MONTHYEARDCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System DCL-23-092, Material Status Report for the Period Ending August 31, 20232023-09-28028 September 2023 Material Status Report for the Period Ending August 31, 2023 DCL-23-077, License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-27027 September 2023 License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors DCL-23-083, Upcoming Meeting with Nuclear Security and Incident Response Staff2023-09-13013 September 2023 Upcoming Meeting with Nuclear Security and Incident Response Staff DCL-23-078, Nuclear Material Transaction Report for New Fuel2023-09-0606 September 2023 Nuclear Material Transaction Report for New Fuel DCL-23-070, Withdrawal of Request Regarding Senior Reactor Operator License Application2023-08-16016 August 2023 Withdrawal of Request Regarding Senior Reactor Operator License Application DCL-23-068, Nuclear Material Transaction Report for New Fuel2023-08-0909 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-066, Nuclear Material Transaction Report for New Fuel2023-08-0303 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-065, Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure2023-07-27027 July 2023 Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure DCL-23-064, Nuclear Material Transaction Report for New Fuel2023-07-26026 July 2023 Nuclear Material Transaction Report for New Fuel DCL-23-054, License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-07-13013 July 2023 License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-055, Nuclear Material Transaction Report for New Fuel2023-07-0606 July 2023 Nuclear Material Transaction Report for New Fuel DCL-23-042, Independent Spent Fuel Storage Installation, Submittal of Quality Assurance Program Description, Revision 02023-05-24024 May 2023 Independent Spent Fuel Storage Installation, Submittal of Quality Assurance Program Description, Revision 0 DCL-23-032, Independent Spent Fuel Storage Installation Docket No. 72-27, Materials License Number SNM-2514 Humboldt Bay Independent Spent Fuel Storage Installation - NRC Requested Notification of Withdrawal from Voluntary Program2023-05-22022 May 2023 Independent Spent Fuel Storage Installation Docket No. 72-27, Materials License Number SNM-2514 Humboldt Bay Independent Spent Fuel Storage Installation - NRC Requested Notification of Withdrawal from Voluntary Program DCL-23-041, 10 CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 20222023-05-22022 May 2023 10 CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 2022 DCL-23-038, Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule2023-05-15015 May 2023 Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule DCL-23-034, 2022 Annual Nonradiological Environmental Operating Report2023-05-0101 May 2023 2022 Annual Nonradiological Environmental Operating Report DCL-23-036, 2022 Annual Radiological Environmental Operating Report2023-05-0101 May 2023 2022 Annual Radiological Environmental Operating Report DCL-23-025, 2022 Annual Radioactive Effluent Release Report2023-05-0101 May 2023 2022 Annual Radioactive Effluent Release Report DCL-2023-512, Submittal of Receiving Water Monitoring Program 2022 Annual Report2023-04-27027 April 2023 Submittal of Receiving Water Monitoring Program 2022 Annual Report DCL-23-035, Response to Request for Additional Information on Request Regarding Senior Reactor Operator License Application2023-04-24024 April 2023 Response to Request for Additional Information on Request Regarding Senior Reactor Operator License Application DCL-23-028, Technical Specification Bases, Revision 142023-04-24024 April 2023 Technical Specification Bases, Revision 14 DCL-2023-511, Report on Discharge Monitoring for the First Quarter of 20232023-04-20020 April 2023 Report on Discharge Monitoring for the First Quarter of 2023 DCL-23-031, Submittal of Annual Report of Occupational Radiation Exposure for 20222023-04-19019 April 2023 Submittal of Annual Report of Occupational Radiation Exposure for 2022 DCL-23-024, Independent Spent Fuel Storage Installation, Response to Nrg Request for Additional Information for Revision to License Amendment Request 22-01 Request for Approval of Alternative Security Measures for Early Warning System2023-04-0404 April 2023 Independent Spent Fuel Storage Installation, Response to Nrg Request for Additional Information for Revision to License Amendment Request 22-01 Request for Approval of Alternative Security Measures for Early Warning System DCL-23-022, 2023 Annual Statement of Insurance for Pacific Gas and Electric Companys Diablo Canyon Power Plant2023-03-29029 March 2023 2023 Annual Statement of Insurance for Pacific Gas and Electric Companys Diablo Canyon Power Plant DCL-23-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22023-03-28028 March 2023 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-23-021, Independent Spent Fuel Storage Installation, Emergency Plan Update2023-03-23023 March 2023 Independent Spent Fuel Storage Installation, Emergency Plan Update DCL-23-020, Responses to NRC Questions Regarding License Renewal Efforts2023-03-17017 March 2023 Responses to NRC Questions Regarding License Renewal Efforts DCL-23-009, Owner'S Activity Report for Unit 2 Twenty-Third Refueling Outage2023-02-22022 February 2023 Owner'S Activity Report for Unit 2 Twenty-Third Refueling Outage DCL-23-008, Request Regarding Senior Reactor Operator License Application2023-02-22022 February 2023 Request Regarding Senior Reactor Operator License Application DCL-2023-503, Annual Sea Turtle Report2023-01-26026 January 2023 Annual Sea Turtle Report DCL-2023-502, (DCPP) 4th Quarter 2022 Report on Discharge Self-Monitoring2023-01-18018 January 2023 (DCPP) 4th Quarter 2022 Report on Discharge Self-Monitoring DCL-22-091, Revised Steam Generator Tube Inspection Report for Twenty-First Refueling Outage2022-12-20020 December 2022 Revised Steam Generator Tube Inspection Report for Twenty-First Refueling Outage DCL-22-089, Core Operating Limits Report for Unit 2 Cycle 242022-12-20020 December 2022 Core Operating Limits Report for Unit 2 Cycle 24 DCL-22-085, Request to Resume Review of the License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application2022-10-31031 October 2022 Request to Resume Review of the License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application DCL-22-041, Site-Specific Decommissioning Cost Estimate, Revision 12022-10-12012 October 2022 Site-Specific Decommissioning Cost Estimate, Revision 1 DCL-22-042, Post-Shutdown Decommissioning Activities Report, Revision 12022-10-12012 October 2022 Post-Shutdown Decommissioning Activities Report, Revision 1 2024-01-29
[Table view] |
Text
PacificGas and Electic Company David H.Oatley Diablo Canyon Power Plant Vice President and P.O. Box 55 General Manager Avila Beach, CA 93424 December 23, 2003 805.545.4350 PG&E Letter DCL-03-179 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Response to NRC Request for Additional Information Regarding License Amendment Request 03-06, "Revision to Technical Specification 3.8.1,
'AC Sources - Operating"'
Dear Commissioners and Staff:
Pacific Gas and Electric (PG&E) Letter DCL-03-060, dated May 29, 2003, submitted License Amendment Request (LAR) 03-06, "Revision to Technical Specification 3.8.1, 'AC Sources - Operating,"' which would extend the completion time for restoring an inoperable diesel generator from 7 days to 14 days.
On August 25, 2003, the NRC staff requested additional information required to complete their review of LAR 03-06. PG&E's response was submitted in PG&E Letter DCL-03-142 dated November 5, 2003. On November 7, 2003, the NRC staff issued a second request for additional information. PG&E's response is provided in .
This additional information does not affect the results of the technical evaluation and no significant hazards consideration determination previously transmitted in PG&E Letter DCL-03-060.
If you have any questions or require additional information, please contact Stan Ketelsen at (805) 545-4720.
Sincerely, David H. Oatley A6bD A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
- Palo Verde . South Texas Project a Wolf Creek
Document Control Desk PG&E Letter DCL-03-179 December 23, 2003 Page 2 jer/3664 Enclosures cc: Edgar Bailey, DHS Bruce S. Malleft David L. Proulx Diablo Distribution cc/enc: Girija S. Shukla A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway . Comanche Peak
PG&E Letter DCL-03-179 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Docket No. 50-275 In the Matter of ) Facility Operating License PACIFIC GAS AND ELECTRIC COMPANY) No. DPR-80 Diablo Canyon Power Plant ) Docket No. 50-323 Units 1 and 2 ) Facility Operating License No. DPR-82 I
AFFIDAVIT David H. Oatley, of lawful age, first being duly sworn upon oath states that he is Vice President and General Manager - Diablo Canyon of Pacific Gas and Electric Company; that he has executed this supplement to License Amendment Request 03-06 on behalf of said company with full power and authority to do so; that he is familiar with the content thereof; and that the facts stated therein are true and correct to the best of his knowledge, information, and belief.
David H. Oatley Vice President and General Manager - Diablo Canyon Subscribed and sworn to before me this 23rd day of December 2003.
SANDRA L. RECTOR otary Public Commission# 1339380 Notary Public - California 2 County of San Luis Obispo 1S San Lus Obispo County -
State of California 1 I~~MyCommn.Expires Jan 12,2006
Enclosure 1 PG&E Letter DCL-03-179 PG&E Response to NRC Request for Additional Information Regarding License Amendment Request 03-06, "Revision to Technical Specification 3.8.1,
'AC Sources - Operating"'
NRC Request Provide a list of the compensatory measures that will be implemented during the diesel generator(DG) 14-day (extended) Completion Time requested by License Amendment Request (LAR) 03-06.
PG&E Response Pacific Gas and Electric Company (PG&E) will establish the following compensatory measures when a DG is removed from service for planned on-line maintenance utilizing the 14-day (extended) Completion Time proposed by PG&E Letter DCL-03-060, dated May 29, 2003, which submitted LAR 03-06, "Revision to Technical Specification 3.8.1,
'AC Sources - Operating."'
Offsite Power Assurance
> Maintain periodic communications with the Diablo Canyon Power Plant (DCPP)
Switching Center and Transmission Operations during the project to ensure no elective maintenance or testing on the offsite power sources is performed.
External Risk Consideration
> Provide assurance that storms or ocean swell events are not expected during the maintenance period.
> Contact the DCPP Switching Center to verify offsite power sources are not in danger of being lost due to wild land fires, other grid related transients, or scheduled work activities.
> Assure that Operations, Maintenance, Engineering, and the Manager of Operations are notified in the event of external events that may jeopardize offsite power sources, and that they determine if postponement of DG maintenance is warranted.
Internal Risk Consideration
> Avoid scheduling site activities that may cause a plant transient on either unit.
Exceptions should be authorized in accordance with DCPP Administrative Procedure AD7.DC6, "On-Line Maintenance Risk Management." (AD7.DC6 provides guidance for managing plant trip, probabilistic, and safety function degradation risk from on-line maintenance, and external and internal conditions, as required by 10 CFR 50.65(a)(4)).
> Avoid performing any testing or elective maintenance on either unit unless it is identified on the approved work week schedule. Exceptions may be approved by the Shift Manager or Work Week Manager. -
1
Enclosure 1 PG&E Letter DCL-03-179 Minimize Duration Clearly identify and obtain agreement on the maintenance scope before starting.
No additions will be made without Engineering and Operations review, including their impact on post-maintenance test requirements.
Verify all parts and equipment necessary for the project have been procured and meet quality related checks.
Support the DG maintenance project on a 24-hour a day schedule.
Management Oversight
> Provide on-shift senior management support in the event conditions develop that jeopardize plant operation (such as wild land fires, high swell warnings, or electrical distribution problems).
> Assign engineering and operations to perform an evaluation in the event project conditions change such that it no longer meets the initial condition requirements or project restrictions, with a determination to be made by the Manager of Operations as to the proper course of action.
Protect Other Mitigation Equipment
> Post caution signs on the affected unit's doors to the following rooms requiring shift foreman permission to perform work within:
o motor-driven and turbine-driven auxiliary feedwater pump rooms o other two DG rooms
> Verify the other two DGs are operable.
> Perform a walkdown verifying the other two DGs and associated areas are clean and in good material condition with no activities being performed which could jeopardize operation.
> Verify redundant safety related systems, subsystems, trains, components and devices dependant on the other two DGs are operable within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of beginning maintenance.
> Perform no elective maintenance or testing on components required to crosstie the vital 4 kV busses between units as required by DCPP emergency operating procedures.
> Perform no elective maintenance or testing (other than normally scheduled surveillances) on either units' DGs.
> Verify all DG fuel oil transfer system surveillance testing is current for the duration of the project.
Contingency Planning
> Place the affected unit's redundant equipment (4 kV and 480 V) in service or on alternate power supplies.
> Conduct operator briefings on applicable normal, abnormal and emergency procedures for reactor trip, loss of electrical power, and restoring electrical power, each shift for the duration of maintenance.