CNL-15-094, Responses to Requests for Additional Information - Developmental Revision I Technical Specification Section 3.8

From kanterella
Jump to navigation Jump to search
Responses to Requests for Additional Information - Developmental Revision I Technical Specification Section 3.8
ML15238B734
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 08/26/2015
From: James Shea
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
CNL-15-094
Download: ML15238B734 (156)


Text



Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-15-094 August 26, 2015 10 CFR 50.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 Construction Permit No. CPPR-92 NRC Docket No. 50-391

Subject:

Watts Bar Nuclear Plant Unit 2, Responses to Requests for Additional Information - Developmental Revision I Technical Specification Section 3.8

References:

1. TVA Letter to NRC, Watts Bar Nuclear Plant Unit 2 - Submittal of Developmental Revision I of the Unit 2 Technical Specification & Technical Specification Bases and Developmental Revision D of the Unit 2 Technical Requirements Manual and Technical Requirements Manual Bases, dated June 16, 2014 [ML14169A525]
2. Email from M. Miernicki (NRC) to G. Arent (TVA), TS Review Clarification RAIs 10 07 2014, dated October 8, 2014 [ML14286A029]
3. TVA Letter to NRC, Watts Bar Nuclear Plant Unit 2, Responses to Requests for Additional Information - Developmental Revision I Technical Specification Sections 3.8 and 5.7, dated February 27, 2015 [ML15064A160]
4. Email from R. Schaaf (NRC) to G. Arent (TVA), Draft of Outstanding Issues on TS Rev I Section 3.8, dated April 27, 2015 By letter dated June 16, 2014, Tennessee Valley Authority (TVA) submitted the Watts Bar Nuclear Plant (WBN) Unit 2 Developmental Revision I of the Technical Specifications (TS) and TS Bases, and Developmental Revision D of the WBN Unit 2 Technical Requirements Manual (TRM) and TRM Bases to the Nuclear Regulatory Commission (NRC) (Reference 1). By electronic mail (email) dated October 8, 2014, the NRC provided a set of requests for additional information (RAIs) regarding Developmental Revision I of TS Sections 3.8 and 5.7 (Reference 2).

By letter dated February 27, 2015, TVA submitted responses to the Reference 2 RAIs (Reference 3). By email dated April 27, 2015, the NRC provided a draft set of RAIs regarding outstanding issues on TS Section 3.8 (Reference 4).

U.S. Nuclear Regulatory Commission CNL-15-094 Page 2 August 26, 2015 The enclosure provides the TVA responses to the Reference 4 RAIs regarding outstanding issues on TS Section 3.8.

There are no new regulatory commitments associated with this letter. Please direct any questions concerning this matter to Gordon Arent at (423) 365-2004.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 26th day of August 2015.

Respectfully, Digitally signed by J. W. Shea DN: cn=J. W. Shea, o=Tennessee J. W. Shea Valley Authority, ou=Nuclear Licensing, email=jwshea@tva.gov, c=US Date: 2015.08.26 14:28:14 -04'00' J. W. Shea Vice President, Nuclear Licensing

Enclosure:

Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 cc (Enclosure):

U.S. Nuclear Regulatory Commission, Region II NRC Senior Resident Inspector - Watts Bar Nuclear Plant, Unit 2 NRC Project Manager - Watts Bar Nuclear Plant, Unit 2



Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8

Background

By letter dated June 16, 2014, Tennessee Valley Authority (TVA) submitted the Watts Bar Nuclear Plant (WBN) Unit 2 Developmental Revision I of the Technical Specifications (TS) and TS Bases, and Developmental Revision D of the WBN Unit 2 Technical Requirements Manual (TRM) and TRM Bases to the Nuclear Regulatory Commission (NRC) (Reference 1). By electronic mail (email) dated October 8, 2014, the NRC provided a set of requests for additional information (RAIs) regarding Developmental Revision I of TS Sections 3.8 and 5.7 (Reference 2). By letter dated February 27, 2015, TVA submitted responses to the Reference 2 RAIs (Reference 3). By email dated April 27, 2015, the NRC provided a draft set of RAIs regarding outstanding issues on TS Section 3.8 (Reference 4).

The following responses to the Reference 4 RAIs address the NRC staff concerns that were communicated to TVA during the public meeting held in Rockville, MD on April 30, 2015.

NRC RAI 1 TS Section 3.8.1 TS Section 3.8.1 is related to operating requirements and surveillance testing of onsite Diesel Generators (DGs) 2A-A and 2B-B. The staff notes that:

1. All four DGs are required to be operable with Unit 2 in Modes 1, 2, 3, or 4.
2. Several DG surveillances in TS Section 3.8.1 are precluded by a note stating, For DGs 2A-A and 2B-B Surveillance shall not be performed in MODE 1, 2, 3, or 4.

The current licensing basis (CLB) of WBN Units 1 and 2 requires support systems such as essential raw cooling water and the component cooling system in each train to be operable.

The CLB states that the minimum combined safety requirements for one accident unit and one non-accident unit or two non-accident units are met by two pumps on the same plant train. With one unit in a shutdown mode and the other unit in Mode 1, some or all the 'common' loads may be operating and can potentially impact the testing of systems/components associated with the shutdown units. Based on the above observations, in its RAI the staff asked the applicant to clarify how all four DGs will be tested to satisfy the surveillance requirements (SRs) for each operating unit.

In response to the RAI, TVA stated that:

1. In the Safety Evaluation related to WBN Unit 1 License Amendment 89, dated November 22, 2011 (Reference 14), Section 3.2, Need for Proposed Change, the NRC accepted proposed changes to allow performance of the preoperational integrated safeguards test of WBN Unit 2 with WBN Unit 1 in MODE 1, 2, 3, or 4.
2. If the NRC grants an Operating License to WBN Unit 2, the proposed changes to the WBN Unit 1 TSs will allow periodic performance of the Surveillances on WBN Unit 2 in MODE 5 or 6 with WBN Unit 1 in MODE 1, 2, 3, or 4.
3. The guidance provided by the Commission in SECY-07-0096, allows the applicant to maintain TS requirements for Unit 2 similar to the requirements for Unit 1.

CNL-15-094 E-1

Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 The staff notes that:

1. The preoperational integrated safeguards test is one time testing required to validate the design and functional capabilities of the plant systems prior to full power operation, compared to the TS surveillances which will be performed routinely over the life of the operating units.
2. SECY-07-0096 also stated that significant changes to the licensing approach would be allowed as necessary to support dual unit operation.

The staff determined that the applicants response did not clarify the impact on safe shutdown capability of the operating unit when equipment required for dual unit operation is removed from service for testing purposes. At WBN Units 1 and 2, the load group A and load group B philosophy for dual unit operation does not appear to provide independence between redundant and/or corresponding components.

The staff considers the applicants response to be inadequate and considers this an open item.

TVA Response The proposed Unit 2 TS SR Notes effectively remove the Mode restriction from the Unit 2 6.9 kV shutdown boards and DGs to allow testing with Unit 2 in Mode 5 or 6 and with Unit 1 in Mode 1, 2, 3, or 4. The existing Unit 1 TS SR Notes effectively remove the Mode restriction from the Unit 1 6.9 kV shutdown boards and DGs to allow testing with Unit 1 in Mode 5 or 6 and with Unit 2 in Mode 1, 2, 3, or 4.

The on-site distribution system at WBN is divided into independent load groups which provide independence of the Emergency Core Cooling Systems (ECCS) between trains and units. This design allows components in one load group to be removed from service or tested without imposing an impact to the redundant train or a significant impact to the operation of the opposite unit. The 6.9 kV shutdown board in each group is protected by an independent set of undervoltage and protective relaying. Additionally, there is no sharing of DGs between load groups. Some systems are common to both units, e.g., Essential Raw Cooling Water (ERCW)

System, Component Cooling System, Auxiliary Air, and various engineered safety feature (ESF) heating, ventilation, and air conditioning (HVAC) loads. Some of these system components are powered from 6.9 kV Shutdown Board 2A-A or 2B-B, which are provided with standby power from the DG 2A-A or 2B-B, respectively. However, redundant trains of common systems are still on independent load groups and therefore, testing will not result in loss of the function.

Although the performance of a Unit 2 loss of offsite power (LOOP) / ESF test with Unit 1 in Mode 1 will result in entering Unit 1 TS Conditions for equipment made inoperable, performance of the SR will not cause a loss of safety function.

The portions of the 6.9 kV and 480 V electrical distribution system that are not being tested will not be significantly affected. The portions of the 6.9 kV and 480 V electrical distribution systems being tested will be de-energized at various points during the test, but significant perturbation of Unit 1 ESF equipment is not anticipated.

CNL-15-094 E-2

Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 The 120 V vital AC and 125 V vital DC systems supported by the unit / train being tested could be challenged due to loss of normal AC power to the associated inverter and loss of the vital battery charger. However, the vital AC board and vital battery board will remain energized by the associated vital battery. Therefore, a loss of a vital board is unlikely and is not anticipated.

For example, during performance of the Unit 2 Train A LOOP / ESF test, the normal power supply to Vital Inverters 1-III and 2-III and the power supply to Vital Battery Charger III will be lost while testing personnel verify that the affected components are in their post-LOOP positions. During this time, LCO 3.8.4, DC Sources - Operating, is not met (loss of power to Vital Battery Charger III). LCO 3.8.4, Condition A, requires power be restored to Vital Battery Charger III within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. However, during performance of the test, Vital Battery Board III remains energized from Vital Battery III, and Inverters 1-III and 2-III remain energized from Vital Battery III. Therefore, the loss of power to Vital Battery Charger III and normal power to Vital Inverters 1-III and 2-III does not result in a loss of function. The expected duration of this condition during the test is approximately 30 minutes. If necessary, the test can be aborted and normal power can be restored to Vital Battery Charger III in approximately 5 to 10 minutes.

Some common systems could be affected during the test (primarily, ERCW, Core Cooling System (CCS), Auxiliary Air and safety-related ventilation systems). For example, during the performance of SR 3.8.1.9, single largest load reject test, the running ERCW pump associated with the DG being tested is placed in the pull-to-lock position to verify acceptable DG response to a loss of the single largest load. This action results in LCO 3.7.8, Essential Raw Cooling Water (ERCW) System, not being met. However, fluctuations in ERCW System pressure should not significantly affect CCS heat exchanger operation or Unit 1 containment temperatures due to the short duration of the test (approximately 30 minutes). Additionally, during performance of the testing, main control room operators monitor ERCW System pressure and make adjustments as necessary to maintain system pressure.

The flexibility of the CCS allows alternate system alignments during the test to minimize impacts to the operating unit. For example, during a test of DG 2A-A, CCS Pump C-S is running to maintain cooling on CCS Train B (provides cooling to both units). CCS pump 2A-A runs in parallel with CCS pump 2B-B to ensure Unit 2 CCS Train A flow. CCS pump 1A-A runs in parallel with CCS pump 1B-B to maintain cooling to the Unit 1 CCS Train A header. Therefore, CCS operation to Unit 1 is unaffected during the test.

Auxiliary air is powered from Unit 2 6.9 kV shutdown boards. However, the normal lineup is for control air (powered from Unit 1 6.9 kV shutdown boards) to provide the motive force for ESF system components, with auxiliary air providing the safety-related backup. Therefore, although the affected ESF trains will be inoperable without a backup auxiliary air compressor, these components will continue to be functional throughout the Unit 2 testing. With one train of auxiliary air unavailable, the applicable TS Conditions of the following LCOs will be entered:

LCO 3.6.9, Emergency Gas Treatment System, LCO 3.7.4, Atmospheric Dump Valves, LCO 3.7.5, Auxiliary Feedwater System, LCO 3.7.10, Control Room Emergency Ventilation System, LCO 3.7.11, Control Room Emergency Air Temperature Control System, and LCO 3.7.12, Auxiliary Building Gas Treatment System. The duration of the TS Condition entries for an unavailable auxiliary air compressor is expected to be no longer than two hours.

CNL-15-094 E-3

Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 In addition, prior to performance of the testing, the following are performed to ensure safe shutdown capability is maintained and to minimize impacts on the operating unit:

x Testing is performed on 6.9 kV shutdown boards and DGs associated with the unit in Mode 5 or 6.

x For Train A testing, Train B is protected. For Train B testing, Train A is protected.

x Each vital battery charger is verified to be aligned to its normal power supply.

x Each 6.9 kV shutdown board is verified to be aligned to its normal power supply.

SR 3.8.1.9 This SR requires the performance of the single largest load reject test for each DG. This test is performed with the DG supplying the 6.9 kV shutdown board, immediately following performance of the LOOP / ESF actuation test (SR 3.8.1.19). Therefore, the test begins with the DG on the 6.9 kV shutdown board with ESF loads connected and the selected ERCW pump running. The ERCW pump switch is then taken to the pull-to-lock position, thereby removing the single largest load from the DG. During the time that the ERCW pump switch is in the pull-to-lock position that train of ERCW is considered inoperable and the appropriate Action of LCO 3.7.8, Essential Raw Cooling Water (ERCW) System, is entered.

SR 3.8.1.10 This SR requires the performance of the full load reject test for each DG. This test is performed with the DG aligned to the 6.9 kV shutdown board connected to offsite power. The DG is loaded as close to design basis conditions as possible (approximately 4300 kW and 3100 kVAR). DG temperatures are then allowed to stabilize. Once conditions are met, a safety injection signal is simulated to trip open the DG output breaker. The impact to the 6.9 kV shutdown board is minimal, and the 6.9 kV shutdown board should remain energized to meet the acceptance criteria for the test.

SR 3.8.1.11 and SR 3.8.1.16 This SR requires the performance of the LOOP test for each DG. After the LOOP is simulated, the DG is verified to start, energize the 6.9 kV shutdown board, auto-connect the emergency loads, achieve steady state voltage and frequency, and operate for at least five minutes. After operating for at least five minutes, the DG is synchronized with offsite power, the loads are transferred to offsite power, and the DG is returned to a ready-to-load condition.

This test is performed with the normal feeder for 6.9 kV Shutdown Board 2A-A open, thereby isolating the 6.9 kV shutdown board from the common station service transformer (CSST). This action places Unit 1 in LCO 3.8.1, Condition A for a loss of offsite power source.

Auxiliary air is powered from Unit 2 6.9 kV shutdown boards, therefore one of the auxiliary air trains will be impacted by de-energizing one of the two Unit 2 6.9 KV shutdown boards.

However, the normal lineup is for control air (powered from Unit 1 6.9 kV shutdown boards) to provide the motive force for ESF system components, with auxiliary air providing the safety-related backup. Therefore, although the affected ESF trains will be inoperable without a backup auxiliary air compressor, these components will continue to be functional throughout the CNL-15-094 E-4

Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 Unit 2 testing. With one train of auxiliary air unavailable, the applicable Conditions of TS LCOs 3.6.9, 3.7.4, 3.7.5, 3.7.10, 3.7.11, and 3.7.12 will be entered.

When this test is performed on Train 2B, CCS pump 1B is re-aligned to ensure CCS Train B remains operable on Unit 1.

Additionally, this test results in the loss of one train of vital DC when the associated 6.9 kV shutdown board is de-energized. This requires Unit 1 entry into LCO 3.8.4, Conditions A and C (restore in 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />). However, the vital AC board and vital battery board will remain energized by the associated vital battery. Therefore, a loss of a vital board is unlikely and is not anticipated.

SR 3.8.1.18 This SR requires verification that the time delay setting for each sequenced load block is within limits. Performance of this test involves individually placing component breakers in test and applying external signals to drive the load sequence relays. There is no impact to the electrical distribution system due to the testing because no loads are connected. However, the LCO Action associated with the component breaker being placed in test is entered during testing of the breaker.

SR 3.8.1.19 and SR 3.8.1.13 SR 3.8.1.19 requires performance of the LOOP / ESF test for each DG. SR 3.8.1.16 requires verification that each DG can synchronize to the offsite power source while loaded with emergency loads upon a simulated restoration of offsite power, transfer loads to the offsite power source, and return to ready-to-load operation. SR 3.8.1.13 requires verification that the DG automatic trips are bypassed on an automatic or emergency start signal. For the DG being tested, the associated 6.9 kV shutdown board is de-energized and load shedding is verified. A manual safety injection actuation signal is initiated. The DG is verified to start, energize the 6.9 kV shutdown board, auto-connect the emergency loads, achieve steady state voltage and frequency, and operate for at least five minutes. In addition, the DG automatic trips are verified to be bypassed.

NRC RAI 2 TS SR 3.8.1.8 Similar to TS 3.8.1 subsections, SR 3.8.1.8 has a note that states that for the 2A-A and 2B-B Shutdown Boards, the Surveillance shall not be performed in MODE 1 or 2. The surveillance requires verification of automatic and manual transfer of each 6.9 kV shutdown board power supply from the normal offsite circuit to each alternate offsite circuit. The staff requested the following information:

1. Clarify when this surveillance will be performed on each of the four shutdown boards that are required when Unit 2 is in Mode 1 or 2.
2. Clarify if each includes shutdown boards 1A-A, 1B-B, 2A-A and 2B-B and how the applicable note for surveillances in Mode 1 or 2 will impact each of the shutdown boards.

CNL-15-094 E-5

Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 TVAs response cites exemptions granted for preoperational testing and the guidance provided by the Commission in SECY-07-0096 for similarity with WBN Unit 1 and using WBN Unit 1 as the reference basis for the review and licensing of WBN Unit 2. The applicant stated the proposed adoption of the WBN Unit 1 TS 3.8.1 SR Notes, as amended by WBN Unit 1 License Amendment 89, represents conforming changes to the WBN Unit 2 TS 3.8.1 SR Notes.

The staff concludes that the TS requirements for dual unit operation should be reviewed for impact on systems required at both units in all operating modes. Simple adoption of constraints associated with a single unit may lead to non-conservative plant conditions with shared systems.

The staff considers the applicants response to be inadequate and considers this an open item.

TVA Response The test consists of manual and auto transfer of 6.9 kV shutdown boards from the normal offsite power supply to the alternate offsite power supply (C or D CSST). The performance of this test does not render the 6.9 kV Shutdown Board inoperable while transferring power sources from the normal feeder to the alternate feeder then back to the normal feeder. The performance of the surveillance will not initiate a significant perturbation in the electrical distribution system that could challenge a plant safety related system, or challenge steady state conditions to the unit online.

Failure of this surveillance will not challenge or cause an operational transient or challenge to plant safety systems for the unit online. The ability of the 6.9 kV shutdown board to transfer to the DG will not be inhibited should the ability of the electrical board to automatically or manually transfer to the alternate feeder breaker not be functional. The LOOP circuits will still automatically strip the board and allow the DG starting and loading sequence to occur providing power to the ESF systems as designed.

NRC RAI 3 TS SR 3.8.1.13 TS SR 3.8.1.13 is related to verification of each DG's automatic trips that are bypassed on automatic or emergency start signal with the exception of

a. Engine overspeed; and
b. Generator differential current The staff requested clarification for specific contacts that will be tested for normal/emergency mode of operation of the DGs and bypassed during emergency mode of operation in accordance with proposed WBN Unit 2 TS SR 3.8.1.13. In response, TVA provided details on the functional requirements of the associated contacts and stated that WBN procedures periodically verify the capability of the DG trip relays and associated instrumentation to actuate a DG trip. TVA did not provide details on the specific contacts and the frequency of testing associated with TS SR 3.8.1.13.

CNL-15-094 E-6

Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 The staff considers the applicants response to be inadequate and considers this an open item.

TVA Response Following the discussions of the public meeting held in Rockville, MD on April 30, 2015, it is TVAs understanding that the NRC requests a copy of the maintenance instructions that test the DG engine overspeed and generator differential current trips. Attachment 1 to this enclosure provides a copy of the maintenance instruction for testing the DG engine overspeed trip. In addition, a copy of the preventative maintenance work instruction for performing the DG 1A-A protective relay functional test (including differential current relay test) and a copy of the preventative maintenance work instruction for performing the DG 1A-A differential current relay calibration test. Preventative maintenance work instructions for DGs 1B-B, 2A-A, and 2B-B provide similar testing of the differential current relays associated with those DGs.

NRC RAI 4 TS SR 3.8.1.14 SR 3.8.1.14 has a requirement to test the DG at postulated accident profile and states:

Verify each DG operating at a power factor 0.8 and 0.9 operates for 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />s:

a. For 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> loaded 4620 kW and 4840 kW and 3465 kVAR and 3630 kVAR; and
b. For the remaining hours of the test loaded 3960 kW and 4400 kW and 2970 kVAR and 3300 kVAR.

The CLB, as stated in Final Safety Analysis Report, Section 8.1.5.3, indicates the postulated accident loading is equal to or greater than the nominal DG rating. Since the proposed lower limit of test load in TS SR 3.8.1.14 (b), 3960 kW and 2970 kVAR, is less than the nominal rating of the DGs, the staff requested TVA to confirm that the DG testing requirements will envelope the postulated accident loads.

In response to the RAI, TVA stated Worst case loading occurs for a simultaneous loss of offsite power and a loss-of-coolant accident on the unit the diesel is associated with. Adequate margin exists between worst case loading and diesel capacity. To satisfy the continuous rating, it may be necessary for operator action to remove certain loads not required for accident mitigation within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> of starting a diesel.

The staff notes that for the DGs to be considered operable, support structures, systems and components (SSC) must be capable of performing the safety functions specified by the design, within the required range of design physical conditions, initiation times, and mission times. In addition, TS operability considerations require that SSCs meet all surveillance requirements.

The satisfactory completion of this SR validates the capability of the DG to perform its required functions as specified in the current licensing basis. The applicant did not confirm that the TS proposed surveillance requirements will envelope the postulated accident loads of the DG.

The staff considers the applicants response to be inadequate and considers this an open item.

CNL-15-094 E-7

Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 TVA Response WBN Unit 1, UFSAR Section 8.1.5.3, provides WBNs commitment to Regulatory Guide (RG) 1.9, Revision 3. RG 1.9, Revision 3, Regulatory Position C2.2, Test Descriptions, provides the following description of the Endurance and Margin Test:

2.2.9 Endurance and Margin Test: Demonstrate full-load carrying capability at a power factor between 0.8 and 0.9 for an interval of not less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, of which 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> are at a load equal to 105 to 110 percent of the continuous rating of the emergency diesel generator, and 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> are at a load equal to 90 to 100 percent of its continuous rating. Verify that voltage and frequency requirements are maintained.

WBN Unit 1, UFSAR Section 8.1.5.3, annotates that the unit fully conforms with Regulatory Position C2.2.9.

In Reference 3, TVA stated that the continuous rating for each DG is 4400 kW. Therefore, per RG 1.9, Revision 3, Regulatory Position C2.2.9, the 22 hour2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> portion of the endurance and margin test is performed at a load equal to at least 90 percent, or, 4400 kW x 0.9 = 3960 kW.

As WBN Unit 1 TS SR 3.8.1.14 requires each DG to be loaded for the remaining hours

[22 hours] at 3960 kW and 4400 kW, this meets RG 1.9, Revision 3, Regulatory Position C2.2.9.

In addition, the current predicted maximum steady-state running loads on the DG for the worst case event are as follows:

0 - 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> of the  DG 1A-A DG 1B-B DG 2A-A DG 2B-B event kW 4313.57 4220.24 4200.69 4332.97 kVA 4969.12 4817.48 4819.42 4990.28 pf 0.868 0.876 0.872 0.868 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to end of the     

event kW 4148.39 4066.52 4033.27 4162.67 kVA 4768.89 4687.93 4625.20 4765.54 pf 0.870 0.867 0.872 0.873



The TS SR 3.8.1.14 requirements to load the DG for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at 4620 to 4840 kW and 3465 to 3630 kVAR, and for the next 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> at 3960 to 4400 kW and 2970 to 3300 kVAR could result in power factors less than 0.8. Therefore, the surveillance instructions (SI) that implement SR 3.8.1.14 require a narrower band for real power (kW) and reactive power (kVAR) to ensure a power factor greater than 0.8.

CNL-15-094 E-8

Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 For time 0 to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, the surveillance instructions (SIs) require real power in the range of 4700 to 4840 kW and reactive power in the range of 3465 to 3525 kVAR. For time 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, the SIs require real power in the range of 4200 to 4400 kW and reactive power in the range of 2970 to 3150 kVAR. Therefore, although not a requirement to meet the acceptance criteria of SR 3.8.1.14 or RG 1.9, Position C2.2.9, the procedural requirements result in DG loading that envelops the predicted accident loads, including the cumulative impacts of DG voltage and frequency at a power factor conservative to the predicted reactive loading on the DG.

NRC RAI 5 TS SR 3.8.4.5 and SR 3.8.4.6 SR 3.8.4.5 and 3.8.4.6 require verification of no visible corrosion at terminals and connectors for the vital and DG batteries. The SR also provides limiting connection resistances for each battery connection to determine battery operability. The SR does not provide an acceptance criterion for the total resistance that should be used for operability determination. The staff requested TVA to confirm that the total battery resistance calculated with each connection at the maximum TS limited value will ensure adequate battery terminal voltage required for safety functions at the end of predicted life. The applicant stated that the WBN has procedures that implement these SRs and that the WBN Unit 2 TSs reflect the same requirements for monitoring and maintaining the batteries that are in the WBN Unit 1 TSs. TVAs response did not clarify the resistance value required to establish battery operability. (This concern is also applicable to SR 3.8.4.9 and SR 3.8.4.10.)

The staff considers the applicants response to be inadequate and considers this an open item.

TVA Response Technical Specification Bases 3.8.4, DC Sources - Operating, LCO section, states that an OPERABLE vital DC electrical power subsystem requires all required batteries and respective chargers to be operating and connected to the associated DC buses.

As stated in the WBN Unit 2 and Unit 1 TS Bases for SR 3.8.4.8, SR 3.8.4.9, and SR 3.8.4.10, visual inspection and resistance measurements of intercell, interrack, intertier, and terminal connections provide an indication of physical damage or abnormal deterioration that could indicate degraded battery condition. In addition, the Bases state that for the purpose of trending, intercell (vital and DG batteries) and intertier (vital and DG batteries) connections are measured from battery post to battery post. Interrack (vital batteries), intertier (DG batteries),

and terminal connections (vital and DG batteries) are measured from terminal lug to battery post.

As described in the TS Bases for SR 3.8.4.13, the battery service test is a test of battery capability, as found, to satisfy the design requirements (battery duty cycle) of the DC electrical power system. The discharge rate and test length should correspond to worst case design duty cycle requirements. This battery service test is used to verify battery operability.

CNL-15-094 E-9

Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 This understanding is reflected in the NRCs approval of Technical Specifications Task Force (TSTF) Traveler TSTF-500, "DC Electrical Rewrite - Update to TSTF-360," Revision 2 as stated in Federal Register Notice (FRN) dated September 1, 2011 (Reference 5). In the approved TSTF-500, the proposed change relocates the requirements of the following: SR 3.8.4.2 (visual inspection and connection resistance), SR 3.8.4.3 (visual inspection for physical damage), SR 3.8.4.4 (remove visible corrosion and ensure that connections are clean and tight), and SR 3.8.4.5 (verification of connection resistance) to the [new] Battery Monitoring and Maintenance Program.

In the evaluation for removal of the visual inspection from TS, the NRC stated the following:

However, visual inspection of the battery terminals for signs of corrosion to ensure that connections are clean and tight are generally considered a routine preventive maintenance activity. Visual inspection of the battery terminals is an important preventive maintenance practice for maintaining a healthy battery (e.g.,

the early identification and cleaning of battery terminal corrosion can prevent corrosion from spreading between the post and the connector). However, visual inspection of the battery terminals alone does not provide an indication of a batterys capability to perform its design function. Therefore, the NRC staff finds these activities to be preventive maintenance and that the parameters can be adequately controlled in the [new] TS [5.5.17] Battery Monitoring and Maintenance Program.

In the evaluation for removal of the resistance verification from TS, the NRC stated the following:

With regard to the resistance verifications of SR 3.8.4.2 and SR 3.8.4.5, the existing values represent limits at which some action should be taken, not necessarily when the operability of the battery is in question. The plant safety analyses do not assume a specific battery inter-cell connection resistance value, but typically assume that the batteries will supply adequate power. Therefore, the key operability issue is the overall battery connection resistance. Between surveillances, the resistance of each battery inter-cell connection varies independently from all the others. Some of these connection resistance values may be higher or lower than others, and the battery will still be able to perform its function and should not be considered inoperable. Overall connection resistance has a direct impact on operability and is adequately determined by completion of the battery service or modified performance discharge tests. Therefore, these activities are more appropriately controlled under the proposed Battery Monitoring and Maintenance Program and [LICENSEE] provided a justification for the monitoring limit.

TVA is not proposing to adopt TSTF-500 at this time. However, the above discussion from the NRC evaluation regarding the performance of a battery service or performance discharge test to determine battery operability in lieu of using battery connection resistance readings is applicable to WBN.

CNL-15-094 E-10

Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 Therefore, consistent with the NRC approved TSTF-500, TVA has determined that no new resistance value is required for SR 3.8.4.5, SR 3.8.4.6, SR 3.8.4.9, or SR 3.8.4.10 to establish battery operability, because the battery operability associated with battery resistance is adequately determined by the battery service test or performance discharge test.

NRC RAI 6 TS 3.8.6.3 TS 3.8.6.3 establishes battery operability based on battery cell parameters and average electrolyte temperatures for vital and DG batteries. If the average electrolyte temperature of the representative cells is outside the lower limit (< 60°F for vital batteries and < 50°F for DG batteries), the battery is considered inoperable. The staff requested clarification about the corresponding temperature correction factors that were used for battery sizing criteria in the design calculations. TVA responded that the WBN Unit 2 TSs reflect the same requirements for monitoring and maintaining the batteries that are in the WBN Unit 1 TSs and there are no new requirements imposed on the batteries.

The staff considers the applicants response to be inadequate and considers this an open item.

TVA Response TVA procedures 0-SI-236-51, 0-SI-236-52, 0-SI-236-53, and 0-SI-236-54, 125 VDC Vital Battery I [II, III, IV] 60 Month Modified Performance Test and 125 VDC Vital Battery Charger I [II, III, IV] Test, provide the steps to perform a battery performance test for each 125 VDC vital battery. Each test uses the battery discharge unit to discharge the respective vital battery at a 5-hour current rate of 414 amps (corrected for temperature) until battery terminal voltage reaches the minimum design voltage of 105 VDC.

After the average electrolyte temperature is determined, a discharge rate temperature correction factor is applied to determine the discharge rate corrected to 77 ºF, as follows:

414 Amps ÷ (1) = (2) Amps (5 hour5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> (Temperature (Corrected Rated Amps) Correction Factor) Discharge Rate)

Where (1) is the Correction Factor from the table below, and (2) is the Corrected Discharge Rate from the table below:

Avg. Cell Correction Corrected Avg. Cell Correction Corrected Temp Factor Disch. Rate Temp Factor Disch. Rate 60 1.110 373 78 0.994 416 65 1.080 383 79 0.987 419 66 1.072 386 80 0.980 422 67 1.064 389 81 0.976 424 68 1.056 392 82 0.972 426 69 1.048 395 83 0.968 428 CNL-15-094 E-11

Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 Avg. Cell Correction Corrected Avg. Cell Correction Corrected Temp Factor Disch. Rate Temp Factor Disch. Rate 70 1.040 398 84 0.964 429 71 1.034 400 85 0.960 431 72 1.029 402 86 0.956 433 73 1.023 405 87 0.952 435 74 1.017 407 88 0.948 437 75 1.011 409 89 0.944 439 76 1.006 412 90 0.940 440 77 1.000 414 95 0.930 445 TVA procedures 0-SI-215-51-A, 0-SI-215-52-B, 0-SI-215-53-A, and 0-SI-215-54-B, Diesel Generator 1A-A [1B-B, 2A-A, 2B-B] 60 Month Performance Test and Battery Charger Test, provide the steps to perform a battery performance test for each DG battery. Each test uses the battery discharge unit to discharge the respective DG battery at a 4-hour current rate of 48 amps (corrected for temperature) until battery terminal voltage reaches the minimum design voltage of 105 VDC.

After the average electrolyte temperature is determined, a discharge rate temperature correction factor is applied to determine the discharge rate corrected to 77 ºF, as follows:

48 Amps ÷ (1) = (2) Amps (4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> (Temperature (Corrected Rated Amps) Correction Factor) Discharge Rate)

Where (1) is the Correction Factor from the table below, and (2) is the Corrected Discharge Rate from the table below:

Avg. Cell Correction Corrected Avg. Cell Correction Corrected Temp Factor Disch. Rate Temp Factor Disch. Rate 60 1.110 43 78 0.994 48 65 1.080 44 79 0.987 49 66 1.072 45 80 0.980 49 67 1.064 45 81 0.976 49 68 1.056 45 82 0.972 49 69 1.048 46 83 0.968 50 70 1.040 46 84 0.964 50 71 1.034 46 85 0.960 50 72 1.029 47 86 0.956 50 73 1.023 47 87 0.952 50 74 1.017 47 88 0.948 51 75 1.011 47 89 0.944 51 76 1.006 48 90 0.940 51 77 1.000 48 95 0.930 52 CNL-15-094 E-12

Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 NRC RAI 7 SR 3.8.4.13 and SR 3.8.4.14 SR 3.8.4.13 and SR 3.8.4.14 are associated with verification of the battery capacity tests.

The DG batteries are required to start the DGs after a four hour SBO event. The TS basis states that the DG battery has sufficient capacity when fully charged to supply required loads for a minimum of 30 minutes following a loss of normal power. The staff requested clarification on the load profile testing that would be used to determine the operability of the DG battery systems.

The TVA response provides details on analytical evaluations performed to demonstrate the adequacy of the DG battery systems and related communications with NRC for WBN2 license application. The applicants response did not confirm that the DG battery systems will be tested using a four hour SBO load profile to demonstrate compliance with requirements of SR 3.8.4.13 and SR 3.8.4.14.

The staff considers the applicants response to be inadequate and considers this an open item.

TVA Response WBN Unit 2 FSAR Section 8.3.1.1, Subheader, Diesel Generator Control Power, states, in part:

The battery has sufficient capacity when fully charged to supply required loads for a minimum of four hours following a loss of normal power. {emphasis added}

Per WBN System Description WB-DC-30-27, AC and DC Control Power Systems - (Unit 1 /

Unit 2), Section 6.2.1, Operating Requirements and System Capacity, the vital batteries have adequate capacity for a period of four hours, without chargers, to provide the necessary DC power to maintain both reactors at hot shutdown, assuming the loss of all AC power sources, i.e., station blackout.

TVA procedures 0-SI-215-41-A, 0-SI-215-42-B, 0-SI-215-43-A, and 0-SI-215-44-B, Diesel Generator 1A-A [1B-B, 2A-A, 2B-B] 18 Month Service Test and Battery Charger Test, provide the steps to perform a battery service test for each DG battery. Each test uses the battery discharge unit to discharge the respective DG battery for 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> at the following values:

TIME AMPERAGE TERMINAL VOLTAGE 0 to 1 minute 120 Amps With a minimum voltage of 105 VDC 1 to 29 minutes 18 Amps throughout the service test.

29 to 30 minutes 90 Amps 30 to 239 minutes 17 Amps 239 to 240 minutes 85 Amps CNL-15-094 E-13

Enclosure Responses to NRC Requests For Additional Information - Developmental Revision I Technical Specification Section 3.8 TVA procedures 0-SI-215-51-A, 0-SI-215-52-B, 0-SI-215-53-A, and 0-SI-215-54-B, Diesel Generator 1A-A [1B-B, 2A-A, 2B-B] 60 Month Performance Test and Battery Charger Test, provide the steps to perform a battery performance test for each DG battery. Each test uses the battery discharge unit to discharge the respective DG battery at a 4-hour current rate of 48 amps (corrected for temperature) until battery terminal voltage reaches the minimum design voltage of 105 VDC.

As such, the Background Section of TS Bases 3.8.4 regarding the capacity of the DG batteries is incorrect and is being changed as follows:

125 V Diesel Generator (DG) DC Electrical Power Subsystem Control power for the DGs is provided by four DG battery systems, one per DG.

Each system is comprised of a battery, a battery charger, distribution center, cabling, and cable ways. The DG 125V DC control power and field-flash circuits have power supplied from their respective 125V distribution panel. The normal supply of DC current is from the associated charger. The battery provides control and field-flash power when the charger is unavailable. The charger supplies the normal DC loads, maintains the battery in a fully charged condition, and recharges (480V AC available) the battery while supplying the required loads regardless of the status of the unit. The batteries are physically and electrically independent. The battery has sufficient capacity when fully charged to supply required loads for a minimum of 30 minutes four hours following a loss of normal power. Each battery is normally required to supply loads during the time interval between loss of normal feed to its charger and the receipt of emergency power to the charger from its respective DG.

References

1. TVA Letter to NRC, Watts Bar Nuclear Plant Unit 2 - Submittal of Developmental Revision I of the Unit 2 Technical Specification & Technical Specification Bases and Developmental Revision D of the Unit 2 Technical Requirements Manual and Technical Requirements Manual Bases, dated June 16, 2014 [ML14169A525].
2. Email from M. Miernicki (NRC) to G. Arent (TVA), TS Review Clarification RAIs 10 07 2014, dated October 8, 2014 [ML14286A029].
3. TVA Letter to NRC, Watts Bar Nuclear Plant Unit 2, Responses to Requests for Additional Information - Developmental Revision I Technical Specification Sections 3.8 and 5.7, dated February 27, 2015 [ML15064A160].
4. Email from R. Schaaf (NRC) to G. Arent (TVA), Draft of Outstanding Issues on TS Rev I Section 3.8, dated April 27, 2015.
5. Federal Register Notice dated September 1, 2011, "Notice of Availability of Proposed Models for Plant-Specific Adoption of Technical Specifications Task Force Traveler TSTF-500, Revision 2, 'DC Electrical Rewrite - Update to TSTF-360.'" [76 FR 54510]

CNL-15-094 E-14

ATTACHMENT 1 Diesel Generator Critical Trip Testing



Watts Bar Nuclear Plant Unit 1 & 2 Maintenance Instruction 0-MI-82.003 Two Year Diesel Generator Engine Inspection Revision 0002 Quality Related Level of Use: Multiple Effective Date: 02-02-2015 Responsible Organization: MMG, Mechanical Maintenance Prepared By: James Boshears Approved By: Wesley Averette

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 2 of 88 Revision Log Revision Affected or Change Effective Page Number Date Numbers Description of Revision/Change 0000 11/18/11 All Superseded MI-82.003, Revision 33 and converted to Word 2007 by PSE (RDD). Added leading 0 to instruction number.

PER 433748 Added MMTP-104 as performance reference.

Added Torquing statement to Precautions.

Deleted all references to Snug tight.

0001 01/10/13 2,4,7,25, PER 588334 Minor Editorial Change: Removed 29,87 the term snug tight from step 6.8[6] and replaced with wrench tight.

PER 498586 added micrometer to tool list, added sub steps to 7.1.2[6], added MI-82.057as a performance reference, added Appendix K.

0002 02/02/15 2,15,25, Per feedback removed inappropriate LV sign off 31,32 from Step 6.8[4]. Performed CV,LV,IV upgrade.

Changed Responsible Org from MSM to MMG.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 3 of 88 Table of Contents

1.0 INTRODUCTION

.......................................................................................................... 4

2.0 REFERENCES

............................................................................................................. 4 3.0 PRECAUTIONS AND LIMITATIONS ........................................................................... 5 4.0 PREREQUISITE ACTIONS .......................................................................................... 6 5.0 ACCEPTANCE CRITERIA ......................................................................................... 10 6.0 PERFORMANCE ........................................................................................................ 11 7.0 POST PERFORMANCE ACTIVITIES ........................................................................ 26 8.0 RECORDS .................................................................................................................. 33 Appendix A: Left Blank .................................................................................................. 34 Appendix B: Affected Component UNID Listing .......................................................... 35 Appendix C: Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A1 ........................................................................... 39 Appendix D: Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A2 ........................................................................... 45 Appendix E: Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B1 ........................................................................... 51 Appendix F: Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B2 ........................................................................... 57 Appendix G: Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A1 ........................................................................... 63 Appendix H: Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A2 ........................................................................... 69 Appendix I: Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B1 ........................................................................... 75 Appendix J: Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B2 ........................................................................... 81 Appendix K: CAMSHAFT OVERSPEED TRIP LINKAGE .............................................. 87 Source Notes............................................................................................. 88

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 4 of 88

1.0 INTRODUCTION

1.1 Purpose This Instruction provides steps for 18-24 month inspection and maintenance of Emergency Diesel Generator Engines to assure safe and reliable operation as recommended by EMD Owners Group (VTD-P318-1280).

1.2 Scope A. This Instruction may be used for each Emergency Diesel Generator Unit.

B. This Instruction performs inspection of only one engine. Performing an inspection on a complete diesel generator (D/G) unit requires two copies of this Instruction.

C. Engine numbers and affected component numbers are listed in Appendix B.

1.3 Frequency and Conditions This Instruction is to be performed every 24 months as scheduled by the Preventive Maintenance Scheduling Program.

2.0 REFERENCES

2.1 Performance References A. SOI-82 Series, System Operating Instruction - Diesel Generator.

B. 0-SI-82 Series, Monthly Diesel Generator Start and Load Test.

C. TI-27 Part III, Cleaning and Cleanness of Fluid Systems and Components.

D. NPG-SPP-18.4.7, Control of Transient Combustibles.

E. MMTP-104, Guidelines and Methodology for Assembling and Tensioning Threaded Connections.

F. MI-82.057, Diesel Generator Overspeed Limit Switch Replacement/Adjustment.

2.2 Developmental References TI-100.07, Augmented Inservice Testing Program.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 5 of 88 2.2.1 Vendor Manuals A. VTM-P318-0120, Power Systems 4750KW Diesel Generator (D/G).

B. VTM-P318-0070, Power Systems D/G Fuel Oil System.

C. VTM-P318-0010, Power Systems D/G Lube Oil System.

D. VTD-P318-1280, ESI-EMD Owners Group Recommended Maintenance Program.

2.2.2 Other N3-82-4002, Standby Diesel Generator System.

3.0 PRECAUTIONS AND LIMITATIONS A. Performance of this Instruction may require a Combustible Material Storage Permit.

B. Diesel engine rooms, with the exception of Fifth Diesel Room, are protected by a CO2 fire protection system. Personnel are to be familiar with audible and visual alarms indicating actuation of CO2 system, and be aware that 20 seconds are provided to exit area before CO2 discharges.

C. Each diesel room is a high noise level area when diesels are running.

Approved hearing protection is required in diesel room while engines are operating.

D. Do not use galvanized containers, fittings, etc. for handling lube oil. Bearings containing silver will be damaged.

E. Rubber gloves should be used when handling kerosene and diesel fuel. Ensure an operable eye wash station is available in the working area.

F. Torquing, unless stated otherwise, is to be achieved using crisscross method and in the following sequence: finger tight, 30%, 60% then 100%. The last pass is to be repeated as necessary until no further rotation of the nut or bolt is observed.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 6 of 88 Date ________

3.0 PRECAUTIONS AND LIMITATIONS (continued)

G. For the purpose of this Instruction the term "wrench tight" refers to using "skill of the craft" to tighten a fastener with a hand wrench, etc., to a degree of tightness that is acceptable to the craftsmen with no further verification. Wrench tight in this MI refers to applications excluded from MMTP-104 per Section 2.0.

The term "finger tight" refers to the tightening of a fastener, or a group of fasteners, in such a manner that brings faces together uniformly and ensures that the fastener(s) cannot be loosened by hand. When fastener preload values are required, subsequent torquing will be necessary .per MMTP-104 section 6.4.3[D], before applying the torque.

4.0 PREREQUISITE ACTIONS 4.1 Planner Actions

[1] ENSURE parts, listed in Section 4.2, and other parts that may be needed, are available and reserved.

[2] INCLUDE copy of Class E cleanliness sheets from TI-27 Part III.

[3] IF required by NPG-SPP-18.4.7, THEN INCLUDE in the WID package Transient Combustible Evaluation forms for temporary storage of oil.

[4] CONTACT the Mechanical Maint. Manager to evaluate the need for completion of just-in-time training, AND ENSURE appropriate training has been completed prior to performance of this MI.

Training required: YES NO Training completed: YES N/A (if NOT reqd)

_________________________/________

Mech. Maint. Mgr./Designee Date

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 7 of 88 Date ________

4.2 Special Tools, M&TE, Parts, and Supplies

[1] ENSURE the following tools are available as needed:

A. Combination wrench set.

B. Hoses & fittings for aftercooler testing.

C. Scraper.

D. Black light

[2] ENSURE the following M&TE is available and within its calibration due date:

DESCRIPTION MINIMUM RANGE REQUIRED ACCURACY Digital Tachometer or 1200 rpm +/- 10 rpm DG-DAQ Manometers or 0 to 10" H2O +/- 2%

Diff. Gauges (4) Differential Outside Micrometer 0 to 1 Inch +/- 0.001 Inch

[3] RECORD M&TE number and calibration due date on Work Initiating Document (WID).

NOTE TIIC numbers and P/Ns are for reference only and are subject to change.

[4] ENSURE the following parts are available:

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 8 of 88 4.2 Special Tools, M&TE, Parts, and Supplies (continued)

ITEM PART NAME PART NO. TIIC NO.

NO. (OLD P/N) 1 Filter Main lube oil elements 8345482 CDB744T 2 Gasket Main lube oil filter cover 8268756 CDT656A 3 Filter, Aux turbocharger (soakback) 8345482 CDB744T oil element 4 Filter, Turbocharger oil element 8322064 CAW782D 5 O-ring, Turbocharger oil filter check 8366436 CAW792A valve 6 O-ring, Turbo filter check valve 8280352 CAW799V 7 O-ring seal, Turbocharger oil filter 8288955 AAT621Y housing 8 Gasket, Turbo oil filter mounting to 9570677 (8366424) CAW791C camshaft oil manifold 9 Gasket, Turbo, tube assembly to 9570765 (8366345) CAW804Y filter 10 Filter, Spin on fuel element 8423132 BYV739Y 11 Gasket, Fuel filter canister 3319541 BPH679M 12 Filter, Canister priming pump fuel 33182 BRJ672J element 13 O-ring, Fuel oil priming strainer, 8343161 AAT222D shell to cover 14 O-ring, Fuel strainer cover to shell 8358905 CAT864M 15 Coupling, AC lube oil circ pump 8274508 CAY653E 16 Spider, AC lube oil circ pump 9312006 ALY973C

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 9 of 88 Date ________

4.2 Special Tools, M&TE, Parts, and Supplies (continued)

NOTE TIIC No. and procurement number (575N, etc.) of replaced parts and supplies used are to be recorded on the WID.

[5] OBTAIN supplies as listed, OR DETERMINE they are available for use:

A. Lubricant, TVA type LZD-40 (BWF997J).

B. Lubricant, MO-2.

C. Thread lubricant/anti-seize.

D. Herculite/floor covering.

E. Clean, lint-free rags.

4.3 Field Preparations

[1] WALKDOWN and ENSURE Hold Order (HO) is correctly placed.

[2] ENSURE both engines are cooled, depressurized, vented and isolated.

[3] ENSURE personnel are aware that D/G unit is in INOP condition and Technical Specifications apply.

4.4 Approvals and Notifications

[1] ENSURE SM/US is aware of work to be performed.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 10 of 88 5.0 ACCEPTANCE CRITERIA A. Specific quantitative or qualitative requirements that are intended to be verified by this test are noted in the action steps with (Acc Crit:) where the verifying action is performed and recorded.

B. Identified adverse conditions and deficiencies in Instruction acceptance criteria will be documented in Work Initiating Document (WID), a WR will be initiated and System Engineer is to be contacted for tracking D/G unavailability, as soon as practical to repair/replace defective components. WR number should be included in WID.

C. Unless otherwise stated, steps may be worked out of sequence or repeated, provided:

1. No prerequisite requirements are violated.
2. No required inspections or verifications are bypassed.

D. Steps which are not applicable may be NA'd with the approval of the Foreman or Responsible Engineer.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 11 of 88 Date ________

6.0 PERFORMANCE GENERAL ENGINE LAYOUT Figure 6.0 NOTES

1) North engine is right hand rotation and south engine is left hand rotation.
2) Refer to Appendix B for a listing of the affected components worked by this instruction.
3) The term "Finger tight" refers to the tightening of a fastener, or a group of fasteners, in such a manner that brings faces together uniformly and ensures that the fastener(s) cannot be loosened by hand. When fastener preload values are required, subsequent torquing will be necessary.

6.1 General

[1] ENSURE precautions and limitations in Section 3.0 have been reviewed.

Initials Date

[2] ENSURE prerequisite actions in Section 4.0 have been met.

Initials Date

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 12 of 88 Date ________

6.1 General (continued)

[3] IDENTIFY and VERIFY proper D/G engine UNID, to be serviced, as specified on the WID.

Initials Date CV Date

[4] RECORD indicated time shown on D/G hour meter mounted in control cabinet:

Indicated hour meter time: ________hr.

Initials Date CAUTION Do not use galvanized containers, fittings, etc. for pumping or storing oil.

[5] VERIFY Class E cleanliness of containers and equipment used for oil, AND DOCUMENT on TI-27 Part III cleanliness data sheet.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 13 of 88 Date ________

6.2 Main Lube Oil Filter Element Replacement NOTE Main lube oil filter is illustrated in Figure 6-1A.

[1] REMOVE square cover from engine mounted lube oil strainer housing (Figure 6-1B).

[2] RAISE and LATCH gate valve handles in the engine strainer housing, AND ALLOW time to drain oil from main lube oil filter housing and oil strainer into engine sump.

MAIN LUBE OIL FILTER Figure 6-1A

[3] LOOSEN nuts on main lube oil filter housing cover allowing remaining oil to leak into drain trough.

[4] SWING hinge bolts clear of housing cover.

[5] OPEN filter housing cover.

[6] REMOVE each of the seven used filter elements,

[7] CONTACT System Engineer for inspection and evaluation of filter element(s) condition, AND PLACE into double bagged trash bags for disposal.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 14 of 88 Date ________

6.2 Main Lube Oil Filter Element Replacement (continued)

LUBE OIL STRAINER Figure 6-1B

[8] CLEAN filter housing, as needed, with clean rags and approved solvent, AND INSPECT housing to Class E cleanliness criteria, THEN DOCUMENT on TI-27, Part III cleanliness data sheet.

[9] INSTALL seven new filter elements.

[10] ENSURE filter elements are fully seated over standpipes.

[11] INSPECT filter housing cover gasket.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 15 of 88 Date ________

6.2 Main Lube Oil Filter Element Replacement (continued)

[12] IF gasket is unacceptable, THEN REPLACE gasket.

[13] ENSURE guide hole in filter housing cover mates with dowel on the filter housing, AND CLOSE cover.

[14] SWING hinge bolts into place, THEN TORQUE nuts to 60 ft-lbs, AND RECORD M&TE ID No.:_____________________.

Initials Date LV Date

[15] CLOSE filter drain gate valve at lube oil strainer.

Initials Date IV Date

[16] DOCUMENT completion of this section.

Initials Date

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 16 of 88 Date ________

6.3 Auxiliary Turbocharger (Soakback) Oil Filter Replacement

[1] LOOSEN two flange nuts holding cover to filter housing.

SOAKBACK OIL FILTER Figure 6-2

[2] ROTATE cover counterclockwise, AND LIFT cover off of container.

[3] REMOVE used filter element.

[4] REMOVE drain plug if accessible and drain oil, THEN VACUUM oil from canister if plug is NOT removed.

[5] CONTACT Responsible Engineer for inspection and evaluation of filter element(s) condition, AND PLACE into double bagged trash bags for disposal.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 17 of 88 Date ________

6.3 Auxiliary Turbocharger (Soakback) Oil Filter Replacement (continued)

[6] CLEAN filter housing, as needed, with approved solvent and lint free rags.

[7] VERIFY Class E cleanliness, AND DOCUMENT on TI-27 Part III cleanliness data sheet.

[8] INSTALL drain plug if removed.

[9] INSTALL new paper element and cover O-ring.

[10] INSTALL cover assembly, AND TIGHTEN nuts Wrench tight.

[11] DOCUMENT completion of this section.

Initials Date

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 18 of 88 Date ________

6.4 Turbocharger Oil Filter Replacement

[1] LOOSEN two flange bolts and nuts, AND ROTATE container to disengage from upper housing.

[2] REMOVE used filter element, THEN CONTACT System Engineer for inspection and evaluation of filter element condition, AND PLACE into double bagged trash bags for disposal.

TURBOCHARGER OIL FILTER Figure 6-3

[3] CLEAN filter housing, as needed, with approved solvent and lint free rags.

[4] INSTALL new paper element.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 19 of 88 Date ________

6.4 Turbocharger Oil Filter Replacement (continued)

[5] REPLACE check valve O-rings, THEN INSPECT both filter check valves inside housing, AND ENSURE proper operation by freedom of movement check.

[6] FILL container with TVA LZD-40 oil.

[7] INSTALL new cover seal, AND POSITION container in upper housing.

[8] VERIFY Class E cleanliness, AND DOCUMENT on TI-27 Part III cleanliness data sheet.

[9] TIGHTEN flange bolts and nuts wrench tight.

[10] DOCUMENT completion of this section.

Initials Date 6.5 Fuel Filter Replacement 6.5.1 Engine Driven Spin-On Filter Replacement NOTE Both fuel filter elements may be removed and changed simultaneously.

[1] UNSCREW twin spin-on fuel filter elements, and PLACE into double bagged trash bags for disposal, THEN DISPOSE of fuel oil into waste oil drum. Element

  1. 1 #2

[2] CLEAN filter housing mount, as needed, with approved solvent and lint free rags.

[3] VERIFY class E cleanliness and DOCUMENT on TI-27 Part III cleanliness data sheet.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 20 of 88 Date ________

6.5.1 Engine Driven Spin-On Filter Replacement (continued)

NOTE Filter element should be tightened by hand until gasket contacts filter body and then turned an additional one-half turn.

[4] APPLY a thin film of fuel oil to gasket, AND FILL filters with diesel fuel, THEN INSTALL new filter oil elements on filter housing. Element

  1. 1 #2 6.5.2 Motor Driven Canister-type Fuel Oil Filter Element Replacement Figure 6-4

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 21 of 88 Date ________

6.5.2 Motor Driven Canister-type Fuel Oil Filter Element Replacement (continued)

NOTE Both fuel filter elements may be removed and changed simultaneously.

[1] LOOSEN and REMOVE filter housing. Element

  1. 1 #2

[2] REMOVE housing with filter element from filter head.

  1. 1 #2

[3] REMOVE used filter element, AND DISPOSE of used filter.

  1. 1 #2

[4] CLEAN filter housing, as needed, with approved solvent and lint free rags.

  1. 1 #2

[5] VERIFY class E cleanliness, AND DOCUMENT on TI-27 Part III cleanliness data sheet.

[6] INSTALL new O-ring into housing.

  1. 1 #2

[7] INSTALL new filter element after filling with clean fuel oil.

  1. 1 #2

[8] INSTALL housing to filter head with retaining nuts, AND TIGHTEN retaining nuts wrench tight.

  1. 1 #2

[9] DOCUMENT completion of this section.

___________/________

Date

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 22 of 88 Date ________

6.6 Fuel Oil Suction Strainer Cleaning NOTES

1) Fuel oil suction strainers are illustrated in Figure 6-5.
2) Both fuel filter elements may be removed and changed simultaneously.

[1] REMOVE shell from cover.

DC MOTOR PRIMING PUMP STRAINER A ENGINE DRIVEN PUMP STRAINER B

[2] REMOVE mesh strainer element from shell, AND DISCARD sediment into waste oil container.

DC MOTOR PRIMING PUMP STRAINER A ENGINE DRIVEN PUMP STRAINER B

[3] CLEAN mesh element, as needed, with approved solvent and lint free rags, AND VERIFY class E cleanliness.

[4] DOCUMENT on TI-27 Part III cleanliness data sheet, OR OBTAIN and REPLACE new mesh element as required REPLACED A. DC Motor Priming Pump Strainer Element Yes No B. Engine Driven Pump Strainer Element Yes No

[5] CLEAN filter shell thoroughly with approved solvent, AND WIPE clean with lint free rags, as needed.

DC MOTOR PRIMING PUMP STRAINER A ENGINE DRIVEN PUMP STRAINER B

[6] VERIFY class E cleanliness, AND DOCUMENT on TI-27 Part III cleanliness data sheet.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 23 of 88 Date ________

6.6 Fuel Oil Suction Strainer Cleaning (continued)

FUEL OIL SUCTION STRAINER Figure 6-5

[7] INSPECT cover O-rings visually for nicks or damage.

DC MOTOR PRIMING PUMP STRAINER A ENGINE DRIVEN PUMP STRAINER B

[8] IF cover O-rings are defective, THEN REPLACE O-rings as required.

DC MOTOR PRIMING PUMP STRAINER A ENGINE DRIVEN PUMP STRAINER B

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 24 of 88 Date ________

6.6 Fuel Oil Suction Strainer Cleaning (continued)

[9] INSERT cleaned or new strainer elements in shell, AND FILL shell with diesel fuel.

DC MOTOR PRIMING PUMP STRAINER A ENGINE DRIVEN PUMP STRAINER B

[10] ATTACH shell to strainer cover.

DC MOTOR PRIMING PUMP STRAINER A ENGINE DRIVEN PUMP STRAINER B

[11] ENSURE O-ring is properly seated, AND TIGHTEN shell wrench tight.

DC MOTOR PRIMING PUMP STRAINER A ENGINE DRIVEN PUMP STRAINER B

[12] DOCUMENT completion of this section.

Initials Date 6.7 Intake Air Filter Inspection

[1] REMOVE reservoir cover.

[2] INSPECT oil with use of light to identify any foreign material.

[3] INSPECT accessible area for defects.

[4] FILL reservoir housing with MO-2 oil to indicator on sight glass, AND VERIFY proper level reached in bullseye sight glass.

Initials Date

[5] INSTALL reservoir cover.

[6] DOCUMENT completion of this section.

Initials Date

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 25 of 88 Date ________

6.8 Six GPM AC Lube Oil Circulation Pump Inspection1

[1] REMOVE coupling cover, AND INSPECT coupling spider for wear and damage.

[2] IF coupling maintenance is required, THEN REPLACE spider or coupling.

NOTE Axial reading is the clearance between the pump and motor coupling halves. The pump and motor need to be bolted in place and the motor armature pulled toward the pump shaft, to its furthest position, before actual reading is taken. All valves and piping should be installed before performing pump to motor alignment.

[3] CHECK axial clearance between coupling halves with shafts in closest position, AND SET at 1/16 to 1/8 in.

[4] CHECK parallel alignment, at 90° intervals, AND ADJUST until the readings are within 0.002 in., THEN CHECK angular alignment, at 90° intervals, AND ADJUST until the readings are within 0.002 in.

Initials Date

[5] INSPECT for pump seal leakage.

[6] INSTALL coupling cover wrench tight with bolting.

[7] DOCUMENT completion of this section.

Initials Date

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 26 of 88 Date ________

7.0 POST PERFORMANCE ACTIVITIES 7.1 Testing 7.1.1 Prestart Check

[1] REQUEST Operations to trip AC auxiliary lube oil pump breaker, AND VERIFY operation of DC auxiliary lube oil pump with (Acc Crit:) greater than 10 psig is indicated on lube oil header pressure gauge.

Initials Date

[2] CHECK engine oil sump level, AND ADD LZD-40 oil to strainer housing as needed to bring level to approximately 1 above full mark on dipstick.

[3] CHECK oil level in strainer housing, AND ADD LZD-40 oil as required until oil overflows the internal dams.

[4] REQUEST Operations to CLOSE breaker for AC auxiliary lube oil pump, AND VERIFY operation of AC pump and trip of back-up DC pump with (Acc Crit:) greater than 10 psig is indicated on lube oil header pressure gauge.

Initials Date

[5] REQUEST Operations to start fuel oil priming pump, AND VERIFY no external leaks.

Initials Date

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 27 of 88 Date ________

7.1.1 Prestart Check (continued)

[6] PERFORM top deck inspection for fuel oil leaks with the fuel oil priming pump running. Black light may be used.

Initials Date

[7] ENSURE lube oil is NOT detected coming from the camshaft bearings with the turbocharger AC auxiliary lube oil circulating pump running.

[8] ENSURE top deck covers are closed.

7.1.2 Diesel Generator Drag Start, Overspeed Trip Test & Aftercooler Differential Pressure Testing

[1] PERFORM the appropriate APPENDIX for the engine being inspected:

APPENDIX C: 1-DIEG-82-A1 APPENDIX G: 2-DIEG-82-A1 APPENDIX D: 1-DIEG-82-A2 APPENDIX H: 2-DIEG-82-A2 APPENDIX E: 1-DIEG-82-B1 APPENDIX I: 2-DIEG-82-B1 APPENDIX F: 1-DIEG-82-B2 APPENDIX J: 2-DIEG-82-B2

[2] DOCUMENT Appendix performed.

Appendix________

Initials Date

[3] ENSURE overspeed trip mechanism of opposite engine is held in LATCHED position.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 28 of 88 Date ________

7.1.2 Diesel Generator Drag Start, Overspeed Trip Test & Aftercooler Differential Pressure Testing (continued)

CAUTION Diesel engine should not be run above 1100 rpm to avoid possible engine damage.

NOTE Communication must be established between individual controlling the fuel rack (performer of overspeed trip test) and individual monitoring the engine rpm.

[4] DESIGNATE someone to MONITOR engine rpm on the control panel and to SIGNAL performer if engine speed exceeds 1100 rpm.4

[5] OBSERVE engine speed with digital tachometer or DG-DAQ, AND INCREASE speed of diesel engine manually with fuel injection linkage UNTIL engine trips, THEN RECORD speed of engine at time of trip.

Setpoint: 1040 rpm (Acc Crit: 1035 to 1050 rpm)

(N/A engine NOT tested).

A. Engine 1 (South) Speed at Trip (as-found)_________rpm B. Engine 2 (North) Speed at Trip (as-found)_________rpm C. M&TE ID No: __________________

Initials Date CV Date

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 29 of 88 Date ________

7.1.2 Diesel Generator Drag Start, Overspeed Trip Test & Aftercooler Differential Pressure Testing (continued)

[6] IF engine tripped at desired rpm setting, THEN

[6.1] ENSURE a minimum of 1/4 inch overtravel of limit switch lever arm as follows (See Appendix K for information):

A. PUSH the limit switch lever arm in the trip direction UNTIL resistance is met. ________

B. MEASURE the overtravel. ________

C. IF 1/4 inch overtravel is not met, THEN PERFORM adjustment using MI-82.057 (Will require a Minor Maintenance WO). ________

[6.2] RESET the mechanical overspeed lever, AND VERIFY the limit switch resets and the overspeed trip annunciation on the Diesel Engine Control Panel reset. ________

[6.3] VERIFY the Unit Lockout annunciators on the Diesel Engine control panel are LIT, AND RESET annunciators using Reset and Unit Lockout Reset pushbutton. ________

[6.4] RESET the overspeed trip annunciation on 0-M-26 using Reset pushbutton. ________

[6.5] MANUALLY RAISE and LOWER the engine overspeed trip lever up and down by hand, AND VERIFY the Overspeed Trip and Unit Lockout annunciators on the Diesel Engine control panel do NOT alarm. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 30 of 88 Date ________

7.1.2 Diesel Generator Drag Start, Overspeed Trip Test & Aftercooler Differential Pressure Testing (continued)

NOTES

1) Loosening trip spring pressure will decrease trip speed.
2) Several adjustments may be required to reach acceptable trip speed.

[7] IF engine did NOT trip at acceptable rpm, THEN PERFORM overspeed trip adjustment as follows:

A. ENSURE diesel engine has reached FULL STOP.

B. REMOVE right cover from overspeed trip housing, AND ADJUST overspeed mechanism to desired setting.

C. INSPECT cover gasket for damage, AND REPLACE gasket as necessary.

D. INSTALL cover and gasket with bolting wrench tight.

[8] REQUEST OPS to START engine, AND REPEAT Steps 7.1.2[3] through 7.1.2[7] as required.

[9] WHEN engine trips at desired rpm setpoint, THEN RECORD speed of engine at time of trip.

North Engine Speed at Trip (as-left)_________rpm Initials Date South Engine Speed at Trip (as-left)_________rpm Initials Date

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 31 of 88 Date ________

7.1.2 Diesel Generator Drag Start, Overspeed Trip Test & Aftercooler Differential Pressure Testing (continued)

[10] TORQUE overspeed cover bolting in crisscross pattern, AND VERIFY bolting is torqued to 30 ft-lbs, THEN RECORD M&TE ID No.:____________________

Initials Date LV Date CAUTION Engine should not be running in excess of idle speed (450 rpm) while installing differential pressure instrument into ductwork.

[11] LOOSEN and REMOVE a bolt at direction of Test Director (fifth is preferred) from top on each side of each (2) aftercooler unit on engine.

NOTE The Low pressure side of aftercooler is the side nearest the engine. Other side is HIGH pressure side.

[12] INSTALL differential pressure instruments into both sides of left aftercooler through housing bolt holes removed in previous step.

[13] INSTALL differential pressure instruments into both sides of right aftercooler through housing bolt holes removed in Step 7.1.2[11].

[14] VERIFY DG is at operating speed (900 rpm).

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 32 of 88 Date ________

7.1.2 Diesel Generator Drag Start, Overspeed Trip Test & Aftercooler Differential Pressure Testing (continued)

[15] RECORD differential pressure across aftercoolers, AND ENSURE differential pressure across each aftercooler is less than or equal to (Acc Crit:) 10 in. H2O:

A. Left Aftercooler Differential Press: _________in. H2O.

B. Right Aftercooler Differential Press: ________in. H2O.

M&TE ID No. A. ________________________

B. ________________________

Initials Date

[16] CHECK lube oil pumps and piping where disassembled to identify any leaks.

Initials Date

[17] CHECK all filters and strainers where disassembled to identify any leaks.

Initials Date

[18] REQUEST Operations to shutdown diesel generator unit.

[19] REMOVE differential pressure instruments, AND INSTALL and TORQUE aftercooler housing bolting to 45 ft-lbs, AND RECORD M&TE ID No._____________________

Initials Date LV Date

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 33 of 88 Date ________

7.2 Restoration

[1] ENSURE tools and materials are removed and work area is clean.

Initials Date

[2] VERIFY satisfactory completion of post performance activities Initials Date

[3] REQUEST Operations to realign diesel generator system for normal standby mode.

Initials Date 8.0 RECORDS 8.1 QA Records The Data Package is a QA record, is handled in accordance with the Document Control and Records Management Program, and contains the following:

A. Completed parts of Sections 4.0, 6.0 and 7.0.

B. Material Procurement Documents.

C. Other sheets added during the performance.

8.2 Non-QA Records None

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 34 of 88 Appendix A (Page 1 of 1)

Left Blank This page left blank to maintain numbering of Appendixes C thru J that are referenced in 0-MI-82.005, 0-MI-82.006 & 0-MI-82.078.

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 35 of 88 Appendix B (Page 1 of 4)

Affected Component UNID Listing GENERATOR 1A-A 1-GEN-082-0001A DIESEL GENERATOR 1A-A 1-DIEG-082-A1 DIESEL GENERATOR ENGINE 1A1 1-DIEG-082-A2 DIESEL GENERATOR ENGINE 1A2 1-FLTR-082-0706A1 ENG 1A1 LUBE OIL FILTER 1-FLTR-082-0706A2 ENG 1A2 LUBE OIL FILTER 1-FLTR-082-0709A1 ENG 1A1 TURBO LUBE OIL FILTER 1-FLTR-082-0709A2 ENG 1A2 TURBO LUBE OIL FILTER 1-FLTR-082-0710A1 ENG 1A1 TURBO SOAKBACK OIL FILTER 1-FLTR-082-0710A2 ENG 1A2 TURBO SOAKBACK OIL FILTER 1-FLTR-018-0066/1A ENG 1A1 ENGINE DRIVEN FUEL PUMP FILTER 1-FLTR-018-0081/1A ENG 1A2 ENGINE DRIVEN FUEL PUMP FILTER 1-FLTR-018-0066/1B ENG 1A1 MOTOR DRIVEN FUEL PUMP FILTER 1-FLTR-018-0081/1B ENG 1A2 MOTOR DRIVEN FUEL PUMP FILTER 1-STN-018-0029/1 ENG 1A1 FUEL OIL PRIMING PUMP STRAINER 1-STN-018-0059/1 ENG 1A2 FUEL OIL PRIMING PUMP STRAINER 1-STN-018-0065/1 ENG 1A1 FUEL OIL PUMP STRAINER 1-STN-018-0080/1 ENG 1A2 FUEL OIL PUMP STRAINER 1-IACL-082-0101 ENG 1A1 INTAKE AIR CLEANER 1-IACL-082-0102 ENG 1A2 INTAKE AIR CLEANER 1-PMP-082-A1 ENG 1A1 LUBE OIL CIRC PUMP 1-PMP-082-A2 ENG 1A2 LUBE OIL CIRC PUMP

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 36 of 88 Appendix B (Page 2 of 4)

Affected Component UNID Listing GENERATOR 1B-B 1-GEN-082-0001B DIESEL GENERATOR 1B-B 1-DIEG-082-B1 DIESEL GENERATOR ENGINE 1B1 1-DIEG-082-B2 DIESEL GENERATOR ENGINE 1B2 1-FLTR-082-0706B1 ENG 1B1 LUBE OIL FILTER 1-FLTR-082-0706B2 ENG 1B2 LUBE OIL FILTER 1-FLTR-082-0709B1 ENG 1B1 TURBO LUBE OIL FILTER 1-FLTR-082-0709B2 ENG 1B2 TURBO LUBE OIL FILTER 1-FLTR-082-0710B1 ENG 1B1 TURBO SOAKBACK OIL FILTER 1-FLTR-082-0710B2 ENG 1B2 TURBO SOAKBACK OIL FILTER 1-FLTR-018-0066/2A ENG 1B1 ENGINE DRIVEN FUEL PUMP FILTER 1-FLTR-018-0081/2A ENG 1B2 ENGINE DRIVEN FUEL PUMP FILTER 1-FLTR-018-0066/2B ENG 1B1 MOTOR DRIVEN FUEL PUMP FILTER 1-FLTR-018-0081/2B ENG 1B2 MOTOR DRIVEN FUEL PUMP FILTER 1-STN-018-0029/2 ENG 1B1 FUEL OIL PRIMING PUMP STRAINER 1-STN-018-0059/2 ENG 1B2 FUEL OIL PRIMING PUMP STRAINER 1-STN-018-0065/2 ENG 1B1 FUEL OIL PUMP STRAINER 1-STN-018-0080/2 ENG 1B2 FUEL OIL PUMP STRAINER 1-IACL-082-0103 ENG 1B1 INTAKE AIR CLEANER 1-IACL-082-0104 ENG 1B2 INTAKE AIR CLEANER 1-PMP-082-B1 ENG 1B1 LUBE OIL CIRC PUMP 1-PMP-082-B2 ENG 1B2 LUBE OIL CIRC PUMP

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 37 of 88 Appendix B (Page 3 of 4)

Affected Component UNID Listing GENERATOR 2A-A 2-GEN-082-0001A DIESEL GENERATOR 2A-A 2-DIEG-082-A1 DIESEL GENERATOR ENGINE 2A1 2-DIEG-082-A2 DIESEL GENERATOR ENGINE 2A2 2-FLTR-082-0706A1 ENG 2A1 LUBE OIL FILTER 2-FLTR-082-0706A2 ENG 2A2 LUBE OIL FILTER 2-FLTR-082-0709A1 ENG 2A1 TURBO LUBE OIL FILTER 2-FLTR-082-0709A2 ENG 2A2 TURBO LUBE OIL FILTER 2-FLTR-082-0710A1 ENG 2A1 TURBO SOAKBACK OIL FILTER 2-FLTR-082-0710A2 ENG 2A2 TURBO SOAKBACK OIL FILTER 2-FLTR-018-0066/3A ENG 2A1 ENGINE DRIVEN FUEL PUMP FILTER 2-FLTR-018-0081/3A ENG 2A2 ENGINE DRIVEN FUEL PUMP FILTER 2-FLTR-018-0066/3B ENG 2A1 MOTOR DRIVEN FUEL PUMP FILTER 2-FLTR-018-0081/3B ENG 2A2 MOTOR DRIVEN FUEL PUMP FILTER 2-STN-018-0029/3 ENG 2A1 FUEL OIL PRIMIMG PUMP STRAINER 2-STN-018-0059/3 ENG 2A2 FUEL OIL PRIMIMG PUMP STRAINER 2-STN-018-0065/3 ENG 2A1 FUEL OIL PUMP STRAINER 2-STN-018-0080/3 ENG 2A2 FUEL OIL PUMP STRAINER 2-IACL-082-0201 ENG 2A1 INTAKE AIR CLEANER 2-IACL-082-0202 ENG 2A2 INTAKE AIR CLEANER 2-PMP-082-A1 ENG 2A1 LUBE OIL CIRC PUMP 2-PMP-082-A2 ENG 2A2 LUBE OIL CIRC PUMP

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 38 of 88 Appendix B (Page 4 of 4)

Affected Component UNID Listing GENERATOR 2B-B 2-GEN-082-0001B DIESEL GENERATOR 2B-B 2-DIEG-082-B1 DIESEL GENERATOR ENGINE 2B1 2-DIEG-082-B2 DIESEL GENERATOR ENGINE 2B2 2-FLTR-082-0706B1 ENG 2B1 LUBE OIL FILTER 2-FLTR-082-0706B2 ENG 2B2 LUBE OIL FILTER 2-FLTR-082-0709B1 ENG 2B1 TURBO LUBE OIL FILTER 2-FLTR-082-0709B2 ENG 2B2 TURBO LUBE OIL FILTER 2-FLTR-082-0710B1 ENG 2B1 TURBO SOAKBACK OIL FILTER 2-FLTR-082-0710B2 ENG 2B2 TURBO SOAKBACK OIL FILTER 2-FLTR-018-0066/4A ENG 2B1 ENGINE DRIVEN FUEL PUMP FILTER 2-FLTR-018-0081/4A ENG 2B2 ENGINE DRIVEN FUEL PUMP FILTER 2-FLTR-018-0066/4B ENG 2B1 MOTOR DRIVEN FUEL PUMP FILTER 2-FLTR-018-0081/4B ENG 2B2 MOTOR DRIVEN FUEL PUMP FILTER 2-STN-018-0029/4 ENG 2B1 FUEL OIL PRIMING PUMP STRAINER 2-STN-018-0059/4 ENG 2B2 FUEL OIL PRIMING PUMP STRAINER 2-STN-018-0065/4 ENG 2B1 FUEL OIL PUMP STRAINER 2-STN-018-0080/4 ENG 2B2 FUEL OIL PUMP STRAINER 2-IACL-082-0203 ENG 2B1 INTAKE AIR CLEANER 2-IACL-082-0204 ENG 2B2 INTAKE AIR CLEANER 2-PMP-082-B1 ENG 2B1 LUBE OIL CIRC PUMP 2-PMP-082-B2 ENG 2B2 LUBE OIL CIRC PUMP

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 39 of 88 Appendix C (Page 1 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A1 Date ________

1.0 DG DRAG START TEST Perform this Appendix when inspecting Engine 1A1 to isolate Engine 1A1 starting air system to allow starting both engines with Engine 1A2 air start motors and verifying voltage and frequency of generator..

ACCEPTANCE CRITERIA: Diesel generator started with one engines air start motors (4) isolated and achieved voltage > 6800V and frequency > 58.8 Hz in

< 10 seconds.

Test Equipment Setup NOTES

1) Install equipment for testing engine overspeed trip device and aftercooler assembly as required.
2) The DG-DAQ is installed at the DG Protection Panel.
3) The System Engineer may assist in DG-DAQ setup.

[1] CONFIGURE PK test blocks for TB1- All jumpers INSTALLED and all thumb nuts WRENCH TIGHT. ________

NOTE Black is positive and white is negative.

[2] CONNECT DG-DAQ Channel 0 black wire to Terminal 2 of the PK test block for TB1 and the white wire to Terminal 4 of the PK test block for TB1, AND INSERT PK test block into TB1. ________

NOTE The current probe should be zeroed prior to connecting to the ES1AY relay.

[3] ZERO the current probe indication. ________

[4] PUT Start signal into DG-DAQ Channel 2, using clamp-on probe around coil wire 11 or 12 of relay ES1AY. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 40 of 88 Appendix C (Page 2 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A1 Date ________

1.0 DG DRAG START TEST (continued)

[5] TURN ON the DG-DAQ. ________

[6] TURN ON the SCXI box. ________

[7] SETUP DG-DAQ Channel 0 for an input of +212 to -212 V dc and multiplication factor of 60.0 ________

CV

[8] SETUP DG-DAQ Channel 2 for an input of +0.1 to -0.1 V dc and multiplication factor of 1.0 ________

CV CAUTION If the valves in the Table 1A1 are not configured in the order given, an alarm initiation is possible.

[9] IMPLEMENT configuration changes in TABLE 1A1 in the sequence listed (top-to-bottom), AND DOCUMENT performance. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 41 of 88 Appendix C (Page 3 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A1 Date ________

1.0 DG DRAG START TEST (continued)

TABLE 1A1 VERIFICATIONS CONFIGURATION RETURN TO NORMAL CHANGE CONFIGURATION CV AFFECTED CHANGE OPS/ PARTY/ OPS/ IV/

COMPONENT DESCRIPTION DATE DATE DATE DATE 1-ISV-82-517A1-A UNLOCK and CLOSE 1-ISV-82-525A1-A UNLOCK and CLOSE 1-ISV-82-520A1-A UNLOCK and CLOSE 1-ISV-82-528A1-A UNLOCK and CLOSE 1-LOV-82-518A1-A OPEN 1-LOV-82-526A1-A OPEN

[10] MANUALLY ACTUATE each of the following solenoid valves by LIFTING the T handle to VENT residual downstream air pressure, THEN RELEASE T handle:

1-FSV-82-160, AIR START SOL VLV ENG 1A1 ________

1-FSV-82-170, AIR START SOL VLV ENG 1A1 ________

[11] PLACE 1-HS-57-47, DG SYNC SWITCH [0-M-26], in SYN. ________

[12] NOTIFY UO that DG will be starting.

[13] ENSURE personnel are in communication to time interval from DG start initiation UNTIL required voltage and frequency are obtained. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 42 of 88 Appendix C (Page 4 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A1 Date ________

1.0 DG DRAG START TEST (continued)

[14] DISPATCH personnel to MONITOR engine 1A1 and 1A2 air start motors during diesel start. ________

[15] START recorder. ________

[16] PROCEED with countdown sequence of 3, 2, 1, START, THEN PRESS 1-HS-82-16A, EMERGENCY START [0-M-26], to initiate DG start. ________

[17] RECORD Time of engine start.

Time:____________ ________

[18] MONITOR 1-EI-82-4, INCOMING VOLTAGE, AND 1-XI-82-2, INCOMING FREQUENCY [0-M-26]. ________

[19] WHEN volts and Frequency are stable, THEN STOP recorder. ________

[20] RECORD from recorder, the Time required for voltage to reach 6800V, and frequency 58.8 Hz.

Time: __________ Seconds __________ ________

[21] VERIFY from recorder that DG voltage was at least 6800V with frequency at least 58.8 Hz within 10 seconds from DG start. (Acc Crit) ________

[22] VERIFY air start motors (4) pinions NOT ENGAGED with flywheel during startup.

A. Engine 1A1 left bank air start motors. ________

B. Engine 1A1 right bank air start motors. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 43 of 88 Appendix C (Page 5 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A1 Date ________

1.0 DG DRAG START TEST (continued)

[23] VERIFY air start motors (4) pinions ENGAGED with flywheel during startup, THEN DISENGAGE.

A. Engine 1A2 left bank air start motors. ________

B. Engine 1A2 right bank air start motors. ________

CAUTION 86 LOR relay cannot be reset if Red light above 86 LOR, is lit.

[24] RESET 1-RLY-82-86LOR1, DG 1A-A EMERGENCY START LOCKOUT [1-ARB-82-A/1]. ________

[25] ENSURE ES1AY Amber light is LIT [1-PNL-211-A-A]. ________

[26] PLACE 1-HS-57-47, DG SYNC switch [0-M-26] in OFF, AND ________

IF overspeed trip test is to be performed, THEN PERFORM Section 7.1.2 of this MI, OR PERFORM Section 7.1.3 of applicable MI. ________

[27] SHUT DOWN DG in accordance with SOI-82.01. ________

[28] RETURN components in Table 1A1 to normal configuration using the reverse sequence (bottom-to-top), AND DOCUMENT performance. ________

[29] TURN OFF the DG-DAQ computer. ________

[30] TURN OFF the SCXI box. ________

[31] TURN OFF the current probe box. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 44 of 88 Appendix C (Page 6 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A1 Date ________

1.0 DG DRAG START TEST (continued)

[32] REMOVE the PK test block from TB1, AND REINSTALL the cover. ________

IV

[33] REMOVE the current probe from the wire at ES1AY relay. ________

[34] NOTIFY SRO/Test Director that the DG-DAQ has been removed from the DG control circuits. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 45 of 88 Appendix D (Page 1 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A2 Date ________

1.0 DG DRAG START TEST Perform this Appendix when inspecting Engine 1A2 to isolate Engine 1A2 starting air system to allow starting both engines with Engine 1A1 air start motors and verifying voltage and frequency of generator..

ACCEPTANCE CRITERIA: Diesel generator started with one engines air start motors (4) isolated and achieved voltage > 6800V and frequency > 58.8 Hz in

< 10 seconds.

Test Equipment Setup NOTES

1) Install equipment for testing engine overspeed trip device and aftercooler assembly as required.
2) The DG-DAQ is installed at the DG Protection Panel.
3) The System Engineer may assist in DG-DAQ setup.

[1] CONFIGURE PK test blocks for TB1- All jumpers INSTALLED and all thumb nuts WRENCH TIGHT. ________

NOTE Black is positive and white is negative.

[2] CONNECT DG-DAQ Channel 0 black wire to Terminal 2 of the PK test block for TB1 and the white wire to Terminal 4 of the PK test block for TB1, AND INSERT PK test block into TB1. ________

NOTE The current probe should be zeroed prior to connecting to the ES1AY relay.

[3] ZERO the current probe indication. ________

[4] PUT Start signal into DG-DAQ Channel 2, using clamp-on probe around coil wire 11 or 12 of relay ES1AY. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 46 of 88 Appendix D (Page 2 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A2 Date ________

1.0 DG DRAG START TEST (continued)

[5] TURN ON the DG-DAQ. ________

[6] TURN ON the SCXI box. ________

[7] SETUP DG-DAQ Channel 0 for an input of +212 to -212 V dc and multiplication factor of 60.0 ________

CV

[8] SETUP DG-DAQ Channel 2 for an input of +0.1 to -0.1 V dc and multiplication factor of 1.0 ________

CV CAUTION If the valves in the Table 1A2 are not configured in the order given, an alarm initiation is possible.

[9] IMPLEMENT configuration changes in TABLE 1A2 in the sequence listed (top-to-bottom), AND DOCUMENT performance. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 47 of 88 Appendix D (Page 3 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A2 Date ________

1.0 DG DRAG START TEST (continued)

TABLE 1A22 VERIFICATIONS CONFIGURATION RETURN TO NORMAL CHANGE CONFIGURATION AFFECTED CHANGE OPS/ CV OPS/ IV/

COMPONENT DESCRIPTION DATE DATE DATE DATE 1-ISV-82-551A2-A UNLOCK and CLOSE 1-ISV-82-559A2-A UNLOCK and CLOSE 1-ISV-82-554A2-A UNLOCK and CLOSE 1-ISV-82-562A2-A UNLOCK and CLOSE 1-LOV-82-552A2-A OPEN 1-LOV-82-560A2-A OPEN

[10] MANUALLY ACTUATE each of the following solenoid valves by LIFTING the T handle to VENT residual downstream air pressure, THEN RELEASE T handle:

1-FSV-82-161, AIR START SOL VLV ENG 1A2 ________

1-FSV-82-171, AIR START SOL VLV ENG 1A2 ________

[11] PLACE 1-HS-57-47, DG SYNC SWITCH [0-M-26], in SYN. ________

[12] NOTIFY UO that DG will be starting,

[13] ENSURE personnel are in communication to time interval from DG start initiation UNTIL required voltage and frequency are obtained. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 48 of 88 Appendix D (Page 4 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A2 Date ________

1.0 DG DRAG START TEST (continued)

[14] DISPATCH personnel to monitor engine 1A1 and 1A2 air start motors during diesel start. ________

[15] START recorder. ________

[16] PROCEED with countdown sequence of 3, 2, 1, START, THEN PRESS 1-HS-82-16A, EMERGENCY START [0-M-26], to initiate DG start. ________

[17] RECORD Time of engine start.

Time:____________ ________

[18] MONITOR 1-EI-82-4, INCOMING VOLTAGE, AND 1-XI-82-2, INCOMING FREQUENCY [0-M-26]. ________

[19] WHEN volts and Frequency are stable, THEN STOP recorder. ________

[20] RECORD from recorder, the Time required for voltage to reach 6800V, and frequency 58.8 Hz.

Time: ________ Seconds ________ ________

[21] VERIFY from recorder that DG voltage was at least 6800V with frequency at least 58.8 Hz within 10 seconds from DG start. (Acc Crit) ________

[22] VERIFY air start motors (4) pinions NOT ENGAGED with flywheel during startup.

A. Engine 1A2 left bank air start motors. ________

B. Engine 1A2 right bank air start motors. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 49 of 88 Appendix D (Page 5 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A2 Date ________

1.0 DG DRAG START TEST (continued)

[23] VERIFY air start motors (4) pinions ENGAGED with flywheel during startup, THEN DISENGAGE.

A. Engine 1A1 left bank air start motors. ________

B. Engine 1A1 right bank air start motors. ________

CAUTION 86 LOR relay cannot be reset if Red light above 86 LOR, is lit.

[24] RESET 1-RLY-82-86LOR1, DG 1A-A EMERGENCY START LOCKOUT [1-ARB-82-A/1]. ________

[25] ENSURE ES1AY Amber light is LIT [1-PNL-211-A-A]. ________

[26] PLACE 1-HS-57-47, DG SYNC switch [0-M-26] in OFF, AND ________

IF overspeed trip test is to be performed, THEN PERFORM Section 7.1.2 of this MI, OR PERFORM Section 7.1.3 of applicable MI. ________

[27] SHUT DOWN DG in accordance with SOI-82.01. ________

[28] RETURN components in Table 1A2 to normal configuration using the reverse sequence (bottom-to-top), AND DOCUMENT performance. ________

[29] TURN OFF the DG-DAQ computer. ________

[30] TURN OFF the SCXI box. ________

[31] TURN OFF the current probe box. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 50 of 88 Appendix D (Page 6 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1A2 Date ________

1.0 DG DRAG START TEST (continued)

[32] REMOVE the PK test block from TB1, AND REINSTALL the cover. ________

IV

[33] REMOVE the current probe from the wire at ES1AY relay. ________

[34] NOTIFY SRO/Test Director that the DG-DAQ has been removed from the DG control circuits. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 51 of 88 Appendix E (Page 1 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B1 Date ________

1.0 DG DRAG START TEST Perform this Appendix when inspecting Engine 1B1 to isolate Engine 1B1 starting air system to allow starting both engines with Engine 1B2 air start motors and verifying voltage and frequency of generator..

ACCEPTANCE CRITERIA: Diesel generator started with one engines air start motors (4) isolated and achieved voltage > 6800V and frequency > 58.8 Hz in

< 10 seconds.

Test Equipment Setup NOTES

1) Install equipment for testing engine overspeed trip device and aftercooler assembly as required.
2) The DG-DAQ is installed at the DG Protection Panel.
3) The System Engineer may assist in DG-DAQ setup.

[1] CONFIGURE PK test blocks for TB1- All jumpers INSTALLED and all thumb nuts WRENCH TIGHT. ________

NOTE Black is positive and white is negative.

[2] CONNECT DG-DAQ Channel 0 black wire to Terminal 2 of the PK test block for TB1 and the white wire to Terminal 4 of the PK test block for TB1, AND INSERT PK test block into TB1. ________

NOTE The current probe should be zeroed prior to connecting to the ES1BY relay.

[3] ZERO the current probe indication. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 52 of 88 Appendix E (Page 2 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B1 Date ________

1.0 DG DRAG START TEST (continued)

[4] PUT Start signal into DG-DAQ Channel 2, using clamp-on probe around coil wire 11 or 12 of relay ES1BY. ________

[5] TURN ON the DG-DAQ. ________

[6] TURN ON the SCXI box. ________

[7] SETUP DG-DAQ Channel 0 for an input of +212 to -212 V dc and multiplication factor of 60.0 ________

CV

[8] SETUP DG-DAQ Channel 2 for an input of +0.1 to -0.1 V dc and multiplication factor of 1.0 ________

CV

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 53 of 88 Appendix E (Page 3 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B1 Date ________

1.0 DG DRAG START TEST (continued)

CAUTION If the valves in the Table 1B1 are not configured in the order given, an alarm initiation is possible.

[9] IMPLEMENT configuration changes in TABLE 1B1 in the sequence listed (top-to-bottom), AND DOCUMENT performance. ________

TABLE 1B12 VERIFICATIONS CONFIGURATION RETURN TO NORMAL CHANGE CONFIGURATION AFFECTED CHANGE OPS/ CV/ OPS/ IV/

COMPONENT DESCRIPTION DATE DATE DATE DATE 1-ISV-82-517B1-B UNLOCK and CLOSE 1-ISV-82-525B1-B UNLOCK and CLOSE 1-ISV-82-520B1-B UNLOCK and CLOSE 1-ISV-82-528B1-B UNLOCK and CLOSE 1-LOV-82-518B1-B OPEN 1-LOV-82-526B1-B OPEN

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 54 of 88 Appendix E (Page 4 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B1 Date ________

1.0 DG DRAG START TEST (continued)

[10] MANUALLY ACTUATE each of the following solenoid valves by LIFTING the T handle to VENT residual downstream air pressure, THEN RELEASE T handle:

1-FSV-82-190, AIR START SOL VLV ENG 1B1 ________

1-FSV-82-200, AIR START SOL VLV ENG 1B1 ________

[11] PLACE 1-HS-57-74, DG SYNC SWITCH [0-M-26], in SYN. ________

[12] NOTIFY UO that DG will be starting.

[13] ENSURE personnel are in communication to time interval from DG start initiation UNTIL required voltage and frequency are obtained. ________

[14] DISPATCH personnel to monitor engine 1B1 and 1B2 air start motors during diesel start. ________

[15] START recorder. ________

[16] PROCEED with countdown sequence of 3, 2, 1, START, THEN PRESS 1-HS-82-46A, EMERGENCY START [0-M-26], to initiate DG start. ________

[17] RECORD Time of engine start.

Time:____________ ________

[18] MONITOR 1-EI-82-34, INCOMING VOLTAGE, AND 1-XI-82-32, INCOMING FREQUENCY [0-M-26]. ________

[19] WHEN volts and Frequency are stable, THEN STOP recorder. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 55 of 88 Appendix E (Page 5 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B1 Date ________

1.0 DG DRAG START TEST (continued)

[20] RECORD from recorder, the Time required for voltage to reach 6800V, and frequency 58.8 Hz.

Time: ________ Seconds ________ ________

[21] VERIFY from recorder that DG voltage was at least 6800V with frequency at least 58.8 Hz within 10 seconds from DG start. (Acc Crit) ________

[22] VERIFY air start motors (4) pinions NOT ENGAGED with flywheel during startup.

A. Engine 1B1 left bank air start motors. ________

B. Engine 1B1 right bank air start motors. ________

[23] VERIFY air start motors (4) pinions ENGAGED with flywheel during startup, THEN DISENGAGE.

A. Engine 1B2 left bank air start motors. ________

B. Engine 1B2 right bank air start motors. ________

CAUTION 86 LOR relay cannot be reset if Red light above 86 LOR, is lit.

[24] RESET 1-RLY-82-86LOR2, DG 1B-B EMERGENCY START LOCKOUT [1-ARB-82-B/1]. ________

[25] ENSURE ES1BY Amber light is LIT [1-PNL-211-B-B]. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 56 of 88 Appendix E (Page 6 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B1 Date ________

1.0 DG DRAG START TEST (continued)

[26] PLACE 1-HS-57-74, DG SYNC switch [0-M-26] in OFF, AND ________

IF overspeed trip test is to be performed, THEN PERFORM Section 7.1.2 of this MI, OR PERFORM Section 7.1.3 of applicable MI. ________

[27] SHUT DOWN DG in accordance with SOI-82.02. ________

[28] RETURN components in Table 1B1 to normal configuration using the reverse sequence (bottom-to-top), AND DOCUMENT performance. ________

[29] TURN OFF the DG-DAQ computer. ________

[30] TURN OFF the SCXI box. ________

[31] TURN OFF the current probe box. ________

[32] REMOVE the PK test block from TB1, AND REINSTALL the cover. ________

IV

[33] REMOVE the current probe from the wire at ES1BY relay. ________

[34] NOTIFY SRO/Test Director that the DG-DAQ has been removed from the DG control circuits. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 57 of 88 Appendix F (Page 1 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B2 Date ________

1.0 DG DRAG START TEST Perform this Appendix when inspecting Engine 1B2 to isolate Engine 1B2 starting air system to allow starting both engines with Engine 1B1 air start motors and verifying voltage and frequency of generator.

ACCEPTANCE CRITERIA: Diesel generator started with one engines air start motors (4) isolated and achieved voltage > 6800V and frequency > 58.8 Hz in

< 10 seconds.

Test Equipment Setup NOTES

1) Install equipment for testing engine overspeed trip device and aftercooler assembly as required.
2) The DG-DAQ is installed at the DG Protection Panel.
3) The System Engineer may assist in DG-DAQ setup.

[1] CONFIGURE PK test blocks for TB1- All jumpers INSTALLED and all thumb nuts WRENCH TIGHT. ________

NOTE Black is positive and white is negative.

[2] CONNECT DG-DAQ Channel 0 black wire to Terminal 2 of the PK test block for TB1 and the white wire to Terminal 4 of the PK test block for TB1, AND INSERT PK test block into TB1. ________

NOTE The current probe should be zeroed prior to connecting to the ES1BY relay.

[3] ZERO the current probe indication. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 58 of 88 Appendix F (Page 2 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B2 Date ________

1.0 DG DRAG START TEST (continued)

[4] PUT Start signal into DG-DAQ Channel 2, using clamp-on probe around coil wire 11 or 12 of relay ES1BY. ________

[5] TURN ON the DG-DAQ. ________

[6] TURN ON the SCXI box. ________

[7] SETUP DG-DAQ Channel 0 for an input of +212 to -212 V dc and multiplication factor of 60.0 ________

CV

[8] SETUP DG-DAQ Channel 2 for an input of +0.1 to -0.1 V dc and multiplication factor of 1.0 ________

CV CAUTION If the valves in the Table 1B2 are not configured in the order given, an alarm initiation is possible.

[9] IMPLEMENT configuration changes in TABLE 1B2 in the sequence listed (top-to-bottom), AND DOCUMENT performance. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 59 of 88 Appendix F (Page 3 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B2 Date ________

1.0 DG DRAG START TEST (continued)

TABLE 1B22 VERIFICATIONS CONFIGURATION RETURN TO NORMAL CHANGE CONFIGURATION AFFECTED CHANGE OPS/ CV/ OPS/ IV/

COMPONENT DESCRIPTION DATE DATE DATE DATE 1-ISV-82-551B2-B UNLOCK and CLOSE 1-ISV-82-559B2-B UNLOCK and CLOSE 1-ISV-82-554B2-B UNLOCK and CLOSE 1-ISV-82-562B2-B UNLOCK and CLOSE 1-LOV-82-552B2-B OPEN 1-LOV-82-560B2-B OPEN

[10] MANUALLY ACTUATE each of the following solenoid valves by LIFTING the T handle to VENT residual downstream air pressure, THEN RELEASE T handle:

1-FSV-82-191, AIR START SOL VLV ENG 1B2 ________

1-FSV-82-201, AIR START SOL VLV ENG 1B2 ________

[11] PLACE 1-HS-57-74, DG SYNC SWITCH [0-M-26], in SYN. ________

[12] NOTIFY UO that DG will be starting,

[13] ENSURE personnel are in communication to time interval from DG start initiation UNTIL required voltage and frequency are obtained. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 60 of 88 Appendix F (Page 4 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B2 Date ________

1.0 DG DRAG START TEST (continued)

[14] DISPATCH personnel to monitor engine 1B1 and 1B2 air start motors during diesel start. ________

[15] START recorder. ________

[16] PROCEED with countdown sequence of 3, 2, 1, START, THEN PRESS 1-HS-82-46A, EMERGENCY START [0-M-26], to initiate DG start. ________

[17] RECORD Time of engine start.

Time:____________ ________

[18] MONITOR 1-EI-82-34, INCOMING VOLTAGE, AND 1-XI-82-32, INCOMING FREQUENCY [0-M-26]. ________

[19] WHEN volts and Frequency are stable, THEN STOP recorder. ________

[20] RECORD from recorder, the Time required for voltage to reach 6800V, and frequency 58.8 Hz.

Time: ________ Seconds ________ ________

[21] VERIFY from recorder that DG voltage was at least 6800V with frequency at least 58.8 Hz within 10 seconds from DG start. (Acc Crit) ________

[22] VERIFY air start motors (4) pinions NOT ENGAGED with flywheel during startup.

A. Engine 1B2 left bank air start motors. ________

B. Engine 1B2 right bank air start motors. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 61 of 88 Appendix F (Page 5 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B2 Date ________

1.0 DG DRAG START TEST (continued)

[23] VERIFY air start motors (4) pinions ENGAGED with flywheel during startup, THEN DISENGAGE.

A. Engine 1B1 left bank air start motors. ________

B. Engine 1B1 right bank air start motors. ________

CAUTION 86 LOR relay cannot be reset if Red light above 86 LOR, is lit.

[24] RESET 1-RLY-82-86LOR2, DG 1B-B EMERGENCY START LOCKOUT [1-ARB-82-B/1]. ________

[25] ENSURE ES1BY Amber light is LIT [1-PNL-211-B-B]. ________

[26] PLACE 1-HS-57-74, DG SYNC switch [0-M-26] in OFF, AND ________

IF overspeed trip test is to be performed, THEN PERFORM Section 7.1.2 of this MI, OR PERFORM Section 7.1.3 of applicable MI. ________

[27] SHUT DOWN DG in accordance with SOI-82.02. ________

[28] RETURN components in Table 1B2 to normal configuration using the reverse sequence (bottom-to-top), AND DOCUMENT performance. ________

[29] TURN OFF the DG-DAQ computer. ________

[30] TURN OFF the SCXI box. ________

[31] TURN OFF the current probe box. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 62 of 88 Appendix F (Page 6 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 1B2 Date ________

1.0 DG DRAG START TEST (continued)

[32] REMOVE the PK test block from TB1, AND REINSTALL the cover. ________

IV

[33] REMOVE the current probe from the wire at ES1BY relay. ________

[34] NOTIFY SRO/Test Director that the DG-DAsq has been removed from the DG control circuits. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 63 of 88 Appendix G (Page 1 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A1 1.0 DG DRAG START TEST Perform this Appendix when inspecting Engine 2A1 to isolate Engine 2A1 starting air system to allow starting both engines with Engine 2A2 air start motors and verifying voltage and frequency of generator..

ACCEPTANCE CRITERIA: Diesel generator started with one engines air start motors (4) isolated and achieved voltage > 6800V and frequency > 58.8 Hz in

< 10 seconds.

Test Equipment Setup NOTES

1) Install equipment for testing engine overspeed trip device and aftercooler assembly as required.
2) The DG-DAQ is installed at the DG Protection Panel.
3) The System Engineer may assist in DG-DAQ setup.

[1] CONFIGURE PK test blocks for TB1- All jumpers INSTALLED and all thumb nuts WRENCH TIGHT. ________

NOTE Black is positive and white is negative.

[2] CONNECT DG-DAQ Channel 0 black wire to Terminal 2 of the PK test block for TB1 and the white wire to Terminal 4 of the PK test block for TB1, AND INSERT PK test block into TB1. ________

NOTE The current probe should be zeroed prior to connecting to the ES2AY relay.

[3] ZERO the current probe indication. ________

[4] PUT Start signal into DG-DAQ Channel 2, using clamp-on probe around coil wire 11 or 12 of relay ES2AY. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 64 of 88 Appendix G (Page 2 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A1 Date ________

1.0 DG DRAG START TEST (continued)

[5] TURN ON the DG-DAQ. ________

[6] TURN ON the SCXI box. ________

[7] SETUP DG-DAQ Channel 0 for an input of +212 to -212 V dc and multiplication factor of 60.0 ________

CV

[8] SETUP DG-DAQ Channel 2 for an input of +0.1 to -0.1 V dc and multiplication factor of 1.0 ________

CV CAUTION If the valves in the Table 2A1 are not configured in the order given, an alarm initiation is possible.

[9] IMPLEMENT configuration changes in TABLE 2A1 in the sequence listed (top-to-bottom), AND DOCUMENT performance. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 65 of 88 Appendix G (Page 3 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A1 Date ________

1.0 DG DRAG START TEST (continued)

TABLE 2A12 VERIFICATIONS CONFIGURATION RETURN TO NORMAL CHANGE CONFIGURATION AFFECTED CHANGE OPS/ CV/ OPS/ IV/

COMPONENT DESCRIPTION DATE DATE DATE DATE 2-ISV-82-517A1-A UNLOCK and CLOSE 2-ISV-82-525A1-A UNLOCK and CLOSE 2-ISV-82-520A1-A UNLOCK and CLOSE 2-ISV-82-528A1-A UNLOCK and CLOSE 2-LOV-82-518A1-A OPEN 2-LOV-82-526A1-A OPEN

[10] MANUALLY ACTUATE each of the following solenoid valves by LIFTING the T handle to VENT residual downstream air pressure, THEN RELEASE T handle:

2-FSV-82-220, AIR START SOL VLV ENG 2A1 ________

2-FSV-82-230, AIR START SOL VLV ENG 2A1 ________

[11] PLACE 2-HS-57-47, DG SYNC SWITCH [0-M-26], in SYN. ________

[12] NOTIFY UO that DG will be starting.

[13] ENSURE personnel are in communication to time interval from DG start initiation UNTIL required voltage and frequency are obtained. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 66 of 88 Appendix G (Page 4 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A1 Date ________

1.0 DG DRAG START TEST (continued)

[14] DISPATCH personnel to monitor engine 2A1 and 2A2 air start motors during diesel start. ________

[15] START recorder. ________

[16] PROCEED with countdown sequence of 3, 2, 1, START, THEN PRESS 2-HS-82-76A, EMERGENCY START [0-M-26], to initiate DG start. ________

[17] RECORD Time of engine start.

Time:____________ ________

[18] MONITOR 2-EI-82-64, INCOMING VOLTAGE, AND 2-XI-82-62, INCOMING FREQUENCY [0-M-26]. ________

[19] WHEN volts and Frequency are stable, THEN STOP recorder. ________

[20] RECORD from recorder, the Time required for voltage to reach 6800V, and frequency 58.8 Hz.

Time: ________ Seconds ________ ________

[21] VERIFY from recorder that DG voltage was at least 6800V with frequency at least 58.8 Hz within 10 seconds from DG start. (Acc Crit) ________

[22] VERIFY air start motors (4) pinions NOT ENGAGED with flywheel during startup.

A. Engine 2A1 left bank air start motors. ________

B. Engine 2A1 right bank air start motors. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 67 of 88 Appendix G (Page 5 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A1 Date ________

1.0 DG DRAG START TEST (continued)

[23] VERIFY air start motors (4) pinions ENGAGED with flywheel during startup, THEN DISENGAGE.

A. Engine 2A2 left bank air start motors. ________

B. Engine 2A2 right bank air start motors. ________

CAUTION 86 LOR relay cannot be reset if Red light above 86 LOR, is lit.

[24] RESET 2-RLY-82-86LOR1, DG 2A-A EMERGENCY START LOCKOUT [2-ARB-82-A/1]. ________

[25] ENSURE ES2AY Amber light is LIT [2-PNL-211-A-A]. ________

[26] PLACE 2-HS-57-47, DG SYNC switch [0-M-26] in OFF, AND ________

IF overspeed trip test is to be performed, THEN PERFORM Section 7.1.2 of this MI, OR PERFORM Section 7.1.3 of applicable MI. ________

[27] SHUT DOWN DG in accordance with SOI-82.03. ________

[28] RETURN components in Table 2A1 to normal configuration using the reverse sequence (bottom-to-top), AND DOCUMENT performance. ________

[29] TURN OFF the DG-DAQ computer. ________

[30] TURN OFF the SCXI box. ________

[31] TURN OFF the current probe box. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 68 of 88 Appendix G (Page 6 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A1 Date ________

1.0 DG DRAG START TEST (continued)

[32] REMOVE the PK test block from TB1, AND REINSTALL the cover. ________

IV

[33] REMOVE the current probe from the wire at ES2AY relay. ________

[34] NOTIFY SRO/Test Director that the DG-DAQ has been removed from the DG control circuits. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 69 of 88 Appendix H (Page 1 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A2 1.0 DG DRAG START TEST Perform this Appendix when inspecting Engine 2A2 to isolate Engine 2A2 starting air system to allow starting both engines with Engine 2A1 air start motors and verifying voltage and frequency of generator..

ACCEPTANCE CRITERIA: Diesel generator started with one engines air start motors (4) isolated and achieved voltage > 6800V and frequency > 58.8 Hz in

< 10 seconds.

Test Equipment Setup NOTES

1) Install equipment for testing engine overspeed trip device and aftercooler assembly as required.
2) The DG-DAQ is installed at the DG Protection Panel.
3) The System Engineer may assist in DG-DAQ setup.

[1] CONFIGURE PK test blocks for TB1- All jumpers INSTALLED and all thumb nuts TIGHT. ________

NOTE Black is positive and white is negative.

[2] CONNECT DG-DAQ Channel 0 black wire to Terminal 2 of the PK test block for TB1 and the white wire to Terminal 4 of the PK test block for TB1, AND INSERT PK test block into TB1. ________

NOTE The current probe should be zeroed prior to connecting to the ES2AY relay.

[3] ZERO the current probe indication. ________

[4] PUT Start signal into DG-DAQ Channel 2, using clamp-on probe around coil wire 11 or 12 of relay ES2AY. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 70 of 88 Appendix H (Page 2 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A2 Date ________

1.0 DG DRAG START TEST (continued)

[5] TURN ON the DG-DAQ. ________

[6] TURN ON the SCXI box. ________

[7] SETUP DG-DAQ Channel 0 for an input of +212 to -212 V dc and multiplication factor of 60.0 ________

CV

[8] SETUP DG-DAQ Channel 2 for an input of +0.1 to -0.1 V dc and multiplication factor of 1.0 ________

CV CAUTION If the valves in the Table 2A2 are not configured in the order given, an alarm initiation is possible.

[9] IMPLEMENT configuration changes in TABLE 2A2 in the sequence listed (top-to-bottom), AND DOCUMENT performance. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 71 of 88 Appendix H (Page 3 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A2 Date ________

1.0 DG DRAG START TEST (continued)

TABLE 2A22 VERIFICATIONS CONFIGURATION RETURN TO NORMAL CHANGE CONFIGURATION AFFECTED CHANGE OPS/ CV/ OPS/ IV/

COMPONENT DESCRIPTION DATE DATE DATE DATE 2-ISV-82-551A2-A UNLOCK and CLOSE 2-ISV-82-559A2-A UNLOCK and CLOSE 2-ISV-82-554A2-A UNLOCK and CLOSE 2-ISV-82-562A2-A UNLOCK and CLOSE 2-LOV-82-552A2-A OPEN 2-LOV-82-560A2-A OPEN

[10] MANUALLY ACTUATE each of the following solenoid valves by lifting the T handle to VENT residual downstream air pressure, THEN RELEASE T handle:

2-FSV-82-221, AIR START SOL VLV ENG 2A2 ________

2-FSV-82-231, AIR START SOL VLV ENG 2A2 ________

[11] PLACE 2-HS-57-47, DG SYNC SWITCH [0-M-26], in SYN. ________

[12] NOTIFY UO that DG will be starting,

[13] ENSURE personnel are in communication to time interval from DG start initiation UNTIL required voltage and frequency are obtained. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 72 of 88 Appendix H (Page 4 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A2 Date ________

1.0 DG DRAG START TEST (continued)

[14] DISPATCH personnel to monitor engine 2A1 and 2A2 air start motors during diesel start. ________

[15] START recorder. ________

[16] PROCEED with countdown sequence of 3, 2, 1, START, THEN PRESS 2-HS-82-76A, EMERGENCY START [0-M-26], to initiate DG start. ________

[17] RECORD Time of engine start.

Time:____________ ________

[18] MONITOR 2-EI-82-64, INCOMING VOLTAGE, AND 2-XI-82-62, INCOMING FREQUENCY [0-M-26]. ________

[19] WHEN volts and Frequency are stable, THEN STOP recorder. ________

[20] RECORD from recorder, the Time required for voltage to reach 6800V, and frequency 58.8 Hz.

Time: ________ Seconds ________ ________

[21] VERIFY from recorder that DG voltage was at least 6800V with frequency at least 58.8 Hz within 10 seconds from DG start. (Acc Crit) ________

[22] VERIFY air start motors (4) pinions NOT ENGAGED with flywheel during startup.

A. Engine 2A2 left bank air start motors. ________

B. Engine 2A2 right bank air start motors. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 73 of 88 Appendix H (Page 5 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A2 Date ________

1.0 DG DRAG START TEST (continued)

[23] VERIFY air start motors (4) pinions ENGAGED with flywheel during startup, THEN DISENGAGE.

A. Engine 2A1 left bank air start motors. ________

B. Engine 2A1 right bank air start motors. ________

CAUTION 86 LOR relay cannot be reset if Red light above 86 LOR, is lit.

[24] RESET 2-RLY-82-86LOR1, DG 2A-A EMERGENCY START LOCKOUT [2-ARB-82-A/1]. ________

[25] ENSURE ES2AY Amber light is LIT [2-PNL-211-A-A]. ________

[26] PLACE 2-HS-57-47, DG SYNC switch [0-M-26] in OFF, AND ________

IF overspeed trip test is to be performed, THEN PERFORM Section 7.1.2 of this MI, OR PERFORM Section 7.1.3 of applicable MI. ________

[27] SHUT DOWN DG in accordance with SOI-82.03. ________

[28] RETURN components in Table 2A2 to normal configuration using the reverse sequence (bottom-to-top), AND DOCUMENT performance. ________

[29] TURN OFF the DG-DAQ computer. ________

[30] TURN OFF the SCXI box. ________

[31] TURN OFF the current probe box. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 74 of 88 Appendix H (Page 6 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2A2 Date ________

1.0 DG DRAG START TEST (continued)

[32] REMOVE the PK test block from TB1, AND REINSTALL the cover. ________

IV

[33] REMOVE the current probe from the wire at ES2AY relay. ________

[34] NOTIFY SRO/Test Director that the DG-DAQ has been removed from the DG control circuits. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 75 of 88 Appendix I (Page 1 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B1 1.0 DG DRAG START TEST Perform this Appendix when inspecting Engine 2B1 to isolate Engine 2B1 starting air system to allow starting both engines with Engine 2B2 air start motors and verifying voltage and frequency of generator..

ACCEPTANCE CRITERIA: Diesel generator started with one engines air start motors (4) isolated and achieved voltage > 6800V and frequency > 58.8 Hz in

< 10 seconds.

Test Equipment Setup NOTES

1) Install equipment for testing engine overspeed trip device and aftercooler assembly as required.
2) The DG-DAQ is installed at the DG Protection Panel.
3) The System Engineer may assist in DG-DAQ setup.

[1] CONFIGURE PK test blocks for TB1- All jumpers INSTALLED and all thumb nuts WRENCH TIGHT. ________

NOTE Black is positive and white is negative.

[2] CONNECT DG-DAQ Channel 0 black wire to Terminal 2 of the PK test block for TB1 and the white wire to Terminal 4 of the PK test block for TB1, AND INSERT PK test block into TB1. ________

NOTE The current probe should be zeroed prior to connecting to the ES2BY relay.

[3] ZERO the current probe indication. ________

[4] PUT Start signal into DG-DAQ Channel 2, using clamp-on probe around coil wire 11 or 12 of relay ES2BY. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 76 of 88 Appendix I (Page 2 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B1 Date ________

1.0 DG DRAG START TEST (continued)

[5] TURN ON the DG-DAQ. ________

[6] TURN ON the SCXI box. ________

[7] SETUP DG-DAQ Channel 0 for an input of +212 to -212 V dc and multiplication factor of 60.0 ________

CV

[8] SETUP DG-DAQ Channel 2 for an input of +0.1 to -0.1 V dc and multiplication factor of 1.0 ________

CV CAUTION If the valves in the Table 2B1 are not configured in the order given, an alarm initiation is possible.

[9] IMPLEMENT configuration changes in TABLE 2B1 in the sequence listed (top-to-bottom), AND DOCUMENT performance. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 77 of 88 Appendix I (Page 3 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B1 Date ________

1.0 DG DRAG START TEST (continued)

TABLE 2B12 VERIFICATIONS CONFIGURATION RETURN TO NORMAL CHANGE CONFIGURATION AFFECTED CHANGE OPS/ CV/ OPS/ IV/

COMPONENT DESCRIPTION DATE DATE DATE DATE 2-ISV-82-517B1-B UNLOCK and CLOSE 2-ISV-82-525B1-B UNLOCK and CLOSE 2-ISV-82-520B1-B UNLOCK and CLOSE 2-ISV-82-528B1-B UNLOCK and CLOSE 2-LOV-82-518B1-B OPEN 2-LOV-82-526B1-B OPEN

[10] MANUALLY ACTUATE each of the following solenoid valves by LIFTING the T handle to VENT residual downstream air pressure, THEN RELEASE T handle:

2-FSV-82-250, AIR START SOL VLV ENG 2B1 ________

2-FSV-82-260, AIR START SOL VLV ENG 2B1 ________

[11] PLACE 2-HS-57-74, DG SYNC SWITCH [0-M-26], in SYN. ________

[12] NOTIFY UO that DG will be starting.

[13] ENSURE personnel are in communication to time interval from DG start initiation until required voltage and frequency are obtained. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 78 of 88 Appendix I (Page 4 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B1 Date ________

1.0 DG DRAG START TEST (continued)

[14] DISPATCH personnel to monitor engine 2B1 and 2B2 air start motors during diesel start. ________

[15] START recorder. ________

[16] PROCEED with countdown sequence of 3, 2, 1, START, THEN PRESS 2-HS-82-106A, EMERGENCY START [0-M-26], to initiate DG start. ________

[17] RECORD Time of engine start.

Time:____________ ________

[18] MONITOR 2-EI-82-94, INCOMING VOLTAGE, AND 2-XI-82-92, INCOMING FREQUENCY [0-M-26]. ________

[19] WHEN volts and Frequency are stable, THEN STOP recorder. ________

[20] RECORD from recorder, the Time required for voltage to reach 6800V, and frequency 58.8 Hz.

Time: ________ Seconds ________ ________

[21] VERIFY from recorder that DG voltage was at least 6800V with frequency at least 58.8 Hz within 10 seconds from DG start. (Acc Crit) ________

[22] VERIFY air start motors (4) pinions NOT ENGAGED with flywheel during startup.

A. Engine 2B1 left bank air start motors. ________

B. Engine 2B1 right bank air start motors. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 79 of 88 Appendix I (Page 5 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B1 Date ________

1.0 DG DRAG START TEST (continued)

[23] VERIFY air start motors (4) pinions ENGAGED with flywheel during startup, THEN DISENGAGE.

A. Engine 2B2 left bank air start motors. ________

B. Engine 2B2 right bank air start motors. ________

CAUTION 86 LOR relay cannot be reset if Red light above 86 LOR, is lit.

[24] RESET 2-RLY-82-86LOR2, DG 2B-B EMERGENCY START LOCKOUT [2-ARB-82-B/1]. ________

[25] ENSURE ES2BY Amber light is LIT [2-PNL-211-B-B]. ________

[26] PLACE 2-HS-57-74, DG SYNC switch [0-M-26] in OFF, AND ________

IF overspeed trip test is to be performed, THEN PERFORM Section 7.1.2 of this MI, OR PERFORM Section 7.1.3 of applicable MI. ________

[27] SHUT DOWN DG in accordance with SOI-82.04. ________

[28] RETURN components in Table 2B1 to normal configuration using the reverse sequence (bottom-to-top), AND DOCUMENT performance. ________

[29] TURN OFF the DG-DAQ computer. ________

[30] TURN OFF the SCXI box. ________

[31] TURN OFF the current probe box. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 80 of 88 Appendix I (Page 6 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B1 Date ________

1.0 DG DRAG START TEST (continued)

[32] REMOVE the PK test block from TB1, AND REINSTALL the cover. ________

IV

[33] REMOVE the current probe from the wire at ES2BY relay. ________

[34] NOTIFY SRO/Test Director that the DG-DAQ has been removed from the DG control circuits. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 81 of 88 Appendix J (Page 1 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B2 Date ________

1.0 DG DRAG START TEST Perform this Appendix when inspecting Engine 2B2 to isolate Engine 2B2 starting air system to allow starting both engines with Engine 2B1 air start motors and verifying voltage and frequency of generator.

ACCEPTANCE CRITERIA: Diesel generator started with one engines air start motors (4) isolated and achieved voltage > 6800V and frequency > 58.8 Hz in

< 10 seconds.

Test Equipment Setup NOTES

1) Install equipment for testing engine overspeed trip device and aftercooler assembly as required.
2) The DG-DAQ is installed at the DG Protection Panel.
3) The System Engineer may assist in DG-DAQ setup.

[1] CONFIGURE PK test blocks for TB1- All jumpers INSTALLED and all thumb nuts WRENCH TIGHT. ________

NOTE Black is positive and white is negative.

[2] CONNECT DG-DAQ Channel 0 black wire to Terminal 2 of the PK test block for TB1 and the white wire to Terminal 4 of the PK test block for TB1, AND INSERT PK test block into TB1. ________

NOTE The current probe should be zeroed prior to connecting to the ES2BY relay.

[3] ZERO the current probe indication. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 82 of 88 Appendix J (Page 2 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B2 Date ________

1.0 DG DRAG START TEST (continued)

[4] PUT Start signal into DG-DAQ Channel 2, using clamp-on probe around coil wire 11 or 12 of relay ES2BY. ________

[5] TURN ON the DG-DAQ. ________

[6] TURN ON the SCXI box. ________

[7] SETUP DG-DAQ Channel 0 for an input of +212 to -212 V dc and multiplication factor of 60.0 ________

CV

[8] SETUP DG-DAQ Channel 2 for an input of +0.1 to -0.1 V dc and multiplication factor of 1.0 ________

CV CAUTION If the valves in the Table 2B2 are not configured in the order given, an alarm initiation is possible.

[9] IMPLEMENT configuration changes in TABLE 2B2 in the sequence listed (top-to-bottom), AND DOCUMENT performance. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 83 of 88 Appendix J (Page 3 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B2 Date ________

1.0 DG DRAG START TEST (continued)

TABLE 2B22 VERIFICATIONS CONFIGURATION RETURN TO NORMAL CHANGE CONFIGURATION AFFECTED CHANGE OPS/ CV/ OPS/ IV/

COMPONENT DESCRIPTION DATE DATE DATE DATE 2-ISV-82-551B2-B UNLOCK and CLOSE 2-ISV-82-559B2-B UNLOCK and CLOSE 2-ISV-82-554B2-B UNLOCK and CLOSE 2-ISV-82-562B2-B UNLOCK and CLOSE 2-LOV-82-552B2-B OPEN 2-LOV-82-560B2-B OPEN

[10] MANUALLY ACTUATE each of the following solenoid valves by LIFTING the T handle to VENT residual downstream air pressure, THEN RELEASE T handle:

2-FSV-82-251, AIR START SOL VLV ENG 2B2 ________

2-FSV-82-261, AIR START SOL VLV ENG 2B2 ________

[11] PLACE 2-HS-57-74, DG SYNC SWITCH [0-M-26], in SYN. ________

[12] NOTIFY UO that DG will be starting,

[13] ENSURE personnel are in communication to time interval from DG start initiation until required voltage and frequency are obtained. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 84 of 88 Appendix J (Page 4 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B2 Date ________

1.0 DG DRAG START TEST (continued)

[14] DISPATCH personnel to monitor engine 2B1 and 2B2 air start motors during diesel start. ________

[15] START recorder. ________

[16] PROCEED with countdown sequence of 3, 2, 1, START, THEN PRESS 2-HS-82-106A, EMERGENCY START [0-M-26], to initiate DG start. ________

[17] RECORD Time of engine start.

Time:____________ ________

[18] MONITOR 2-EI-82-94, INCOMING VOLTAGE, AND 2-XI-82-92, INCOMING FREQUENCY [0-M-26]. ________

[19] WHEN volts and Frequency are stable, THEN STOP recorder. ________

[20] RECORD from recorder, the Time required for voltage to reach 6800V, and frequency 58.8 Hz.

Time: ________ Seconds ________ ________

[21] VERIFY from recorder that DG voltage was at least 6800V with frequency at least 58.8 Hz within 10 seconds from DG start. (Acc Crit) ________

[22] VERIFY air start motors (4) pinions NOT ENGAGED with flywheel during startup.

A. Engine 2B2 left bank air start motors. ________

B. Engine 2B2 right bank air start motors. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 85 of 88 Appendix J (Page 5 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B2 Date ________

1.0 DG DRAG START TEST (continued)

[23] VERIFY air start motors (4) pinions ENGAGED with flywheel during startup, THEN DISENGAGE.

A. Engine 2B1 left bank air start motors. ________

B. Engine 2B1 right bank air start motors. ________

CAUTION 86 LOR relay cannot be reset if Red light above 86 LOR, is lit.

[24] RESET 2-RLY-82-86LOR2, DG 2B-B EMERGENCY START LOCKOUT [2-ARB-82-B/1]. ________

[25] ENSURE ES2BY Amber light is LIT [2-PNL-211-B-B]. ________

[26] PLACE 2-HS-57-74, DG SYNC switch [0-M-26] in OFF, AND ________

IF overspeed trip test is to be performed, THEN PERFORM Section 7.1.2 of this MI, OR PERFORM Section 7.1.3 of applicable MI. ________

[27] SHUT DOWN DG in accordance with SOI-82.04. ________

[28] RETURN components in Table 2B2 to normal configuration using the reverse sequence (bottom-to-top), AND DOCUMENT performance. ________

[29] TURN OFF the DG-DAQ computer. ________

[30] TURN OFF the SCXI box. ________

[31] TURN OFF the current probe box. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 86 of 88 Appendix J (Page 6 of 6)

Diesel Generator Drag Start Test With Air Start Motors Isolated For Engine 2B2 Date ________

1.0 DG DRAG START TEST (continued)

[32] REMOVE the PK test block from TB1, AND REINSTALL the cover. ________

IV

[33] REMOVE the current probe from the wire at ES2BY relay. ________

[34] NOTIFY SRO/Test Director that the DG-DAQ has been removed from the DG control circuits. ________

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 87 of 88 Appendix K (Page 1 of 1)

CAMSHAFT OVERSPEED TRIP LINKAGE

WBN Two Year Diesel Generator Engine 0-MI-82.003 Unit 1 & 2 Inspection Rev. 0002 Page 88 of 88 Source Notes (Page 1 of 1)

Implementing Requirements Statement Source Document Statement Revised lube oil pump coupling WBPER960412 1 alignments. Action Sequence 04 Enhanced procedure by providing WBPER 01-006411-000 2 configuration sequencing of valves in tables 1A1 thru 2B2 for Appendices C thru J.

Add second party verification signoffs WB PER 03-004039-000 3 for setup of software inputs on the DG-DAQ recorder.

Add requirement to designate WB PER 03-012056-00 4 someone to monitor engine rpm during overspeed test.

WATTS BAR NUCLEAR PLANT PREVENTATIVE MAINTENANCE (PM)

WORK INSTRUCTIONS UNIT 1 DG 1A-A PROTECTIVE RELAY FUNCTIONAL TEST PM #: 600108453 REVISION: 4 UNID: 1-GEN-82-1A-A WO #: WO NUMBER Effective Date: 1-22-2015 Planning Organization: MEG, Electrical Prepared By: Alan Franklin Reviewed By: Terry Benson

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 Revision Log Revision Affected Description of Revision or Change Revised By/ Page Number Date Numbers Include PMCR/PER Number 0 Replaces MI-82.50.01 General Revision. Rev 1 revised order of sections to enhance performance. Deleted 1

steps to streamline test. Added performance mode.

Revision 2 reformatted to current standards, changed sponsoring organizational title, added items to update tool list, deleted statement in Precautions & Limitations (B) to pull fuses 2 1-FU-275-R75/K3 and 1-FU-275-R75/K4, added Section to perform functional by Shutdown Board 1A-A Bus Differentials, and added annunciation Windows 195A and 280A.

Added 1.0 Precautions & LimitationsSection I.

Revision 3 revised to current standards.

Changed Organizational Titles. Revised frequency. Identified section 3.2 as a Critical Section. Added steps to CONFIRM LO relays 3 reset in Post Performance section. Added Performance references and included 0-PI-OPS-1.1, Jumper Control Process there and in the Precautions and Limitations. REF PER 140641.

Updated PM steps to current standards of NPG-SPP-07.6. Changed file name from 1220F to 600108453. Updated PM to reflect new PM 4 ABF/1-22-15 ALL template and ready for BSL. Converted to MAXIMO format. Create future Work Orders in Approved status.

Page 2 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 SCOPE: The purpose of this Preventative Maintenance (PM) Instruction is to perform protective relay functional test for WBN-1-GEN-082-0001A-A, DIESEL GENERATOR 1A-A.

General Info:

Vendor Drawing: 0126D4093 Vendor Manual: NONE TVA Drawings: 1-45W760-82-1, -2, -4, -5, -8, 1-45W760-211-4 Commitments:

None Recommended Tools:

6" Insulated Alignment Tool Thin Insulating Strips (3)

Step Stool Flashlight Extension Cord Field Copies (2)

Radios (3)

Patch Cable Jumper Recommended M&TE:

0-10A AC Variable Current Source with leads Page 3 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 Recommended Materials:

See Maximo

References:

0-PI-OPS-1.1 Jumper Control Process Contract 74C2-84376 RSS: 0167, 5296, 6453, 8330, 6460, 8750, 6458, 3977, 6454, 8139, 0629 Page 4 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 1.0 EQUIPMENT CATEGORY 1.1 See work order form and associated asset form for equipment classification.

1.2 See NEDP-4 for material requirements.

2.0 REQUIREMENTS 2.1 If directed by the work supervisor, then WO steps may be re-performed and/or worked out of sequence unless the WO contains a specific requirement that steps be performed in sequence.

Page 5 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 3.0 PRECAUTIONS AND LIMITATIONS 3.1 If determined additional work or work outside original scope of work order is required that cannot be accomplished IAW MMDP-1, Section 3.1.2, then document information needed for re-planning in actual work performed section and return work order to planning.

3.2 The purpose of this PM is to provide instructions for performing functional tests on the protective relays associated with Diesel Generator 1A-A.

3.3 This PM requires advance scheduling with Operations and multiple test personnel will be required. The DG must be removed from service and made inoperative. Minimum configuration requirements are that the air start valves be closed and tagged on a hold order clearance and 6.9kV Shutdown Board 1A-A panel 6 ACB 1912 be in the test position and available to test close and trip.

3.4 This PM involves temporary configuration changes. If work on this PM is interrupted and equipment is left unattended for more than one hour before completion, then place a temporary equipment control tag in accordance with plant administrative instructions to identify each configuration change item or area not returned to normal.

3.5 The acceptability of the PM will be based on the correct performance of all steps.

Any step that fails to respond correctly and cannot be verified shall be evaluated and documented in Section 7.0, and a Service Request (SR) initiated as applicable to correct the failure. The PM performance may proceed even though the specific step related to annunciator and display point responses were not obtained.

3.6 The test personnel performing this PM should be observant of the condition of the protective relays. Any abnormalities such as pitted contacts, broken/cracked covers, cleanliness, etc., should be noted and a work order initiated as applicable to correct the condition.

3.7 This PM may be performed in whole or part depending on the requirements of the work order or the routine schedule. It is acceptable to perform Sections out of sequence. N/A, initial, date, and explain the parts that are not performed.

Page 6 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 3.8 This PM may be performed in all modes of operation with the conditions and restraints specified in Technical Specification Sections 3.8.1 and 3.8.2.

3.9 Relay covers will be removed as needed for testing.

3.10 This PM will operate Differential Auxiliary Relay Device 86S1A to the TRIP position. This operation will INOP automatic transfer from the Normal Supply breaker 1-BKR-211-1716/16-A to the Alternate Supply breaker 1-BKR-211-1932/1-A. While 86S1A is in the trip position the 6.9 KV Shutdown Board 1A-A will be INOPERABLE but will remain AVAILABLE.

3.11 Control electrical jumpers in accordance with 0-PI-OPS-1.1 Jumper Control Process.

Page 7 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 4.0 PREREQUISITES 4.1 OBTAIN a clearance PRIOR to starting work, OR ENSURE an approved JSA has been approved to perform the work. N/A if not required.

Clearance Number: __________________ JSA NONE REQUIRED Performed By: __________________________________ Date: _____________

4.2 OBTAIN SM/SRO permission and UO of tests to be performed.

Performed By: _________________________ Date: ______________________

4.3 NOTIFY UO the following annunciator windows and display points are affected by performance of this PM.

A. Annunciator Windows PANEL WINDOW NO. DESCRIPTION 0-XA-55-26A 195A DG 1A-A AUTO START LOCKED OUT 0-XA-55-26A 197D Operation DG Protective Relay 0-XA-55-26A 201C 6.9 SD BD 1A-A PWR FAILUREUV/OV/CONTROL 0-XA-55-L4A 280A DG 1A-A AUTO START LOCKED OUT 0-XA-55-L4A 282D DG Protective Relay Operation B. Annunciator Display 1-MON-55-37 POINT DESCRIPTION 195A DG 1A-A AUTO START LOCKED OUT 197D DG 1A-A Protective Relay Operation 201C 6.9 SD BD 1A-A PWR FAILURE UV/OV/CONTROL Performed By: _________________________ Date: ______________________

Page 8 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 NOTE 125VDC control power to DG excitation system and protective relays must be available.

4.4 ENSURE breakers 1-BKR-82-A/1, 1-BKR-82-A/2 and 1-BKR-82-A/3 in DG distribution panel 1-DPL-82-A are CLOSED.

Performed By: _________________________ Date: ______________________

4.5 INDICATE as-found position of 1-BKR-211-1912/6-A:

CONNECTED DISCONNECTED TEST OPEN CLOSED SEISMIC Performed By: _________________________ Date: ______________________

NOTE Step 4.6 is required for Sections 5.22, 5.23 and 5.24. The 52STA test link is NOT to be installed.

4.6 REQUEST Operations to place 1-BKR-211-1912/6-A in TEST with test coupler installed and available to test close and trip.

Performed By: _________________________ Date: ______________________

Peer Check: __________________________ Date: ______________________

Page 9 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 5.0 WORK INSTRUCTIONS 5.1 ENSURE equipment to be worked is the same as that specified in the scope of this PM Work Instruction PRIOR to starting work activities.

Performed By: __________________________________ Date: _____________

Peer Check: ____________________________________ Date: _____________

5.2 ENSURE 1-RLY-82-86LOR1 DG 1A-A EMERGENCY START LOCKOUT is reset.

5.3 ENSURE 1-RLY-82-86GA1 DG 1A-A PROTECTIVE RELAY LOCKOUT is reset.

5.4 INDICATE as-found position of 0-HS-55-L4A [0-L-4].

ON OFF 

Performed By: _________________________ Date: ______________________

5.5 ENSURE 0-HS-55-L4A is in the ON position.

Performed By: _________________________ Date: ______________________

Peer Check: __________________________ Date: ______________________

5.6 ENSURE Window 197D is not illuminated.

5.7 ENSURE Window 282D is not illuminated.

Page 10 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 5.8 Manually TRIP 1-RLY-82-86GA1, and A. ENSURE Window 197D is illuminated.

B. ENSURE Window 282D is illuminated.

C. ENSURE Display Point 197D indicated alarm.

D. ENSURE Safety Shutdown Relays are picked up.

5.9 RESET 1-RLY-82-86GA1.

5.10 ENSURE Window 197D is not illuminated.

5.11 ENSURE Window 282D is not illuminated.

5.12 ENSURE Display Point 197D indicated normal.

5.13 RESET 1-HS-82-20 DG AUTO SAFETY SHUTDOWN RELAY-RESET [0-M-26]

and ENSURE safety shutdown relays dropped out.

5.14 Manually TRIP 1-RLY-82-86LOR1.

5.15 Manually CLOSE and HOLD Device 32X contacts, and A. ENSURE Window 197D is illuminated.

B. ENSURE Window 282D is illuminated.

C. ENSURE Display Point 197D indicated alarm.

Page 11 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 5.16 Manually OPEN Device 32X contacts, and A. ENSURE Window 197D is not illuminated.

B. ENSURE Window 282D is not illuminated.

C. ENSURE Display Point 197D indicated normal.

5.17 Manually CLOSE and HOLD Device 64X contacts, and A. ENSURE Window 197D is illuminated.

B. ENSURE Window 282D is illuminated.

C. ENSURE Display Point 197D indicated alarm.

5.18 Manually OPEN Device 64X contacts, and A. ENSURE Window 197D is not illuminated.

B. ENSURE Window 282D is not illuminated.

C. ENSURE Display Point 197D indicated normal.

5.19 Manually CLOSE and HOLD Device 40X contacts, and A. ENSURE Window 197D is illuminated.

B. ENSURE Window 282D is illuminated.

C. ENSURE Display Point 197D indicated alarm.

Page 12 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 5.20 Manually OPEN Device 40X contacts, and A. ENSURE Window 197D is not illuminated.

B. ENSURE Window 282D is not illuminated.

C. ENSURE Display Point 197D indicated normal.

5.21 RESET 1-RLY-82-86LOR1.

Page 13 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 5.22 FUNCTIONAL TEST OF DEVICE 50 INSTANTANEOUS OVERCURRENT RELAY NOTE This test requires that at least one of the feeders to 1-BD-211-A-A be closed and a temporary jumper be installed on panel 6 ACB 1912 52STA switch.

A. ENSURE that 1-BKR-211-1932/1-A, 1-BKR-211-1718/11-A, OR 1-BKR-211-1716/16-A is CLOSED.

B. INSTALL a jumper from Terminal Block C point 12 to Terminal Block B point 12 inside panel 6 on 1-BD-211-A-A.

Performed By: _________________________ Date: ______________________

Peer Check: __________________________ Date: ______________________

C. CLOSE 1-BKR-211-1912/6-A using test close pushbutton.

D. Manually CLOSE Device 50 A-Phase Unit contact, and

1) CONFIRM Device 50 A-Phase target exposed.
2) CONFIRM 1-BKR-211-1912/6-A tripped.

Performed By: _________________________ Date: ______________________

E. CLOSE 1-BKR-211-1912/6-A using test close pushbutton.

F. Manually CLOSE Device 50 B-Phase Unit contact, and

1) CONFIRM Device 50 B-Phase target exposed.
2) CONFIRM 1-BKR-211-1912/6-A tripped.

Performed By: _________________________ Date: ______________________

Page 14 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 G. CLOSE 1-BKR-211-1912/6-A using test close pushbutton.

H. Manually CLOSE Device 50 C-Phase Unit contact, and

1) CONFIRM Device 50 C-Phase target exposed.
2) CONFIRM 1-BKR-211-1912/6-A tripped.

Performed By: _________________________ Date: ______________________

I. REPLACE cover on Device 50 and RESET targets.

J. REMOVE jumper from Terminal Block C point 12 and Terminal Block B point 12 inside panel 6 on 1-BD-211-A-A.

Performed By: _________________________ Date: ______________________

IV: ___________________________________ Date: _____________________

Page 15 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4

                                                              • CRITICAL SECTION*******************************

5.23 FUNCTIONAL TEST OF DEVICE 87S1A BUS DIFFERENTIAL RELAY WARNING Removal of the following PK block covers inhibits the bus differential relay protection.

WARNING The following eight steps if not correctly performed in sequence could result in loss of 6.9kV Shutdown Board power.

A. REMOVE Panel 12 PK block covers from PK blocks TD1 and TD2.

Performed By: _________________________ Date: ______________________

CV: __________________________________ Date: _____________________

B. PLACE shorting link between terminals 7 and 8 on PK test plug and INSERT test plug into PK block TD1.

Performed By: _________________________ Date: ______________________

CV: __________________________________ Date: _____________________

C. CLOSE 1-BKR-211-1912/6-A.

Performed By: _________________________ Date: ______________________

Page 16 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4

                                                      • CRITICAL SECTION (CONT.)***************************

NOTE Annunciation windows 201C and 282D will be actuated when 5.23 D is performed. This is checked in a separate PM.

D. Manually CLOSE device 87S1A A-Phase Differential Relay contacts and CONFIRM the following:

1) Device 86S1A in trip position.
2) 1-BKR-211-1912/6-A is open.

Performed By: _________________________ Date: ______________________

E. REPLACE cover and ENSURE target is reset on 87S1A A-Phase Differential Relay.

Performed By: _________________________ Date: ______________________

CV: __________________________________ Date: _____________________

F. RESET device 86S1A.

Performed By: _________________________ Date: ______________________

CV: __________________________________ Date: _____________________

G. REMOVE PK test plug from PK block TD1.

H. REPLACE panel 12 PK block covers on PK blocks TD1 and TD2.

Performed By: _________________________ Date: ______________________

CV: __________________________________ Date: _____________________

                                                          • END CRITICAL SECTION*****************************

Page 17 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 5.24 FUNCTIONAL TEST OF DEVICE 32 REVERSE POWER RELAY NOTE Device 32 contains a directional unit located at the top of the relay and a time unit located at the bottom of the relay.

A. CLOSE 1-BKR-211-1912/6-A using test close pushbutton.

NOTE Diesel Generator 1A-A Safety Shutdown relays and annunciations will be actuated in Step 5.24 B.

B. Momentarily CLOSE Device 32 time unit contacts and

1) CONFIRM 1-RLY-82-86GA1 tripped.

Performed By: _________________________ Date: ______________________

2) CONFIRM 1-BKR-211-1912/6-A tripped.

Performed By: _________________________ Date: ______________________

3) CONFIRM Device 32 target exposed.

Performed By: _________________________ Date: ______________________

C. RESET 1-RLY-82-86GA1.

D. RESET 1-HS-82-20 [0-M-26].

E. ENSURE Device 32 target is reset.

F. REPLACE cover on Device 32.

Page 18 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 5.25 FUNCTIONAL TEST OF DEVICE 46 PHASE BALANCE CURRENT RELAY NOTE Device 46 contains an upper and lower unit. Each unit is equipped with a left and right contact.

NOTE Each trip of 1-RLY-82-86GA1 will cause annunciations to alarm and DG safety shutdown relays to pickup. This was checked earlier.

A. Momentarily Close Device 46 upper left contact, and

1) CONFIRM 1-RLY-82-86GA1 tripped.

Performed By: _________________________ Date: ______________________

2) CONFIRM Device 46 target exposed.

Performed By: _________________________ Date: ______________________

B. RESET 1-RLY-82-86GA1.

C. Momentarily CLOSE Device 46 upper right contact, and CONFIRM 1-RLY-82-86GA1 tripped.

Performed By: _________________________ Date: ______________________

D. RESET 1-RLY-82-86GA1.

E. Momentarily CLOSE Device 46 lower left contact, and CONFIRM 1-RLY-82-86GA1 tripped.

Performed By: _________________________ Date: ______________________

Page 19 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 F. RESET 1-RLY-82-86GA1.

G. Momentarily CLOSE Device 46 lower right contact, and CONFIRM 1-RLY-82-86GA1 tripped.

Performed By: _________________________ Date: ______________________

H. RESET 1-RLY-82-86GA1.

I. RESET 1-HS-82-20 [0-M-26].

J. ENSURE Device 46 target is reset.

K. REPLACE cover on Device 46.

Page 20 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 5.26 FUNCTIONAL TEST OF DEVICE 40 LOSS OF FIELD RELAY NOTE Device 40 contains a top directional unit, a middle distance unit, and a bottom undervoltage unit.

NOTE Each trip of 1-RLY-82-86GA1 will cause annunciations to alarm and DG safety shutdown relays to pickup. This was checked earlier.

A. ENSURE 1-HS-82-29B Loss of Field Cutout Switch [LFS switch, located on 1-PNL-82-A] is ON.

B. ENSURE "Loss of Field" red alarm light [1-PNL-82-A] is not illuminated.

C. Manually CLOSE bottom unit right hand contact, middle unit left contact, and top unit left contact on Device 40 simultaneously and CONFIRM 1-RLY-82-86GA1 tripped and Loss of Field red alarm light is illuminated while contacts are closed.

D. PLACE 1-HS-82-29B in CUTOUT.

E. PLACE 1-HS-82-29B ON.

F. RESET 1-RLY-82-86GA1.

G. Manually CLOSE bottom unit left hand contact, middle unit left contact, and top unit left contact on Device 40 simultaneously, and

1) CONFIRM Device 40 target exposed.
2) CONFIRM 1-RLY-82-86GA1 tripped.

Performed By: _________________________ Date: ______________________

Page 21 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 H. PLACE 1-HS-82-29B in CUTOUT.

I. ENSURE Device 40 target unit is dropped out and target reset.

J. PLACE 1-HS-82-29B ON.

K. RESET 1-RLY-82-86GA1.

L. RESET 1-HS-82-20 [0-M-26].

M. REPLACE cover on Device 40.

Page 22 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 5.27 FUNCTIONAL TEST OF DEVICE 87 DIFFERENTIAL RELAY NOTE Device 87 disconnect switches are numbered 1 to 10 on the bottom left to right and 11 to 20 on the top right to left.

NOTE Each trip of 1-RLY-82-86GA1 will cause annunciations to alarm and DG safety shutdown relays to pickup. This was checked earlier.

A. OPEN Device 87 disconnect switches 3, 17, and 19 and ISOLATE with insulating strips B. Manually CONNECT AC current source to relay side of switches 3 and 17.

C. APPLY 0.2 A to relay, and

1) CONFIRM Device 87 target light is illuminated.
2) CONFIRM 1-RLY-82-86GA1 tripped.

Performed By: _________________________ Date: ______________________

D. Manually REMOVE AC current source from relay.

E. REMOVE insulating strips and CLOSE Device 87disconnect switches 3, 17, and 19.

F. RESET Device 87 target light.

G. RESET 1-RLY-82-86GA1.

Page 23 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 H. OPEN Device 87 disconnect switches 4, 13, and 15 and ISOLATE with insulating strips I. Manually CONNECT AC current source to relay side of switches 4 and 13.

J. APPLY 0.2 A to relay, and

1) CONFIRM Device 87 target light is illuminated.
2) CONFIRM 1-RLY-82-86GA1 is tripped.

Performed By: _________________________ Date: ______________________

K. Manually REMOVE AC current source from relay.

L. REMOVE insulating strips and CLOSE Device 87 disconnect switches 4, 13, and 15.

M. RESET Device 87 target light.

N. RESET 1-RLY-82-86GA1.

O. OPEN Device 87 disconnect switches 5, 7, and 9 and ISOLATE with insulating strips.

P. Manually CONNECT AC current source to relay side of switches 5 and 7.

Q. APPLY 0.2 A to relay, and

1) CONFIRM Device 87 target light is illuminated.
2) CONFIRM 1-RLY-82-86GA1 tripped.

Performed By: _________________________ Date: ______________________

R. Manually REMOVE AC current source from relay.

Page 24 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 S. REMOVE insulating strips and CLOSE Device 87 disconnect switches 5, 7, and 9.

T. RESET Device 87 target light.

U. REPLACE cover on Device 87.

V. RESET 1-RLY-82-86GA1.

W. RESET 1-HS-82-20.

5.28 FUNCTIONAL TEST OF DEVICE 51 OVERCURRENT RELAY A. Manually CLOSE and HOLD Device 51 contact, and

1) CONFIRM Device 51 target exposed.
2) ENSURE Window 197D is illuminated.
3) ENSURE Window 282D is illuminated.
4) ENSURE Display Point 197D indicated alarm.

B. RELEASE Device 51 contact, and

1) RESET Device 51 target.
2) ENSURE Window 197D is not illuminated.
3) ENSURE Window 282D is not illuminated.
4) ENSURE Display Point 197D indicated normal.

C. REPLACE cover on Device 51.

Page 25 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 5.29 FUNCTIONAL TEST OF DEVICE 59N NEUTRAL OVERVOLTAGE RELAY A. Manually CLOSE and HOLD Device 59N contact, and

1) CONFIRM Device 59N target exposed.
2) ENSURE Window 197D is illuminated.
3) ENSURE Window 282D is illuminated.
4) ENSURE Display Point 197D indicated alarm.

B. RELEASE Device 59N contact, and

1) RESET Device 59N target.
2) ENSURE Window 197D is not illuminated.
3) ENSURE Window 282D is not illuminated.
4) ENSURE Display Point 197D indicated normal.

C. REPLACE cover on Device 59N.

Page 26 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 5.30 FUNCTIONAL TEST OF DEVICE 64 DC FIELD GROUND DETECTOR RELAY NOTE Field Ground Detected red alarm light is reset by pushbutton on 1-PNL-82-A/2. Depressing this pushbutton may cause any alarm that was previously in to alarm again both locally and in the control room.

A. ENSURE Field Ground Detected red alarm light [1-PNL-82-A/2] is not illuminated.

B. Manually CLOSE and HOLD Device 64 left hand contact, and

1) ENSURE Field Ground Detected red alarm light is illuminated.
2) ENSURE Window 197D is illuminated.
3) ENSURE Window 282D is illuminated.
4) ENSURE Display Point 197D indicated alarm.

C. RELEASE Device 64 left hand contact, and

1) ENSURE Field Ground Detected red alarm light is not illuminated.
2) ENSURE Window 197D is not illuminated.
3) ENSURE Window 282D is not illuminated.
4) ENSURE Display Point 197D indicated normal.

D. Manually CLOSE and HOLD Device 64 right hand contact, and

1) ENSURE Field Ground Detected red alarm light is illuminated.
2) ENSURE Window 197D is illuminated.
3) ENSURE Window 282D is illuminated.
4) ENSURE Display Point 197D indicated alarm.

Page 27 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 E. RELEASE Device 64 right hand contact, and

1) ENSURE Field Ground Detected red alarm light is not illuminated.
2) ENSURE Window 197D is not illuminated.
3) ENSURE Window 282D is not illuminated.
4) ENSURE Display Point 197D indicates normal.

F. REPLACE cover on Device 64.

Page 28 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 5.31 FUNCTIONAL TEST OF DEVICES 51VA, 51VB, AND 51VC VOLTAGE CONTROLLED OVERCURRENT RELAYS NOTE Devices 51V contain a directional unit located at the top of the relay and a time unit located at the bottom of the relay.

A. Manually CLOSE and HOLD Device 51VA Time Unit contact, and

1) CONFIRM Device 51VA target exposed.
2) ENSURE Window 197D is illuminated.
3) ENSURE Window 282D is illuminated.
4) ENSURE Display Point 197D indicated alarm.

B. RELEASE Device 51VA Time Unit contact, and

1) RESET Device 51VA target.
2) ENSURE Window 197D is not illuminated.
3) ENSURE Window 282D is not illuminated.
4) ENSURE Display Point 197D indicated normal.

C. Manually CLOSE and HOLD Device 51VB Time Unit contact, and

1) CONFIRM Device 51VB target exposed.
2) ENSURE Window 197D is illuminated.
3) ENSURE Window 282D is illuminated.
4) ENSURE Display Point 197D indicated alarm.

Page 29 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 D. RELEASE Device 51VB Time Unit contact, and

1) RESET Device 51VB target.
2) ENSURE Window 197D is not illuminated.
3) ENSURE Window 282D is not illuminated.
4) ENSURE Display Point 197D indicated normal.

E. Manually CLOSE and HOLD Device 51VC Time Unit contact, and

1) CONFIRM Device 51VC target exposed.
2) ENSURE Window 197D is illuminated.
3) ENSURE Window 282D is illuminated.
4) ENSURE Display Point 197D indicated alarm.

F. RELEASE Device 51VC Time Unit contact, and

1) RESET Device 51VC target.
2) ENSURE Window 197D is not illuminated.
3) ENSURE Window 282D is not illuminated.
4) ENSURE Display Point 197D indicated normal.

G. REPLACE cover on Device 51VA.

H. REPLACE cover on Device 51VB.

I. REPLACE cover on Device 51VC.

Page 30 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 5.32 FUNCTIONAL TEST OF DEVICE 59 AC OVERVOLTAGE RELAY A. Manually CLOSE and HOLD Device 59 contact and ENSURE Overvoltage red light [1-PNL-82-A] is illuminated.

B. RELEASE Device 59 contact and ENSURE Overvoltage red light is not illuminated.

C. REPLACE cover on Device 59 and ENSURE target is reset.

5.33 CONFIRM all work is complete and component is ready for PMT.

Performed By: __________________________________ Date: _____________

Page 31 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 6.0 POST MAINTENANCE TEST 6.1 Maintenance Test:

A. None Required 6.2 Return to Operability Test (RTO): as recommended by planning A. None Required 6.3 Response Time Testing (RTT):

A. None Required 6.4 Additional RTO/RTT Testing as Required by Operations:

A. PERFORM additional RTO/RTT testing as required by operations as follows:

IF no additional RTO/RTT is required, THEN N/A below signatures, ELSE RECORD additional test(s) below.

Additional RTO PMT added by SRO_____________________________________ Date: _____________

Additional RTO PMT approved by SRO_____________________________________ Date: _____________

Page 32 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 7.0 POST WORK ACTIVITIES 7.1 RETURN 1-BKR-211-1912/6-A to as-found position or as directed by Operations, and INDICATE as-left position of 1-BKR-211-1912/6-A.

CONNECTED DISCONNECTED TEST OPEN CLOSED SEISMIC Performed By: _________________________ Date: ______________________

Peer Check: __________________________ Date: ______________________

7.2 CONFIRM all relay plugs and covers installed, targets reset, and auxiliary relays reset.

Performed By: _________________________ Date: ______________________

Peer Check: __________________________ Date: ______________________

7.3 CONFIRM test coupler removed.

Performed By: _________________________ Date: ______________________

7.4 CONFIRM that all relay cases and covers are in good state of cleanliness.

Performed By: _________________________ Date: ______________________

7.5 RETURN 0-HS-55-L4A [0-L-4] to as-found position or as directed by Operations, and INDICATE as-left position:

ON OFF Performed By: _________________________ Date: ______________________

Page 33 of 34 Template Rev 8/10/14

UNID: 1-GEN-82-1A-A PM Work PM 600108453 WO #: WO NUMBER Instructions Rev: 4 7.6 REQUEST OPS to release hold order.

Performed By: _________________________ Date: ______________________

7.7 ENSURE 1-RLY-82-86LOR1 DG 1A-A EMERGENCY START LOCKOUT is reset.

Performed By: _________________________ Date: ______________________

Peer Check: __________________________ Date: ______________________

7.8 ENSURE 1-RLY-82-86GA1 DG 1A-A PROTECTIVE RELAY LOCKOUT is reset.

Performed By: _________________________ Date: ______________________

Peer Check: __________________________ Date: ______________________

7.9 NOTIFY SM/SRO and UO that work is complete.

Performed By: _________________________ Date: ______________________

7.10 CONFIRM that all sign-off entries are complete or N/A.

Performed By: _________________________ Date: ______________________

7.11 IF any unacceptable condition found during performance of this PM is not corrected, THEN RECORD "AS-FOUND" condition, and CONTACT responsible engineer for evaluation and corrective action. N/A if not required.

Engineer Notified: ______________________________

Performed By: _________________________ Date: ______________________

Page 34 of 34 Template Rev 8/10/14

WATTS BAR NUCLEAR PLANT PREVENTATIVE MAINTENANCE (PM)

WORK INSTRUCTIONS UNIT 1 6900V Diesel Generator 1A-A Differential Relay Calibration Test PM #: 600108466 REVISION: 2 UNID: 1-GEN-082-0001A-A WO #: WO NUMBER Effective Date: 1-20-15 Planning Organization: MEG, Electrical Prepared By: T. Benson Reviewed By: A. Franklin

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 Revision Log Revision Affected Description of Revision or Change Revised By/ Page Number Date Numbers Include PMCR/PER Number Previously 0 Approved All Replaces MI-82.069.

Deletes all references to the Carbon Pile method of test, adds 2nd Party / Concurrent Previously verification requirements for relay removal and 1 Approved All re-installation, and performs minor reformatting.

TAB PMUG 0440W Converted to new format 2 01/14/15 All Assigned 600108466 as new PM Number Page 2 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 SCOPE: The purpose of this Preventative Maintenance (PM) Instruction is to 6900V Diesel Generator 1A-A Differential Relay Calibration Test.

General Info:

Vendor Drawing: None Vendor Manual: WBN-VTM-AS08-0010 TVA Drawings: 1-45W760-82-1 and 1-45W760-82-5 Commitments:

None Recommended Tools:

Standard tool kit Various test leads Westinghouse stand and plug Recommended M&TE:

Doble Relay Test Set(s)

DC Voltmeter Dranetz 325 Polymeter or equivalent Page 3 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 Recommended Materials:

Glass Cleaner Towels Gang Trip Relay (Stand-In) 125 Vdc Power Supply (Sorensen or equivalent)

Controller

References:

TVA Field Test Manual, Volume 1, Book 1.

Relay Setting Sheet (RSS) 6458, dated 07-18-79.

Page 4 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 1.0 EQUIPMENT CATEGORY 1.1 See work order form and associated asset form for equipment classification.

1.2 See NEDP-4 for material requirements.

2.0 REQUIREMENTS 2.1 If directed by the work supervisor, then WO steps may be re-performed and/or worked out of sequence unless the WO contains a specific requirement that steps be performed in sequence.

3.0 PRECAUTIONS AND LIMITATIONS 3.1 This Instruction provides detailed steps to calibrate the Device 87 Differential Relay associated with Diesel Generator (DG) 1A-A.

3.2 The differential relay may be calibrated only when DG 1A-A can be inoperable.

Removal of differential relay may cause DG 1A-A to be inoperable.

3.3 The use of duplicate M&TE for double verification of reading is recommended.

3.4 Protest and Doble Relay Test Sets may be used to calibrate relay.

3.5 Do not exceed 30 amps applied for test purposes.

3.6 Any test current over continuous rating (20 A restraint and 10 A operating) should not be applied for more than 31 seconds.

3.7 While making adjustments to restraint resistors, do not exceed the continuous current rating of the restraint or operating circuits.

3.8 Device 87 Differential Relay is located on 1-ARB-082-A/1A.

Page 5 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 3.9 As-left relay data is to be within r 5% of setting for minimum pickup and pickup at 5 Amps restraint.

3.10 Responsible Engineer should be notified as soon as possible if relay cannot be calibrated to r 5%.

3.11 Steps may be repeated as necessary.

3.12 If determined additional work or work outside original scope of work order is required that cannot be accomplished IAW MMDP-1, Section 3.1.2, then document information needed for re-planning in actual work performed section and return work order to planning.

Page 6 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 4.0 PREREQUISITES 4.1 OBTAIN a clearance PRIOR to starting work, OR ENSURE an approved JSA has been approved to perform the work. N/A if not required.

Clearance Number: __________________ JSA NONE REQUIRED Performed By: __________________________________ Date: _____________

4.2 OBTAIN SM / SRO permission and NOTIFY UO of tests to be performed.

4.3 RECORD plant mode of operation: _____________

Page 7 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 5.0 WORK INSTRUCTIONS 5.1 ENSURE equipment to be worked is the same as that specified in the scope of this PM Work Instruction PRIOR to starting work activities.

Performed By: __________________________________ Date: _____________

Peer Check: ____________________________________ Date: _____________

5.2 REMOVE cover and Device 87 Relay from panel 1-ARB-082-A/1A.

Performed By: __________________________________ Date: _____________

Peer Check by: _________________________ Date:______________________

5.3 Visually INSPECT relay for broken or damaged posts, loose connections, and capacitor electrolyte leakage.

NOTE Contact status may be monitored via trip indicator light on relay except during operational test where gang trip relay will be used.

5.4 PASS operating current through Studs 3, 4, and 5 using the test circuit for Phase 1 shown in Appendix A.

5.5 CHECK and RECORD the as-found Phase 1 minimum pickup current in Appendix B.

5.6 IF the reading is outside the acceptable range, THEN A. DISCONNECT the 125 Vdc from the relay.

B. ADJUST the top left resistor (rear view of relay) as needed.

C. CONNECT the 125 Vdc to the relay.

Page 8 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 5.7 CHECK and RECORD the as-left Phase 1 minimum pickup current in Appendix B.

5.8 CHECK and RECORD the as-found Studs 3, 4, and 5 operating current required for Phase 1 pickup with 5 Amps restraint current passing through Stud 19 in Appendix B.

5.9 IF reading is outside the acceptable range, THEN A. DISCONNECT the 125 Vdc from the relay.

B. ADJUST the top right resistor (rear view of relay) as needed.

C. CONNECT the 125 Vdc to the relay.

5.10 CHECK and RECORD the as-left Studs 3, 4, and 5 operating current required for Phase 1 pickup with 5 Amps restraint current passing through Stud 19 in Appendix B.

5.11 CHECK and RECORD the Studs 3, 4, and 5 operating current required for Phase 1 pickup with 10, 15, and 20 Amps restraint current passing through Stud 19 in Appendix B.

5.12 ALTER the test circuit connections shown in Appendix A by placing the return test lead on Stud 19 and the restraint test lead on Stud 17.

5.13 CHECK and RECORD the Studs 3, 4, and 5 operating current required for Phase 1 pickup with restraint currents of 5, 10, 15 and 20 Amps passing through Stud 17 in Appendix B.

5.14 RESET the gang trip relay.

5.15 RESET the trip indicator light on the relay.

5.16 INCREASE the operate current to the relay through Studs 3, 4, and 5 above 0.14 Amps, and CONFIRM the gang trip relay is TRIPPED and the trip indicator light is LIT.

Performed By: __________________________________ Date: _____________

Page 9 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 5.17 PASS operating current through Studs 3, 4, and 5 using the test circuit for Phase 2 shown in Appendix A.

5.18 DETERMINE and RECORD the as-found Phase 2 minimum pickup current in Appendix B.

5.19 IF the reading is outside the acceptable range, THEN A. DISCONNECT the 125 Vdc from the relay.

B. ADJUST the middle left resistor (rear view of relay) as needed.

C. CONNECT the 125 Vdc to the relay.

5.20 CHECK and RECORD the as-left Phase 2 minimum pickup current in Appendix B.

5.21 CHECK and RECORD the as-found Studs 3, 4, and 5 operating current required for Phase 2 pickup with 5 Amps restraint current passing through Stud 15 in Appendix B.

5.22 IF reading is outside the acceptable range, THEN A. DISCONNECT the 125 Vdc from the relay.

B. ADJUST the middle right resistor (rear view of relay) as needed.

C. CONNECT the 125 Vdc to the relay.

5.23 CHECK and RECORD as-left Studs 3, 4, and 5 operating current required for Phase 2 pickup with 5 Amps restraint current passing through Stud 15 in Appendix B.

5.24 CHECK and RECORD the Studs 3, 4, and 5 operating current required for Phase 2 pickup with 10, 15, and 20 Amps restraint current passing through Stud 15 Appendix B.

Page 10 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 5.25 ALTER the test circuit connection shown in Appendix A by placing the return test lead on Stud 15 and the restraint test lead on Stud 13.

5.26 CHECK and RECORD the Studs 3, 4, and 5 operating current required for Phase 2 pickup with 5, 10, 15, and 20 Amps restraint current passing through Stud 13 in Appendix B.

5.27 RESET the gang trip relay.

5.28 RESET the trip indicator light on the relay.

5.29 INCREASE the operating current to the relay through studs 3, 4, and 5 above 0.14 Amps, and CONFIRM the gang trip relay is TRIPPED and the trip indicator light is LIT.

Performed By: __________________________________ Date: _____________

5.30 PASS operating current through Studs 3, 4, and 5 using the test circuit for Phase 3 shown in Appendix A.

5.31 CHECK and RECORD the as-found Phase 3 minimum pickup current in Appendix B.

5.32 IF the reading is outside the acceptable range, THEN A. DISCONNECT the 125 Vdc from the relay.

B. ADJUST the bottom left resistor (rear view of relay) as needed.

C. CONNECT the 125 Vdc to the relay.

5.33 CHECK and RECORD the as-left Phase 3 minimum pickup current in Appendix B.

5.34 CHECK and RECORD as-found Studs 3, 4, and 5 operating current required for Phase 3 pickup with 5 Amps restraint passing through Stud 9 in Appendix B.

Page 11 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 5.35 IF reading is outside the acceptable range, THEN A. DISCONNECT the 125 Vdc from the relay.

B. ADJUST the bottom right resistor (rear view of relay) as needed.

C. CONNECT the 125 Vdc to the relay.

5.36 CHECK and RECORD as-left Studs 3, 4, and 5 operating current required for Phase 3 pickup with 5 Amps restraint current passing through Stud 9 in Appendix B.

5.37 CHECK and RECORD the Studs 3, 4, and 5 operating current required for Phase 3 pickup with 10, 15, and 20 Amps restraint current passing through Stud 9 in Appendix B.

5.38 ALTER the test circuit connection shown in Appendix A by placing the return test lead on Stud 9 and the restraint test lead on Stud 7 5.39 CHECK and RECORD the Studs 3, 4 and 5 operating current required for Phase 3 pickup with restraint currents of 5, 10, 15, and 20 Amps passing through Stud 7 in Appendix B.

5.40 RESET the gang trip relay.

5.41 RESET the trip indicator light on the relay.

5.42 INCREASE the operating current to the relay through studs 3, 4, and 5 above 0.14 Amps, and CONFIRM the gang trip relay is TRIPPED and the trip indicator light is LIT.

Performed By: __________________________________ Date: _____________

5.43 ENSURE relay data is within acceptable range.

5.44 ENSURE relay cover is in a good state of cleanliness.

Page 12 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 5.45 RETURN relay to panel 1-ARB-082-A/1A and CLOSE all test switches except test switch No. 1 (red handle).

5.46 ENSURE trip indicator light is NOT LIT.

5.47 CLOSE test switch No. 1 (red handle) and REPLACE cover on Device 87 Differential Relay.

Performed By: __________________________________ Date: _____________

Peer Check by: _________________________ Date:______________________

5.48 CONFIRM all work is complete and component is ready for PMT.

Performed By: __________________________________ Date: _____________

Page 13 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 6.0 POST MAINTENANCE TEST 6.1 Maintenance Test:

A. None Required 6.2 Return to Operability Test (RTO): as recommended by planning A. None Required 6.3 Response Time Testing (RTT):

A. None Required 6.4 Additional RTO/RTT Testing as Required by Operations:

A. PERFORM additional RTO/RTT testing as required by operations as follows:

IF no additional RTO/RTT is required, THEN N/A below signatures, ELSE RECORD additional test(s) below.

Additional RTO PMT added by SRO_____________________________________ Date: _____________

Additional RTO PMT approved by SRO_____________________________________ Date: _____________

Page 14 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 7.0 POST WORK ACTIVITIES 7.1 NOTIFY UO that testing is complete on this Instruction.

7.2 NOTIFY SM / SRO that tests are complete on this Instruction.

7.3 IF any unacceptable condition found during performance of this PM is not corrected, then RECORD as found condition, and RETURN to supervision for evaluation and corrective action.

Comments: _______________________________________________________

Page 15 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 APPENDIX A Page 1 of 1 WESTINGHOUSE TYPE SA-1 DIFFERENTIAL RELAY TEST CONNECTIONS Doble Relay Test Sets Method of Test:

Page 16 of 17 Template Rev 8/10/14

UNID: 1-GEN-082-0001A-A PM Work PM 600108466 WO #: WO NUMBER Instructions Rev: 2 APPENDIX B Page 1 of 1 DEVICE 87 DIFFERENTIAL RELAY TEST DATA P RESTRAINT INSTR OPERATE CURRENT H CURRENT MANUAL (STUDS 3, 4, AND 5)

ACCEPTABLE A OPER RANGE AS- AS-S STUD APPLIED CURR STEP STEP E VALUE FOUND LEFT 19 0 0.140 0.133 to 0.147 5.5 _____ 5.7 _____

19 5 0.250 0.240 to 0.260 5.8 _____ 5.10 _____

1 19 10 1.1 N/A N/A N/A 5.11 _____

19 15 2.5 N/A N/A N/A 5.11 _____

19 20 4.5 N/A N/A N/A 5.11 _____

17 5 0.250 N/A N/A N/A 5.13 _____

17 10 1.1 N/A N/A N/A 5.13 _____

17 15 2.5 N/A N/A N/A 5.13 _____

17 20 4.5 N/A N/A N/A _____

5.13 15 0 0.140 0.133 to 0.147 5.18 _____ 5.20 _____

15 5 0.250 0.240 to 0.260 5.21 _____ 5.23 _____

2 15 10 1.1 N/A N/A N/A 5.24 _____

15 15 2.5 N/A N/A N/A 5.24 _____

15 20 4.5 N/A N/A N/A 5.24 _____

13 5 0.250 N/A N/A N/A 5.26 _____

13 10 1.1 N/A N/A N/A 5.26 _____

13 15 2.5 N/A N/A N/A 5.26 _____

13 20 4.5 N/A N/A N/A 5.26 _____

9 0 0.140 0.133 to 0.147 5.31 _____ 5.33 _____

9 5 0.250 0.240 to 0.260 5.34 _____ 5.36 _____

3 9 10 1.1 N/A N/A N/A 5.37 _____

9 15 2.5 N/A N/A N/A 5.37 _____

9 20 4.5 N/A N/A N/A 5.37 _____

7 5 0.250 N/A N/A N/A 5.39 _____

7 10 1.1 N/A N/A N/A 5.39 _____

7 15 2.5 N/A N/A N/A 5.39 _____

7 20 4.5 N/A N/A N/A 5.39 _____

Visual Inspection performed Yes No Page 17 of 17 Template Rev 8/10/14