3F0797-34, Confirms Util Schedule for Completing CR-3 Thermo-Lag Resolution Program & to Address Open Requests for Exemptions Needed in Support of Licensee Schedule.Subj Program Will Be Completed on or Before 001229

From kanterella
Jump to navigation Jump to search
Confirms Util Schedule for Completing CR-3 Thermo-Lag Resolution Program & to Address Open Requests for Exemptions Needed in Support of Licensee Schedule.Subj Program Will Be Completed on or Before 001229
ML20196H762
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 07/26/1997
From: Holden J
FLORIDA POWER CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
3F0797-34, 3F797-34, NUDOCS 9708010009
Download: ML20196H762 (4)


Text

__

{'.

y .!

Florida Power c EU.3 Dock 2t No. 50 302 July 26,1997 3F0797-34 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001

Subject:

Current Status and Schedule Overview of Crystal River 3 (CR-3)

Thermo-Lag Resolution Program

References:

1. FPC to NRC letter, 3F1295-05, dated December 21,1995
2. FPC to NRC letter, 3F0996-19, dated September 27,1996
3. FPC to NRC letter, 3F0197-10, dated January 29,1997
4. FPC to NRC letter, 3F0696-04, dated June 21,1996

Dear Sir:

The purpose of this letter is to confirm Florida Power Corporation's (FPC) schedule for completing the CR-3 Thermo-Lag Resolution Program, and to address the open requests for exemptions needed in support of our schedule.

On December 21,1995, FPC provided the Nuclear Regulatory Commission (NRC) with the details and an implementation schedule for the CR-3 Thermo-Lag Resolution Program (Reference 1). Subsequently, FPC informed the NRC, in Reference letters 2 and 3, of schedule delays on some of the program milestones.

A meeting was requested by the NRC to discuss current program status and potential schedule delays. On May 20,1997, FPC met with the NRC and provided a presentation and status of the Thermo-Lag Resolution Program. This was subsequently reaffirmed in another meeting with the NRC on CR-3 Appendix R issues on June 11,1997. 1

^~

9708010009 970726 'T / g PDR ADOCK 05000302 @lllllll{llllll'lllllll

.... .- .. - Off p PDR CRYSTAL RIVER ENERGY COMPLEX: 1s7so w Pow., Line si. . crystes av.e. Fionio. 3442s s70s a tas2 7ss-64ss A Flo,ida P, ogress Company

O U. S. Nuclear Regulatory Commission 3F0797-34 Page 2 of 3 The following status and schedule information are provided for the four elements of the CR-3 Thermo-Lag Resolution Program:

Analvsis Changes Removing Reliance on Thermo-Lag Fire Barriers Re-analysis of Thermo-Lag fire barrier reliance is scheduled to be completed 90 days following restart from the current outage. This effort has been accelerated and is anticipated to be completed ahead of schedule. The overall estimate for reduction in reliance on Thermo-Lag fire barriers using re-analysis remains at 62%.

Barrier Uogrades and Reolacement Installation of Mecatiss fire barriers in the Control Complex and upgrades of Reactor Building radiant energy shields is complete. The overall estimate for reduction in reliance on Thermo-Lag fire barriers for these plant modifications is 5%. The NRC indicated they would review the 10 CFR 50.59 evaluation for removing Thermo-Lag from the NI detectors in the Reactor Building as an Inspector Follow-up Item. FPC l considers this item closed, pending NRC review.

Plant Modifications  !

As provided in our original Thermo-Lag resolution program, Reference 1, plant modifications were originally scheduled for two refueling outages with an overall completion date in December 2000. It is now estimated that 40% of the required plant modifications will be completed prior to restart from the current outage. The overall estimate for reduction in reliance on Thermo-Lag fire barriers using plant modifications is 18%, hence an estimated 7% reduction in Thermo-Lag fire barriers will be achieved prior to restart from the current outage.

Thermo-Lag Exemotica Reouest As provided in Reference 4, the fourth element of the CR-3 Thermo-Lag resolution is an exemption request. This exemption request includes installing additional i sprinklers in the Auxiliary and Intermediate Buildings and replacing damaged .

l Thermo-Lag in the Intermediate Building with Mecatiss. The design of the new l sprinklers is currently underway, but installation will no longer be possible during the current outage. Sprinkler installation will begin during the next operating cycle and be completed during Refuel 11. FPC requires this exemption to meet the

~

overall schedule for Thermo-Lag resolution for the remaining 15% of the Thermo-Lag fire barriers. As stated in the June 11,1997 meeting, FPC has confirmed that  !

l l

l

. . -. , . . - .~. - .__ ~ _ . ---- . ---

'.- l i

i U. S. Nuclear Regulatory Commission  !

3F0797-34

! Page 3 of 3 [

l none of the open Appendix R issues _ at CR-3 would impact the validity of this exemption request. NRC action is requested on the Thermo-Lag exemption request.

l ~ Emergencv Lighting Exemotion Reauest I I

FPC also requested an exemption for Emergency Lighting in Reference 4. Based on  !

resolution of open Appendix R issues in conformance with Appendix R l

. requirements, none of the open Appendix R issues at CR-3 will have any impact on this exemption. No further Emergency Lighting exemption requests are required. .

NRC action is requested on the Emergency Lighting exemption. )

Conclusions FPC has made excellent progress in resolving Thermo-Lag fire barrier. issues at CR- j

3. No further exemption requests are required. The CR-3 Thermo-Lag resolution j

~

program is on schedule and will be completed on or before December 29,2000.

However, final completion of this program is dependent on NRC decisions regarding  ;

l FPC's exemption request, Reference 4. In order to maintain current schedules, FPC  !

is proceeding with design and installation assuming that these exemptions will be i granted'as requested. l I

Attachment 1 contains a list of commitments made in this letter. If you have any l questions regarding this letter, please contact D. F. Kunsemiller, Manager, Nuclear

! Licensing at (352) 563-4566.

l

Sincerely, l

l hib-l J. J. Holden, Director l

Nuclear Engineering and Projects 4

l JJH/jnb Attachment

! xc: Regional Administrator, Region ll ]

Senior Resident Inspector NRR Project Manager i

l l

i U.S. Nuclear Regulatory Commission Attachment 1

! 3F0797-34 Page 1 of 1 l

l ATTACHMENT 1 List of Regulatory Commitments The following table identifies those actions committed to by Florida Power Corporation in this document. Any other actions discussed in the submittal represents intended or planned actions by Florida Power Corporation. They are described to the NRC for the NRC's information and are not regulatory commitments. Please notify the Manager, Nuclear Licensing, of any questions regarding this document or- any associated regulatory commitments.

ID Number Commitment ' Commitment Date 3F0797-34-1 Complete approximately 40% of the Prior to Restart Thermo-Lag circuit modifications, as

! described in the referenced letter, prior to restart from the current outage. <

, 3F0797-34-2 Following issuance of the Thermo-Lag Prior to Restart from l exemption, begin the installation of Refuel 11 l

sprinklers in the exempted areas during i

the next operating cycle and be completed during Refuel 11. ,

l l

l I

l i

A i

i