Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 03/08/1994
From: Beard P
FLORIDA POWER CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
3F0394-03, 3F394-3, GL-89-10, NUDOCS 9403160327
Download: ML20064G734 (9)


Text

_

Florida Power CORPORATION Na f6Ju March 8, 1994 3F0394-03 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555

Subject:

Motor Operated Valve (MOV) Program Status

References:

Draft Generic Letter 89-10 Supplement 6 FPC to NRC letter, 3F0992-05, dated September 18, 1992

Dear Sir:

The purpose of this letter is to provide a summary status concerning Generic Letter (GL) 89-10 MOV related activities and to clarify the scope of valve setup and testing at Florida Power Corporation (FPC).

FPC is continuing M0V work activities which should result in all GL 89-10 program MOVs being appropriately setup with the best available data by the end of Refuel

9. Refuel 9, which is the third refuel since GL 85-10 was issued, is scheduled for completion in early June,1994. Enclosed, as an atachment, is a table of GL 89-10 MOVs, their status, and any-applicable notes.

There are, however, several outstanding MOV issues that continue to challenge FPC resources and may affect our MOV program. :These issues are as follows:

a Valve mispositioning, for PWRs, remains an unresolved issue that can significantly affect the scope of work associat ed with certain valves.

FPC has not included valve mispositioning induced dPs as an input to determine valve operation.

= Reduced voltage is considered in M0V calculations. Some calculations are being revised to incorporate new information.

= Pressure locking and thermal binding will be addressed when generic communications are developed.

El1 A $

CRYSTAL RNER ENERGY COMPLEX: 15760 W Power une St . Crystal River, Florida 344284708 e (904) 795-6486 k

^ *" "

9403160327 940300 PDR ADOCK 05000302 P PDR

O. S. Nuclear Regulatory Commission 3F0394-03 Page 2 of 9-

. Our goal is to ensure all currently identified GL 89-10 MOV issues are either resolved or action plans in effect by the end of June, 1994.

The enclosed attachment lists those valves that are included in the GL 89-10 program.

Sincerely, P. M. Beard, Jr.

b Senior Vice President Nuclear Operations PMB/PVF:ff Attachment xc: Regional Administrator NRR Project Manager Senior Resident Inspector l

U. S. Nuclear Regulatory Commission 3F0394-03 Page 3 of 9 ATTACHMENT GL 89-10 MOVs are grouped into the following test categories at FPC:

= Dynamic Testing - these valves are tested at differential pressures as close to design basis conditions as possible and are setup to operate at design basis conditions using diagnostic equipment.

= Functional Verification - these valves are tested by stroking the valve to its safety function position during the normal course of operating the nuclear plant, primarily using surveillance procedures and operating procedures. They are setup, statically, to a thrust setting derived from applicable calculations. Diagnostic equipment is used for initial setup .

- = Head Pressure Testing - these valves use the head of the tank they are connected to for developing the required dP. Diagnostic equipment is used for initial setup'.

= Not Practical Due to Plant Conditions - these valves are typically stroke checked under static conditions and most are setup using a thrust setting.

These valves will be tested using the EPRI developed program or a suitable alternative.

DYNAMIC IESTING Valva Valve Description Comments Tag #

ASV-5 Steam Inlet Isolation to dP testing and setup complete.

the Turbine Driven Emergency Feedwater Pump DHV-7 "B" Train LPI/DH dP testing and setup scheduled for Discharge Cross-Tie Refuel 9 or earlier.

DHV-8 "A" Train LPI/DH dP testing and setup scheduled for Discharge Cross-Tie Refuel 9 or earlier.

DHV-11 "A" Train LPI Tie to HPI ReducedpPtestperformed, setup Suction Header complete DHV-12 "B" Train LPI Tie to HPI ReducedpPtestperformed, setup Suction Header complete DHV-91 DH/LPI to PZR Spray dP testing and setup complete. .

Isolation DWV-160 DW Isolation to RB Reduced dP testing and setup complete2,

+

+

O. S. Nuclear Regulatory Commission 3F0394-03 Page 4 of 9 EFV-11 Turbine Driven Emergency dP testing and setup complete.

Feedwater Pump Isolation to "A" 0TSG EFV-14 Motor Driven Emergency dP testing and setup complete.

Feedwater Pump Isolation to "A" 0TSG EFV-32 Turbine Driven Emergency dP testing and setup complete.

Feedwater Pump Isolation to "B" 0TSG EFV-33 Motor Driven Emergency dP testing and setup complete.

Feedwater Pump Isolation to "B" 0TSG FWV-14 "A" Main Feedwater Pump Initial dP testing and setup complete.

Suction Additional dP testing scheduled for Refuel 9.

FWV-15 "B" Main Feedwater Initial dP testing and setup complete.

Suction Additional dP testing scheduled for Refuel 9.

FWV-28 Main Feedwater Discharge dP testing and setup complete3 .

Cross-Tie FWV-29 "B" Main Feedwater Main dP testing and setup complete'.

Block i FWV-30 "A" Main Feedwater Main dP testing and setup complete'.

Block FWV-31 "A" Main Feedwater Low dP testing and setup complete3 .

Load Block l FWV-32 "B" Main Feedwater low dP testing and setup complete3 .

Load Block FVW-33 "B" Main Feedwater dP testing and setup complete3 .

Start-Up Block j FWV-36 "A" Main Feedwater ReducedglPtestingandsetup Start-Up Block complete '3.

MUV-18 RCP Seal Injection Reduced dP testing and setup complete2 ,

Isolation Block MUV-23 HPI Control to "A" RCS dP testing and setup complete.

Loop

~

1 U. S. Nuclear Regulatory Commission 1 3F0394-03 Page 5 of 9 MUV-24 HPI Control to "A" RCS dP testing and setup complete.

Loop MUV-25 HPI Control to "B" RCS dP testing and setup complete.

Loop i I

MUV-26 HPI Control to "B" RCS dP testing and setup complete.  ;

Loop MUV-27 RCS Makeup Block dP testing and setup complete.

1 MUV-53 Outboard MVP dP testing cpmplete, setup scheduled Recirculation Isolation for Refuel 9 MUV-257 Inboard MVP dPtestingcpmplete,setupscheduled Recirculation Isolation for Refuel 9 FUNCTIONAL VERIFICATION Valve Valve Name Comments Tag #

ASV-204 Steam Inlet Isolation to Setup scheduled for Refuel 9.

the Turbine Driven Emergency Feedwater Pump CAV-1 PZR Steam Space Sample Setup scheduled for Refuel 9.

Isolation CAV-3 -PZR Water Space Sample Setup scheduled for Refuel 9.

Isolation CAV-4 "A" OTSG Shell Side Setup scheduled for Refuel 9.

Sample Isolation '

CAV-5 "A" 0TSG Shell Side Setup scheduled for Refuel 9.

Sample Isolation CAV-126 RCS Letdown Isolation Setup scheduled for Refuel 9.

CFV-11 "A" Core Flood Tank Setup scheduled for Refuel 9.

Sample Isolation CFV-12 "B" Core Flood Tank Setup seneduled for Refuel 9.

Sample Isolation CFV-15 "B" Core Flood Tank Vent Setup scheduled for Refuel 9.

Isolation

U. S. Nuclear Regulatory Commission 3F0394-03 Page 6 of 9 CFV-16 "A" Core Flood Tank Vent Setup scheduled for Refuel 9.

Isolation DHV-39 DH Drop Line Isolation Setup complete.

to DHP-1A DHV-40 DH Drop Line Isolation Setup complete.

to DHP-18 DHV-110 "A" Train LPI/DHR Flow Setup complete.

Control DHV-lll "B" Train LPI/DHR Flow Setup complete.

, Control MUV-3 Discharge Cross-fie for Setup complete.

MVP-1B and MVP-lC MUV-9 Discharge Cross-Tie for Setup complete.

MVP-1A and MVP-1B MUV-38 Letdown Cooler 3A Inlet Setup scheduled for Refuel 96 .

Isolation MUV-39 Letdown Cooler 3B Inlet Set;n scheduled for Refuel 9 6, Isolation MUV-62 Suction Cross-Tie for dP testing and setup complete.

MVP-1B and MVP-lC MUV-69 Suction Cross-Tie for dP testing and setup complete.

MUP-1A and MVP-1B MUV-498 Letdown Cooler 3C Inlet Setup scheduled for Refuel 96 ,

Isolation RCV-13 PZR Spray Block Setup complete.

RCV-14 PZR Spray Control Valve replacement with testing and setup scheduled for Refuel 9.

RCV-53 LPI/DH to PZR Spray Setup complete.

Isolation / Control

.' U. S. Nuclear Regulatory Commission 3F0394-03 Page 7 of 9 HEAD PRESSURE TESTING Valve Valve Name Comments Tag #

BSV-16 BSP-18 Suction Isolation Testing and setup complete.

BSV-17 BSP-1A Suction Isolation Testing and setup complete.

DHV-34 BWST Outlet Isolation to Testing and setup complete.

DHP-1A (LPI)

DHV-35 BWST Outlet Isolation to Testing and setup scheduled for Refuel DHP-1B (LPI) 9 or earlier.

MUV-58 BWST Outlet Isolation to Testing and setup complete.

HPI, "B" Train MUV-73 BWST Outlet Isolation to Testing and setup complete.

HPI, "A" Train NoT PRACTICAL TO IEST Valve Valve Name Comments Tag #

BSV-3 "B" Train RB Spray Setup complete.

Isolation / Control BSV-4 "A" Train RB Spray Setup complete.  !

Isolation / Control DHV-3 DH Drop Line Isolation Setup complete.

(Inside RB)

DHV-4 DH Drop Line Isolation Setup complete.

(Inside RB)

DHV-5 "A" Train LPI Injection LimitedpPtestperformed, setup complete DHV-6 "B" Train LPI Injection LimitedpPtestperformed, setup complete DHV-41 DH Drop Line Isolation Setup complete.

(Outside RB) l DHV-42 RB Sump.to "A" Train LPI Setup complete.

U. S. Nuclear Regulatory Commission 3F0394-03 Page 8 of 9 i

DHV RB Sump to "B" Train LPI Setup complete.

MSV Steam Isolation from "A" Limited dP testing and setup complete7.

OTSG to the Turbine Driven Emergency Feedwater Pump MSV-56 Steam Isolation from "B" Limited dP testing and setup complete7 .

OTSG to the Turbine Driven Emergency Feedwater Pump MUV-40 Letdown Cooler 3A Outlet Setup scheduled for Refuel 9.

Isolation MUV-41 Letdown Cooler 3B Outlet Setup scheduled for Refuel 9.

Isolation MUV-258 RCP-1A Controlled Bleed- LimitedpPte:' performed, setup Off Isolation complete MUV-259 RCP-1B Controlled Bleed- LimitedpPtestperformed, setup Off Isolation complete MUV-260 RCP-lC Controlled Bleed- Limited pP test performed, setup Off Isolation complete MUV-261 RCP-ID Controlled Bleed- LimitedpPtestperformed, setup Off Isolation complete MUV-505 Letdown Cooler 3C Outlet Setup scheduled for Refuel 9.

Isolation ,

RCV-Il PORV Block Existing valve setup complete. Valve replacement, atesting and setup is scheduled for Refuel 9.

WDV-3 RB Sump Isolation Setup complete.

WDV-60 RC Drain Tank Vent Setup complete.

Isolation WDV-94 RC Drain Tank /RC Drain Reducedp'Ptestperformed, 7 setup Pump Isolation complete .

WDV-405 RB Vent Header Isolation Setup complete.

WDV-406 RB Vent Header Isolation Setup complete. ,

9

^

U. S. Nuclear Regulatory Commission 3F0394-03 Page 9 of 9

- Notes:

1. Diagnostic equipment is also used post maintenance, as needed, and when performing periodic testing at the determined frequency.
2. dP established between 50% and 80% of design basis.
3. Reliance on operator action, during low powcr operation, minimizes the differential pressure FWV-28 would have to close against.
4. Reliance on either the related train feedwater pump trip or its associated suction valve closing significantly reduces the dP across these valves.
5. Accuracy associated with the original method is considered unacceptable due to rising - rotating stem. .
6. Screening for removal from program.
7. dp is typically < 50% of design basis pressure or test results are not ,

currently beneficial. Further evaluations pending EPRI test program results.