MONTHYEARML20217F9941999-10-15015 October 1999 Discusses FPC 970819 Request for Temporary Relief from ASME Code Section XI Requirements to Repair ASME Class 3 Nuclear Service & Decay Heat Sea Water System Piping.Forwards SE Containing Results of Staff Review ML20217J5171999-10-13013 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Plant,Unit 3 & Did Not Identify Any New Areas That Warranted More than Core Insp Program.Previously Planned Regional Initiative Insp of safety-related Mod Will Be Performed 3F1099-14, Requests Copy of NRC Radtrad Code & Copy of User Instructions.Conditions for Receiving Code Listed1999-10-13013 October 1999 Requests Copy of NRC Radtrad Code & Copy of User Instructions.Conditions for Receiving Code Listed 3F1099-11, Provides Info on Requested Minor Permit Mod of Encl NPDES Permit.No New Regulatory Commitments Are Made1999-10-0404 October 1999 Provides Info on Requested Minor Permit Mod of Encl NPDES Permit.No New Regulatory Commitments Are Made ML20212L0771999-10-0404 October 1999 Forwards SER Accepting Licensee Relief Requests 98-012 Through 98-018 Involving Containment Insps at Crystal River Unit 3 Pursuant to 10CFR50.55a(a)(3)(i) & 10CFR50.55a(a)(3)(ii) ML20217D6551999-10-0101 October 1999 Requests That Natl Communication Sys Arrange for Licensee Participation in Government Emergency Telecommunications Service,Per NRC Info Notice 99-025 ML20212J8481999-10-0101 October 1999 Forwards Safety Evaluation Re Second 10 Yr Interval ISI Program Requests for Relief 98-009-II.Reliefs Granted for 98-009-II,Parts B & C & 98-010-II & 98-011-II 3F0999-03, Notifies of Approved Change to NPDES Permit Applicable to Crystal River Unit 3 IAW Section 3.2.3 of Epp.Proposed Change Was Approved on 990914 by State of Fl & Provided in Attachment1999-09-27027 September 1999 Notifies of Approved Change to NPDES Permit Applicable to Crystal River Unit 3 IAW Section 3.2.3 of Epp.Proposed Change Was Approved on 990914 by State of Fl & Provided in Attachment 3F0999-18, Notifies NRC That Due Date for Commitment Common to Ltrs 980115 & 980209 Will Be Extended.Revised Completion Date for Cable Ampacity Project Is 0003311999-09-27027 September 1999 Notifies NRC That Due Date for Commitment Common to Ltrs 980115 & 980209 Will Be Extended.Revised Completion Date for Cable Ampacity Project Is 000331 ML20212F7251999-09-23023 September 1999 Discusses Staff Review of Util 980330 Response,As Suppl on 990514,to GL 97-06, Degradation of SG Internals. Staff Concludes That Licensee Responses to GL Provide Reasonable Assurance That Condition of SG Internals Acceptable ML20212F7331999-09-23023 September 1999 Discusses Util Licensing Action for GL 98-01, Year 2000 Readiness of Computer Systems at Nuclear Power Plants. NRC Ack Efforts Util Completed to Date in Preparing Crystal River,Unit 3 for Y2K Transition 3F0999-20, Forwards Summary Re Justification to Defer USI A-46 Commitment,Per Work Needed to Resolve GL 87-03, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Usi A-461999-09-21021 September 1999 Forwards Summary Re Justification to Defer USI A-46 Commitment,Per Work Needed to Resolve GL 87-03, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Usi A-46 ML20212E6741999-09-21021 September 1999 Forwards Safety Evaluation Accepting Proposed EAL Changes Submitted by ,As Supplemented by 981120,990713 & 0831 Ltrs,Incorporating Guidance in NUMARC/NESP-007,Rev 2, Methodology for Development of Eals 3F0999-01, Forwards FPC Crystal River Unit 3 Plant Reference Simulator Four-Year Simulator Certification Rept Sept 1995-Sept 1999, Per 10CFR55.45(b)(5)(ii) & 10CFR55.45(b)(5)(iv)1999-09-17017 September 1999 Forwards FPC Crystal River Unit 3 Plant Reference Simulator Four-Year Simulator Certification Rept Sept 1995-Sept 1999, Per 10CFR55.45(b)(5)(ii) & 10CFR55.45(b)(5)(iv) 3F0999-19, Provides Clarification of Minor Inconsistency Identified During Review of NRC SE for Plant Third 10-year Interval Inservice Insp Program Plan & Associated Requests for Relief1999-09-15015 September 1999 Provides Clarification of Minor Inconsistency Identified During Review of NRC SE for Plant Third 10-year Interval Inservice Insp Program Plan & Associated Requests for Relief ML20212F3141999-09-13013 September 1999 Forwards Insp Rept 50-302/99-05 on 990704-0814.Violations Noted,But Being Treated as non-cited Violations ML20211L9081999-09-0303 September 1999 Informs of Completion of Licensing Action for GL 92-08, Thermo-Lag 330-1 Fire Barriers, Dtd 921217,for Crystal River Unit 3 ML20211Q7581999-09-0101 September 1999 Forwards Summary of 990812-13 Training Managers Conference in Atlanta,Georgia Re Recent Changes to Operator Licensing Program.List Conference Attendees,Copy of Presentation Slides & List of Participant Questions Encl 3F0899-23, Provides Addl Info in Response to Several NRC Staff Questions Needed to Complete Review of Request to Adopt NEI 97-03,Draft Final Rev 3, Methodology for Development of Eals1999-08-31031 August 1999 Provides Addl Info in Response to Several NRC Staff Questions Needed to Complete Review of Request to Adopt NEI 97-03,Draft Final Rev 3, Methodology for Development of Eals ML20211G7111999-08-30030 August 1999 Modifies Approval of 980521 Request for Exception to 10CFR50.4(b)(6) & Grants Util Approval to Submit Copies of Future Updates to FSAR as Listed ML20211G7031999-08-30030 August 1999 Informs of Approval of Util 980521 Request for Exception to 10CFR50.4(b)(6),allowing Util to Submit Updates to Plant Ufsar.Ltr Modifies That Approval & Grants Util Approval 3F0899-07, Provides Formal Notification to NRC of FPC Plans Relative to Renewal of Crystal River Unit 3,FOL DPR-72.FPC Plans to Submit Application for License Renewal by End of 20021999-08-27027 August 1999 Provides Formal Notification to NRC of FPC Plans Relative to Renewal of Crystal River Unit 3,FOL DPR-72.FPC Plans to Submit Application for License Renewal by End of 2002 ML20212C1351999-08-27027 August 1999 Requests Withholding of Proprietary Version of Enhanced Spent Fuel Storage Project Engineering Input 3F0899-20, Forwards six-month fitness-for-duty Program Performance Data for Period 990101-990630,IAW 10CFR26.711999-08-26026 August 1999 Forwards six-month fitness-for-duty Program Performance Data for Period 990101-990630,IAW 10CFR26.71 3F0899-05, Forwards Response to NRC 990716 RAI Re Proposed Alternate Repair Criteria for Axial Tube End crack-like Indications in Crystal River Unit 31999-08-20020 August 1999 Forwards Response to NRC 990716 RAI Re Proposed Alternate Repair Criteria for Axial Tube End crack-like Indications in Crystal River Unit 3 3F0899-17, Submits Relief Request 99-0001-RR,seeking NRC Approval for Evaluation Performed by Util on through-wall Flaw in Nuclear Svc & Decay Heat Sea Water (RW) Sys,Per Guidance of GL 90-051999-08-19019 August 1999 Submits Relief Request 99-0001-RR,seeking NRC Approval for Evaluation Performed by Util on through-wall Flaw in Nuclear Svc & Decay Heat Sea Water (RW) Sys,Per Guidance of GL 90-05 3F0899-16, Informs That Licensee Is Requesting State of Fl Dept of Environ Protection to Make Changes in Plant NPDES Permit to Modify Conditions on Use of Biocide in Instrument Air Compressor Sys.No New Commitments Are Made in Submittal1999-08-19019 August 1999 Informs That Licensee Is Requesting State of Fl Dept of Environ Protection to Make Changes in Plant NPDES Permit to Modify Conditions on Use of Biocide in Instrument Air Compressor Sys.No New Commitments Are Made in Submittal 3F0899-02, Forwards Rev 2 to Cycle 11 COLR IAW Plant TS Section 5.6.2.18.Rev 1 of Cycle 11 COLR Was Not Submitted Due to Administrative Error.Changes Made in Rev 1 Listed & Incorporated in Encl Rev 21999-08-16016 August 1999 Forwards Rev 2 to Cycle 11 COLR IAW Plant TS Section 5.6.2.18.Rev 1 of Cycle 11 COLR Was Not Submitted Due to Administrative Error.Changes Made in Rev 1 Listed & Incorporated in Encl Rev 2 3F0899-06, Forwards Monthly Operating Rept for July 1999 for Crystal River,Unit 3,per ITS 5.7.1.2.Revised Repts for Apr,May & June 1999,also Encl.Data on Line Item 6 Updated to Agree with More Accurate Computer Point That Measures Value1999-08-13013 August 1999 Forwards Monthly Operating Rept for July 1999 for Crystal River,Unit 3,per ITS 5.7.1.2.Revised Repts for Apr,May & June 1999,also Encl.Data on Line Item 6 Updated to Agree with More Accurate Computer Point That Measures Value 05000302/LER-1997-038, Forwards LER 97-038-01,IAW 10CFR50.73(c).Submittal Also Provides Notification That Commitment Common to LER 97-038-00 & Reply to NOV 50-302/97-16 Has Been Revised & Revised Commitment Has Been Implemented1999-08-13013 August 1999 Forwards LER 97-038-01,IAW 10CFR50.73(c).Submittal Also Provides Notification That Commitment Common to LER 97-038-00 & Reply to NOV 50-302/97-16 Has Been Revised & Revised Commitment Has Been Implemented ML20210Q4511999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 ML20210P0741999-08-0505 August 1999 Forwards SE Accepting Licensee 980416 & 1130 Ltrs Re Third 10-year Interval ISI Program Plan & Associated Requests for Relief for Plant,Unit 3 3F0799-30, Forwards List of Licensing Actions Currently Estimated for Fys 2000 & 2001,in Response to Administrative Ltr 99-02,dtd 9906031999-07-29029 July 1999 Forwards List of Licensing Actions Currently Estimated for Fys 2000 & 2001,in Response to Administrative Ltr 99-02,dtd 990603 ML20210G8551999-07-27027 July 1999 Forwards Insp Rept 50-302/99-04 on 990523-0703.One Violation Identified & Being Treated as Noncited Violation 3F0799-09, Provides Response to NRC 990625 Telcon RAI Re Util Use of Relief Request 98-009-II for Plant ASME Section XI, Inservice Insp Second Interval.Ltr Established No New Regulatory Commitments1999-07-19019 July 1999 Provides Response to NRC 990625 Telcon RAI Re Util Use of Relief Request 98-009-II for Plant ASME Section XI, Inservice Insp Second Interval.Ltr Established No New Regulatory Commitments ML20209H5211999-07-16016 July 1999 Forwards Request for Addl Info Re Licensee Proposed Alternate Repair Criteria for Axial Tube End crack-like Indications in CR-3 once-through Steam Generators in Order to Complete Review ML20209G3231999-07-15015 July 1999 Forwards Biological Opinion Issued by Natl Marine Fisheries (NMFS) of Dept of Commerce.Nmfs Concluded That Operation of Cw Intake Sys of Crystal River Not Likely to Jeopardize Existence of Species Listed in Biological Opinion ML20209G3481999-07-15015 July 1999 Transmits Natl Marine Fisheries Svc (NMFS) Biological Opinion Based on Review of Continued Use of Cw Intake Sys at Crystal River Energy Complex.Concludes That Continued Use of Cw Intake Sys Not Likely to Adversely Affect Gulf Sturgeon 3F0799-21, Forwards Copy of Revised NPDES Permit IAW Section 3.2.3 of Unit 3 Environ Protection Plan,Per 990430 Request to Allow Use of Biocide in Station Air Compressor Cooling Sys. Wastewater Permit FL0000159 Issued 990630 Also Encl1999-07-14014 July 1999 Forwards Copy of Revised NPDES Permit IAW Section 3.2.3 of Unit 3 Environ Protection Plan,Per 990430 Request to Allow Use of Biocide in Station Air Compressor Cooling Sys. Wastewater Permit FL0000159 Issued 990630 Also Encl 3F0799-05, Requests Exemption from 10CFR70.51, Matl Balance,Inventory & Records Requirements, as It Relates to 10CFR70.51(d) Re Physical Inventory of SNM for Crystal River Unit 3.Detailed Justification for Request,Encl1999-07-14014 July 1999 Requests Exemption from 10CFR70.51, Matl Balance,Inventory & Records Requirements, as It Relates to 10CFR70.51(d) Re Physical Inventory of SNM for Crystal River Unit 3.Detailed Justification for Request,Encl 3F0799-25, Forwards License Renewal Applications for Four Individuals, IAW 10CFR55.57.Without Encl1999-07-14014 July 1999 Forwards License Renewal Applications for Four Individuals, IAW 10CFR55.57.Without Encl 3F0799-26, Provides Notice of Change in Status for Senior Operator,Iaw 10CFR50.74(a).RD Demontfort,License Number SOP 20528-2,has Been Reassigned & No Longer Requires License Effective 9907301999-07-14014 July 1999 Provides Notice of Change in Status for Senior Operator,Iaw 10CFR50.74(a).RD Demontfort,License Number SOP 20528-2,has Been Reassigned & No Longer Requires License Effective 990730 3F0799-22, Provides Update & Rev to Submittal Made by Util Ltr with Regard to EAL Classification Methodology for Unit 3.Reponses to NRC Staff Questions Provided as Attachment D to Ltr & Reflects Discussions Held1999-07-13013 July 1999 Provides Update & Rev to Submittal Made by Util Ltr with Regard to EAL Classification Methodology for Unit 3.Reponses to NRC Staff Questions Provided as Attachment D to Ltr & Reflects Discussions Held 3F0799-03, Forwards Rev 5-0 to Safeguards Contingency Plan,Replacing Current Rev to Safeguards Contingency Plan,Rev 4,in Entirety.Rev Withheld,Per 10CFR73.211999-07-0808 July 1999 Forwards Rev 5-0 to Safeguards Contingency Plan,Replacing Current Rev to Safeguards Contingency Plan,Rev 4,in Entirety.Rev Withheld,Per 10CFR73.21 3F0799-02, Submits Rev 7-3 to Physical Security Plan,Replacing Current Rev to CR-3 Physical Security Plan,Rev 7-2,in Entirety.Rev Withheld,Per 10CFR73.211999-07-0808 July 1999 Submits Rev 7-3 to Physical Security Plan,Replacing Current Rev to CR-3 Physical Security Plan,Rev 7-2,in Entirety.Rev Withheld,Per 10CFR73.21 ML20196L1261999-07-0707 July 1999 Discusses Closeout of TAC MA0538 Re License Response to RAI Re GL 92-01,Rev 1,Suppl 1, Rv Structural Integrity, Issued on 950519 to Plant,Unit 3 3F0799-10, Submits Copy of Historical NPDES Permit Rev That Was Made in 1997 Re Use of Biocide at Crystal River Unit 31999-07-0707 July 1999 Submits Copy of Historical NPDES Permit Rev That Was Made in 1997 Re Use of Biocide at Crystal River Unit 3 ML20196J4991999-07-0101 July 1999 Advises That Info Contained in ,Which Included TR BAW-2346P,will Be Withheld from Public Disclosure,Per 10CFR2.790(b)(5) ML20209C0811999-06-25025 June 1999 Forwards Overdue Controlled Document Transmittals for Listed Documents 3F0699-06, Submits Final Response to GL 98-01,Suppl 1 Re Year 2000 Readiness of Nuclear Power Plants.Year 2000 Readiness Disclosure for Crystal River,Unit 3,encl1999-06-23023 June 1999 Submits Final Response to GL 98-01,Suppl 1 Re Year 2000 Readiness of Nuclear Power Plants.Year 2000 Readiness Disclosure for Crystal River,Unit 3,encl 1999-09-03
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEAR3F1099-14, Requests Copy of NRC Radtrad Code & Copy of User Instructions.Conditions for Receiving Code Listed1999-10-13013 October 1999 Requests Copy of NRC Radtrad Code & Copy of User Instructions.Conditions for Receiving Code Listed 3F1099-11, Provides Info on Requested Minor Permit Mod of Encl NPDES Permit.No New Regulatory Commitments Are Made1999-10-0404 October 1999 Provides Info on Requested Minor Permit Mod of Encl NPDES Permit.No New Regulatory Commitments Are Made 3F0999-03, Notifies of Approved Change to NPDES Permit Applicable to Crystal River Unit 3 IAW Section 3.2.3 of Epp.Proposed Change Was Approved on 990914 by State of Fl & Provided in Attachment1999-09-27027 September 1999 Notifies of Approved Change to NPDES Permit Applicable to Crystal River Unit 3 IAW Section 3.2.3 of Epp.Proposed Change Was Approved on 990914 by State of Fl & Provided in Attachment 3F0999-18, Notifies NRC That Due Date for Commitment Common to Ltrs 980115 & 980209 Will Be Extended.Revised Completion Date for Cable Ampacity Project Is 0003311999-09-27027 September 1999 Notifies NRC That Due Date for Commitment Common to Ltrs 980115 & 980209 Will Be Extended.Revised Completion Date for Cable Ampacity Project Is 000331 3F0999-20, Forwards Summary Re Justification to Defer USI A-46 Commitment,Per Work Needed to Resolve GL 87-03, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Usi A-461999-09-21021 September 1999 Forwards Summary Re Justification to Defer USI A-46 Commitment,Per Work Needed to Resolve GL 87-03, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Usi A-46 3F0999-01, Forwards FPC Crystal River Unit 3 Plant Reference Simulator Four-Year Simulator Certification Rept Sept 1995-Sept 1999, Per 10CFR55.45(b)(5)(ii) & 10CFR55.45(b)(5)(iv)1999-09-17017 September 1999 Forwards FPC Crystal River Unit 3 Plant Reference Simulator Four-Year Simulator Certification Rept Sept 1995-Sept 1999, Per 10CFR55.45(b)(5)(ii) & 10CFR55.45(b)(5)(iv) 3F0999-19, Provides Clarification of Minor Inconsistency Identified During Review of NRC SE for Plant Third 10-year Interval Inservice Insp Program Plan & Associated Requests for Relief1999-09-15015 September 1999 Provides Clarification of Minor Inconsistency Identified During Review of NRC SE for Plant Third 10-year Interval Inservice Insp Program Plan & Associated Requests for Relief 3F0899-23, Provides Addl Info in Response to Several NRC Staff Questions Needed to Complete Review of Request to Adopt NEI 97-03,Draft Final Rev 3, Methodology for Development of Eals1999-08-31031 August 1999 Provides Addl Info in Response to Several NRC Staff Questions Needed to Complete Review of Request to Adopt NEI 97-03,Draft Final Rev 3, Methodology for Development of Eals ML20212C1351999-08-27027 August 1999 Requests Withholding of Proprietary Version of Enhanced Spent Fuel Storage Project Engineering Input 3F0899-07, Provides Formal Notification to NRC of FPC Plans Relative to Renewal of Crystal River Unit 3,FOL DPR-72.FPC Plans to Submit Application for License Renewal by End of 20021999-08-27027 August 1999 Provides Formal Notification to NRC of FPC Plans Relative to Renewal of Crystal River Unit 3,FOL DPR-72.FPC Plans to Submit Application for License Renewal by End of 2002 3F0899-20, Forwards six-month fitness-for-duty Program Performance Data for Period 990101-990630,IAW 10CFR26.711999-08-26026 August 1999 Forwards six-month fitness-for-duty Program Performance Data for Period 990101-990630,IAW 10CFR26.71 3F0899-05, Forwards Response to NRC 990716 RAI Re Proposed Alternate Repair Criteria for Axial Tube End crack-like Indications in Crystal River Unit 31999-08-20020 August 1999 Forwards Response to NRC 990716 RAI Re Proposed Alternate Repair Criteria for Axial Tube End crack-like Indications in Crystal River Unit 3 3F0899-16, Informs That Licensee Is Requesting State of Fl Dept of Environ Protection to Make Changes in Plant NPDES Permit to Modify Conditions on Use of Biocide in Instrument Air Compressor Sys.No New Commitments Are Made in Submittal1999-08-19019 August 1999 Informs That Licensee Is Requesting State of Fl Dept of Environ Protection to Make Changes in Plant NPDES Permit to Modify Conditions on Use of Biocide in Instrument Air Compressor Sys.No New Commitments Are Made in Submittal 3F0899-17, Submits Relief Request 99-0001-RR,seeking NRC Approval for Evaluation Performed by Util on through-wall Flaw in Nuclear Svc & Decay Heat Sea Water (RW) Sys,Per Guidance of GL 90-051999-08-19019 August 1999 Submits Relief Request 99-0001-RR,seeking NRC Approval for Evaluation Performed by Util on through-wall Flaw in Nuclear Svc & Decay Heat Sea Water (RW) Sys,Per Guidance of GL 90-05 3F0899-02, Forwards Rev 2 to Cycle 11 COLR IAW Plant TS Section 5.6.2.18.Rev 1 of Cycle 11 COLR Was Not Submitted Due to Administrative Error.Changes Made in Rev 1 Listed & Incorporated in Encl Rev 21999-08-16016 August 1999 Forwards Rev 2 to Cycle 11 COLR IAW Plant TS Section 5.6.2.18.Rev 1 of Cycle 11 COLR Was Not Submitted Due to Administrative Error.Changes Made in Rev 1 Listed & Incorporated in Encl Rev 2 05000302/LER-1997-038, Forwards LER 97-038-01,IAW 10CFR50.73(c).Submittal Also Provides Notification That Commitment Common to LER 97-038-00 & Reply to NOV 50-302/97-16 Has Been Revised & Revised Commitment Has Been Implemented1999-08-13013 August 1999 Forwards LER 97-038-01,IAW 10CFR50.73(c).Submittal Also Provides Notification That Commitment Common to LER 97-038-00 & Reply to NOV 50-302/97-16 Has Been Revised & Revised Commitment Has Been Implemented 3F0899-06, Forwards Monthly Operating Rept for July 1999 for Crystal River,Unit 3,per ITS 5.7.1.2.Revised Repts for Apr,May & June 1999,also Encl.Data on Line Item 6 Updated to Agree with More Accurate Computer Point That Measures Value1999-08-13013 August 1999 Forwards Monthly Operating Rept for July 1999 for Crystal River,Unit 3,per ITS 5.7.1.2.Revised Repts for Apr,May & June 1999,also Encl.Data on Line Item 6 Updated to Agree with More Accurate Computer Point That Measures Value 3F0799-30, Forwards List of Licensing Actions Currently Estimated for Fys 2000 & 2001,in Response to Administrative Ltr 99-02,dtd 9906031999-07-29029 July 1999 Forwards List of Licensing Actions Currently Estimated for Fys 2000 & 2001,in Response to Administrative Ltr 99-02,dtd 990603 3F0799-09, Provides Response to NRC 990625 Telcon RAI Re Util Use of Relief Request 98-009-II for Plant ASME Section XI, Inservice Insp Second Interval.Ltr Established No New Regulatory Commitments1999-07-19019 July 1999 Provides Response to NRC 990625 Telcon RAI Re Util Use of Relief Request 98-009-II for Plant ASME Section XI, Inservice Insp Second Interval.Ltr Established No New Regulatory Commitments ML20209G3481999-07-15015 July 1999 Transmits Natl Marine Fisheries Svc (NMFS) Biological Opinion Based on Review of Continued Use of Cw Intake Sys at Crystal River Energy Complex.Concludes That Continued Use of Cw Intake Sys Not Likely to Adversely Affect Gulf Sturgeon 3F0799-25, Forwards License Renewal Applications for Four Individuals, IAW 10CFR55.57.Without Encl1999-07-14014 July 1999 Forwards License Renewal Applications for Four Individuals, IAW 10CFR55.57.Without Encl 3F0799-21, Forwards Copy of Revised NPDES Permit IAW Section 3.2.3 of Unit 3 Environ Protection Plan,Per 990430 Request to Allow Use of Biocide in Station Air Compressor Cooling Sys. Wastewater Permit FL0000159 Issued 990630 Also Encl1999-07-14014 July 1999 Forwards Copy of Revised NPDES Permit IAW Section 3.2.3 of Unit 3 Environ Protection Plan,Per 990430 Request to Allow Use of Biocide in Station Air Compressor Cooling Sys. Wastewater Permit FL0000159 Issued 990630 Also Encl 3F0799-05, Requests Exemption from 10CFR70.51, Matl Balance,Inventory & Records Requirements, as It Relates to 10CFR70.51(d) Re Physical Inventory of SNM for Crystal River Unit 3.Detailed Justification for Request,Encl1999-07-14014 July 1999 Requests Exemption from 10CFR70.51, Matl Balance,Inventory & Records Requirements, as It Relates to 10CFR70.51(d) Re Physical Inventory of SNM for Crystal River Unit 3.Detailed Justification for Request,Encl 3F0799-26, Provides Notice of Change in Status for Senior Operator,Iaw 10CFR50.74(a).RD Demontfort,License Number SOP 20528-2,has Been Reassigned & No Longer Requires License Effective 9907301999-07-14014 July 1999 Provides Notice of Change in Status for Senior Operator,Iaw 10CFR50.74(a).RD Demontfort,License Number SOP 20528-2,has Been Reassigned & No Longer Requires License Effective 990730 3F0799-22, Provides Update & Rev to Submittal Made by Util Ltr with Regard to EAL Classification Methodology for Unit 3.Reponses to NRC Staff Questions Provided as Attachment D to Ltr & Reflects Discussions Held1999-07-13013 July 1999 Provides Update & Rev to Submittal Made by Util Ltr with Regard to EAL Classification Methodology for Unit 3.Reponses to NRC Staff Questions Provided as Attachment D to Ltr & Reflects Discussions Held 3F0799-02, Submits Rev 7-3 to Physical Security Plan,Replacing Current Rev to CR-3 Physical Security Plan,Rev 7-2,in Entirety.Rev Withheld,Per 10CFR73.211999-07-0808 July 1999 Submits Rev 7-3 to Physical Security Plan,Replacing Current Rev to CR-3 Physical Security Plan,Rev 7-2,in Entirety.Rev Withheld,Per 10CFR73.21 3F0799-03, Forwards Rev 5-0 to Safeguards Contingency Plan,Replacing Current Rev to Safeguards Contingency Plan,Rev 4,in Entirety.Rev Withheld,Per 10CFR73.211999-07-0808 July 1999 Forwards Rev 5-0 to Safeguards Contingency Plan,Replacing Current Rev to Safeguards Contingency Plan,Rev 4,in Entirety.Rev Withheld,Per 10CFR73.21 3F0799-10, Submits Copy of Historical NPDES Permit Rev That Was Made in 1997 Re Use of Biocide at Crystal River Unit 31999-07-0707 July 1999 Submits Copy of Historical NPDES Permit Rev That Was Made in 1997 Re Use of Biocide at Crystal River Unit 3 ML20209C0811999-06-25025 June 1999 Forwards Overdue Controlled Document Transmittals for Listed Documents 3F0699-12, Provides Suppl Info for LAR 240,rev 0 & Pump Curve for EFP-3 to Facilitate Review,As Requested1999-06-23023 June 1999 Provides Suppl Info for LAR 240,rev 0 & Pump Curve for EFP-3 to Facilitate Review,As Requested 3F0699-06, Submits Final Response to GL 98-01,Suppl 1 Re Year 2000 Readiness of Nuclear Power Plants.Year 2000 Readiness Disclosure for Crystal River,Unit 3,encl1999-06-23023 June 1999 Submits Final Response to GL 98-01,Suppl 1 Re Year 2000 Readiness of Nuclear Power Plants.Year 2000 Readiness Disclosure for Crystal River,Unit 3,encl 3F0699-08, Provides Updated Info to Licensee Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions. Ltr Establishes No New Regulatory Commitments1999-06-21021 June 1999 Provides Updated Info to Licensee Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions. Ltr Establishes No New Regulatory Commitments 3F0699-09, Forwards FPC 1998 Annual Financial Repts for Two Participating co-owners of Crystal River Unit 3.Financial Statements & Independent Auditors Repts for City of Alachua,Fl,Encl1999-06-0404 June 1999 Forwards FPC 1998 Annual Financial Repts for Two Participating co-owners of Crystal River Unit 3.Financial Statements & Independent Auditors Repts for City of Alachua,Fl,Encl 3F0599-21, Submits Addendum to B&W Owners Group Topical Rept BAW-2346P, Rev 0.Addendum Includes Leak Rate Values Based on CR-3 Plant Specific Main Steam Line Break Tube Loads1999-05-28028 May 1999 Submits Addendum to B&W Owners Group Topical Rept BAW-2346P, Rev 0.Addendum Includes Leak Rate Values Based on CR-3 Plant Specific Main Steam Line Break Tube Loads 3F0599-10, Submits Changes Made to Crystal River,Unit 3 Its,As Required by ITS 5.6.2.17.Encl Provides Revs to Plant ITS Bases That Will Update NRC Copies of Its.Instructions for Updating ITS, Encl1999-05-26026 May 1999 Submits Changes Made to Crystal River,Unit 3 Its,As Required by ITS 5.6.2.17.Encl Provides Revs to Plant ITS Bases That Will Update NRC Copies of Its.Instructions for Updating ITS, Encl ML20207E4341999-05-25025 May 1999 Submits 30-day Written Rept on Significant PCT Changes in ECCS Analysis for ANO-1.CRAFT2 Limiting PCT for ANO-1 Was Bounded by 1859 F PCT Calculated at 2568 Mwt for Crystal River 3 Cold Leg Pump Discharge Break Size of 0.125 Ft 3F0599-22, Forwards non-proprietary Version of B&Wog Topical Rept BAW-2346NP, Alternate Repair Criteria for Tube End Cracking in Tube-to-Tubesheet Roll Joint of Once-Through Sgs1999-05-21021 May 1999 Forwards non-proprietary Version of B&Wog Topical Rept BAW-2346NP, Alternate Repair Criteria for Tube End Cracking in Tube-to-Tubesheet Roll Joint of Once-Through Sgs 3F0599-18, Forwards 1998 Annual Radiological Environ Operating Rept for Crystal River,Unit 3. Rept Is Submitted in Accordance with CR-3 ITS 5.7.1.1(b) & Section 6.6 of ODCM1999-05-14014 May 1999 Forwards 1998 Annual Radiological Environ Operating Rept for Crystal River,Unit 3. Rept Is Submitted in Accordance with CR-3 ITS 5.7.1.1(b) & Section 6.6 of ODCM 3F0599-17, Submits Update Response to GL 97-06, Degradation of SG Internals. Ltr Establishes No New Regulatory Commitments1999-05-14014 May 1999 Submits Update Response to GL 97-06, Degradation of SG Internals. Ltr Establishes No New Regulatory Commitments 3F0599-07, Submits Guarantee of Payment of Deferred Premiums for CR-3 in Accordance with 10CFR140.21.Internal Cash Flow Projection Was Prepared in Accordance with Suggested Format Outlined in Reg Guide 9.4 Dtd Sept 19781999-05-14014 May 1999 Submits Guarantee of Payment of Deferred Premiums for CR-3 in Accordance with 10CFR140.21.Internal Cash Flow Projection Was Prepared in Accordance with Suggested Format Outlined in Reg Guide 9.4 Dtd Sept 1978 3F0599-03, Provides Update Curves for Facility Pressure/Temp Limits Rept,Rev 2 & Updated Rev Bar ITS Pages Associated with LAR, in Response to NRC RAI Re Subject LAR1999-05-12012 May 1999 Provides Update Curves for Facility Pressure/Temp Limits Rept,Rev 2 & Updated Rev Bar ITS Pages Associated with LAR, in Response to NRC RAI Re Subject LAR 3F0599-05, Responds to 990402 RAI Re Third 10-year Interval ISI Program Plan Requests for Relief.Util Revised Relief Requests 98-010-II,98-003-PT,98-005-PT & 98-001-SS Based on Responses to Rai.Revised Relief Requests Encl1999-05-12012 May 1999 Responds to 990402 RAI Re Third 10-year Interval ISI Program Plan Requests for Relief.Util Revised Relief Requests 98-010-II,98-003-PT,98-005-PT & 98-001-SS Based on Responses to Rai.Revised Relief Requests Encl 3F0599-08, Forwards Licensee Clarification of Info Provided in Amend 171 Re post-LOCA Boron Dilution Precipitation Prevention.Ltr Establishes No New Regulatory Commitments1999-05-0303 May 1999 Forwards Licensee Clarification of Info Provided in Amend 171 Re post-LOCA Boron Dilution Precipitation Prevention.Ltr Establishes No New Regulatory Commitments 3F0599-09, Forwards Crystal River Unit 3 Radioactive Effluent Release Rept - 1998 & Revised Crystal River Unit 3 Radioactive Effluent Release Rept - 1997. Licensee Informs That ODCM & PCP Were Not Revised During 19981999-05-0101 May 1999 Forwards Crystal River Unit 3 Radioactive Effluent Release Rept - 1998 & Revised Crystal River Unit 3 Radioactive Effluent Release Rept - 1997. Licensee Informs That ODCM & PCP Were Not Revised During 1998 3F0499-24, Forwards Summary of Proposed Changes to Crystal River,Unit 3 NPDES Permit,That Are Being Submitted to Florida Dept of Environ Protection.Proposed Change Will Allow Use of Scale Inhibitor,Biocides & Foam Control Agent1999-04-30030 April 1999 Forwards Summary of Proposed Changes to Crystal River,Unit 3 NPDES Permit,That Are Being Submitted to Florida Dept of Environ Protection.Proposed Change Will Allow Use of Scale Inhibitor,Biocides & Foam Control Agent 3F0499-09, Forwards FPC Annual Financial Rept & Annual Financial Repts for Eight of Ten Participating co-owners of Crystal River Unit 3 Nuclear Station.Outstanding Annual Financial Rept Will Be Submitted by 9907301999-04-30030 April 1999 Forwards FPC Annual Financial Rept & Annual Financial Repts for Eight of Ten Participating co-owners of Crystal River Unit 3 Nuclear Station.Outstanding Annual Financial Rept Will Be Submitted by 990730 3F0499-23, Submits Repts Required by App B,Environ Protection Plan,Of Crystal River,Unit 3 Operating License.Fl Dept of Environ Protection Has Provided Clarification Re Ph Monitoring Requirements1999-04-23023 April 1999 Submits Repts Required by App B,Environ Protection Plan,Of Crystal River,Unit 3 Operating License.Fl Dept of Environ Protection Has Provided Clarification Re Ph Monitoring Requirements 3F0499-18, Informs of Recent Senior Management Change at Fpc,Which Will Not Affect Std Recipients of Incoming NRC Correspondence. Updated Util Mailing List,Encl1999-04-20020 April 1999 Informs of Recent Senior Management Change at Fpc,Which Will Not Affect Std Recipients of Incoming NRC Correspondence. Updated Util Mailing List,Encl 3F0499-05, Forwards Rev 19 to Radiological Emergency Response Plan. Changes to Plan Marked with Vertical Bars in Left Margin1999-04-16016 April 1999 Forwards Rev 19 to Radiological Emergency Response Plan. Changes to Plan Marked with Vertical Bars in Left Margin 3F0499-08, Forwards FPC Annual ITS Dose Rept for Period Jan-Dec 1998. Rept Provides person-rem Radiation Exposures,According to Work & Job Function,At CR-3 for Period Jan-Dec 19981999-04-16016 April 1999 Forwards FPC Annual ITS Dose Rept for Period Jan-Dec 1998. Rept Provides person-rem Radiation Exposures,According to Work & Job Function,At CR-3 for Period Jan-Dec 1998 1999-09-27
[Table view] |
Text
_
Florida Power CORPORATION Na f6Ju March 8, 1994 3F0394-03 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
Subject:
Motor Operated Valve (MOV) Program Status
References:
Draft Generic Letter 89-10 Supplement 6 FPC to NRC letter, 3F0992-05, dated September 18, 1992
Dear Sir:
The purpose of this letter is to provide a summary status concerning Generic Letter (GL) 89-10 MOV related activities and to clarify the scope of valve setup and testing at Florida Power Corporation (FPC).
FPC is continuing M0V work activities which should result in all GL 89-10 program MOVs being appropriately setup with the best available data by the end of Refuel
- 9. Refuel 9, which is the third refuel since GL 85-10 was issued, is scheduled for completion in early June,1994. Enclosed, as an atachment, is a table of GL 89-10 MOVs, their status, and any-applicable notes.
There are, however, several outstanding MOV issues that continue to challenge FPC resources and may affect our MOV program. :These issues are as follows:
a Valve mispositioning, for PWRs, remains an unresolved issue that can significantly affect the scope of work associat ed with certain valves.
FPC has not included valve mispositioning induced dPs as an input to determine valve operation.
= Reduced voltage is considered in M0V calculations. Some calculations are being revised to incorporate new information.
= Pressure locking and thermal binding will be addressed when generic communications are developed.
El1 A $
CRYSTAL RNER ENERGY COMPLEX: 15760 W Power une St . Crystal River, Florida 344284708 e (904) 795-6486 k
^ *" "
9403160327 940300 PDR ADOCK 05000302 P PDR
O. S. Nuclear Regulatory Commission 3F0394-03 Page 2 of 9-
. Our goal is to ensure all currently identified GL 89-10 MOV issues are either resolved or action plans in effect by the end of June, 1994.
The enclosed attachment lists those valves that are included in the GL 89-10 program.
Sincerely, P. M. Beard, Jr.
b Senior Vice President Nuclear Operations PMB/PVF:ff Attachment xc: Regional Administrator NRR Project Manager Senior Resident Inspector l
U. S. Nuclear Regulatory Commission 3F0394-03 Page 3 of 9 ATTACHMENT GL 89-10 MOVs are grouped into the following test categories at FPC:
= Dynamic Testing - these valves are tested at differential pressures as close to design basis conditions as possible and are setup to operate at design basis conditions using diagnostic equipment.
= Functional Verification - these valves are tested by stroking the valve to its safety function position during the normal course of operating the nuclear plant, primarily using surveillance procedures and operating procedures. They are setup, statically, to a thrust setting derived from applicable calculations. Diagnostic equipment is used for initial setup .
- = Head Pressure Testing - these valves use the head of the tank they are connected to for developing the required dP. Diagnostic equipment is used for initial setup'.
= Not Practical Due to Plant Conditions - these valves are typically stroke checked under static conditions and most are setup using a thrust setting.
These valves will be tested using the EPRI developed program or a suitable alternative.
DYNAMIC IESTING Valva Valve Description Comments Tag #
ASV-5 Steam Inlet Isolation to dP testing and setup complete.
the Turbine Driven Emergency Feedwater Pump DHV-7 "B" Train LPI/DH dP testing and setup scheduled for Discharge Cross-Tie Refuel 9 or earlier.
DHV-8 "A" Train LPI/DH dP testing and setup scheduled for Discharge Cross-Tie Refuel 9 or earlier.
DHV-11 "A" Train LPI Tie to HPI ReducedpPtestperformed, setup Suction Header complete DHV-12 "B" Train LPI Tie to HPI ReducedpPtestperformed, setup Suction Header complete DHV-91 DH/LPI to PZR Spray dP testing and setup complete. .
Isolation DWV-160 DW Isolation to RB Reduced dP testing and setup complete2,
+
+
O. S. Nuclear Regulatory Commission 3F0394-03 Page 4 of 9 EFV-11 Turbine Driven Emergency dP testing and setup complete.
Feedwater Pump Isolation to "A" 0TSG EFV-14 Motor Driven Emergency dP testing and setup complete.
Feedwater Pump Isolation to "A" 0TSG EFV-32 Turbine Driven Emergency dP testing and setup complete.
Feedwater Pump Isolation to "B" 0TSG EFV-33 Motor Driven Emergency dP testing and setup complete.
Feedwater Pump Isolation to "B" 0TSG FWV-14 "A" Main Feedwater Pump Initial dP testing and setup complete.
Suction Additional dP testing scheduled for Refuel 9.
FWV-15 "B" Main Feedwater Initial dP testing and setup complete.
Suction Additional dP testing scheduled for Refuel 9.
FWV-28 Main Feedwater Discharge dP testing and setup complete3 .
Cross-Tie FWV-29 "B" Main Feedwater Main dP testing and setup complete'.
Block i FWV-30 "A" Main Feedwater Main dP testing and setup complete'.
Block FWV-31 "A" Main Feedwater Low dP testing and setup complete3 .
Load Block l FWV-32 "B" Main Feedwater low dP testing and setup complete3 .
Load Block FVW-33 "B" Main Feedwater dP testing and setup complete3 .
Start-Up Block j FWV-36 "A" Main Feedwater ReducedglPtestingandsetup Start-Up Block complete '3.
MUV-18 RCP Seal Injection Reduced dP testing and setup complete2 ,
Isolation Block MUV-23 HPI Control to "A" RCS dP testing and setup complete.
Loop
~
1 U. S. Nuclear Regulatory Commission 1 3F0394-03 Page 5 of 9 MUV-24 HPI Control to "A" RCS dP testing and setup complete.
Loop MUV-25 HPI Control to "B" RCS dP testing and setup complete.
Loop i I
MUV-26 HPI Control to "B" RCS dP testing and setup complete. ;
Loop MUV-27 RCS Makeup Block dP testing and setup complete.
1 MUV-53 Outboard MVP dP testing cpmplete, setup scheduled Recirculation Isolation for Refuel 9 MUV-257 Inboard MVP dPtestingcpmplete,setupscheduled Recirculation Isolation for Refuel 9 FUNCTIONAL VERIFICATION Valve Valve Name Comments Tag #
ASV-204 Steam Inlet Isolation to Setup scheduled for Refuel 9.
the Turbine Driven Emergency Feedwater Pump CAV-1 PZR Steam Space Sample Setup scheduled for Refuel 9.
Isolation CAV-3 -PZR Water Space Sample Setup scheduled for Refuel 9.
Isolation CAV-4 "A" OTSG Shell Side Setup scheduled for Refuel 9.
Sample Isolation '
CAV-5 "A" 0TSG Shell Side Setup scheduled for Refuel 9.
Sample Isolation CAV-126 RCS Letdown Isolation Setup scheduled for Refuel 9.
CFV-11 "A" Core Flood Tank Setup scheduled for Refuel 9.
Sample Isolation CFV-12 "B" Core Flood Tank Setup seneduled for Refuel 9.
Sample Isolation CFV-15 "B" Core Flood Tank Vent Setup scheduled for Refuel 9.
Isolation
U. S. Nuclear Regulatory Commission 3F0394-03 Page 6 of 9 CFV-16 "A" Core Flood Tank Vent Setup scheduled for Refuel 9.
Isolation DHV-39 DH Drop Line Isolation Setup complete.
to DHP-1A DHV-40 DH Drop Line Isolation Setup complete.
to DHP-18 DHV-110 "A" Train LPI/DHR Flow Setup complete.
Control DHV-lll "B" Train LPI/DHR Flow Setup complete.
, Control MUV-3 Discharge Cross-fie for Setup complete.
MVP-1B and MVP-lC MUV-9 Discharge Cross-Tie for Setup complete.
MVP-1A and MVP-1B MUV-38 Letdown Cooler 3A Inlet Setup scheduled for Refuel 96 .
Isolation MUV-39 Letdown Cooler 3B Inlet Set;n scheduled for Refuel 9 6, Isolation MUV-62 Suction Cross-Tie for dP testing and setup complete.
MVP-1B and MVP-lC MUV-69 Suction Cross-Tie for dP testing and setup complete.
MUP-1A and MVP-1B MUV-498 Letdown Cooler 3C Inlet Setup scheduled for Refuel 96 ,
Isolation RCV-13 PZR Spray Block Setup complete.
RCV-14 PZR Spray Control Valve replacement with testing and setup scheduled for Refuel 9.
RCV-53 LPI/DH to PZR Spray Setup complete.
Isolation / Control
.' U. S. Nuclear Regulatory Commission 3F0394-03 Page 7 of 9 HEAD PRESSURE TESTING Valve Valve Name Comments Tag #
BSV-16 BSP-18 Suction Isolation Testing and setup complete.
BSV-17 BSP-1A Suction Isolation Testing and setup complete.
DHV-34 BWST Outlet Isolation to Testing and setup complete.
DHP-1A (LPI)
DHV-35 BWST Outlet Isolation to Testing and setup scheduled for Refuel DHP-1B (LPI) 9 or earlier.
MUV-58 BWST Outlet Isolation to Testing and setup complete.
HPI, "B" Train MUV-73 BWST Outlet Isolation to Testing and setup complete.
HPI, "A" Train NoT PRACTICAL TO IEST Valve Valve Name Comments Tag #
BSV-3 "B" Train RB Spray Setup complete.
Isolation / Control BSV-4 "A" Train RB Spray Setup complete. !
Isolation / Control DHV-3 DH Drop Line Isolation Setup complete.
(Inside RB)
DHV-4 DH Drop Line Isolation Setup complete.
(Inside RB)
DHV-5 "A" Train LPI Injection LimitedpPtestperformed, setup complete DHV-6 "B" Train LPI Injection LimitedpPtestperformed, setup complete DHV-41 DH Drop Line Isolation Setup complete.
(Outside RB) l DHV-42 RB Sump.to "A" Train LPI Setup complete.
U. S. Nuclear Regulatory Commission 3F0394-03 Page 8 of 9 i
DHV RB Sump to "B" Train LPI Setup complete.
MSV Steam Isolation from "A" Limited dP testing and setup complete7.
OTSG to the Turbine Driven Emergency Feedwater Pump MSV-56 Steam Isolation from "B" Limited dP testing and setup complete7 .
OTSG to the Turbine Driven Emergency Feedwater Pump MUV-40 Letdown Cooler 3A Outlet Setup scheduled for Refuel 9.
Isolation MUV-41 Letdown Cooler 3B Outlet Setup scheduled for Refuel 9.
Isolation MUV-258 RCP-1A Controlled Bleed- LimitedpPte:' performed, setup Off Isolation complete MUV-259 RCP-1B Controlled Bleed- LimitedpPtestperformed, setup Off Isolation complete MUV-260 RCP-lC Controlled Bleed- Limited pP test performed, setup Off Isolation complete MUV-261 RCP-ID Controlled Bleed- LimitedpPtestperformed, setup Off Isolation complete MUV-505 Letdown Cooler 3C Outlet Setup scheduled for Refuel 9.
Isolation ,
RCV-Il PORV Block Existing valve setup complete. Valve replacement, atesting and setup is scheduled for Refuel 9.
WDV-3 RB Sump Isolation Setup complete.
WDV-60 RC Drain Tank Vent Setup complete.
Isolation WDV-94 RC Drain Tank /RC Drain Reducedp'Ptestperformed, 7 setup Pump Isolation complete .
WDV-405 RB Vent Header Isolation Setup complete.
WDV-406 RB Vent Header Isolation Setup complete. ,
9
^
U. S. Nuclear Regulatory Commission 3F0394-03 Page 9 of 9
- Notes:
- 1. Diagnostic equipment is also used post maintenance, as needed, and when performing periodic testing at the determined frequency.
- 2. dP established between 50% and 80% of design basis.
- 3. Reliance on operator action, during low powcr operation, minimizes the differential pressure FWV-28 would have to close against.
- 4. Reliance on either the related train feedwater pump trip or its associated suction valve closing significantly reduces the dP across these valves.
- 5. Accuracy associated with the original method is considered unacceptable due to rising - rotating stem. .
- 6. Screening for removal from program.
- 7. dp is typically < 50% of design basis pressure or test results are not ,
currently beneficial. Further evaluations pending EPRI test program results.