5 General Design Criterion 12, 1967 - Instrumentation and Control

Instrumentation and controls are provided as required to monitor and maintain the PG&E Design Class I portion of the steam generator blowdown system variables within

prescribed operating ranges.

10.4.8.1.6 General Design Criterion 16, 1967 - Monitoring Reactor Coolant Pressure Boundary The steam generator blowdown system provides means for monitoring the reactor

coolant pressure boundary to detect leakage.

10.4.8.1.7 General Design Criterion 17, 1967 - Monitoring Radioactivity Releases Means are provided for monitoring the facility effluent discharge path for radioactivity

that could be released from the steam generator blowdown system.

10.4.8.1.8 General Design Criterion 21, 1967 - Single Failure Definition

The PG&E Design Class I portion of the steam generator blowdown system is designed to tolerate a single failure during the period of recovery following an accident without loss of its protective function, including multiple failures resulting from a single event, which is treated as a single failure.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-35 Revision 23 December 2016 10.4.8.1.9 General Design Criterion 54, 1971 - Piping Systems Penetrating Containment The steam generator blowdown system is pr ovided with leakage detection, isolation, and containment capabilities having redun dancy, reliability, and performance capabilities which reflect the importance to safety of isolating this system. The steam

generator blowdown system is provided with a capability to test periodically the operability of the isolation valves and associated apparatus and to determine if valve

leakage is within acceptable limits.

10.4.8.1.10 General Design Criterion 57, 1971 - Closed System Isolation Valves

The steam generator blowdown system contains piping connected to containment penetrations that are neither part of the reactor coolant pressure boundary nor

connected directly to the containment atmosphere. These penetrations are provided

with one local or remote-manual valve outside the containment.

10.4.8.1.11 Steam Generator Blowdown System Safety Function Requirements

(1) Protection from Missiles and Dynamic Effects The PG&E Design Class I portion of the steam generator blowdown system is designed to be protected against the effects of missiles and dynamic effects, which may result

from equipment failures.

(2) Decay Heat Removal

The steam generator blowdown system is designed to facilitate the removal of decay

heat from the reactor coolant system.

10.4.8.1.12 10 CFR 50.49 - Environmental Qualification

Steam generator blowdown system components that require environmental qualification (EQ) are qualified to the requirements of 10 CFR 50.49.

10.4.8.1.13 10 CFR 50.55a(f) - Inservice Testing Requirements Steam generator blowdown system ASME Code components are tested to the requirements of 10 CFR 50.55a(f)(4) and a(f)(5) to the extent practical.

10.4.8.1.14 10 CFR 50.55a(g) - Inservice Inspection Requirements Steam generator blowdown system ASME Code components are inspected to the requirements of 10 CFR 50.55a(g)(4) and a(g)(5) to the extent practical.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-36 Revision 23 December 2016 10.4.8.1.15 10 CFR 50.62 - Anticipated Transient Without Scram The PG&E Design Class I portion of the steam generator blowdown system is isolated upon receipt of a signal from the Anticipated Transient Without Scram (ATWS)

Mitigation System Actuation Circuitry (AMSAC).

10.4.8.1.16 10 CFR Part 50 Appendix R (Section I II.G, J, and L) - Fire Protection Program for Nuclear Power Facilit ies Operating Prior to January 1, 1979 The PG&E Design Class I portion of the steam generator blowdown system is designed to isolate to maintain steam generator inventory to facilitate decay heat removal to achieve and maintain a safe shutdown condition for fire events.

Section III.G - Fire Protection of Safe Shutd own Capability: Fire protection of the steam generator blowdown system is provided by a combination of physical separation, fire-

rated barriers, and/or automatic suppression and detection.

Section III.J - Emergency Lighting: Emergency lighting or battery operated lights (BOL)

are provided in areas where operation of the steam generator blowdown system may be

required to safely shutdown the Unit following a fire.

Section III.L - Alternative and Dedicated Shutdown Capa bility: Safe shutdown capabilities are provided in the control room and locally at the steam generator blowdown system containment isolation valves for the safe shutdown of the plant

following a fire event.

10.4.8.1.17 Regulatory Guide 1.97, Revision 3, May 1983 - Instrumentation for Light-Water-Cooled Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident

The steam generator blowdown system containment isolation valve position status is

required for post-accident instrumentation.

10.4.8.1.18 Generic Letter 89-08, May 1989 - Erosion/Corrosion-Induced Pipe Wall Thinning DCPP has implemented formalized procedures and administrative controls to assure

long-term implementation of its erosion/corrosion monitoring program for the steam

generator blowdown system.

10.4.8.2 System Description A piping and instrumentation schematic for the steam generator blowdown system is

shown in Figure 3.2-4.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-37 Revision 23 December 2016 The steam generator blowdown system for each unit is composed of two processing paths. One path discharges blowdown flow via the steam generator blowdown tank to

the circulating water discharge tunnel. The other path recycles blowdown flow to the

main condenser via the blowdown treatment system and/or the blowdown treatment

bypass line. The recycle path can discharge a portion of blowdown flow to the

discharge tunnel. Blowdown flow for each unit can be directed to either blowdown path

alone, or to both paths simultaneously. The blow down piping is also used as the interface between the steam generators and the Rapid Fill and Drain System that was

added to facilitate operation of the steam generators during Unit outages.

Blowdown flow in the discharge path is processed via the steam generator blowdown tank; approximately 35 percent of the blowdown flow flashes to steam inside the tank

and is vented to the atmosphere. The remaining liquid, approximately 65 percent of the

blowdown flow, is discharged by gravity to the condenser circulating water discharge.

Blowdown flow in the recycle path may be processed by the blowdown treatment system or the blowdown treatment bypass line. This treatment system reduces the temperature and pressure of the water. The treatment system may also demineralize and recycle the blowdown water to the condensate system. In the treatment system, blowdown enters a flash tank where it is reduced in pressure. Flashed water vapor is

vented from the tank through a pressure control valve to either a feedwater heater to

improve cycle thermal efficiency or to the main condenser. The blowdown liquid then

passes through a heat exchanger where the temperature is further reduced to approximately 110

°F. The liquid may then enter a prefilter and demineralizer before being recycled to the main condenser. If required, a portion of the flash tank liquid flowing out of the heat exchangers can be routed to the plant outfall via the blowdown overboard drain line to improve the secondary water chemistry.

Blowdown water first passes through a prefilter and is then directed through one of two

60 cubic foot mixed bed demineralizers. The demineralizer removes both radioactive

and nonradioactive ionic impurities. The liquid is then recycled to the main condenser.

The blowdown treatment bypass line routes the depressurized, undemineralized

blowdown directly to the condenser.

The blowdown tank process path and the blowdown treatment portion of the recycle

process path are designed to accommodate 150 gpm of blowdown water total from four

steam generators on a continuous basis. The blow down tank process path also allows a total flow of 320 gpm temporarily during certain plant conditions.

The blowdown treatment bypass portion of the recycle path, including the flash tank, is

designed for 1 percent of the main steaming rate at 100 percent plant load from four

steam generators on a continuous basis (approximately 400 gpm total).

The steam generator blowdown system is classified as PG&E Design Class I from the

steam generator nozzles up to and including the isolation valves outside of the

containment and PG&E Design Class II downstream of the containment isolation DCPP UNITS 1 &

2 FSAR UPDATE 10.4-38 Revision 23 December 2016 valves. The classification and applica ble codes for the steam generator blowdown system are identified in the DCPP Q-List (re fer to Reference 8 of Section 3.2).

The blowdown system's effect on plant safety is minimal, since neither the blowdown

function nor the treatment function is required continuously. Either function may be

interrupted temporarily to replace failed components. Neither function is required to

operate following a LOCA.

Ruptured components or failed-open valves could caus e unplanned blowdown of secondary steam. Since blowdown piping in this system is 6 inches or smaller, such

pipe break accidents fall within the category of minor secondary system pipe breaks.

Consequences of this type of accident are detailed in Sections 15.2.14 and 15.3.2. The

probability of radiation leakage is small since the system is normally nonradioactive. If, however, a failure of a blowdown pipe occurs while steam generator leakage is also taking place, the consequences are within the limits described in Section 15.3.2 for

minor secondary system pipe breaks.

All filter and demineralizer components are located in the auxiliary building, from which

leakage is processed through the liquid radwaste system. An automatically controlled isolation valve provides shutoff of the blowdown discharge path to the plant outfall if

significant activity is detected. In any case, the results of failure are bounded by those

of the pipe break referred to above (refer to Section 10.4.8.3.7).

The evaluation of radiological and environmental effects is treated in Section 11.2.

10.4.8.3 Safety Evaluation 10.4.8.3.1 General Design Criterion 2, 1967 - Performance Standards The containment structure and auxiliary building, which contain the steam generator blowdown systems PG&E Design Class I components, are PG&E Design Class I (refer to Section 3.8). These buildings or applicable portions thereof are designed to

withstand the effects of winds and tornadoes (refe r to Section 3.3), floods and tsunamis (refer to Section 3.4), external missiles (refer to Section 3.5), earthquakes (refer to

Section 3.7), and other natural phenomena (refer to Sections 3.8.2.1.3 and 3.8.2.3.3 for the containment and auxiliary buildings, respectively), and to protect the system SSCs

to ensure their safety functions and designs are maintained.

The PG&E Design Class I portions of the steam generator blowdown system are designed to perform their safety functions under the effects of earthquakes.

10.4.8.3.2 General Design Criterion 3, 1971 - Fire Protection The steam generator blowdown system is designed to the fire protection guidelines of BTP APCSB 9.5-1 (refer to Appendix 9.5B, Table B-1).

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-39 Revision 23 December 2016 10.4.8.3.3 General Design Criterion 9, 1967 - Reactor Coolant Pressure Boundary Suspended and dissolved solids that are brought in by the feedwater concentrate in the steam generator shell-side water during plant operation. Water must be blown down

using the steam generator blowdown system to maintain water chemistry as specified in

plant procedures. Sampling and monitoring of nonradioactive solids is accomplished by

continuous conductivity measurements and grab sample analysis.

The steam generator blowdown system protects the steam generator tubes, which are a

part of the reactor coolant pressure boundary, from degradation during their lifetime.

This is in compliance with the steam generator tube integrity requirements of Generic

Letter 85-02.

10.4.8.3.4 General Design Criterion 11, 1967 - Control Room Controls, and position indication, for the steam generator blowdown system containment isolation valves are provided in the control room such that the system may be manually operated to perform its safety function.

The system isolation valves can be operated manually from the main control room.

These valves can also be closed by local ly venting air from the valve operator solenoids if access to the control room is lost.

10.4.8.3.5 General Design Criterion 12, 1967 - Instrumentation and Control

The outboard containment isolation valves close on the containment isolation signal, Phase A. The inboard containment isolation valves close on the steam line isolation

signal. Refer to Table 6.2-39.

The outboard containment isolation valves also close automatically on an AFW pump

start (refer to Section 6.5.2.1.2), AMSAC ac tuation (refer to Section 7.6.2.3), and high radioactivity in the blowdown system (refer to Sections 10.4.8.3.7 and 11.4.2.1.2.2).

10.4.8.3.6 General Design Criterion 16, 1967 - Monitoring Reactor Coolant Pressure Boundary

Steam generator blowdown radiation detectors are available to detect steam generator

tube leakage as described in Section 5.2.3.

23 and Table 5.2-16. The radiation monitoring system is described in Section 11.4.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-40 Revision 23 December 2016 10.4.8.3.7 General Design Criterion 17, 1967 - Monitoring Radioactivity Releases

The steam generator blowdown system is continuously monitored for radioactivity. The sampling system parallels the blowdown flow from each steam generator. Continuous sampling and monitoring for radioactivity is accomplished with a single composite

sample taken from the four steam generator sample lines and passed through a

radiation monitor.

The criterion used for isolation of the blowdown system is based on the concentration of

activity in the blowdown. When the samplin g system radiation monitor detects a preset activity level, the steam generator blowdown isolation valves and the blowdown tank

effluent valve close. The isolation system has been designed so that the blowdown

tank effluent valve closes before any significant radioactive liquid reaches the effluent

isolation valve. Upon detection of activity, plant personnel may process the blowdown

via the blowdown treatment system as directed by Chemistry.

The radiation monitoring system is described in Section 11.4.

10.4.8.3.8 General Design Criterion 21, 1967 - Single Failure Definition

The instrumentation and control circuits for the steam generator blowdown system containment isolation function are redundant in the sense that a single failure cannot prevent containment isolation (refer to Section 6.2.4.4.5). The valve control circuits are supplied with separate Class 1E 125-Vdc power. The isolation valves will fail closed on

a loss of air or power.

10.4.8.3.9 General Design Criterion 54, 1971 - Piping Systems Penetrating Containment The steam generator blowdown system isolation valves required for containment

closure are periodically tested for operability.

Testing of the components required for the containment isolation system (CIS) is discussed in Section 6.2.4.

10.4.8.3.10 General Design Criterion 57, 1971 - Closed System Isolation Valves

The steam generator blowdown system containment penetrations comply with the requirements of GDC 57, 1971, as described in Section 6.2.4 and Table 6.2-39.

10.4.8.3.11 Steam Generator Blowdown System Safety Function Requirements

(1) Protection from Missiles and Dynamic Effects The PG&E Design Class I portion of the steam generator blowdown system is protected

from the effects of missiles and dynamic effects as described in Sections 3.5.1 and

3.6.2.1.1, respectively.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-41 Revision 23 December 2016 (2) Decay Heat Removal The steam generator blowdown system facilitates the removal of decay heat from the

reactor coolant system by isolating on an AFW pump start or an AMSAC actuation (refer to Sections 6.5 and 7.6.2.3, respectively) and maintaining steam generator

inventory.

10.4.8.3.12 10 CFR 50.49 - Environmental Qualification

The steam generator blowdown system containment isolation valves are required to function in harsh environments under accident conditions and are qualified to the

applicable environmental conditions to ensure that they will continue to perform their safety functions. Section 3.11 describes the DCPP EQ Program and the requirements

for the environmental design of electrical and related mechanical equipment. The

valves are listed on the EQ Master List.

10.4.8.3.13 10 CFR 50.55a(f) - Inservice Testing Requirements Steam generator blowdown system components that are within the IST program are the

four inboard containment blowdown isolation valves, the four outboard containment

blowdown isolation valves, and the four outb oard containment sample isolation valves.

The inservice testing (IST) requirements for these components are contained in the IST

Program Plan and comply with the ASME code for Operation and Maintenance of

Nuclear Power Plants.

10.4.8.3.14 10 CFR 50.55a(g) - Inservice Inspection Requirements The steam generator blowdown system piping has a periodic inservice inspection (ISI) program in accordance with the ASME B&PV Code,Section XI.

10.4.8.3.15 10 CFR 50.62 - Anticipated Transient Without Scram The blowdown flow from the steam generators is automatically isolated as a result of an AMSAC actuation (refer to Section 7.6.2.3).

10.4.8.3.16 10 CFR Part 50 Appendix R (Section I II.G, J, and L) - Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979 10 CFR Part 50 Appendix R requires the evaluation of the safe shutdown capability for DCPP in the event of a fire and the loss of offsite power. The steam generator blowdown system satisfies the applicable req uirements of 10 CFR Part 50 Appendix R, Sections III.G, J, and L.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-42 Revision 23 December 2016 Section III.G - Fire Protection of Safe Shutd own Capability: The inboard blowdown isolation valves and the outboard isolation valves (if the inboard valves fail to close) are the minimum required equipment to bring the plant to a cold shutdown condition. These components are provided with fire protection features appropriate to the requirements of

Section III.G.

Section III.J - Emergency Lighting: Emergency lighting or battery operated lights (BOL)

are provided in areas where operation of the steam generator blowdown system

containment isolation valves may be required for safe shutdown following a fire as

defined by 10 CFR Part 50, Appendix R, Section IIIJ (refer to Appendix 9.5D).

Section III.L - Alternative and Dedicated Shutdown Capa bility: Safe shutdown capabilities are provided in the control room and at alternate locations in accordance with 10 CFR Part 50 Appendix R, Section III.L (refer to Section 7.4 and Appendix 9.5E).

The ability to safely shut down the plant following a fire in any fire area is summarized in

Section 4.0 of Appendix 9.5A.

10.4.8.3.17 Regulatory Guide 1.97, Revision 3, May 1983 - Instrumentation for Light-Water-Cooled Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident

The steam generator blowdown system's outboard cont ainment isolation valves indications are credite d for compliance with Regulatory Guide 1.97, Revision 3. The steam generator blowdown tank vent does not require monitoring.

Refer to Table 7.5-6, Notes 56 and 59.

10.4.8.3.18 Generic Letter 89-08, May 1989 - Erosion/Corrosion-Induced Pipe Wall Thinning

DCPP procedures identify the interdepartmental responsibilities and interfaces for the

Flow-Accelerated Corrosion (FAC) Monitoring Program for the steam generator blowdown system.

10.4.8.4 Tests and Inspections The steam generator blowdown system is op erated continuously during plant operation, thereby demonstrating system operability without the special inspections or testing

required for standby systems. Equipment evaluations and inspections are performed

periodically on the blowdown systems.

10.4.8.5 Instrumentation Applications Instrumentation for the steam generator blowdown system is discussed in Sections 10.4.8.3.4 and 10.4.8.3.5.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-43 Revision 23 December 2016 10.4.9 CONDENSATE AND FEEDWAT ER CHEMICAL INJECTION SYSTEM Chemical feed equipment is provided for chemical additions to the discharge of the condensate polishing system, to the main feedwater pumps suction header, and to the discharge of the auxiliary feedwater pumps (refer to Figure 3.2-3 for the location of the

injection points). The chemicals are injected into the condensate and feedwater system

to prevent corrosion in the feedwater system and the steam generators. The

condensate and feedwater chemical injection system has no safety function and is

classified as PG&E Design Class II.

10.4.9.1 Design Bases 10.4.9.1.1 General Design Criterion 3, 1971 - Fire Protection The condensate and feedwater chemical injection system is designed and located to minimize, consistent with other safety requirements, the probability and effect of fires and explosions.

10.4.9.1.2 General Design Criterion 9, 1967 - Reactor Coolant Pressure Boundary

The materials of construction of the pressure-retaining boundary of the steam generator tubes are protected by control of secondary chemistry from corrosion that might

otherwise reduce the system structural integrity during its service lifetime. The

condensate and feedwater chemical injection system functions to contribute to the

secondary chemistry control.

10.4.9.1.3 Condensate and Feedwater Chemical Injection System Safety Function Requirement (1) Internal Flooding The condensate and feedwater chemical injection system is designed to be protected against the effects of internal flooding which may result from equipment failures.

10.4.9.1.4 Regulatory Guide 1.78, June 1974, Assumptions for Evaluating the Habitability of a Nuclear Power Plant Control Room During a Postulated Hazardous Chemical Release The DCPP control room is appropriately protected from hazardous chemicals that may be discharged as a result of equipment failures, operator errors, or events and

conditions outside the control of the plant.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-44 Revision 23 December 2016 10.4.9.2 System Description The steam generator blowdown system protects the steam generator tubes, which are a part of the reactor coolant pressure boundary, from degradation during their lifetime.

This is in compliance with the steam generator tube integrity requirements of Generic

Letter 85-02.

Three sets of chemical feed pumps are available in each unit for the main feedwater

system. The first set consists of 3 chemical feed pumps used to inject chemicals.

Individual pumps are dedicated to ethanolamine and hydrazine/carbohydrazine

injection, with the third pump on standby for either service. The pumps are not used

under normal operating conditions.

During normal operation, a second chemical injection feed system in each unit is used

to inject concentrated ethanolamine and hydrazine solutions.

The condensate hydrazine and ethanolamine feed system for each unit consists of a

250-gallon stainless steel hydrazine day tank with two chemical feed pumps, one in

operation and one standby, and a 250-gallon stainless steel ethanolamine day tank with

two chemical feed pumps, one in operation and one standby. Bulk 35 percent (by

weight) hydrazine is stored in liquibins and is pumped by a transfer pump to the

hydrazine day tank. A 6,000 gallon closed vertical pressure vessel, with a fume

scrubber and two transfer pumps, stores and supplies the ethanolamine hydroxide

chemical (85 percent aqueous solution of ethanolamine) for both units. The

concentrated solution is pumped as needed to the ethanolamine day tank. The four

chemical feed pumps output is manually controlled. The desired ethanolamine and hydrazine concentration in the condensate can be controlled manually. The water is monitored for conductivity and dissolved oxygen at the condensate pump discharge.

Conductivity and dissolved oxygen, plus pH and hydrazine concentration, are also monitored at the final feedwater header before branching to the four steam generators.

A third chemical feed system is available, but not normally used. It is similar to the 2nd

chemical system described above, except the hydrazine day tank is 200 gallons, the

ethanolamine day tank is 300 gallons, and has 4 chemical feed pumps. Condensate

from the condensate pump discharge header can be used to dilute the hydrazine and

ethanolamine in the respective chemical day tank.

The auxiliary feedwater pump chemical feed system for each unit consists of a 500 gallon stainless steel tank, a 300 gallon stainless steel tank, and five chemical feed

pumps that are piped so that the fifth pump is used as a shared spare. The chemical

feed rate will be manually controlled. The chemical feed pumps pump into the

discharge side of the auxiliary feedwater pumps. An injection line runs to the discharge

of each of the three auxiliary feedwater pumps.

The secondary boric acid system consists of two boric acid mix/feed tanks (each tank

having a capacity of 1325 gallons), three 50 percent feed pumps (each pump having a DCPP UNITS 1 &

2 FSAR UPDATE 10.4-45 Revision 23 December 2016 capacity of 60 gallons per hour), and a screw feeder for loading the boric acid to the mix/feed tanks. Also provided are two tank mixers (mechanical agitators) for ensuring a complete and thorough mixing of the boric acid solution in the tanks. The pumping

injection flow rate will be manually controlled , primarily based on the boric acid concentration in the steam generator blowdown.

10.4.9.3 Safety Evaluation 10.4.9.3.1 General Design Criterion 3, 1971 - Fire Protection The chemicals of the condensate and feedwater chemical injection system (Hydrazine/Carbohydrazine, Ethanolamine and Boric Acid) are stored in accordance with the requirements of Branch Technical Position 9.5-1 (refer to Appendix 9.5B, Table

B-1). 10.4.9.3.2 General Design Criterion 9, 1967 - Reactor Coolant Pressure Boundary

The condensate and feedwater chemical injection system is designed to provide the following chemical additions to the condens ate and feedwater systems to reduce steam generator tube corrosion:

(1) Ethanolamine to the discharge line of each demineralizer in the condensate polishing system or to the condensate pumps' discharge

header when the condensate polisher system is out of service, as

required, to control the pH of the f eedwater and steam generator water.

(2) Hydrazine, or a mixture of hydrazine and carbohydrazide, to the main feedwater pump suction piping to scavenge oxygen from the feedwater to

a level within procedural guid elines with a residual of hydrazine at the inlet to the steam generators. Because of the similarity with hydrazine and

carbohydrazide being bounded, from a safety and environmental

perspective, by hydrazine, the mixture will be handled as if it were

hydrazine.

(3) Ethanolamine and hydrazine, or other chemicals as specified by chemistry procedures, to the auxiliary feedwater pumps discharge to control the

chemistry in the steam generators when the auxiliary feedwater pumps

are used to supply water to steam generators.

(4) Boric acid solution to the main feedwater pump suction piping to reduce denting of tubes in the steam generator.

(5) Other chemicals as specified by chemistry procedures.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-46 Revision 23 December 2016 The system provides the capability to condition the water in the steam generator during wet lay-up, hydrotesting, and other times when the main feedwater system is not in

operation.

The condensate and feedwater chemical injection systems are designed to provide

adequate amounts of conditioning chemical s to the secondary system, as required, for the prevention of corrosion in the condensate and feedwater systems and the steam

generator tubes.

The condensate and feedwater chemical injection system protects the steam generator

tubes, which are a part of the reactor coolant pressure boundary, from degradation

during their lifetime. This is in compliance with the steam generator tube integrity

requirements of Generic Letter 85-02.

10.4.9.3.3 Condensate and Feedwater Chemical Injection System Safety Function Requirement (1) Internal Flooding

The ethanolamine/hydrazine injection pumps and supply tanks for the condensate system are located in the turbine building west butt ress and the turbine building. The concentrations in the ethanolamine and hydrazine supply tanks can be up to 85 percent

and 35 percent, respectively. The tanks are vented to the outside of the building. There

are no engineered safety features in the vicinity that would be damaged or rendered

inaccessible by a ruptured supply tank.

The bulk ethanolamine storage tank, its fume scrubber, and its two transfer pumps are located in the turbine building west buttress, which houses the condensate polishers.

Toppling of this vertical tank is not expected to damage the nearby PG&E Design Class

I diesel fuel oil lines which are ins ide an adequately covered recessed pipe trench. Any accidental chemical spill, which is harmless to the steel pipes, would be confined within the trench and be prevented from reaching the diesel generator room by firestops.

The auxiliary feedwater pump chemical injection system supply tanks are located in the

auxiliary building over a ventilatio n opening at the 115 foot elevation floor. The auxiliary feedwater pumps served are located below on the 100-foot elevation floor. A ruptured

supply tank could cause 300 or 500 gallons of solution to fall partially on motor-driven

auxiliary feedwater pump 1-3 or 2-3.

The motor has a drip-proof enclosure and the

centerline of the pump motor unit is 2 feet-6 inches above the 100-foot floor elevation.

The area is drained by two 4 inch floor drains. The floor area in the vicinity of the

auxiliary feedwater pumps is in excess of 10 00 square feet so that 500 gallons would cause less than 1 inch of depth on the floor.

Motor-driven auxiliary feedwater pump 1-3 or 2-3 could be impacted, due to water in the motor, by this accident; however, the

second motor-driven pump and the turbine-driven pump would still be available.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-47 Revision 23 December 2016 The boric acid mix/feed tanks are located in the turbine building at the 85-foot elevation (ground level). The boric acid feed pumps are also located at this elevation. The floor

area at this elevation (ground level) is large enough so that a ruptured feed tank would

cause only a negligible depth of water on the floor, even though up to 1100 gallons of solution could be released. The only PG&E Design Class I component that could be affected by water is the diesel generator fire protection controls for Unit 1 only. These

controls are wall mounted in a splash-proof box. In addition, the feed tanks are

constrained to prevent any lateral movement or overturning and resist a seismic event.

There are no other engineered safety features in the vicinity that would be damaged or

rendered inaccessible by a ruptured feed tank. The feed tanks are purged with nitrogen

and vented to the building.

10.4.9.3.4 Regulatory Guide 1.78, June 1974, Assumptions for Evaluating the Habitability of a Nuclear Power Plant Control Room During a Postulated Hazardous Chemical Release

The DCPP control room is adequately protected from hazardous chemicals that may be

discharged from the condensate and feedwater chemical injection system. These chemicals have been analyzed to show that they do not adversely impact the control

room.

Details of the control room habitability evaluations are discussed in Sections 6.4.1 and

9.4.1.

The condensate hydrazine and ethanolamine feed system for each unit consists of a

250-gallon stainless steel hydrazine day tank with two chemical feed pumps, one in operation and one standby, and a 250-gallon stainless steel ethanolamine day tank with two chemical feed pumps, one in operation and one standby. Bulk 35 percent (by

weight) hydrazine is stored in liquibins provided by the chemical supplier. A 6,000 gallon closed vertical pressure vessel stores and supplies the ethanolamine hydroxide chemical (85 percent aqueous solution of ethanolamine) for both units.

A third chemical feed system is available, but not normally used. It is similar to the 2nd

chemical system described above, except the hydrazine day tank is 200 gallons, the

ethanolamine day tank is 300 gallons.

The auxiliary feedwater pump chemical feed system for each unit consists of a 500 gallon stainless steel tank and a 300 gallon stainless steel tank.

The secondary boric acid system consists of two boric acid mix/feed tanks each tank

having a capacity of 1325 gallons.

10.4.9.4 Tests and Inspections Tests and inspections of the condensate and feedwater chemical injection system are

done in accordance with plant procedures.

DCPP UNITS 1 &

2 FSAR UPDATE 10.4-48 Revision 23 December 2016 10.4.9.5 Instrumentation Applications The rate of feed of the chemical injection pumps into the main condensate and feedwater systems is proportioned to feedwater flow with manual adjustment of rate of

chemical injection to rate of feedwater flow. The main condensate and feedwater

supply tanks are equipped with level gauge glasses. The auxiliary feedwater supply tanks are equipped with low level alarm switches in addition to level gauge glasses.

The chemical feed pump motors will alarm on overcurrent.

The pumping injection flow rate for the boric acid injection system will be manually

controlled based on the boric acid concentration in the steam generator blowdown.

The feed tanks are equipped with level ind icators and the feed pumps include thermal overload protection.

10.4.10 REFERENCES

1. Final Environmental Statement for Diablo Canyon Power Plant, U.S. Nuclear Regulatory Commission, Washington, D.C., May 1973.

10.4.11 REFERENCE DRAWINGS Figures representing controlled engineering drawings a re incorporated by reference and

are identified in Table 1.6-1. The contents of the drawings are controlled by DCPP

procedures.

DCPP UNITS 1 & 2 FSAR UPDATE TABLE 10.0-1 Sheet 1 of 5 Revision 23 December 2016 APPLICABLE DESIGN BASIS CRITERIA CRITERIA TITLE APPLICABILITY Steam and Power Conversion Turbine- Generator Main Steam System Main Condenser Main Condenser Evacuation System Turbine Gland Sealing System Turbine Bypass System Circulating Water System Condensate Polishing System Condensate and Feedwater System Steam Generator Blowdown System Condensate and Feedwater Chemical Injection System Section 10.2 10.3 10.4.1 10.4.2 10.4.3 10.4.4 10.4.5 10.4.6 10.4.7 10.4.8 10.4.9

1. General Design Criteria Criterion 2, 1967 Performance Standards X X X X Criterion 3, 1971 Fire Protection X X X X X X Criterion 4, 1967 Sharing of Systems X Criterion 9, 1967 Reactor Coolant Pressure Boundary X X X Criterion 11, 1967 Control Room X X X X Criterion 12, 1967 Instrumentation and Control System X X X X Criterion 15, 1967 Engineered Safety Features Protection Systems X X Criterion 16, 1967 Monitoring Reactor Coolant Pressure Boundary X Criterion 17, 1967 Monitoring Radioactivity Releases X X X X Criterion 21, 1967 Single Failure Definition X X X Criterion 49, 1967 Containment Design Basis X X Criterion 54, 1971 Piping Systems Penetrating Containment X X X X DCPP UNITS 1 & 2 FSAR UPDATE TABLE 10.0-1 Sheet 2 of 5 Revision 23 December 2016 CRITERIA TITLE APPLICABILITY Steam and Power Conversion Turbine- Generator Main Steam System Main Condenser Main Condenser Evacuation System Turbine Gland Sealing System Turbine Bypass System Circulating Water System Condensate Polishing System Condensate and Feedwater System Steam Generator Blowdown System Condensate and Feedwater Chemical Injection System Section 10.2 10.3 10.4.1 10.4.2 10.4.3 10.4.4 10.4.5 10.4.6 10.4.7 10.4.8 10.4.9
1. General Design Criteria (contd.)

Criterion 57, 1971 Closed System Isolation Valves X X X X 2. System Safety Functional Requirements Protection from Missiles X Protection from Missiles and Dynamic Effects X X X X Decay Heat Removal X X Main Steam Isolation X Secondary Side Pressure Control X Steam Flow Restriction X Reactor Coolant System Cooldown X Internal Flooding X X X X Main Feedwater Isolation X 3. 10 CFR Part 50 50.49 Environmental Qualification of Electric Equipment Important to Safety for Nuclear Power Plants X X X DCPP UNITS 1 & 2 FSAR UPDATE TABLE 10.0-1 Sheet 3 of 5 Revision 23 December 2016 CRITERIA TITLE APPLICABILITY Steam and Power Conversion Turbine- Generator Main Steam System Main Condenser Main Condenser Evacuation System Turbine Gland Sealing System Turbine Bypass System Circulating Water System Condensate Polishing System Condensate and Feedwater System Steam Generator Blowdown System Condensate and Feedwater Chemical Injection System Section 10.2 10.3 10.4.1 10.4.2 10.4.3 10.4.4 10.4.5 10.4.6 10.4.7 10.4.8 10.4.9

3. 10 CFR Part 50 (contd.)

50.55a(f)

Inservice Testing Requirements X X X X 50.55a(g)

Inservice Inspection Requirements X X X X 50.62 Requirements of Reduction of Risk from Anticipated Transients Without Scram (ATWS)

Events for Light-Water-Cooled Nuclear Power Plants X X X 50.63 Loss of All Alternating Current Power X X Appendix R Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979 X X X X DCPP UNITS 1 & 2 FSAR UPDATE TABLE 10.0-1 Sheet 4 of 5 Revision 23 December 2016 CRITERIA TITLE APPLICABILITY Steam and Power Conversion Turbine- Generator Main Steam System Main Condenser Main Condenser Evacuation System Turbine Gland Sealing System Turbine Bypass System Circulating Water System Condensate Polishing System Condensate and Feedwater System Steam Generator Blowdown System Condensate and Feedwater Chemical Injection System Section 10.2 10.3 10.4.1 10.4.2 10.4.3 10.4.4 10.4.5 10.4.6 10.4.7 10.4.8 10.4.9

4. Regulatory Guides Regulatory Guide 1.78, June 1974 Assumptions for Evaluating the Habitability of a Nuclear Power Plant Control Room During a Postulated Hazardous Chemical Release X X Regulatory Guide 1.97, Revision 3, May 1983 Instrumentation for Light-Water-Cooled Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident X X X 5. NRC NUREG NUREG-0737, November 1980 Clarification of TMI Action Plan Requirements X X X 6. NRC Generic Letters Generic Letter 89-08, May 1989 Erosion/Corrosion-Induced Pipe Wall Thinning X X X X DCPP UNITS 1 & 2 FSAR UPDATE TABLE 10.0-1 Sheet 5 of 5 Revision 23 December 2016 CRITERIA TITLE APPLICABILITY Steam and Power Conversion Turbine- Generator Main Steam System Main Condenser Main Condenser Evacuation System Turbine Gland Sealing System Turbine Bypass System Circulating Water System Condensate Polishing System Condensate and Feedwater System Steam Generator Blowdown System Condensate and Feedwater Chemical Injection System Section 10.2 10.3 10.4.1 10.4.2 10.4.3 10.4.4 10.4.5 10.4.6 10.4.7 10.4.8 10.4.9
6. NRC Generic Letters (contd)

Generic Letter 89-10, June 1989 Safety-Related Motor-Operated Valve Testing and Surveillance X 7. Branch Technical Position Branch Technical Position ASB 10-2, March 1978 Design Guidelines for Water Hammers in Steam Generators with Top Feedring Designs X DCPP UNITS 1 & 2 FSAR UPDATE Revision 23 December 2016 TABLE 10.1-1 STEAM BYPASS AND RELIEF VALVES Design Class (a) Relieves to Pressure Mode Pressure (b) Capacity +/- 10% Main Steam Power-operated Valves (10% Atmospheric Dump Valves):

I Atmosphere Operating 790 psia 327,255 lb/hr Maximum 1,179 psia 495,949 lb/hr

Turbine Bypass Valves (40% Cooldown and Bypass Valves):

II Condenser Operating 790 psia 527,099 lb/hr Maximum 1,165 psia 789,875 lb/hr

Power-operated Steam Relief Valves (35% Atmospheric Dump Valves):

II Atmosphere Operating 790 psia 612,014 lb/hr Maximum 1,165 psia 917,123 lb/hr

Main Steam Spring-loaded Safety Valves:

Design Class Relieves to Set Pressure At 3% Accumulation Valve Full Open Orifice Size (inches) I Atmosphere 1,065 psig 803,790 lb/hr 867,431 lb/hr 4.515 I Atmosphere 1,078 psig 813,471 lb/hr 877,875 lb/hr 4.515 I Atmosphere 1,090 psig 822,408 lb/hr 887,516 lb/hr 4.515 I Atmosphere 1,103 psig 832,090 lb/hr 897,960 lb/hr 4.515 I Atmosphere 1,115 psig 841,027 lb/hr 907,601 lb/hr 4.515

(a) PG&E Design Class; refer to Table 3.2-1

(b) Ref.: DCMs M-46 (U-1) and M-71 (U-2) 10% pressure values from envelopes of lines 227 and 228, which have the highest accident pressure 35% pressure values from envelope of line 590, which supplies the PORVs 40% pressure values from envelope of line 587 supplying the valves

DCPP UNITS 1 & 2 FSAR UPDATE Revision 19 May 2010 TABLE 10.1-2 SECONDARY SYSTEM OPERATING PARAMETERS AT 100 PERCENT RATED POWER Mass of water in one steam generator, lb 102,600 Mass of steam in one steam generator, lb 6,900

Secondary side operating temperature, °F 522

Steam generator blowdown tank capacity, ft 3 641 Air ejector flowrate - rated, scfm 25

- expected average, scfm 2.5

Total mass of water in secondary system, lb 2,800,000

Total mass of steam in secondary system, lb 60,000

DCPP UNITS 1 & 2 FSAR UPDATE Revision 22 May 2015 HISTORICAL INFORMATION IN ITALICS BELOW NOT REQUIRED TO BE REVISED TABLE 10.3-1 MAIN STEAM LINE VALVE PLANT STARTUP LEAKAGE TEST RESULTS Valve Type and Leakage Path Quantity Leakage per Valve Leakage to atmosphere through seat of 6-inch safety valves (a) 20 10 bubbles/min Leakage to atmosphere through seat of

8-inch power-operated relief valves 4 24 cc/hr Leakage to auxiliary feed pump turbine

through seat of 4-inch isolation valves 2 6 cc/hr Leakage to atmosphere through stems of

gate valves in series with power-operated

relief valves (b) 4 12 cc/hr Leakage to atmosphere through stems of

main steam isolation valves (c) 4 4 cc/hr Leakage to atmosphere through stems of

globe valves bypassing the main steam

isolation valves 4 negligible

(a) Tested in accordance with API Standard 527. Test made after popping with nitrogen and then pressure reduced to 92 percent of nitrogen popping pressure.

(b) Tested seat at 1500 psig for 3 minutes. Result shown is maximum of all valves tested -

hydro test.

(c) Requirement: leakage per valve shall not exceed 2 cc of water per hour when subjected to hydrostatic pressure of 1100 psig, or 0.06 scfh of air with a differential pressure of 80 psi.

There are two valves per valve assembly. These are purchase specifications, not

operational test requirements.

DCPP UNITS 1 & 2 FSAR UPDATE Revision 23 December 2016 10.3-2

SUMMARY

OF RESULTS UNDER PIPE RUPTURE CONDITIONS Check Valve Isolation Valve Velocity at disk impact, rad/sec 74.7 77.6 Acceleration at disk impact, rad/sec 2 6373 5474 Energy at disk impact, 10 6 in-lb 0.817 0.888 Maximum flowrate through valve, lb/sec 2767 3220 DCPP UNITS 1 & 2 FSAR UPDATE Revision 22 May 2015 TABLE 10.4-1 MAIN CONDENSER PERFORMANCE DATA The condenser for each unit has two shells. The data given below are based on the full load

heat balance.

Characteristics Unit 1 Shell Unit 2 Shell Total heat load, Btu/hr (c) 8.19 x 10 9 8.19 x 10 9 Absolute pressure in condensing zone, in. Hg (with 56.5°F circulating water temperature at inlet to

condenser)

1.71 1.71 Circulating water flow, gpm (d) 862,000 862,000 Average velocity in tube, ft/sec 6.8 6.8 Effective surface area, ft 2 (e) 618,150 618,150 Cleanliness factor, % (a) 85 85 Tube outside diameter, in.

1 1 Tube BWG 22 22 Tube overall length, ft 40 ft 9 in.

40 ft 9 in.

Tube effective length, ft 40.56 40.56 Number of tubes 58,216 58,216 Total condensate stored at maximum operating level

(82 ft-6 in.), cu ft 18,880 (b) 18,880 (b)

(a) This is the percent of clean tube heat transfer coefficient used in the design of the condenser. (b) There is a single hotwell for each unit.

(c) The Unit 1 and Unit 2 condensers were originally rated for a nominal heat load of 7.6x10 9 Btu/hr. The post Alstom LP Turbine Retrofit heat loads based upon the Alstom supplied Full Load heat balance diagrams for Unit 1 and Unit 2 are bounded by the Westinghouse approximated value shown in the table. Refer to Figures 10.1-6 and 10.1-2

for the full load heat balances, Unit 1 and Unit 2, respectively. (d) This is a nominal value based on pump design documents and impacts on flow due to varying tidal conditions. (e) Vendor supplied value. It is considered a nominal value.

FIGURE 10.2-1 STEAM GENERATOR CHARACTERISTIC PRESSURE CURVES UNITS 1 AND 2 DIABLO CANYON SITE FSAR UPDATE Revision 18 October 2008 Revision 11 November 1996 FIGURE 10.3-6 LOCATION OF STEAM LINES AND VALVES UNITS 1 AND 2 DIABLO CANYON SITE FSAR UPDATE Revision 11 November 1996 FIGURE 10.4-2 REVISION OF STEAM GENERATOR FEEDWATER PIPING STEAM GENERATORS 1 AND 4 UNITS 1 AND 2 DIABLO CANYON SITE FSAR UPDATE Revision 11 November 1996 FIGURE 10.4-3 REVISION OF STEAM GENERATOR FEEDWATER PIPING STEAM GENERATORS 2 AND 3 UNITS 1 AND 2 DIABLO CANYON SITE FSAR UPDATE