MONTHYEARCNL-15-001, Application to Revise Technical Specification 4.2.1, Fuel Assemblies, (WBN-TS-15-03)2015-03-31031 March 2015 Application to Revise Technical Specification 4.2.1, Fuel Assemblies, (WBN-TS-15-03) Project stage: Request CNL-15-051, Guarantee of Payment of Deferred Premiums - 2014 Annual Report2015-04-0707 April 2015 Guarantee of Payment of Deferred Premiums - 2014 Annual Report Project stage: Request CNL-15-077, Correction to Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03)2015-04-28028 April 2015 Correction to Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) Project stage: Request ML15121A8262015-05-0101 May 2015 Annual Radioactive Effluent Release Report - 2014 Project stage: Request CNL-15-079, Reply to Notice of Violation (EA-14-179)2015-05-0101 May 2015 Reply to Notice of Violation (EA-14-179) Project stage: Other ML15127A2502015-05-14014 May 2015 Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Application to Increase Tritium Production Absorbing Rods Project stage: Acceptance Review CNL-15-092, Response to NRC Request to Supplement the Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03)2015-05-27027 May 2015 Response to NRC Request to Supplement the Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) Project stage: Supplement CNL-15-093, Response to NRC Request to Supplement Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Radiological Protection and Radiological Consequences2015-06-15015 June 2015 Response to NRC Request to Supplement Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Radiological Protection and Radiological Consequences Project stage: Supplement CNL-15-104, Submittal of Revision 106, Appendix C to Central Emergency Control Center, Radiological Emergency Plan2015-06-15015 June 2015 Submittal of Revision 106, Appendix C to Central Emergency Control Center, Radiological Emergency Plan Project stage: Request ML15173A0972015-06-26026 June 2015 Acceptance Review Results for Requested License Amendment to Increase Tpbar Production Project stage: Acceptance Review ML15173A1142015-06-26026 June 2015 Letter for Individual Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for Hearing Project stage: Other ML15173A1162015-06-26026 June 2015 FRN for Individual Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for Hearing Project stage: Other ML15225A3772015-08-12012 August 2015 Tennessee Valley Authority Presentation to NRC on Tpbar LAR 8-12-15 Project stage: Other ML15226A4662015-08-14014 August 2015 NRR E-mail Capture - Request for Additional Information Regarding Tritium Production License Amendment Project stage: RAI ML15236A3152015-08-24024 August 2015 NRR E-mail Capture - Watts Bar Unit 1- Draft RAIs- Tpbars Amendment MF6050 Project stage: Draft Other ML15238A5782015-08-25025 August 2015 NRR E-mail Capture - Watts Bar 1- Final Rad Protection RAIs for MF6050 Project stage: RAI CNL-15-172, Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Response to NRC Request for Additional Information - Reactor Systems Branch2015-09-14014 September 2015 Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Response to NRC Request for Additional Information - Reactor Systems Branch Project stage: Response to RAI ML15225A3752015-09-17017 September 2015 August 12, 2015 - Summary of Public Meeting Regarding Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Increase Tritium Production Project stage: Meeting CNL-15-192, Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Response to NRC Request for Additional Information - Radiation Protection and Consequence Branch2015-09-25025 September 2015 Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Response to NRC Request for Additional Information - Radiation Protection and Consequence Branch Project stage: Response to RAI ML15278A0482015-10-0202 October 2015 NRR E-mail Capture - Tpbar RAIs Part 3b- Arcb Project stage: RAI ML15286A0012015-10-0909 October 2015 NRR E-mail Capture - Regulatory Audit Plan - TVA License Amendment Request Regarding Tritium Producing Burnable Absorber Rods - CAC No. MF6050 Project stage: Other CNL-15-232, Attachment 1, CE-15-588-NP-Attachment, Rev. 1 and Attachment 3, CE-15-611-NP-Attachment Regarding Proposed Response to NRC RAIs Nos. 1, 2, 3, and 4 Regarding LAR for Increasing the Maximum Number of Tpbars in Watts Bar, Unit 1. (Non-Propr2015-11-30030 November 2015 Attachment 1, CE-15-588-NP-Attachment, Rev. 1 and Attachment 3, CE-15-611-NP-Attachment Regarding Proposed Response to NRC RAIs Nos. 1, 2, 3, and 4 Regarding LAR for Increasing the Maximum Number of Tpbars in Watts Bar, Unit 1. (Non-Proprie Project stage: Response to RAI CNL-15-216, Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) (TAC No. MF6050) - Response to NRC Request for Additional Information - Radiation Protection and Consequence Branch2015-12-22022 December 2015 Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) (TAC No. MF6050) - Response to NRC Request for Additional Information - Radiation Protection and Consequence Branch Project stage: Response to RAI CNL-15-263, Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Supplemental Information Related to the Onsite Regulatory Audit at Pacific Northwest National Laboratory2015-12-29029 December 2015 Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) - Supplemental Information Related to the Onsite Regulatory Audit at Pacific Northwest National Laboratory Project stage: Supplement CNL-16-030, Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) (TAC No. MF6050) - Supplement to Response to NRC Request for Additional Information - Radiation Protection and Consequence Branch2016-02-22022 February 2016 Application to Revise Technical Specification 4.2.1, Fuel Assemblies (WBN-TS-15-03) (TAC No. MF6050) - Supplement to Response to NRC Request for Additional Information - Radiation Protection and Consequence Branch Project stage: Supplement 2015-05-27
[Table View] |
Text
Watts Bar Nuclear Plant Unit 1 TPBAR Loading Increase License Amendment Request Alignment Meeting
2 Agenda Introduction and Purpose WBN Unit 1 TPBAR Loading Plans Licensing Activities Schedule Timeline for WBN Unit 1 TPBAR Program Proposed Technical Specification Changes Post-LOCA Subcriticality Analysis Radiological Analysis NRC Review with TVA and DOE Support Summary
3 Introduction
- TVA requested a change to the Watts Bar Nuclear Plant (WBN)
Unit 1 Technical Specifications to increase the number of Tritium Producing Burnable Absorber Rods (TPBARs) that can be irradiated from 704 to 1792
- TVA requested NRC approval by August 31, 2016, to support an increased TPBAR loading in Cycle 15 (spring of 2017) for DOE National Nuclear Security Administration (NNSA) needs
4 Purpose
- Provide a high level overview of the License Amendment Request (LAR)
- Discuss the schedule of the LAR review to meet the NNSA need date
- Offer TVA and DOE support of NRC technical reviews
5 WBN Unit 1 TPBAR Loading Plans Cycle Date TPBAR Loading Tech Spec Limit C13 April 2014 704 704 C14 October 2015 704 704 C15 March 2017 1104 1792*
C16 October 2018 1504 1792*
C17 April 2020 1792 1792*
Licensing Activities Schedule 6
July 2014 June 2017 January 2015 January 2016 January 2017 1792 TPBAR License Amendment Key Milestones April 2015 - August 2016 NRC Review August 2016 NRC SER for 1792 TPBARs June 2015 Submit LAR Supplemental
Response
April 2017 Cycle 15 Startup August 2014 Pre-Application Meeting with NRC March 2016 Start Cycle 15 Fuel Design August 2015 Review Kickoff Meeting with NRC March 2015 Submit LAR February 2016 NRC Management Meeting on Review Status March 2016 - October 2016 Fuel Design & Delivery July 2016 Start Cycle 15 Fuel Fabrication February 2016
7 Timeline for WBN Unit 1 TPBAR Program
- May 1996 - DOE/NRC Memorandum of Understanding (MOU) formed the basis for NRC review and consultation on possible use of Commercial Light Water Reactors (CLWRs) for producing tritium
- Oct 1996 - TVA agreed to irradiate 32 TPBARs in four Lead Test Assemblies (LTAs) at WBN Unit 1
- Sept 1997 - WBN Unit 1 Amendment 8 (LTAs) issued
- Oct 1997 - 32 TPBARs loaded in Cycle 2
8 Timeline for WBN Unit 1 TPBAR Program (cont.)
- Sept 2002 - WBN Unit 1 Amendment 40 approved up to 2304 TPBARs
- Oct 2003 - WBN Unit 1 Amendment 48 reduced loading to 240 TPBARs to address post-LOCA subcriticality margin issue
- Oct 2003 - 240 TPBARs loaded in Cycle 6
- Mar 2005 - TVA notified NRC of interim cumulative TPBAR tritium release limits
- While higher than projected permeation rates were investigated
- Apr 2005 - 240 TPBARs loaded in Cycle 7
9 Timeline for WBN Unit 1 TPBAR Program (cont.)
- Nov 2006 - 240 TPBARs loaded in Cycle 8
- Jan 2008 - WBN Unit 1 Amendment 67 approved up to 400 TPBARs
- Mar 2008 - 368 TPBARs loaded in Cycle 9
- May 2009 - WBN Unit 1 Amendment 77 approved up to 704 TPBARs
- Oct 2009 - 240 TPBARs loaded in Cycle 10
- May 2011 - 544 TPBARs loaded in Cycle 11
10 Timeline for WBN Unit 1 TPBAR Program (cont.)
- Oct 2012 - 544 TPBARs loaded in Cycle 12
- May 2014 - 704 TPBARs loaded in Cycle 13
- Jan 2015 - TVA notified NRC of updated program controls to remove interim measures for permeation while maintaining doses and release concentrations within regulatory requirements
- Oct 2015 - 704 TPBARs planned for loading in Cycle 14
11 Current License Amendment Request
- LAR submitted to NRC on March 31, 2015
- Correction letter submitted to NRC on April 28, 2015
- Provided supplemental information in letters dated May 27, 2015, and June 15, 2015, in response to NRC requests
- NRC accepted LAR for review on June 26, 2015
Proposed Technical Specification Changes
> yyyy ppm and < zzzz ppm
13 Post-LOCA Subcriticality Analysis
- Post-LOCA subcriticality analysis method consistent with method previously used in WBN Unit 1 Amendment 77 with the following key changes:
- Eliminated 40 gpm dilution source in containment sump (requires plant modifications)
- Updated time-dependent lithium leaching rate based on testing
- RCS boron concentration reduced by increased Integral Fuel Burnable Absorber (IFBA) loading
- Results demonstrate sufficient margin for 1792 TPBARs
14 Radiological Analysis
- Radiological analysis in WBN Unit 1 Amendment 40 assumed 2304 TPBARs and permeation rate of 1 Ci/TPBAR/year
- Current LAR supported by new radiological analysis for:
- Realistic scenario of up to 1900 TPBARs at 5 Ci/TPBAR/year
- Bounding (Design Basis) scenario of up to 2500 TPBARs at 10 Ci/TPBAR/year
- Regulatory criteria in 10 CFR Part 20, Part 50.67, Part 50 Appendix I, and Part 100 are all satisfied
15 NRC Review with TVA and DOE Support
- Due to the importance of meeting the NNSA need for increased TPBAR irradiation in WBN Unit 1 Cycle 15, TVA requests essential completion of NRC technical reviews prior to initiation of fuel and core design activities on March 2, 2016
- TVA and DOE will provide any support needed for expeditious technical reviews
- TVA and DOE are willing to send technical experts to meet with NRC reviewers to provide any needed background information or discussion of the various LAR sections
- TVA requests at least monthly updates from the NRC Project Manager regarding the progress of the technical reviews
16 Summary
- LAR requests increased TPBAR loadings beginning with WBN Unit 1 Cycle 15 to meet NNSA needs
- LAR addresses post-LOCA subcriticality margin, required plant modifications, lithium leaching rates, and radiological analysis
- TVA and DOE offer technical support for NRC reviewers
- TVA requests monthly progress updates from NRC Project Manager
- TVA requests NRC technical reviews near completion by March 2, 2016
- TVA requests NRC approval by August 31, 2016