MONTHYEARCNL-15-001, Application to Revise Technical Specification 4.2.1, Fuel Assemblies, (WBN-TS-15-03)2015-03-31031 March 2015 Application to Revise Technical Specification 4.2.1, Fuel Assemblies, (WBN-TS-15-03) Project stage: Request CNL-15-077, Correction to Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03)2015-04-28028 April 2015 Correction to Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) Project stage: Request ML15121A8262015-05-0101 May 2015 Annual Radioactive Effluent Release Report - 2014 Project stage: Request ML15127A2502015-05-14014 May 2015 Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Application to Increase Tritium Production Absorbing Rods Project stage: Acceptance Review CNL-15-092, Response to NRC Request to Supplement the Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03)2015-05-27027 May 2015 Response to NRC Request to Supplement the Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) Project stage: Supplement CNL-15-093, Response to NRC Request to Supplement Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Radiological Protection and Radiological Consequences2015-06-15015 June 2015 Response to NRC Request to Supplement Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Radiological Protection and Radiological Consequences Project stage: Supplement CNL-15-104, Submittal of Revision 106, Appendix C to Central Emergency Control Center, Radiological Emergency Plan2015-06-15015 June 2015 Submittal of Revision 106, Appendix C to Central Emergency Control Center, Radiological Emergency Plan Project stage: Request ML15173A0972015-06-26026 June 2015 Acceptance Review Results for Requested License Amendment to Increase Tpbar Production Project stage: Acceptance Review ML15173A1142015-06-26026 June 2015 Letter for Individual Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for Hearing Project stage: Other ML15173A1162015-06-26026 June 2015 FRN for Individual Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for Hearing Project stage: Other ML15225A3772015-08-12012 August 2015 Tennessee Valley Authority Presentation to NRC on Tpbar LAR 8-12-15 Project stage: Other ML15226A4662015-08-14014 August 2015 NRR E-mail Capture - Request for Additional Information Regarding Tritium Production License Amendment Project stage: RAI ML15236A3152015-08-24024 August 2015 NRR E-mail Capture - Watts Bar Unit 1- Draft RAIs- Tpbars Amendment MF6050 Project stage: Draft Other ML15238A5782015-08-25025 August 2015 NRR E-mail Capture - Watts Bar 1- Final Rad Protection RAIs for MF6050 Project stage: RAI CNL-15-172, Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Response to NRC Request for Additional Information - Reactor Systems Branch2015-09-14014 September 2015 Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Response to NRC Request for Additional Information - Reactor Systems Branch Project stage: Response to RAI ML15225A3752015-09-17017 September 2015 August 12, 2015 - Summary of Public Meeting Regarding Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Increase Tritium Production Project stage: Meeting CNL-15-192, Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Response to NRC Request for Additional Information - Radiation Protection and Consequence Branch2015-09-25025 September 2015 Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Response to NRC Request for Additional Information - Radiation Protection and Consequence Branch Project stage: Response to RAI ML15278A0482015-10-0202 October 2015 NRR E-mail Capture - Tpbar RAIs Part 3b- Arcb Project stage: RAI ML15286A0012015-10-0909 October 2015 NRR E-mail Capture - Regulatory Audit Plan - TVA License Amendment Request Regarding Tritium Producing Burnable Absorber Rods - CAC No. MF6050 Project stage: Other CNL-15-232, Attachment 1, CE-15-588-NP-Attachment, Rev. 1 and Attachment 3, CE-15-611-NP-Attachment Regarding Proposed Response to NRC RAIs Nos. 1, 2, 3, and 4 Regarding LAR for Increasing the Maximum Number of Tpbars in Watts Bar, Unit 1. (Non-Propr2015-11-30030 November 2015 Attachment 1, CE-15-588-NP-Attachment, Rev. 1 and Attachment 3, CE-15-611-NP-Attachment Regarding Proposed Response to NRC RAIs Nos. 1, 2, 3, and 4 Regarding LAR for Increasing the Maximum Number of Tpbars in Watts Bar, Unit 1. (Non-Proprie Project stage: Response to RAI CNL-15-216, Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) (TAC No. MF6050) - Response to NRC Request for Additional Information - Radiation Protection and Consequence Branch2015-12-22022 December 2015 Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) (TAC No. MF6050) - Response to NRC Request for Additional Information - Radiation Protection and Consequence Branch Project stage: Response to RAI CNL-15-263, Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Supplemental Information Related to the Onsite Regulatory Audit at Pacific Northwest National Laboratory2015-12-29029 December 2015 Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Supplemental Information Related to the Onsite Regulatory Audit at Pacific Northwest National Laboratory Project stage: Supplement CNL-16-030, Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) (TAC No. MF6050) - Supplement to Response to NRC Request for Additional Information - Radiation Protection and Consequence Branch2016-02-22022 February 2016 Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) (TAC No. MF6050) - Supplement to Response to NRC Request for Additional Information - Radiation Protection and Consequence Branch Project stage: Supplement 2015-05-27
[Table View] |
|
---|
Category:Letter type:CNL
MONTHYEARCNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions CNL-24-016, Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-01-10010 January 2024 Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-23-052, Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability2024-01-0909 January 2024 Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability CNL-23-062, Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018)2024-01-0808 January 2024 Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018) CNL-23-069, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) CNL-23-001, Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01)2023-12-13013 December 2023 Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01) CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 CNL-23-045, License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010)2023-08-0707 August 2023 License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010) CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions CNL-23-020, Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06)2023-06-28028 June 2023 Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06) CNL-23-049, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan .2023-06-26026 June 2023 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan . CNL-23-044, Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out2023-06-0101 June 2023 Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out CNL-23-042, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-05-16016 May 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-043, Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09)2023-05-0404 May 2023 Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09) CNL-23-030, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2023-04-27027 April 2023 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-23-032, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 412023-04-27027 April 2023 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 41 CNL-23-033, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-04-24024 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-029, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-04-11011 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-023, Annual Insurance Status Report2023-03-30030 March 2023 Annual Insurance Status Report CNL-23-022, Decommissioning Funding Status Report2023-03-29029 March 2023 Decommissioning Funding Status Report CNL-23-024, TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report2023-03-29029 March 2023 TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report CNL-23-002, Application to Revise Watts Bar Nuclear Plant Units 1 and 2 Technical Specifications to Change the Number of Tritium Producing Burnable Absorber Rods (WBN-TS-21-02) and Proposed Revision to Reactor Vessel Surveillance Capsule Removal Sche2023-03-20020 March 2023 Application to Revise Watts Bar Nuclear Plant Units 1 and 2 Technical Specifications to Change the Number of Tritium Producing Burnable Absorber Rods (WBN-TS-21-02) and Proposed Revision to Reactor Vessel Surveillance Capsule Removal Schedu CNL-23-021, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-03-0808 March 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-015, Expedited Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-22-08)2023-02-27027 February 2023 Expedited Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-22-08) CNL-23-003, Browns Nuclear Plant, Units 1, 2 & 3; Sequoyah Nuclear Plant, Units 1 & 2; and Watts Bar Nuclear Plant, Units 1 & 2 - Organizational Topic Report TVA-NPOD89-A2023-01-30030 January 2023 Browns Nuclear Plant, Units 1, 2 & 3; Sequoyah Nuclear Plant, Units 1 & 2; and Watts Bar Nuclear Plant, Units 1 & 2 - Organizational Topic Report TVA-NPOD89-A CNL-23-009, Response to Request for Additional Information Request to Revise Technical Specification 3.4.122023-01-0404 January 2023 Response to Request for Additional Information Request to Revise Technical Specification 3.4.12 CNL-23-008, Tennessee Valley Authority Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2022-12-22022 December 2022 Tennessee Valley Authority Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-22-109, Steam Generator Tube Inspection Report to Reflect TSTF-577 Reporting Requirements2022-12-22022 December 2022 Steam Generator Tube Inspection Report to Reflect TSTF-577 Reporting Requirements CNL-22-101, American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Request for Alternative WBN-2-ISI-012022-11-28028 November 2022 American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Request for Alternative WBN-2-ISI-01 CNL-22-106, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-14, Revision 38, Nuclear Emergency Public Information Organization and Operat2022-11-28028 November 2022 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-14, Revision 38, Nuclear Emergency Public Information Organization and Operatio CNL-22-099, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2022-10-31031 October 2022 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-22-098, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC EPIP-7, Rev. 45 & CECC EPIP-8, Rev. 552022-10-17017 October 2022 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC EPIP-7, Rev. 45 & CECC EPIP-8, Rev. 55 CNL-22-085, Response to Request for Additional Information Regarding Sequoyah Nuclear Plant (Sqn), Units 1 and 2 and Watts Bar Nuclear Plant (Wbn), Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Al2022-09-0202 September 2022 Response to Request for Additional Information Regarding Sequoyah Nuclear Plant (Sqn), Units 1 and 2 and Watts Bar Nuclear Plant (Wbn), Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alte CNL-22-077, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2022-08-11011 August 2022 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-22-030, Application to Revise Technical Specification 3.4.12, Low Temperature Overpressure Protection System for Sequoyah Nuclear Plant (SQN-TSC-22-01) and TS 3.4.12 Cold Overpressure Mitigation System for Watts Bar Nuclear Plant (WBN-TS-22-03)2022-07-27027 July 2022 Application to Revise Technical Specification 3.4.12, Low Temperature Overpressure Protection System for Sequoyah Nuclear Plant (SQN-TSC-22-01) and TS 3.4.12 Cold Overpressure Mitigation System for Watts Bar Nuclear Plant (WBN-TS-22-03) CNL-22-039, Application to Revise Technical Specifications to Adopt TSTF-554-A, Revision 1, Revise Reactor Coolant Leakage Requirements (BFN TS-537) (SQN-21-05) (WBN-TS-21-04)2022-07-13013 July 2022 Application to Revise Technical Specifications to Adopt TSTF-554-A, Revision 1, Revise Reactor Coolant Leakage Requirements (BFN TS-537) (SQN-21-05) (WBN-TS-21-04) CNL-22-071, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections (SQN-TS-21-03 and WBN-TS-21-08)2022-07-13013 July 2022 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections (SQN-TS-21-03 and WBN-TS-21-08) CNL-22-070, Status Regarding the Improved Flood Mitigation System Project2022-06-30030 June 2022 Status Regarding the Improved Flood Mitigation System Project CNL-22-008, and Watts Bar Nuclear Plant - Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules (BFN-TS-541, SQN-TS-21-09, and WBN-TS-22-002)2022-06-13013 June 2022 and Watts Bar Nuclear Plant - Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules (BFN-TS-541, SQN-TS-21-09, and WBN-TS-22-002) CNL-22-064, Response to Request for Additional Information Regarding Tennessee Valley Authority License Amendment Request to Revise Emergency Plan Implementing Procedure Regarding Seismic Event Emergency Action Level Change2022-06-0909 June 2022 Response to Request for Additional Information Regarding Tennessee Valley Authority License Amendment Request to Revise Emergency Plan Implementing Procedure Regarding Seismic Event Emergency Action Level Change CNL-22-068, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2022-06-0808 June 2022 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-22-047, Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2022-05-23023 May 2022 Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions CNL-22-043, Response to Request for Additional Information and Confirmation of Information Regarding Application to Modify Watts Bar Nuclear Plant Units 1 and 2 Technical Specification 3.7.8 to Support Shutdown Board.2022-05-0202 May 2022 Response to Request for Additional Information and Confirmation of Information Regarding Application to Modify Watts Bar Nuclear Plant Units 1 and 2 Technical Specification 3.7.8 to Support Shutdown Board. CNL-22-046, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan.2022-04-28028 April 2022 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan. 2024-01-09
[Table view] |
Text
1101 Market Street, Chattanooga, Tennessee 37402 CNL-15-092 May 27 , 2015 10 CFR 50.90 ATTN : Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 1 Facility Operating License Nos. NFP-90 NRC Docket No . 50-390
Subject:
Response to NRC Request to Supplement the Application to Revise Technical Specification 4.2.1, "Fuel Assemblies" (WBN-TS-15-03)
Reference:
- 1. Letter From TVA to NRC , "Application to Revise Technical Specification 4.2.1, 'Fuel Assemblies ,' (WBN-TS-15-03) ," dated March 31 , 2015 (ADAMS Accession No. ML15098A446)
- 2. Letter From NRC to TVA, "Watts Bar Nuclear Plant, Unit 1 -
Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Application to Increase Tritium Producing Absorber Rods (TAC NO . MF6050)," dated May 14, 2015 (ADAMS Accession No . ML15127A250)
By letter dated March 31 , 2015 (Reference 1), Tennessee Valley Authority (TVA) submitted a license amendment request (LAR) to revise Watts Bar Nuclear Plant (WBN), Unit 1 Technical Specification (TS) 4.2.1, "Fuel Assemblies ," to increase the maximum number of Tritium Producing Burnable Absorber Rods (TPBARs) that can be irradiated per cycle from 704 to 1,792. The proposed change also revises TS 3.5.1, "Accumulators," Surveillance Requirement (SR) 3.5.1 .4 and TS 3.5.4, "Refueling Water Storage Tank (RWST)," SR 3.5.4.3 to delete outdated information related to the Tritium Production Program .
By letter dated May 14, 2015 , the Nuclear Regulatory Commission (NRC) requested that TVA provide additional information to supplement the LAR.
U. S. Nuclear Regulatory Commission Page 2 May 27 , 2015 The enclosure to this letter provides the requested human factors supplemental information. As stated in the Reference 2 letter, this supplement is due May 28, 2015 .
Supplemental information responses to Enclosures 2 and 3 of the Reference 2 letter will be provided in a separate TVA letter consistent with the requested due date of June 15, 2015.
Consistent with the standards set forth in Title 10 of the Code of Federal Regulations (1 0 CFR), Part 50.92(c) , TVA has determined that the additional information, as provided in this letter, does not affect the no significant hazards consideration associated with the proposed application previously provided in Reference 1.
Additionally, in accordance with 10 CFR 50.91(b)(1) , TVA is sending a copy of this letter and the enclosures to the Tennessee Department of Environment and Conservation .
There are no new regulatory commitments associated with this submittal. Please address any questions regarding this request to Mr. Edward D. Schrull at (423) 751-3850.
I declare under penalty of perjury that the foregoing is true and correct. Executed on this 27th day of May 2015.
a President, Nuclear Licensing WBN-TS-15-03 Supplemental Information Enclosure cc (Enclosure) :
NRC Regional Administrator- Region II NRC Resident Inspector- Watts Bar Nuclear Plant NRC Project Manager- Watts Bar Nuclear Plant Director, Division of Radiological Health- Tennessee State Department of Environment and Conservation
U.S. Nuclear Regulatory Commission Page3 May 27, 2015 CWS/EDS Enclosure bee (Enclosure):
NSRB EDMS B. M. Duckett bee (w/o Enclosure 2):
G. P. Arent M. A. Balduzzi R. M. Bateman C. A. Borrelli G. A. Boerschig J. M. Casner C. R. Church S. M. Connors E. W. Cobey D. M. Czufin S. M. Douglas J.P. Grimes J. M. Keck M. W. McBrearty E. D. Schrull J. W.Shea M.D. Skaggs S. A. Vance K. T. Walsh B. A. Wetzel R. C. Williams ECM
ENCLOSURE TENNESSEE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT UNIT1 WBN-TS-15-03 Supplemental Information Information needed by the U.S. Nuclear Regulatory Commission staff to begin its review of the Tennessee Valley Authority's (TVA) request to increase tritium producing burnable absorber rods related to human factors considerations is described below.
On page E1-8 of 18 of TVA's March 31, 2015, submittal, TVA states:
In order to eliminate this unborated dilution source and the associated manual actions, TVA will replace the containment isolation thermal relief check valves on the lower compartment supply lines to the containment for WBN [Watts Bar Nuclear Plant], Unit 1 Component Cooling Water System and Essential Raw Cooling Water (ERCW) System with simple relief valves.
E1-1 Provide a list of the operator actions being eliminated, changed, or added in support of the license amendment request (LAR) (list the operator actions approved in Amendment No. 51 and indicate which ones are being eliminated or changed).
E1-2 Provide a list procedures that require revision in support of the LAR (number, title, and revision).
E1-3 Provide a list of any training required to support of the LAR.
E1-4 Identify any changes to the control room interface (displays, controls, alarms) resulting from this LAR.
E1-5 Identify any changes to the simulator required to support the LAR.
E1-6 Describe any required changes to the Safety Parameter Display System.
TVA Response The following Operator Manual Actions described in WBN, Unit 1 License Amendment 51 will be eliminated by the design change replacing the containment isolation thermal relief check valves on the lower compartment supply lines to the containment for WBN, Unit 1 Component Cooling Water System (CCS) and Essential Raw Cooling Water (ERCW) System with simple relief valves (i.e., passive devices).
- 1. Manual isolation of the six-inch ERCW supply to the lower containment cooler Group D from the main supply Header 1B by closing the safety-related valve 1-ISV-67-5238, which is located in the Auxiliary Building at elevation 692, within 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> after the postulated accident.
CNL-15-092 E1 of2
- 2. Manual isolation of the six-inch CCS supply and return lines for the reactor coolant pump oil cooler penetrating containment by closing safety-related valves 1-ISV-70-516 (supply) and 1-ISV-70-700 (return), as applicable within 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> of the accident, concurrent with the single failure of the outboard containment isolation valve to close.
WBN, Unit 1 License Amendment 51 also described other activities required to implement the above Operator Manual Actions. TVA anticipates that scaffolding to access ERCW supply valve 1-ISV-67-5238 and the associated administrative controls will no longer be required following implementation of the design change described in the LAR. In addition, TVA anticipates that changes to Emergency Operating Instruction 1-E-0, "Reactor Trip of Safety Injection,"
Revision 5, to remove the above Operator Manual Actions and subsequent operator training on the deletion of the Operator Manual Actions will be required.
TVA anticipates that there will be no changes to the control room interface (displays, controls, alarms), simulator, and Safety Parameter Display System required to support the design change because the manual actions are performed remotely from the control room. However, the design change has not been finalized. Therefore, additional procedure changes and training needs may be identified as the design change progresses through the development and approval process.
TVA procedure NPG-SPP-09.3, "Plant Modifications and Engineering Change Control,"
provides requirements to manage the content, impact review, and implementation of design changes. These requirements provide assurance that the affected Disciplines and Departments review the change as it is developed for impact to items under their control, such as procedures, training, control room interfaces, and the simulator.
CNL-15-092 E2 of2